Monthly State Let Construction Report For San Antonio District As Of Mar 13, 2024 Page 5 Of 7

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayCS
FromALONG FM 2790, COTTAGE ST., AND PRAIRIE
ToIN LYTLE: MEDINA, ATASCOSA, BEXAR COUNTY
CSJ0915-00-252
Proj IDSTP 2023(490)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1244334.0083637.486.7
Work Order11-16-23
Work Began02-08-24
Work Completed
Time Computed12-16-23
Contract Working Days280
Addl Days Granted0
Working Days Charged14
Percent Time Used5
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-252
BARRICADES UNLIMITED (2.30)
A K FUQUAY CONSTRUCTION (8.26)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.81)
Contract #10233218
Totals1244334.0068648.4083637.486.7

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CONTROL FY 2023
ToPROJECT 1
CSJ0915-00-253
Proj IDC 915-00-253
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011505725.721360799.3590.3
Work Order03-16-23
Work Began08-07-23
Work Completed
Time Computed06-14-23
Contract Working Days260
Addl Days Granted0
Working Days Charged93
Percent Time Used35
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-253
ALAMO CRANE SERVICE, INC. (0.87)
FIBERTEL, LLC (4.20)
FLASHER EQUIPMENT COMPANY (3.77)
LOZANO TRUCKING COMPANY, INC. (1.03)
M & M STRIPING & POWER WASHING, LLC (1.30)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.09)
Contract #02233231
Totals1505725.72336746.751360799.3590.3

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CONTROL FY 2023
ToPROJECT 2
CSJ0915-00-254
Proj IDC 915-00-254
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011347419.72504049.5637.4
Work Order06-28-23
Work Began10-24-23
Work Completed
Time Computed09-26-23
Contract Working Days260
Addl Days Granted0
Working Days Charged53
Percent Time Used20
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-254
LOZANO TRUCKING COMPANY, INC. (1.15)
FIBERTEL, LLC (4.69)
Contract #05233234
Totals1347419.728600.00504049.5637.4

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-257
Proj IDC 915-00-257
Work TypeTRAFFIC CONTROL DEVICES
 
0.0015176271.91552326.9910.6
Work Order07-19-23
Work Began00-00-00
Work Completed
Time Computed10-17-23
Contract Working Days191
Addl Days Granted0
Working Days Charged52
Percent Time Used27
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-257
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06233217
Totals5176271.91375547.12552326.9910.6

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-258
Proj IDC 915-00-258
Work TypeBRIDGE WIDENING OR REHABILITATION
 
1984026.00812620.5040.9
Work Order08-03-23
Work Began10-31-23
Work Completed
Time Computed09-02-23
Contract Working Days173
Addl Days Granted0
Working Days Charged63
Percent Time Used36
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-258
D&G ENERGY CORPORATION (0.67)
Contract #06233421
Totals1984026.00172838.13812620.5040.9

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CONTROL FY 2024
ToPROJECT 1
CSJ0915-00-259
Proj IDC 915-00-259
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011607455.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-06-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days260
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-259
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243031
Totals1607455.000.000.000.0

CountyBEXAR
HighwayVA
FromON POST OAK TR., IN FAIR OAKS RANCH
ToFROM SILVER SPUR TR. TO ROLLING ACRES TR
CSJ0915-00-264
Proj IDSTP 2023(949)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2147579.651510700.6970.3
Work Order08-03-23
Work Began00-00-00
Work Completed
Time Computed09-01-23
Contract Working Days150
Addl Days Granted0
Working Days Charged73
Percent Time Used48
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-264
A K FUQUAY CONSTRUCTION (3.96)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.94)
BARRICADES UNLIMITED (0.44)
LONE STAR EROSION CONTROL (2.54)
TRP CONSTRUCTION GROUP, LLC (2.24)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.35)
LONE STAR PAVING COMPANY (16.05)
Contract #06233623
Totals2147579.65260092.121510700.6970.3

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-269
Proj IDC 915-00-269
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012236322.000.000.0
Work Order11-08-23
Work Began00-00-00
Work Completed
Time Computed12-08-23
Contract Working Days257
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-269
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10233017
Totals2236322.000.000.000.0

CountyBEXAR
HighwayCS
FromN WALTERS ST @ UPRR & LARRY STREET
To.
CSJ0915-12-532
Proj IDBR 1402(214)
Work TypeBRIDGE REPLACEMENT
 
