Monthly State Let Construction Report For San Antonio District As Of Mar 13, 2024 Page 6 Of 7

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBANDERA
HighwayCR
FromENGLISH CROSSING RD
ToAT MEDINA RIVER
CSJ0915-47-039
Proj IDBR 2021(338)
Work TypeBRIDGE REPLACEMENT
 
0.1252422534.821178088.7948.6
Work Order01-06-23
Work Began05-08-23
Work Completed
Time Computed03-07-23
Contract Working Days206
Addl Days Granted0
Working Days Charged146
Percent Time Used70
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-47-039
GREGORY PILE DRIVING, INC. (7.41)
TEXAS MATERIALS GROUP, INC. (2.41)
DIIBS SPECIALISTS, LLC (0.45)
Contract #12223013
Totals2422534.8293828.231178088.7948.6

CountyWILSON
HighwayFM 1344
FromFM 541
To0.089 MI N OF CR 209
CSJ1122-04-012
Proj IDSSW 1122-4-12
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.0583715022.064321500.8899.9
CountyWILSON
HighwayFM 1344
FromFM 541
ToCR 209
CSJ1122-04-013
Proj IDC 1122-4-13
Work TypeREHABILITATION OF EXISTING ROAD
 
4.1312485892.432307604.7292.8
Work Order10-20-21
Work Began03-14-22
Work Completed
Time Computed11-19-21
Contract Working Days445
Addl Days Granted59
Working Days Charged326
Percent Time Used64
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1122-04-012
INTERSTATE BARRICADES & MARKINGS, INC. (2.00)
LONE STAR EROSION CONTROL (2.90)
MURRAY CONSTRUCTION (0.32)
TERRA CONSTRUCTION LLC (12.64)
BARRICADES UNLIMITED (0.34)
EGGEMEYER LAND CLEARING, LLC (0.18)
DIIBS SPECIALISTS, LLC (0.51)
Contract #09213028
Totals6200914.4942955.896629105.6099.9

CountyCOMAL
HighwayFM 1103
FromIH 35
ToGUADALUPE C/L
CSJ1268-01-013
Proj IDC 1268-1-13
Work TypeWIDEN NON-FREEWAY
 
0.1502322510.897691178.6399.9
CountyGUADALUPE
HighwayFM 1103
FromCOMAL C/L
ToRODEO WAY
CSJ1268-02-027
Proj IDC 1268-2-27
Work TypeWIDEN NON-FREEWAY
 
3.74036973113.365504996.4314.8
Work Order07-20-21
Work Began11-01-22
Work Completed
Time Computed10-18-21
Contract Working Days793
Addl Days Granted351
Working Days Charged9
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1268-01-013
ADCOCK 4 INVESTMENTS, LLC (7.29)
COX COMMERCIAL CONSTRUCTION LLC (6.89)
DEPENDABLE FENCE (2.76)
FIBERTEL, LLC (0.00)
ALAMO CRANE SERVICE, INC. (0.00)
G 6 CONSTRUCTION, INC. (2.03)
GEOSOURCE, INC. (0.10)
KELLER NORTH AMERICA, INC. (1.69)
PRESIDIO CONTRACTING, LLC (0.93)
ROADWAY SPECIALTIES, INC. (0.36)
S & S BRIDGE PAINTING, INC. (0.73)
TRP CONSTRUCTION GROUP, LLC (1.07)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.17)
E-Z BEL CONSTRUCTION, LLC (5.25)
C&M CONCRETE (1.19)
FRANK JR REINFORCEMENT LLC (0.00)
BADGER DAYLIGHTING CORP. (0.01)
Contract #06213203
Totals39295624.2580687.8113196175.0633.5

CountyBEXAR
HighwayFM 2252
FromEVANS ROAD
ToCOMAL/BEXAR COUNTY LINE
CSJ1433-01-028
Proj IDF 2023(674)
Work TypeWIDEN NON-FREEWAY
 
0.083104707.454477.694.2
CountyCOMAL
HighwayFM 2252
FromBEXAR/COMAL COUNTY LINE
ToFM 3009
CSJ1433-02-044
Proj IDSTP 2023(675)MM
Work TypeWIDEN NON-FREEWAY
 
