Monthly State Let Construction Report For Odessa District As Of Apr 10, 2018 Page 1 Of 2

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWARD
HighwayBI 20-D
FromAT SL 464.
To.
CSJ0004-03-049
Proj IDSTP 1702(023)HES
Work TypeINSTALL TRAFFIC SIGNALS
 
0.416562624.3095001.8816.8
Work Order07-06-17
Work Began00-00-00
Work Completed
Time Computed10-05-17
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0004-03-049
JONES BROTHERS, INC. (22.69)
BARRICADES UNLIMITED (6.19)
Contract #05173022
Totals562624.300.0095001.8816.8

CountyWARD ETC
HighwaySS 57 ETC
From0.1 MI EAST OF FM 1219
To0.1 MI WEST OF FM 1219
CSJ0004-03-050
Proj IDSTP 2017(144)HESG
Work TypeINSTALL FLASHING BEASON AND SIGNALS
 
164.082619319.30231997.2037.4
Work Order11-22-16
Work Began11-07-17
Work Completed
Time Computed02-21-17
Contract Working Days143
Addl Days Granted0
Working Days Charged18
Percent Time Used12
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0004-03-050
DOUBLE A CONTRACTING, L.P. (2.32)
BARRICADES UNLIMITED (3.90)
DK CONTRACTING, LLC (7.41)
Contract #10163211
Totals619319.3019800.90231997.2037.4

CountyWARD
HighwayIH 20
FromFM 1219
ToEAST BI 20-D
CSJ0004-04-086
Proj IDNH 2017(031)
Work TypeRECONSTRUCT PAVEMENT
 
10.72314274035.0113328517.3393.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-16
Work Began04-26-17
Work Completed
Time Computed01-20-17
Contract Working Days327
Addl Days Granted0
Working Days Charged253
Percent Time Used77
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0004-04-086
DUSTROL, INC. (2.85)
F & W ELECTRICAL CONTRACTORS, INC. (2.15)
CHEROKEE SERVICES (0.69)
DOUBLE A CONTRACTING, L.P. (1.52)
BARRICADES UNLIMITED (0.58)
RICE ENVIRONMENTAL SERVICES (2.16)
RPV CONSTRUCTION (2.60)
CI CONSTRUCTORS, INC. (0.12)
PENHALL COMPANY (0.15)
Contract #09163203
Totals14274035.010.0013328517.3393.3

CountyECTOR
HighwayBI 20-E
FromEAST SL 338
ToMIDLAND COUNTY LINE
CSJ0005-01-107
Proj IDNH 2018(618)
Work TypePLANE AND OVERLAY
 
11.95411187689.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days201
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-01-107
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183206
Totals11187689.050.000.000.0

CountyMARTIN
HighwayIH 20
FromWEST OF SH 137
ToEAST OF BI 20-F EAST INTERCHANGE
CSJ0005-04-071
Proj IDNH 2018(266)
Work TypePLANE,HOTMIX,MBGF & PAV MRKS
 
3.4915784004.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days137
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-04-071
BARRICADES UNLIMITED (0.76)
CONTRACTORS SERVICE COMPANY (0.57)
HJC FARMS, INC. (0.27)
PRIMATE CONSTRUCTION, INC. (0.16)
A BROTHERS MILLING, LLC (3.72)
DOUBLE A CONTRACTING, L.P. (1.13)
Contract #11173215
Totals5784004.910.000.000.0

CountyECTOR
HighwayIH 20
FromDIXIE BLVD
ToMONAHANS DRAW
CSJ0005-13-056
Proj IDBR 1702(495)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
4.1003958979.20992151.2625.0
Work Order11-01-17
Work Began01-15-18
Work Completed
Time Computed01-01-18
Contract Working Days300
Addl Days Granted0
Working Days Charged59
Percent Time Used19
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-13-056
JONES BROS. DIRT & PAVING CONTRACTORS, INC. (11.22)
R.E.B. TRUCKING (0.49)
DOUBLE A CONTRACTING, L.P. (2.12)
BARRICADES UNLIMITED (2.01)
RPV CONSTRUCTION (12.64)
HUNTER CONCRETE PUMPING, INC. (1.72)
Contract #07173212
Totals3958979.20150114.08992151.2625.0

CountyMIDLAND
HighwayIH 20
FromWEST OF FM 1788
ToEAST OF FM 1788
CSJ0005-14-080
Proj IDIM 0201(189)
Work TypeEXTEND ON/OFF RAMPS
 
