Monthly State Let Construction Report For Odessa District As Of May 10, 2024 Page 3 Of 4

Last Update: Friday, May 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWINKLER
HighwaySH 302
FromLOVING COUNTY LINE
To2700 FEET WEST OF SH 115
CSJ0479-04-038
Proj IDSTP 2B20(250)
Work TypeREHABILITATION OF EXISTING ROAD
 
12.65443485104.9028620523.2566.5
Work Order10-28-20
Work Began03-08-21
Work Completed
Time Computed01-26-21
Contract Working Days515
Addl Days Granted87
Working Days Charged721
Percent Time Used119
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0479-04-038
DTM TRUCKING, INC. (3.50)
WILLIS ELECTRIC CO., LP (0.41)
FLASHER EQUIPMENT COMPANY (1.01)
HOOT JOHNSON CONSTRUCTION, INC. (7.56)
FLAT LINE, INC. (0.22)
SIBONEY CONTRACTING CO. (12.62)
WILD WEST TRUCKING, LLC (1.91)
WILD WEST TRUCKING, LLC (3.28)
HJC FARMS, INC. (0.27)
BARRICADES UNLIMITED (1.06)
TRP CONSTRUCTION GROUP, LLC (1.06)
PEYSON TRANSPORT, LLC (3.37)
BIG R TRUCKING TX LLC (1.14)
Contract #09203003
Totals43485104.901543439.5128620523.2566.5

CountyMARTIN
HighwaySH 176
FromAT FM 3033
To.
CSJ0548-02-041
Proj IDSTP 2023(759)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2555865.45812647.6731.7
CountyREEVES
HighwayFM 2119
FromAT BI 20-B
To.
CSJ1183-01-015
Proj IDSTP 2023(760)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2057938.881112.000.0
Work Order12-06-23
Work Began04-02-24
Work Completed
Time Computed03-06-24
Contract Working Days191
Addl Days Granted0
Working Days Charged19
Percent Time Used9
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0548-02-041
JVH4 SERVICES, LLC (0.19)
A BROTHERS MILLING, LLC (0.83)
WILLIS ELECTRIC CO., LP (14.73)
DOUBLE A CONTRACTING, L.P. (1.53)
PROFESSIONAL TRAFFIC CONTROL LLC (0.14)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.50)
KIMRAD TRANSPORT (0.09)
PEYSON TRANSPORT, LLC (2.61)
BARRICADES UNLIMITED (0.18)
Contract #06233243
Totals4613804.33653219.41813759.6717.6

CountyMARTIN
HighwaySH 176
FromAT FM 829
To.
CSJ0548-02-043
Proj IDC 548-2-43
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
5880107.874970312.1684.5
Work Order08-03-23
Work Began11-06-23
Work Completed
Time Computed11-02-23
Contract Working Days142
Addl Days Granted0
Working Days Charged103
Percent Time Used72
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0548-02-043
CONTRACTORS SERVICE, LTD. (0.84)
ALTEX LANDSCAPE CONSTRUCTION, INC. (1.16)
DK CONTRACTING, LLC (0.64)
DOUBLE A CONTRACTING, L.P. (1.33)
DUSTROL, INC. (1.95)
R.E.B.D. TRUCKING LLC (0.00)
WILLIS ELECTRIC CO., LP (2.26)
W. S. CONSTRUCTION COMPANY (3.99)
Contract #06233426
Totals5880107.871124698.684970312.1684.5

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-205
Proj IDC 906-00-205
Work TypeBRIDGE MAINTENANCE
 
1677753.001984019.8999.9
Work Order04-05-23
Work Began07-17-23
Work Completed
Time Computed07-04-23
Contract Working Days260
Addl Days Granted0
Working Days Charged186
Percent Time Used71
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-205
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233216
Totals1677753.00548678.831984019.8999.9

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-217
Proj IDC 906-00-217
Work TypeTRAFFIC CONTROL DEVICES
 
3409957.444171893.1099.9
Work Order04-19-23
Work Began09-07-23
Work Completed
Time Computed09-07-23
Contract Working Days134
Addl Days Granted0
Working Days Charged108
Percent Time Used80
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-217
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03233015
Totals3409957.440.004171893.1099.9

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-235
Proj IDC 906-00-235
Work TypeBRIDGE MAINTENANCE
 
1854643.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days256
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-235
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243023
Totals1854643.000.000.000.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-236
Proj IDC 906-00-236
Work TypeTRAFFIC CONTROL DEVICES
 
2462826.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-236
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05243230
Totals2462826.300.000.000.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-238
Proj IDC 906-00-238
Work TypeTRAFFIC CONTROL DEVICES
 
3391078.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days69
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-238
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243027
Totals3391078.240.000.000.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-239
Proj IDC 906-00-239
Work TypeTRAFFIC CONTROL DEVICES
 
705606.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days21
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MIJELUM, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-239
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243217
Totals705606.100.000.000.0

