Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | WINKLER |
Highway | SH 302 |
From | LOVING COUNTY LINE |
To | 2700 FEET WEST OF SH 115 |
CSJ | 0479-04-038 |
Proj ID | STP 2B20(250) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 12.654 | 43485104.90 | | 28620523.25 | 66.5 |
Work Order | 10-28-20 |
Work Began | 03-08-21 |
Work Completed | |
Time Computed | 01-26-21 |
Contract Working Days | 515 |
Addl Days Granted | 87 |
Working Days Charged | 721 |
Percent Time Used | 119 |
Contractor(s) |
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0479-04-038 DTM TRUCKING, INC. (3.50) WILLIS ELECTRIC CO., LP (0.41) FLASHER EQUIPMENT COMPANY (1.01) HOOT JOHNSON CONSTRUCTION, INC. (7.56) FLAT LINE, INC. (0.22) SIBONEY CONTRACTING CO. (12.62) WILD WEST TRUCKING, LLC (1.91) WILD WEST TRUCKING, LLC (3.28) HJC FARMS, INC. (0.27) BARRICADES UNLIMITED (1.06) TRP CONSTRUCTION GROUP, LLC (1.06) PEYSON TRANSPORT, LLC (3.37) BIG R TRUCKING TX LLC (1.14)
|
Contract # | 09203003 |
| Totals | 43485104.90 | 1543439.51 | 28620523.25 | 66.5 |
|
County | MARTIN |
Highway | SH 176 |
From | AT FM 3033 |
To | . |
CSJ | 0548-02-041 |
Proj ID | STP 2023(759)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 2555865.45 | | 812647.67 | 31.7 |
County | REEVES |
Highway | FM 2119 |
From | AT BI 20-B |
To | . |
CSJ | 1183-01-015 |
Proj ID | STP 2023(760)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 2057938.88 | | 1112.00 | 0.0 |
Work Order | 12-06-23 |
Work Began | 04-02-24 |
Work Completed | |
Time Computed | 03-06-24 |
Contract Working Days | 191 |
Addl Days Granted | 0 |
Working Days Charged | 19 |
Percent Time Used | 9 |
Contractor(s) |
RAGLE CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0548-02-041 JVH4 SERVICES, LLC (0.19) A BROTHERS MILLING, LLC (0.83) WILLIS ELECTRIC CO., LP (14.73) DOUBLE A CONTRACTING, L.P. (1.53) PROFESSIONAL TRAFFIC CONTROL LLC (0.14) KING GEORGE TRAFFIC SOLUTIONS LLC (0.50) KIMRAD TRANSPORT (0.09) PEYSON TRANSPORT, LLC (2.61) BARRICADES UNLIMITED (0.18)
|
Contract # | 06233243 |
| Totals | 4613804.33 | 653219.41 | 813759.67 | 17.6 |
|
County | MARTIN |
Highway | SH 176 |
From | AT FM 829 |
To | . |
CSJ | 0548-02-043 |
Proj ID | C 548-2-43 |
Work Type | INTERSECTION & OPERATIONAL IMPRV |
|
| | 5880107.87 | | 4970312.16 | 84.5 |
Work Order | 08-03-23 |
Work Began | 11-06-23 |
Work Completed | |
Time Computed | 11-02-23 |
Contract Working Days | 142 |
Addl Days Granted | 0 |
Working Days Charged | 103 |
Percent Time Used | 72 |
Contractor(s) |
JONES BROS. DIRT & PAVING CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0548-02-043 CONTRACTORS SERVICE, LTD. (0.84) ALTEX LANDSCAPE CONSTRUCTION, INC. (1.16) DK CONTRACTING, LLC (0.64) DOUBLE A CONTRACTING, L.P. (1.33) DUSTROL, INC. (1.95) R.E.B.D. TRUCKING LLC (0.00) WILLIS ELECTRIC CO., LP (2.26) W. S. CONSTRUCTION COMPANY (3.99)
|
Contract # | 06233426 |
| Totals | 5880107.87 | 1124698.68 | 4970312.16 | 84.5 |
|
County | ECTOR |
Highway | VA |
From | DISTRICTWIDE |
To | . |
CSJ | 0906-00-205 |
Proj ID | C 906-00-205 |
Work Type | BRIDGE MAINTENANCE |
|
| | 1677753.00 | | 1984019.89 | 99.9 |
Work Order | 04-05-23 |
Work Began | 07-17-23 |
Work Completed | |
Time Computed | 07-04-23 |
Contract Working Days | 260 |
Addl Days Granted | 0 |
Working Days Charged | 186 |
Percent Time Used | 71 |
Contractor(s) |
SCOTT TUCKER CONSTRUCTION COMPANY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-205 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01233216 |
| Totals | 1677753.00 | 548678.83 | 1984019.89 | 99.9 |
|
County | ECTOR |
Highway | VA |
From | DISTRICTWIDE |
To | . |
CSJ | 0906-00-217 |
Proj ID | C 906-00-217 |
Work Type | TRAFFIC CONTROL DEVICES |
|
| | 3409957.44 | | 4171893.10 | 99.9 |
Work Order | 04-19-23 |
Work Began | 09-07-23 |
Work Completed | |
Time Computed | 09-07-23 |
Contract Working Days | 134 |
Addl Days Granted | 0 |
Working Days Charged | 108 |
Percent Time Used | 80 |
Contractor(s) |
L&L COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-217 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03233015 |
| Totals | 3409957.44 | 0.00 | 4171893.10 | 99.9 |
|
County | ECTOR |
Highway | VA |
From | DISTRICTWIDE |
To | . |
CSJ | 0906-00-235 |
Proj ID | C 906-00-235 |
