Monthly State Let Construction Report For Odessa District As Of Jun 08, 2018 Page 2 Of 2

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyANDREWS
HighwaySH 176
FromNM STATE LINE
To3.3 MI NORTH OF FM 1967
CSJ0548-05-048
Proj IDSTP 1602(296)
Work TypeWIDEN SUBGRADE,PASSING LANES
 
11.61610506607.7411085508.5099.9
Work Order09-19-16
Work Began01-27-17
Work Completed
Time Computed12-19-16
Contract Working Days360
Addl Days Granted0
Working Days Charged281
Percent Time Used78
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0548-05-048
CONTRACTORS SERVICE COMPANY (0.45)
REECE CONSTRUCTION CO., INC. (2.58)
WILLIS ELECTRIC CO., LP (0.57)
DTM TRUCKING, INC. (4.56)
R.E.B. TRUCKING (2.52)
DOUBLE A CONTRACTING, L.P. (2.05)
Contract #07163206
Totals10506607.74794994.9311085508.5099.9

CountyANDREWS
HighwaySH 176
FromSH 115
To0.187 MI SOUTH OF FM 181
CSJ0548-05-049
Proj IDSTP 2018(680)
Work TypeRECONSTRUCT AND WIDEN
 
12.34811368797.761173026.3510.3
Work Order03-05-18
Work Began03-21-18
Work Completed
Time Computed03-21-18
Contract Working Days259
Addl Days Granted0
Working Days Charged50
Percent Time Used19
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0548-05-049
CONTRACTORS SERVICE COMPANY (1.08)
DESERT PAVING, INC. (2.94)
DK CONTRACTING, LLC (0.86)
DOUBLE A CONTRACTING, L.P. (2.46)
WOLFE CONSTRUCTION GROUP, INC. (0.36)
R.E.B. TRUCKING (6.12)
LPZ ENTERPRISES, LLC (1.92)
DTM TRUCKING, INC. (5.60)
Contract #02183003
Totals11368797.76594108.401173026.3510.3

CountyREEVES
HighwayPR 30B
FromWITHIN BALMORHEA STATE PARK
To.
CSJ0626-01-007
Proj IDC 626-1-7
Work TypePLANE,UNDERSEAL,2"FILL&PAV MARKINGS
 
1.000560740.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0626-01-007
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183210
Totals560740.000.000.000.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-159
Proj IDSTP 2018(620)
Work TypeNON-IH PAVEMENT MARKINGS
 
389.9381063374.410.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-18-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-159
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183231
Totals1063374.410.000.000.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE PAVEMENT MARKINGS
To.
CSJ0906-00-161
Proj IDSTP 2018(621)
Work TypeIH PAVEMENT MARKINGS_(2018)
 
1.0001029975.870.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days69
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-161
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183219
Totals1029975.870.000.000.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-169
Proj IDC 906-00-169
Work TypeNON-SITE SPECIFIC TRAFFIC SIGNALS
 
0.0013256207.302446586.7775.1
Work Order10-22-15
Work Began05-12-16
Work Completed
Time Computed02-20-16
Contract Working Days240
Addl Days Granted100
Working Days Charged208
Percent Time Used61
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-169
BARRICADES UNLIMITED (2.34)
DESERT PAVING, INC. (6.04)
MICA CORPORATION (6.28)
CONTRACTORS SERVICE COMPANY (2.19)
JONES BROS. DIRT & PAVING CONTRACTORS, INC. (1.68)
GESCH CONTRACTING, INC. (1.16)
WEST TEXAS CONTRACTORS (0.48)
JOSH FRANKLIN DRILLING, LLC (0.69)
BATTEN DRILLING, INC. (0.42)
FUSION COMMUNICATIONS, LLC (0.68)
Contract #07153220
Totals3256207.3079064.312446586.7775.1

CountyMIDLAND
HighwaySL 250
From0.7 MI W OF FAIRGROUNDS ROAD
To1.0 MI EAST OF FAIRGROUNDS RD.
CSJ1188-02-084
Proj IDC 1188-2-84
Work TypeCONSTRUCT O/P, MAINLANES, AND RAMPS
 