2.70048399179.515471766.8111.3
Work Order08-23-23
Work Began00-00-00
Work Completed
Time Computed11-21-23
Contract Working Days744
Addl Days Granted0
Working Days Charged24
Percent Time Used3
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1433-01-028
A K FUQUAY CONSTRUCTION (1.32)
BARRICADES UNLIMITED (0.17)
FLASHER EQUIPMENT COMPANY (1.01)
HB FARMER FOUNDATION, LLC (3.05)
THE LEVY COMPANY, INC. (3.20)
LONE STAR PAVING COMPANY (13.23)
EGGEMEYER LAND CLEARING, LLC (0.10)
Contract #05233006
Totals48503886.964644276.335476244.5011.2

CountyBEXAR
HighwayFM 2252
FromAT EVANS ROAD
To.
CSJ1433-01-029
Proj IDSTP 2020(824)MM
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.3376358310.657166878.4099.9
CountyBEXAR
HighwayFM 2252
FromAT EVANS ROAD
To.
CSJ1433-01-033
Proj IDROW 1433-1-33
Work TypeRIGHT OF WAY
 
0.337221712.00189245.3685.3
Work Order09-08-20
Work Began11-30-20
Work Completed
Time Computed10-08-20
Contract Working Days303
Addl Days Granted40
Working Days Charged435
Percent Time Used126
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1433-01-029
SCOTT DERR PAINTING CO, LLC (0.13)
TEXAS MATERIALS GROUP, INC. (15.18)
THE LEVY COMPANY, INC. (5.21)
TRP CONSTRUCTION GROUP, LLC (0.34)
VOGES DRILLING CO. (5.71)
FLASHER EQUIPMENT COMPANY (1.03)
GEOSOURCE, INC. (0.31)
J. R. (JOE) RAMON & SONS, INC. (0.78)
LONE STAR EROSION CONTROL (5.18)
ROADWAY SPECIALTIES, INC. (0.41)
HERMANOS STEEL, LLC (0.50)
AARON CONCRETE CONTRACTORS, L.P. (1.19)
AETOS CONSTRUCTION L.L.C. (1.42)
KELLER NORTH AMERICA, INC. (0.00)
Contract #05203210
Totals6580022.650.007356123.7699.9

CountyWILSON
HighwayFM 1346
From0.345 MI N OF FM 775
ToFM 775
CSJ1437-02-016
Proj IDSTP 2022(693)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.345853370.48857518.0399.9
Work Order08-11-22
Work Began10-10-22
Work Completed
Time Computed09-10-22
Contract Working Days59
Addl Days Granted0
Working Days Charged59
Percent Time Used100
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1437-02-016
THE LEVY COMPANY, INC. (0.76)
FLASHER EQUIPMENT COMPANY (5.87)
RONALD R. WAGNER & CO., LP (3.62)
Contract #06223431
Totals853370.480.00857518.0399.9

CountyBEXAR
HighwayFM 1516
FromFM 78
ToIH 10
CSJ1477-01-043
Proj IDF 2023(874)
Work TypeWIDEN NON-FREEWAY
 
2.87754388108.631081675.721.9
CountyBEXAR
HighwayFM 1516
FromFM 78
ToIH 10
CSJ1477-01-044
Proj IDSTP 1902(103)
Work TypeRIGHT OF WAY
 
2.87714553433.600.000.0
Work Order09-07-23
Work Began01-03-24
Work Completed
Time Computed12-06-23
Contract Working Days973
Addl Days Granted0
Working Days Charged19
Percent Time Used1
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1477-01-043
A K FUQUAY CONSTRUCTION (0.57)
A BROTHERS MILLING, LLC (0.52)
EGGEMEYER LAND CLEARING, LLC (0.13)
DC CIVIL CONSTRUCTION, LLC (11.66)
DEPENDABLE FENCE (0.68)
D&G ENERGY CORPORATION (2.29)
S&S BRIDGE PAINTING (0.07)
BENTON-GEORGIA, LLC (2.37)
ROADWAY SPECIALTIES, INC. (0.26)
TRP CONSTRUCTION GROUP, LLC (0.96)
Contract #08233002
Totals68941542.23434053.391081675.721.5