0.0621567047.861419213.8793.1
Work Order04-06-22
Work Began09-13-22
Work Completed
Time Computed05-06-22
Contract Working Days108
Addl Days Granted0
Working Days Charged160
Percent Time Used148
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-532
DIIBS SPECIALISTS, LLC (3.22)
HYDRO TECHNOLOGIES, INC. (6.50)
Contract #02223219
Totals1567047.8637267.951419213.8793.1

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
ToON STATE SYSTEM
CSJ0915-12-574
Proj IDF 2022(884)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.0012791621.982623984.4693.9
Work Order09-21-22
Work Began11-07-22
Work Completed
Time Computed10-21-22
Contract Working Days204
Addl Days Granted0
Working Days Charged174
Percent Time Used85
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-574
FUQUAY, INC. (3.67)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (1.76)
LOZANO CONSTRUCTION COMPANY, INC. (1.25)
FLASHER EQUIPMENT COMPANY (0.87)
HOLES OF SAN ANTONIO (0.46)
A K FUQUAY CONSTRUCTION (3.67)
Contract #08223218
Totals2791621.9825470.742623984.4693.9

CountyBEXAR
HighwayCS
FromON CASTROVILLE RD AT CUPPLES RD
To.
CSJ0915-12-624
Proj IDSTP 2022(690)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.8002074271.501409752.9567.9
Work Order08-04-22
Work Began01-10-23
Work Completed
Time Computed09-03-22
Contract Working Days297
Addl Days Granted0
Working Days Charged265
Percent Time Used89
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-624
FIBERTEL, LLC (5.02)
CATO ELECTRIC COMPANY (0.14)
BEXAR COUNTY TRAFFIC CONTROLLERS, LLC (1.26)
Contract #06223422
Totals2074271.504180.001409752.9567.9

CountyBEXAR
HighwayVA
FromVARIOUS LOCATION ON
ToIH 35 S AND IH 37 S
CSJ0915-12-664
Proj IDCM 2021(405)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
0.0015046004.495436483.1499.9
Work Order05-04-21
Work Began10-18-21
Work Completed
Time Computed08-02-21
Contract Working Days160
Addl Days Granted77
Working Days Charged237
Percent Time Used100
Contractor(s)
SICE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-664
MCA COMMUNICATIONS, INC. (2.92)
USA AMTECH, INC. (9.51)
APTUS GROUP USA, LLC (11.68)
AZTECA UTILITY RR SERVICES INC (9.51)
RAILPROS FIELD SERVICES, INC. (0.03)
GROUND HOG FOUNDATION DRILLING (1.13)
MCRAY CRANE (0.83)
Contract #03213009
Totals5046004.4915880.705436483.1499.9

CountyBEXAR
HighwayCR ETC
FromIN BEXAR COUNTY ON N FOSTER RD
ToAT CANDLE MEADOW
CSJ0915-12-693
Proj IDSTP 2022(691)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.2391705802.681771988.6899.9
Work Order07-27-22
Work Began10-31-22
Work Completed
Time Computed08-26-22
Contract Working Days130
Addl Days Granted10
Working Days Charged124
Percent Time Used88
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-693
ALAMO CRANE SERVICE, INC. (0.35)
FIBERTEL, LLC (3.81)
TRP CONSTRUCTION GROUP, LLC (13.81)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (1.52)
LOZANO CONSTRUCTION COMPANY, INC. (0.46)
CATO ELECTRIC COMPANY (0.41)
Contract #06223623
Totals1705802.680.001771988.6899.9

CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON PLEASANTON RD
ToAT HARDING BLVD
CSJ0915-12-696
Proj IDSTP 2024(389)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200420898.530.000.0
CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON GOLIAD RD
ToAT CLARK AVE
CSJ0915-12-709
Proj IDSTP 2024(389)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
455820.700.000.0
CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON GOLIAD RD
ToAT PECAN VALLEY
CSJ0915-12-710
Proj IDSTP 2024(389)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
349938.170.000.0
CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON HUEBNER RD
ToAT HUEBNER ES
CSJ0915-12-711
Proj IDSTP 2024(389)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200293322.190.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-05-23
Work Began00-00-00
Work Completed
Time Computed03-04-24
Contract Working Days129
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-696
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11233019
Totals1519979.590.000.000.0

CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON SAN PEDRO AVE
ToAT SAHARA DR
CSJ0915-12-698
Proj IDSTP 2023(535)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200408559.23456382.1299.9
CountyBEXAR
HighwayCS
FromIN SAN ANTONIO ON E. SOUTHCROSS BLVD
ToAT PECAN VALLEY
CSJ0915-12-708
Proj IDSTP 2023(535)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200397172.61392212.6198.7
CountyBEXAR
Highway0000000
FromIN SAN ANTONIO ON S FLORES ST
ToAT SAYERS AVE
CSJ0915-12-714
Proj IDSTP 2023(535)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
280986.50261304.0092.9
Work Order04-26-23
Work Began08-21-23
Work Completed
Time Computed05-26-23
Contract Working Days129
Addl Days Granted0
Working Days Charged89
Percent Time Used68
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-698
ALAMO CRANE SERVICE, INC. (0.37)
FIBERTEL, LLC (5.62)
FLASHER EQUIPMENT COMPANY (3.80)
LOZANO TRUCKING COMPANY, INC. (0.39)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (2.62)
Contract #03233026
Totals1086718.348748.171109898.7399.9

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS ON IH 10
ToFROM DE ZAVALA TO SL 13
CSJ0915-12-770
Proj IDSTP 2023(627)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
491128.33336538.9168.5
Work Order06-14-23
Work Began00-00-00
Work Completed
Time Computed09-12-23
Contract Working Days78
Addl Days Granted0
Working Days Charged21
Percent Time Used26
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-770
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05233048
Totals491128.33197453.83336538.9168.5

CountyWILSON
HighwayCR
FromCR 235 AT DRY CREEK
To.
CSJ0915-14-045
Proj IDBR 2022(415)
Work TypeBRIDGE REPLACEMENT
 
0.008557521.70546179.2897.9
Work Order04-12-23
Work Began07-05-23
Work Completed
Time Computed07-11-23
Contract Working Days175
Addl Days Granted0
Working Days Charged81
Percent Time Used46
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-14-045
BARRICADES UNLIMITED (1.86)
Contract #03233035
Totals557521.701250.00546179.2897.9

CountyWILSON
HighwayCS
FromON EL CAMINO REAL TRAIL FROM TRAIL ST
ToHOSPITAL BLVD (HWY 97)
CSJ0915-14-048
Proj IDSTP 2022(749)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1044921.00919285.0888.3
Work Order09-07-23
Work Began00-00-00
Work Completed
Time Computed11-05-23
Contract Working Days55
Addl Days Granted0
Working Days Charged60
Percent Time Used109
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-14-048
LONE STAR EROSION CONTROL (3.62)
Contract #08233048
Totals1044921.00118367.58919285.0888.3

CountyCOMAL
HighwayCS
FromIN NEW BRAUNFELS ON BARBAROSA RD
ToAT FM 1101
CSJ0915-17-072
Proj IDSTP 2022(692)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.1041402180.241442146.3799.9
CountyCOMAL
HighwayFM 1101
From0.1 MI WEST OF FM 306
To0.1 MI EAST OF FM 306
CSJ1272-01-021
Proj IDSTP 2022(739)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.193532636.40589109.2499.9
Work Order07-27-22
Work Began01-02-23
Work Completed
Time Computed08-26-22
Contract Working Days91
Addl Days Granted0
Working Days Charged90
Percent Time Used98
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-17-072
ALAMO CRANE SERVICE, INC. (0.09)
FIBERTEL, LLC (1.60)
FUQUAY, INC. (0.25)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (2.06)
LONE STAR PAVING COMPANY (13.79)
LOZANO CONSTRUCTION COMPANY, INC. (0.73)
M & M STRIPING & POWER WASHING, LLC (2.12)
MB PRIME LLC (0.20)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.21)
Contract #06223635
Totals1934816.641101.402031255.6199.9

CountyMEDINA
HighwayCR
FromCR 2615 @ MEDINA RIVER
To.
CSJ0915-45-056
Proj IDBR 2022(416)
Work TypeBRIDGE REPLACEMENT
 
730221.01489631.7467.0
Work Order07-19-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days149
Addl Days Granted0
Working Days Charged92
Percent Time Used61
Contractor(s)
ACEE CONSTRUCTION LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-45-056
A K FUQUAY CONSTRUCTION (1.18)
BEAIRD DRILLING (6.80)
DIIBS SPECIALISTS, LLC (4.46)
TRP CONSTRUCTION GROUP, LLC (3.09)
FLASHER EQUIPMENT COMPANY (1.19)
SPENCER PIER DRILLING CO (6.69)
Contract #06233039
Totals730221.0197881.30489631.7467.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7