1.70012997699.175800248.6744.6
Work Order06-07-17
Work Began09-15-17
Work Completed
Time Computed09-06-17
Contract Working Days306
Addl Days Granted0
Working Days Charged154
Percent Time Used50
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1188-02-084
A BROTHERS MILLING, LLC (0.50)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.31)
CONTRACTORS SERVICE COMPANY (0.57)
COPPELL CONSTRUCTION CO., INC. (16.88)
DIIBS SPECIALISTS (0.79)
DOUBLE A CONTRACTING, L.P. (0.82)
W.S. CONSTRUCTION COMPANY (10.93)
WILLIS ELECTRIC CO., LP (7.99)
AARON CONCRETE CONTRACTORS, L.P. (0.63)
ATC CONSTRUCTION, LLC (0.57)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.31)
R.E.B. TRUCKING (0.02)
FUSION COMMUNICATIONS, LLC (0.38)
Contract #05173202
Totals12997699.17215914.315800248.6744.6

CountyMIDLAND
HighwaySH 158
FromI20 NFR
ToBS 158
CSJ1188-02-096
Proj IDNH 2017(475)
Work TypeFRONTAGE ROAD REHABILITATION
 
6.0135830487.106832146.9799.9
Work Order03-08-17
Work Began06-27-17
Work Completed
Time Computed06-07-17
Contract Working Days140
Addl Days Granted65
Working Days Charged197
Percent Time Used96
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1188-02-096
BOLER EQUIPMENT (0.48)
BARRICADES UNLIMITED (5.64)
DESERT PAVING, INC. (0.17)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (5.00)
TEX OP CONSTRUCTION, LP (1.91)
R.E.B. TRUCKING (2.75)
LPZ ENTERPRISES, LLC (7.54)
Contract #02173240
Totals5830487.10259958.036832146.9799.9

CountyREEVES
HighwayFM 1450
FromUS 285
To8.5 MILES EAST OF US 285
CSJ1639-01-014
Proj IDSTP 2018(879)
Work TypeROADWAY REHABILITATION
 
8.50010632822.070.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1639-01-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183245
Totals10632822.070.000.000.0

CountyMIDLAND
HighwayFM 1787
From0.3 MI EAST OF RM 1492
ToFM 1788
CSJ1717-02-022
Proj IDC 1717-2-22
Work TypeROADWAY RESTORATION
 
3.7513144999.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-08-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1717-02-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183024
Totals3144999.250.000.000.0

CountyWARD ETC
HighwayFM 1776 ETC
FromSH 18
ToPECOS RIVER
CSJ2262-01-016
Proj IDSTP 2018(090)
Work TypeSEAL COAT PROGRAM (2018)
 
264.3369505066.176880488.4072.3
Work Order02-05-18
Work Began04-30-18
Work Completed
Time Computed04-30-18
Contract Working Days75
Addl Days Granted0
Working Days Charged25
Percent Time Used33
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 2262-01-016
VIZCAINO, L.P. (10.79)
BARRICADES PLUS, LLC (1.46)
Contract #12173229
Totals9505066.174353830.476880488.4072.3

CountyREEVES
HighwayRM 652
FromAT SALT CREEK
To.
CSJ2451-03-015
Proj IDBR 2017(327)
Work TypeREPLACE BRIDGE 06-195-0-2451-03-01
 
0.2993993994.333810649.2495.6
Work Order04-24-17
Work Began07-27-17
Work Completed
Time Computed07-24-17
Contract Working Days173
Addl Days Granted6
Working Days Charged187
Percent Time Used104
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2451-03-015
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.43)
HJC FARMS, INC. (5.99)
BARRICADES UNLIMITED (0.77)
PENHALL COMPANY (0.22)
BOWMAN ENGINEERING & CONSULTING, INC (0.81)
BOWMAN ENGINEERING & CONSULTING, INC (0.51)
Contract #03173236
Totals3993994.3360138.603810649.2495.6

CountyECTOR
HighwayFM 3503
FromJBS PARKWAY INTERSECTION
To0.7 MILES SOUTH
CSJ3570-01-009
Proj IDDMO 2010(951)
Work TypeREALIGN EXISTING ROADWAY
 
0.6991899899.890.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-08-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days172
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3570-01-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183240
Totals1899899.890.000.000.0

page 1 | page 2