CountyATASCOSA
HighwayFM 1333
FromSH 173
ToCOUNTY ROAD 310
CSJ1740-03-019
Proj IDSTP 2023(525)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.9934025335.992516920.4162.5
Work Order05-05-23
Work Began07-24-23
Work Completed
Time Computed08-03-23
Contract Working Days109
Addl Days Granted15
Working Days Charged115
Percent Time Used92
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1740-03-019
WEST TEXAS ROCK RESOURCES, LLC (0.11)
FLASHER EQUIPMENT COMPANY (2.41)
A K FUQUAY CONSTRUCTION (2.97)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.21)
Contract #03233215
Totals4025335.99211247.852516920.4162.5

CountyBEXAR
HighwayFM 2790
FromFISCHER RD.
ToIH 410
CSJ1741-02-036
Proj IDF 2023(120)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.5715905629.845630045.4495.3
CountyBEXAR
HighwayFM 2790
FromFISCHER RD.
ToIH 410
CSJ1741-02-038
Proj IDROW 1741-02-038
Work TypeRIGHT OF WAY
 
1.5711787097.601672227.9093.5
Work Order10-11-22
Work Began11-10-22
Work Completed
Time Computed11-10-22
Contract Working Days255
Addl Days Granted10
Working Days Charged252
Percent Time Used95
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1741-02-036
EGGEMEYER LAND CLEARING, LLC (0.29)
FLASHER EQUIPMENT COMPANY (2.17)
LONE STAR EROSION CONTROL (2.22)
DUSTROL, INC. (1.77)
TEXAS MATERIALS GROUP, INC. (26.97)
THE LEVY COMPANY, INC. (0.11)
Contract #09223039
Totals7692727.44905473.897302273.3494.9

CountyKENDALL
HighwayRM 1376
FromRM 473
To0.8 MI SOUTH OF UPPER SISTERDALE RD
CSJ1899-02-021
Proj IDSTP 2023(956)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.0035653830.46417655.617.3
Work Order08-03-23
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days160
Addl Days Granted8
Working Days Charged10
Percent Time Used5
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1899-02-021
STX CIVIL (10.67)
A K FUQUAY CONSTRUCTION (5.79)
ROADWAY SPECIALTIES, INC. (2.25)
FLASHER EQUIPMENT COMPANY (1.72)
THE LEVY COMPANY, INC. (0.21)
Contract #06233419
Totals5653830.46417655.61417655.617.3

CountyBEXAR
HighwaySL 1604
FromSH 16
ToIH 10
CSJ2452-02-083
Proj IDF 2021(488)
Work TypeWIDEN FREEWAY
 
5.333144233735.21106036189.1973.5
CountyBEXAR
HighwaySL 1604
FromSH 16
ToIH 10
CSJ2452-02-132
Proj IDROW 2452-2-132
Work TypeRIGHT OF WAY
 
5.3333839369.213398231.7788.5
Work Order05-04-21
Work Began05-10-21
Work Completed
Time Computed05-10-21
Contract Working Days962
Addl Days Granted0
Working Days Charged853
Percent Time Used88
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2452-02-083
THE LEVY COMPANY, INC. (6.16)
EGGEMEYER LAND CLEARING, LLC (0.05)
FLASHER EQUIPMENT COMPANY (0.65)
DEPENDABLE FENCE (0.72)
ROYAL REBAR (2.33)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (0.17)
BADECO, INC (2.37)
LONE STAR EROSION CONTROL (0.18)
Z & L CONCRETE CONTRACTORS, INC. (4.72)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.19)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.10)
ROADWAY CONSTRUCTION, LLC (3.23)
ROADWAY SPECIALTIES, INC. (0.13)
TEXAS HIGHWAY WALLS (7.64)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.12)
SCOTT DERR PAINTING CO, LLC (0.05)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.00)
LIGHT IT UP ELECTRIC (0.00)
A. H. BECK FOUNDATION CO., INC. (0.00)
DAKOTA UTILITY CONTRACTORS, INC. (0.00)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (0.16)
JT UNDERGROUND AND UTILITY CONSTRUCTION INC (0.00)
FIBERTEL, LLC (0.00)
STRUCTURAL INTEGRITY GROUP LLC (0.04)
HARRIS HARDROCK TRENCHING, L.L.C. (0.00)
SUPERIOR GROUTING SERVICES, INC. (0.00)
MPR SERVICES (0.08)
SK CONCRETE SERVICES LLC (0.23)
SWEEPING CORPORATION OF AMERICA, LLC (0.02)
Contract #04213001
Totals148073104.422704347.83109434420.9673.9