CountyECTOR
HighwayVA
FromUS 67/FM 1776
ToSH 349
CSJ0906-00-255
Proj IDSTP 2023(592)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3569917.502918662.5881.7
Work Order07-12-23
Work Began09-18-23
Work Completed
Time Computed09-18-23
Contract Working Days253
Addl Days Granted0
Working Days Charged132
Percent Time Used52
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-255
FC TRAFFIC CONTROL, INC. (1.36)
APOLLO CONSTRUCTORS, INC. (45.85)
Contract #06233013
Totals3569917.503500.002918662.5881.7

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-257
Proj IDC 906-00-257
Work TypeTRAFFIC CONTROL DEVICES
 
850900.00663706.0078.0
Work Order05-10-23
Work Began08-21-23
Work Completed
Time Computed09-08-23
Contract Working Days106
Addl Days Granted0
Working Days Charged42
Percent Time Used39
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-257
FC TRAFFIC CONTROL, INC. (0.24)
MICA CORPORATION (2.71)
Contract #04233035
Totals850900.000.00663706.0078.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-267
Proj IDC 906-00-267
Work TypeTRAFFIC CONTROL DEVICES
 
1139465.00861730.9075.6
Work Order05-17-23
Work Began09-11-23
Work Completed
Time Computed09-11-23
Contract Working Days79
Addl Days Granted7
Working Days Charged56
Percent Time Used65
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-267
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04233224
Totals1139465.00264391.95861730.9075.6

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-268
Proj IDC 906-00-268
Work TypeTRAFFIC CONTROL DEVICES
 
5500864.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-268
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12233210
Totals5500864.550.000.000.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-282
Proj IDBR 2024(781)
Work TypeBRIDGE MAINTENANCE
 
2165724.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-03-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days330
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-282
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243215
Totals2165724.000.000.000.0

CountyMIDLAND
HighwayCS
FromAT SCHARBAUER DRAW
To.
CSJ0906-32-050
Proj IDBR 2B23(292)
Work TypeBRIDGE REPLACEMENT
 
1625626.500.000.0
CountyMIDLAND
HighwayCS
FromAT MIDLAND DRAW
To.
CSJ0906-32-058
Proj IDBR 2B23(292)
Work TypeBRIDGE REPLACEMENT
 
910623.500.000.0
CountyMIDLAND
HighwayCS
FromAT MIDLAND DRAW
To.
CSJ0906-32-061
Proj IDBR 2B23(292)
Work TypeBRIDGE REPLACEMENT
 
1360388.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-18-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days174
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0906-32-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243024
Totals3896638.500.000.000.0

CountyMIDLAND
HighwayCS
FromBELMONT ST
To.
CSJ0906-32-060
Proj IDSTP 2B23(013)HESG
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
496352.870.000.0
Work Order09-13-23
Work Began00-00-00
Work Completed
Time Computed12-13-23
Contract Working Days91
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-32-060
BARRICADES UNLIMITED (1.05)
KING & GEORGE, LLC (1.84)
Contract #08233263
Totals496352.870.000.000.0

CountyMIDLAND
HighwayCS
FromA ST
ToC ST
CSJ0906-32-064
Proj IDSTP 2024(995)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1982263.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days289
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0906-32-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05243035
Totals1982263.220.000.000.0

CountyMIDLAND
HighwaySL 250
FromAT NORTH A STREET
To.
CSJ1188-02-118
Proj IDC 1188-2-118
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1609466.840.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1188-02-118
WILLIS ELECTRIC CO., LP (0.52)
BARRICADES UNLIMITED (0.89)
DK CONTRACTING, LLC (0.92)
TRP CONSTRUCTION GROUP, LLC (2.91)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.59)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.52)
Contract #01243231
Totals1609466.840.000.000.0

CountyWINKLER
HighwayFM 1232
FromSH 302
ToSH 115
CSJ1371-01-023
Proj IDF 2023(150)
Work TypeREHABILITATION OF EXISTING ROAD
 
19548504.6498800.000.5
Work Order11-16-23
Work Began00-00-00
Work Completed
Time Computed02-15-24
Contract Working Days390
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1371-01-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10233203
Totals19548504.640.0098800.000.5

CountyREEVES
HighwayFM 1450
From8 MILES EAST OF US285
ToPECOS COUNTY LINE
CSJ1639-01-016
Proj IDF 2023(524)
Work TypeREHABILITATION OF EXISTING ROAD
 
17.56181336501.6428530865.5035.0
Work Order04-13-23
Work Began09-05-23
Work Completed
Time Computed07-13-23
Contract Working Days420
Addl Days Granted139
Working Days Charged151
Percent Time Used27
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1639-01-016
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.17)
WILLIS ELECTRIC CO., LP (0.47)
DOUBLE A CONTRACTING, L.P. (0.76)
FC TRAFFIC CONTROL, INC. (0.16)
MARCOM"S MOWING SERVICE, LLC (0.17)
A.L. CONSTRUCTION LLC (1.00)
WILD WEST TRUCKING, LLC (1.61)
A BROTHERS MILLING, LLC (0.18)
Contract #03233002
Totals81336501.642681784.6328530865.5035.0

page 1 | page 2 | page 3 | page 4