Work Type | BRIDGE MAINTENANCE |
|
| | 1854643.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 256 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
RELMCO, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-235 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04243023 |
| Totals | 1854643.00 | 0.00 | 0.00 | 0.0 |
|
County | ECTOR |
Highway | VA |
From | DISTRICTWIDE |
To | . |
CSJ | 0906-00-236 |
Proj ID | C 906-00-236 |
Work Type | TRAFFIC CONTROL DEVICES |
|
| | 2462826.30 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 100 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
WILLIS ELECTRIC CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-236 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05243230 |
| Totals | 2462826.30 | 0.00 | 0.00 | 0.0 |
|
County | ECTOR |
Highway | VA |
From | DISTRICTWIDE |
To | . |
CSJ | 0906-00-238 |
Proj ID | C 906-00-238 |
Work Type | TRAFFIC CONTROL DEVICES |
|
| | 3391078.24 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 69 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
DOUBLE A CONTRACTING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-238 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03243027 |
| Totals | 3391078.24 | 0.00 | 0.00 | 0.0 |
|
County | ECTOR |
Highway | VA |
From | DISTRICTWIDE |
To | . |
CSJ | 0906-00-239 |
Proj ID | C 906-00-239 |
Work Type | TRAFFIC CONTROL DEVICES |
|
| | 705606.10 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 21 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MIJELUM, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-239 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03243217 |
| Totals | 705606.10 | 0.00 | 0.00 | 0.0 |
|
County | ECTOR |
Highway | VA |
From | US 67/FM 1776 |
To | SH 349 |
CSJ | 0906-00-255 |
Proj ID | STP 2023(592)VRU |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 3569917.50 | | 2918662.58 | 81.7 |
Work Order | 07-12-23 |
Work Began | 09-18-23 |
Work Completed | |
Time Computed | 09-18-23 |
Contract Working Days | 253 |
Addl Days Granted | 0 |
Working Days Charged | 132 |
Percent Time Used | 52 |
Contractor(s) |
WILLIS ELECTRIC CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-255 FC TRAFFIC CONTROL, INC. (1.36) APOLLO CONSTRUCTORS, INC. (45.85)
|
Contract # | 06233013 |
| Totals | 3569917.50 | 3500.00 | 2918662.58 | 81.7 |
|
County | ECTOR |
Highway | VA |
From | DISTRICTWIDE |
To | . |
CSJ | 0906-00-257 |
Proj ID | C 906-00-257 |
Work Type | TRAFFIC CONTROL DEVICES |
|
| | 850900.00 | | 663706.00 | 78.0 |
Work Order | 05-10-23 |
Work Began | 08-21-23 |
Work Completed | |
Time Computed | 09-08-23 |
Contract Working Days | 106 |
Addl Days Granted | 0 |
Working Days Charged | 42 |
Percent Time Used | 39 |
Contractor(s) |
WILLIS ELECTRIC CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-257 FC TRAFFIC CONTROL, INC. (0.24) MICA CORPORATION (2.71)
|
Contract # | 04233035 |
| Totals | 850900.00 | 0.00 | 663706.00 | 78.0 |
|
County | ECTOR |
Highway | VA |
From | DISTRICTWIDE |
To | . |
CSJ | 0906-00-267 |
Proj ID | C 906-00-267 |
Work Type | TRAFFIC CONTROL DEVICES |
|
| | 1139465.00 | | 861730.90 | 75.6 |
Work Order | 05-17-23 |
Work Began | 09-11-23 |
Work Completed | |
Time Computed | 09-11-23 |
Contract Working Days | 79 |
Addl Days Granted | 7 |
Working Days Charged | 56 |
Percent Time Used | 65 |
Contractor(s) |
HJC FARMS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-267 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04233224 |
| Totals | 1139465.00 | 264391.95 | 861730.90 | 75.6 |
|
County | ECTOR |
Highway | VA |
From | DISTRICTWIDE |
To | . |
CSJ | 0906-00-268 |
Proj ID | C 906-00-268 |
Work Type | TRAFFIC CONTROL DEVICES |
|
| | 5500864.55 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 01-04-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MICA CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-268 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12233210 |
| Totals | 5500864.55 | 0.00 | 0.00 | 0.0 |
|
County | ECTOR |
Highway | VA |
From | DISTRICTWIDE |
To | . |
CSJ | 0906-00-282 |
Proj ID | BR 2024(781) |
Work Type | BRIDGE MAINTENANCE |
|
| | 2165724.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 05-03-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 330 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-282 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03243215 |