CountyBEXAR
HighwaySL 1604
FromAT FM 2696- BLANCO RD
To.
CSJ2452-02-117
Proj IDF 2021(615)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
0.50036911674.6613980930.6537.8
CountyBEXAR
HighwaySL 1604
FromAT FM 2696- BLANCO RD
To.
CSJ2452-02-121
Proj IDROW 2452-2-121
Work TypeRIGHT OF WAY
 
0.5006764542.912668133.6039.4
CountyBEXAR
HighwaySL 1604
FromIH 10
ToUS 281
CSJ2452-02-128
Proj IDSTP 2021(616)MM
Work TypeWIDEN FREEWAY
 
8.044195816872.89114461839.5258.4
CountyBEXAR
HighwaySL 1604
FromIH 10
ToUS 281
CSJ2452-02-131
Proj IDROW 2452-2-131
Work TypeRIGHT OF WAY
 
8.0444448754.714647599.2099.9
Work Order08-02-21
Work Began11-01-21
Work Completed
Time Computed11-01-21
Contract Working Days1,135
Addl Days Granted0
Working Days Charged680
Percent Time Used59
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 2452-02-117
ERFURT BLASTING COMPANY, INC. (0.62)
ADCOCK 4 INVESTMENTS, LLC (2.51)
WILLIAMS ROAD, LLC (0.08)
GUERRA UNDERGROUND LLC (1.92)
TEXAS MATERIALS GROUP, INC. (12.89)
TRP CONSTRUCTION GROUP, LLC (0.63)
THE LEVY COMPANY, INC. (4.85)
BADECO, INC (2.35)
TORO BRAVO CONSTRUCTION, LLC (3.00)
GEOSOURCE, INC. (0.03)
LIGHT IT UP ELECTRIC (0.00)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (1.21)
OSCAR ORDUNO, INC. (4.56)
LONE STAR EROSION CONTROL (0.08)
SUPERIOR TRAFFIC SERVICES, LLC (0.14)
ROADWAY SPECIALTIES, INC. (0.85)
PANTHER CREEK TRANSPORTATION, INC. (1.16)
HOSS LAND SERVICES LLC (0.00)
BEAIRD DRILLING (1.95)
AUSTIN BRIDGE & ROAD SERVICES, LP (0.00)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.19)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.01)
DAKOTA UTILITY CONTRACTORS, INC. (0.04)
ZAMCO TRUCKING, LLC (0.26)
TEXSON TRANSPORT (0.02)
M&M DIRECTIONAL DRILLING, LLC (0.01)
SUPERIOR PUMP SOLUTIONS LLC (0.02)
HARRIS HARDROCK TRENCHING, L.L.C. (0.00)
KOPPL PIPELINE SERVICES, INC (0.00)
PUMPCO, INC. (0.00)
TEXAS CUTTING & CORING GP, INC. (0.01)
TDW (US), INC. (0.00)
BOSWELL & SON CONSTRUCTION SERVICES (0.84)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.01)
MTAM CORPORATION (0.17)
J.O.A. TRADES LLC (0.10)
STAR CONCRETE PUMPING (0.15)
BOBCAT TRUCKING, INC. (0.59)
PRIMATE CONSTRUCTION, LP (0.09)
COMAL AGGREGATE LLC (0.09)
NATIONAL RAILROAD SAFETY SERVICES, INC. (0.07)
CHOCTAW ERECTORS, INC. (0.18)
CURB PLANET INC. (0.00)
VALOR CRANE & EQUIPMENT LLC (0.10)
SOUTH TEXAS PAINTING CO. (0.29)
Contract #06213001
Totals243941845.175375288.57135758502.9755.6