1.15411801426.9912059132.6899.9
Work Order06-11-15
Work Began08-09-16
Work Completed
Time Computed10-10-15
Contract Working Days210
Addl Days Granted131
Working Days Charged333
Percent Time Used97
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-14-080
BARRICADES UNLIMITED (2.48)
DTM TRUCKING, INC. (0.24)
R.E.B. TRUCKING (1.44)
TEXOP CONSTRUCTION (0.28)
WILLIS ELECTRIC CO., LP (9.29)
WEST TEXAS RUMBLE STRIP (0.03)
DESERT PAVING, INC. (2.80)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.16)
REECE CONSTRUCTION CO., INC. (7.17)
BOLER EQUIPMENT (2.41)
JOSH FRANKLIN DRILLING, LLC (0.67)
RPV CONSTRUCTION (0.88)
DK CONTRACTING, LLC (0.13)
FUSION COMMUNICATIONS, LLC (0.11)
Contract #04153049
Totals11801426.9932511.5512059132.6899.9

CountyPECOS ETC
HighwayUS 67 ETC
From0.2 MI S OF CHANCELLOR RD
ToBREWSTER COUNTY LINE
CSJ0075-02-027
Proj IDSTP 1702(215)HESG
Work TypeEDGELINE & CENTERLINE RUMBLE STRIPS
 
420.5572345678.911581929.2767.4
Work Order06-14-17
Work Began10-24-17
Work Completed
Time Computed09-13-17
Contract Working Days160
Addl Days Granted0
Working Days Charged119
Percent Time Used74
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0075-02-027
RED SIXTEEN CONSTRUCTION, INC (2.82)
Contract #05173242
Totals2345678.91323318.161581929.2767.4

CountyPECOS
HighwayUS 67 ETC
From1.1 MI NORTH OF IH 10
To14.2 MI NORTH OF IH 10
CSJ0076-01-028
Proj IDSTP 1702(031)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
15.2435286212.001322080.4025.0
Work Order06-14-17
Work Began10-09-17
Work Completed
Time Computed09-13-17
Contract Working Days288
Addl Days Granted0
Working Days Charged122
Percent Time Used42
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0076-01-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173228
Totals5286212.00198831.401322080.4025.0

CountyREEVES
HighwayUS 285
FromCULBERSON COUNTY LINE
ToRM 652
CSJ0139-02-025
Proj IDNH 2018(774)
Work TypeRECONSTRUCT AND WIDEN
 
14.02932027183.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days545
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0139-02-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183201
Totals32027183.640.000.000.0

CountyREEVES
HighwayUS 285
FromCR 232
ToSH 302
CSJ0139-03-039
Proj IDNH 1702(685)
Work TypeRECONSTRUCT AND WIDEN
 
10.04715005109.234429405.1029.5
Work Order09-14-17
Work Began12-14-17
Work Completed
Time Computed12-14-17
Contract Working Days380
Addl Days Granted0
Working Days Charged68
Percent Time Used17
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0139-03-039
DOUBLE A CONTRACTING, L.P. (1.13)
DUSTROL, INC. (0.14)
HJC FARMS, INC. (0.77)
BRUNDAGE-BONE (0.07)
SAENZ TRANSPORT, LLC (8.04)
Contract #08173004
Totals15005109.231172413.314429405.1029.5

CountyREEVES
HighwayUS 285
FromRM 652
ToCR 232
CSJ0139-03-040
Proj IDNH 1602(182)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
10.80612525496.024729177.9337.7
Work Order08-19-16
Work Began02-14-17
Work Completed
Time Computed11-18-16
Contract Working Days332
Addl Days Granted0
Working Days Charged214
Percent Time Used64
Contractor(s)
CI CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0139-03-040
BARRICADES UNLIMITED (0.67)
HJC FARMS, INC. (2.02)
PAVEMENT MARKINGS INC. (0.84)
W.S. CONSTRUCTION COMPANY (2.11)
DK CONTRACTING, LLC (0.40)
Contract #06163203
Totals12525496.02730494.554729177.9337.7

CountyUPTON
HighwaySH 349
FromRM 2401
To6.6 MI SOUTH OF RM 2401
CSJ0380-11-025
Proj IDSTP 1502(619)
Work TypeREHABILITATION OF EXISTING ROAD
 