| Totals | 2165724.00 | 0.00 | 0.00 | 0.0 |
|
County | MIDLAND |
Highway | CS |
From | AT SCHARBAUER DRAW |
To | . |
CSJ | 0906-32-050 |
Proj ID | BR 2B23(292) |
Work Type | BRIDGE REPLACEMENT |
|
| | 1625626.50 | | 0.00 | 0.0 |
County | MIDLAND |
Highway | CS |
From | AT MIDLAND DRAW |
To | . |
CSJ | 0906-32-058 |
Proj ID | BR 2B23(292) |
Work Type | BRIDGE REPLACEMENT |
|
| | 910623.50 | | 0.00 | 0.0 |
County | MIDLAND |
Highway | CS |
From | AT MIDLAND DRAW |
To | . |
CSJ | 0906-32-061 |
Proj ID | BR 2B23(292) |
Work Type | BRIDGE REPLACEMENT |
|
| | 1360388.50 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 04-18-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 174 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
DELGADO'S CONTRACTORS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0906-32-050 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01243024 |
| Totals | 3896638.50 | 0.00 | 0.00 | 0.0 |
|
County | MIDLAND |
Highway | CS |
From | BELMONT ST |
To | . |
CSJ | 0906-32-060 |
Proj ID | STP 2B23(013)HESG |
Work Type | INTERSECTION & OPERATIONAL IMPRV |
|
| | 496352.87 | | 0.00 | 0.0 |
Work Order | 09-13-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 12-13-23 |
Contract Working Days | 91 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TI-ZACK CONCRETE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0906-32-060 BARRICADES UNLIMITED (1.05) KING & GEORGE, LLC (1.84)
|
Contract # | 08233263 |
| Totals | 496352.87 | 0.00 | 0.00 | 0.0 |
|
County | MIDLAND |
Highway | CS |
From | A ST |
To | C ST |
CSJ | 0906-32-064 |
Proj ID | STP 2024(995)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1982263.22 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 289 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TI-ZACK CONCRETE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0906-32-064 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05243035 |
| Totals | 1982263.22 | 0.00 | 0.00 | 0.0 |
|
County | MIDLAND |
Highway | SL 250 |
From | AT NORTH A STREET |
To | . |
CSJ | 1188-02-118 |
Proj ID | C 1188-2-118 |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1609466.84 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 02-02-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 64 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
REECE ALBERT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1188-02-118 WILLIS ELECTRIC CO., LP (0.52) BARRICADES UNLIMITED (0.89) DK CONTRACTING, LLC (0.92) TRP CONSTRUCTION GROUP, LLC (2.91) K. L. DURHAM CONSTRUCTION, L.L.C. (0.59) ALTEX LANDSCAPE CONSTRUCTION, INC. (0.52)
|
Contract # | 01243231 |
| Totals | 1609466.84 | 0.00 | 0.00 | 0.0 |
|
County | WINKLER |
Highway | FM 1232 |
From | SH 302 |
To | SH 115 |
CSJ | 1371-01-023 |
Proj ID | F 2023(150) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| | 19548504.64 | | 98800.00 | 0.5 |
Work Order | 11-16-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 02-15-24 |
Contract Working Days | 390 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
JONES BROS. DIRT & PAVING CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1371-01-023 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10233203 |
| Totals | 19548504.64 | 0.00 | 98800.00 | 0.5 |
|
County | REEVES |
Highway | FM 1450 |
From | 8 MILES EAST OF US285 |
To | PECOS COUNTY LINE |
CSJ | 1639-01-016 |
Proj ID | F 2023(524) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 17.561 | 81336501.64 | | 28530865.50 | 35.0 |
Work Order | 04-13-23 |
Work Began | 09-05-23 |
Work Completed | |
Time Computed | 07-13-23 |
Contract Working Days | 420 |
Addl Days Granted | 139 |
Working Days Charged | 151 |
Percent Time Used | 27 |
Contractor(s) |
A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1639-01-016 TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.17) WILLIS ELECTRIC CO., LP (0.47) DOUBLE A CONTRACTING, L.P. (0.76) FC TRAFFIC CONTROL, INC. (0.16) MARCOM"S MOWING SERVICE, LLC (0.17) A.L. CONSTRUCTION LLC (1.00) WILD WEST TRUCKING, LLC (1.61) A BROTHERS MILLING, LLC (0.18)
|
Contract # | 03233002 |
| Totals | 81336501.64 | 2681784.63 | 28530865.50 | 35.0 |
|