CountyBEXAR
HighwaySL 1604
From2.0 MILES WEST OF US 281
ToUS 281
CSJ2452-02-130
Proj IDF 2023(958)
Work TypeWIDEN FREEWAY
 
57353322.111236476.922.1
CountyBEXAR
HighwaySL 1604
From2.0 MILES WEST OF US 281
ToUS 281
CSJ2452-02-133
Proj IDROW 2452-2-133
Work TypeRIGHT OF WAY
 
500286.650.000.0
CountyBEXAR
HighwaySL 1604
FromUS 281
ToREDLAND ROAD
CSJ2452-03-113
Proj IDBR 2024(530)
Work TypeWIDEN FREEWAY
 
1.585134747440.251606225.641.1
CountyBEXAR
HighwaySL 1604
FromUS 281
ToREDLAND ROAD
CSJ2452-03-129
Proj ID
Work TypeRIGHT OF WAY
 
1.585338973.760.000.0
Work Order11-30-23
Work Began00-00-00
Work Completed
Time Computed02-28-24
Contract Working Days1,009
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PULICE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2452-02-130
BLUE CHIP SERVICES, LLC (0.07)
THE LEVY COMPANY, INC. (4.74)
AFECOM, INC (0.84)
BEAIRD DRILLING (1.23)
DEPENDABLE FENCE (0.74)
A&J REBAR LLC (0.42)
SK CONCRETE SERVICES LLC (0.01)
PERFORMANCE EQUIPMENT SERVICE (0.58)
Contract #10233202
Totals192940022.772842702.562842702.561.4

CountyKENDALL
HighwayFM 1621
FromIH 10 WB FR
ToN FRONT ST
CSJ2519-01-007
Proj IDSSW 2519-1-7
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.8957314033.366113566.4184.5
Work Order06-30-22
Work Began10-03-22
Work Completed
Time Computed07-30-22
Contract Working Days207
Addl Days Granted13
Working Days Charged281
Percent Time Used127
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2519-01-007
CAPITAL EXCAVATION COMPANY (30.27)
FLASHER EQUIPMENT COMPANY (4.03)
PRESIDIO CONTRACTING, LLC (2.91)
LONE STAR EROSION CONTROL (2.61)
DIIBS SPECIALISTS, LLC (2.49)
EGGEMEYER LAND CLEARING, LLC (0.88)
TEXAS CUTTING & CORING GP, INC. (0.00)
Contract #06223010
Totals7314033.36211233.896113566.4184.5

CountyMEDINA
HighwayFM 2200
FromAT FRANCISCO PEREZ CREEK
To.
CSJ2520-01-015
Proj IDBR 2023(527)
Work TypeBRIDGE REPLACEMENT
 
0.2111196252.75434952.7636.3
CountyMEDINA
HighwayFM 2200
FromVIRGINIA DR
ToCR 764 (HUNTZER LN.)
CSJ2520-01-016
Proj IDSTP 2023(528)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.2005010276.103791524.5475.6
Work Order04-19-23
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days309
Addl Days Granted3
Working Days Charged148
Percent Time Used47
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2520-01-015
D&G ENERGY CORPORATION (0.78)
LONE STAR EROSION CONTROL (5.25)
TEXAS SHAFTS, INC. (1.64)
FLASHER EQUIPMENT COMPANY (2.22)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.32)
TORO BRAVO CONSTRUCTION, LLC (0.16)
Contract #03233218
Totals6206528.85266605.304226477.3068.0

CountyMEDINA
HighwayFM 2676
From1.52 MI E. OF SH 173
ToAT HONDO CREEK
CSJ2649-01-035
Proj IDBR 2023(384)
Work TypeBRIDGE REPLACEMENT
 