20.51217114217.0716617431.0097.0
Work Order09-22-15
Work Began05-04-16
Work Completed
Time Computed05-01-16
Contract Working Days374
Addl Days Granted40
Working Days Charged392
Percent Time Used94
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0380-11-025
BARRICADES UNLIMITED (3.10)
HJC FARMS, INC. (0.26)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (5.61)
DTM TRUCKING, INC. (5.27)
ALL-IN CONSTRUCTION (0.50)
LEGACY HOMESTEAD DEVELOPMENT CEDAR EATERS OF TEXAS (0.39)
MIDTEX MULCHING, LLC (0.26)
FOUTSCO PAVING COMPANY, LLC (0.61)
Contract #08153004
Totals17114217.07127064.1116617431.0097.0

CountyMIDLAND
HighwaySH 158
From4 MI SE OF IH 20
ToGLASSCOCK COUNTY LINE
CSJ0463-03-049
Proj IDNH 1702(332)
Work TypePAVEMENT OVERLAY
 
12.1273997554.79808946.0920.2
Work Order07-20-17
Work Began11-14-17
Work Completed
Time Computed08-20-17
Contract Working Days60
Addl Days Granted0
Working Days Charged25
Percent Time Used41
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0463-03-049
DOUBLE A CONTRACTING, L.P. (5.01)
HUDSON, INC. (0.39)
PMI PAVEMENT MARKING, INC. (0.34)
Contract #06173211
Totals3997554.790.00808946.0920.2

CountyREEVES
HighwaySH 302
FromUS 285
ToPECOS RIVER
CSJ0479-01-019
Proj IDSTP 2018(622)
Work TypeROADWAY REHABILITATION AND WIDENING
 
5.60312502318.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days272
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0479-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183205
Totals12502318.480.000.000.0

CountyREEVES
HighwayRM 652
FromUS 285
ToPECOS RIVER
CSJ0493-01-013
Proj IDSTP 1702(333)
Work TypeROADWAY RESTORATION
 
5.6395983269.302875559.3248.0
Work Order07-21-17
Work Began10-23-17
Work Completed
Time Computed10-20-17
Contract Working Days107
Addl Days Granted40
Working Days Charged95
Percent Time Used64
Contractor(s)
CI CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0493-01-013
DK CONTRACTING, LLC (0.43)
Z-TEK (7.75)
PMI PAVEMENT MARKING, INC. (2.61)
Contract #06173008
Totals5983269.30817289.602875559.3248.0

CountyANDREWS
HighwaySH 176
FromNM STATE LINE
To3.3 MI NORTH OF FM 1967
CSJ0548-05-048
Proj IDSTP 1602(296)
Work TypeWIDEN SUBGRADE,PASSING LANES
 
11.61610506607.749948426.0194.6
Work Order09-19-16
Work Began01-27-17
Work Completed
Time Computed12-19-16
Contract Working Days360
Addl Days Granted0
Working Days Charged239
Percent Time Used66
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0548-05-048
CONTRACTORS SERVICE COMPANY (0.45)
REECE CONSTRUCTION CO., INC. (2.58)
WILLIS ELECTRIC CO., LP (0.57)
DTM TRUCKING, INC. (4.56)
R.E.B. TRUCKING (2.52)
DOUBLE A CONTRACTING, L.P. (2.05)
Contract #07163206
Totals10506607.74568861.639948426.0194.6

CountyANDREWS
HighwaySH 176
FromSH 115
To0.187 MI SOUTH OF FM 181
CSJ0548-05-049
Proj IDSTP 2018(680)
Work TypeRECONSTRUCT AND WIDEN
 
12.34811368797.7661894.200.5
Work Order03-05-18
Work Began03-21-18
Work Completed
Time Computed03-21-18
Contract Working Days259
Addl Days Granted0
Working Days Charged7
Percent Time Used2
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0548-05-049
CONTRACTORS SERVICE COMPANY (1.08)
DESERT PAVING, INC. (2.94)
DK CONTRACTING, LLC (0.86)
DOUBLE A CONTRACTING, L.P. (2.46)
WOLFE CONSTRUCTION GROUP, INC. (0.36)
R.E.B. TRUCKING (6.12)
LPZ ENTERPRISES, LLC (1.92)
DTM TRUCKING, INC. (5.60)
Contract #02183003
Totals11368797.7661894.2061894.200.5

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-159
Proj IDSTP 2018(620)
Work TypeNON-IH PAVEMENT MARKINGS
 
389.9381063374.410.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-159
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183231
Totals1063374.410.000.000.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE PAVEMENT MARKINGS
To.
CSJ0906-00-161
Proj IDSTP 2018(621)
Work TypeIH PAVEMENT MARKINGS_(2018)
 
1.0001029975.870.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days69
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-161
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183219
Totals1029975.870.000.000.0

page 1 | page 2