0.1754254249.681699294.4739.9
Work Order01-06-23
Work Began06-05-23
Work Completed
Time Computed03-07-23
Contract Working Days284
Addl Days Granted0
Working Days Charged127
Percent Time Used44
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2649-01-035
DIIBS SPECIALISTS, LLC (1.51)
TORO BRAVO CONSTRUCTION, LLC (1.26)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.14)
GREGORY PILE DRIVING, INC. (7.26)
FLASHER EQUIPMENT COMPANY (0.51)
TEXAS MATERIALS GROUP, INC. (4.57)
FARR FOUNDATION, INC. (7.32)
AAA DRILLING FOUNDATION COMPANY, INC. (5.42)
Contract #12223232
Totals4254249.68156394.211699294.4739.9

CountyBEXAR
HighwayFM 2696
From0.1 MI NORTH OF CALICO LANDING
ToWILDERNESS OAK
CSJ2708-01-033
Proj IDSTP 2024(534)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.367778577.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed03-03-24
Contract Working Days89
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2708-01-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243035
Totals778577.000.000.000.0

CountyATASCOSA
HighwayFM 2924
FromFM 791
ToFM 99
CSJ2975-01-009
Proj IDF 2022(047)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.1347308202.927293243.2699.7
Work Order10-20-21
Work Began01-17-22
Work Completed
Time Computed11-19-21
Contract Working Days456
Addl Days Granted0
Working Days Charged400
Percent Time Used87
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2975-01-009
TERRA CONSTRUCTION LLC (5.94)
LONE STAR EROSION CONTROL (1.77)
INTERSTATE BARRICADES & MARKINGS, INC. (1.82)
HIGHWAY BARRICADES AND SERVICES, LLC (0.31)
BARRICADES UNLIMITED (0.28)
WEST TEXAS ROCK RESOURCES, LLC (0.09)
TEXAS GUARDRAIL CONTRACTORS LLC (0.47)
DIIBS SPECIALISTS, LLC (0.64)
EGGEMEYER LAND CLEARING, LLC (0.40)
Contract #09213027
Totals7308202.926487.867293243.2699.7

CountyKENDALL
HighwayFM 3351
FromSH 46
ToKENDALL/COMAL COUNTY LINE
CSJ3212-04-009
Proj IDF 2023(677)
Work TypeOVERLAY
 
3.680992293.83235739.2523.7
CountyKENDALL
HighwayFM 3351
FromKENDALL WOODS DR
To0.2 MI SOUTH OF SH 46
CSJ3212-04-010
Proj IDSTP 2023(678)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.8701803552.63863490.1947.8
CountyKENDALL
HighwayFM 3351
From0.2 MI NORTH OF GUTHRIE RD
ToKENDALL/COMAL COUNTY LINE
CSJ3212-04-012
Proj IDSTP 2023(678)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.5651221952.59667843.4454.6
CountyCOMAL
HighwayFM 3351
FromKENDALL/COMAL COUNTY LINE
ToBEXAR/COMAL COUNTY LINE
CSJ3212-05-015
Proj IDF 2023(677)
Work TypeOVERLAY
 
3.1462242729.50245974.5010.9
Work Order06-14-23
Work Began09-12-23
Work Completed
Time Computed09-12-23
Contract Working Days213
Addl Days Granted0
Working Days Charged103
Percent Time Used48
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3212-04-009
TERRA CONSTRUCTION LLC (7.83)
FLASHER EQUIPMENT COMPANY (0.91)
GEOSOURCE, INC. (0.53)
TRP CONSTRUCTION GROUP, LLC (5.66)
EGGEMEYER LAND CLEARING, LLC (0.87)
RPV CONSTRUCTION, LLC (1.20)
A K FUQUAY CONSTRUCTION (1.27)
GREYCO CONSTRUCTION, LLC (4.57)
Contract #05233211
Totals6260528.55229507.252013047.3832.1

CountyCOMAL
HighwayFM 3351
FromAT CIBOLO CREEK
To.
CSJ3212-05-013
Proj IDSTP 2024(729)MM
Work TypeBRIDGE REPLACEMENT
 
12162006.550.000.0
CountyCOMAL
HighwayFM 3351
FromAT CIBOLO CREEK
To.
CSJ3212-05-017
Proj IDF 2022(741)
Work TypeUTILITY ADJUSTMENTS
 
396071.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-06-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days527
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3212-05-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243205
Totals12558077.550.000.000.0