Monthly Local Let Maintenance Report For Lufkin District As Of Sep 10, 2024 Page 3 Of 6

Last Update: Tuesday, September 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN JACINTO
HighwaySH0150
FromSAN JACINTO COUNTY
ToSAN JACINTO COUNTY
CSJ6456-63-001
Proj IDSUP - 645663001
Work TypeLITTER REMOVAL
 
0.01053213.9951291.5096.3
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed10-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged336
Percent Time Used92
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6456-63-001
BURKE CENTER (0.00)
Contract #09231133
Totals53213.992847.7451291.5096.3

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6456-99-001
Proj IDRMC - 645699001
Work TypeRAISED PAVEMENT MARKERS
 
0.010288179.00166593.4757.8
Work Order12-11-23
Work Began12-18-23
Work Completed
Time Computed12-18-23
Contract Working Days365
Addl Days Granted0
Working Days Charged258
Percent Time Used70
Contractor(s)
BRYDL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231105
Totals288179.000.00166593.4757.8

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY MAINTENANCE SECTION
ToVARIOUS ROADWAYS
CSJ6457-91-001
Proj IDRMC - 645791001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010173170.0082575.0047.6
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed02-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6457-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231103
Totals173170.0014500.0082575.0047.6

CountyHOUSTON
HighwayUS0287
FromHOUSTON COUNTY
ToVARIOUS LOCATIONS
CSJ6457-95-001
Proj IDRMC - 645795001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010175000.00178720.0099.9
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed02-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WAYLON BOYLES
SUBCONTRACTOR(S) FOR CCSJ: 6457-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231102
Totals175000.0030060.00178720.0099.9

CountySAN AUGUSTINE
HighwayUS0096
FromSAN AUGUSTINE COUNTY MAINTENANCE SECTION
ToVARIOUS ROADWAYS
CSJ6457-99-001
Proj IDRMC - 645799001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010116118.0742956.8836.9
Work Order00-00-00
Work Began02-07-24
Work Completed
Time Computed02-07-24
Contract Working Days365
Addl Days Granted0
Working Days Charged207
Percent Time Used56
Contractor(s)
JCW CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231104
Totals116118.070.0042956.8836.9

CountyPOLK
HighwayUS0059
FromPOLK COUNTY
ToVARIOUS LOCATIONS
CSJ6458-05-001
Proj IDRMC - 645805001
Work TypeTREE REMOVAL
 
0.010170832.00134181.0078.5
Work Order00-00-00
Work Began03-01-24
Work Completed
Time Computed03-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6458-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231101
Totals170832.000.00134181.0078.5

CountySHELBY
HighwaySH0007
FromSHELBY COUNTY
ToSABINE COUNTY
CSJ6458-34-001
Proj IDMMC - 645834001
Work TypeEMULSION
 
0.010252800.00448569.0599.9
Work Order12-08-23
Work Began12-11-23
Work Completed
Time Computed12-11-23
Contract Working Days120
Addl Days Granted240
Working Days Charged265
Percent Time Used73
Contractor(s)
CLEVELAND ASPHALT PRODUCTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6458-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231161
Totals252800.00206868.26448569.0599.9

CountyNACOGDOCHES
HighwayFM0343
FromNACOGDOCHES COUNTY
ToSAN AUGUSTINE COUNTY
CSJ6458-85-001
Proj IDMMC - 645885001
Work TypeEMULSION
 
0.010251700.00508839.8599.9
Work Order00-00-00
Work Began12-14-23
Work Completed
Time Computed12-14-23
Contract Working Days120
Addl Days Granted240
Working Days Charged262
Percent Time Used72
Contractor(s)
CLEVELAND ASPHALT PRODUCTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6458-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231162
Totals251700.00108798.28508839.8599.9

CountyNACOGDOCHES
HighwayFM0343
FromNACOGDOCHES COUNTY
ToVARIOUS LOCATIONS
CSJ6459-01-001
Proj IDSUP - 645901001
Work TypeSTATE USE CONTRACT
 
0.01048490.0016015.0033.0
Work Order00-00-00
Work Began01-01-24
Work Completed
Time Computed01-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged305
Percent Time Used83
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6459-01-001
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER (0.00)
Contract #10231130
Totals48490.001790.0016015.0033.0

CountyPOLK
HighwayUS0059
FromPOLK COUNTY
ToPOLK COUNTY
CSJ6459-03-001
Proj IDSUP - 645903001
Work TypeJANITORIAL MAINTENANCE
 
0.01033872.2828226.9083.3
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged305
Percent Time Used83
Contractor(s)
WORKQUEST
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6459-03-001
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT (0.00)
Contract #10231131
Totals33872.282822.6928226.9083.3

CountySHELBY
HighwaySH0007
FromSHELBY COUNTY
ToSHELBY COUNTY
CSJ6459-05-001
Proj IDSUP - 645905001
Work TypeGROUNDS MAINTENANCE
 
0.010124635.0476313.6861.2
Work Order11-01-23
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged305
Percent Time Used83
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6459-05-001
RUCON, INC. (0.00)
Contract #10231132
Totals124635.048976.2976313.6861.2

CountyNACOGDOCHES
HighwayUS0059
FromNACOGDOCHES COUNTY
ToVARIOUS LOCATIONS
CSJ6460-05-001
Proj IDSUP - 646005001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.01024200.0020032.0082.7
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed12-01-23
Contract Working Days365
Addl Days Granted90
Working Days Charged275
Percent Time Used60
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6460-05-001
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER (0.00)
Contract #11231132
Totals24200.0015930.0020032.0082.7

CountyPOLK
HighwayUS0059
FromPOLK COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6460-07-001
Proj IDSUP - 646007001
Work TypePICNIC AREA MAINTENANCE
 
0.01041596.6120397.1349.0
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed12-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged275
Percent Time Used75
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6460-07-001
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER (0.00)
Contract #11231133
Totals41596.612852.5120397.1349.0

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6460-09-001
Proj IDSUP - 646009001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.01036950.004908.0013.2
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed12-01-23
Contract Working Days365
Addl Days Granted90
Working Days Charged275
Percent Time Used60
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6460-09-001
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER (0.00)
Contract #11231134
Totals36950.000.004908.0013.2

CountyTRINITY
HighwayUS0287
FromTRINITY COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6460-13-001
Proj IDSUP - 646013001
Work TypeGROUNDS MAINTENANCE
 
0.01046646.5018463.5039.5
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed12-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged275
Percent Time Used75
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6460-13-001
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER (0.00)
Contract #11231136
Totals46646.503823.5018463.5039.5

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY DISTRICT
ToVARIOUS LOCATIONS
CSJ6462-51-001
Proj IDSUP - 646251001
Work TypeGROUNDS MAINTENANCE
 
0.01025577.8010096.5039.4
Work Order00-00-00
Work Began01-01-24
Work Completed
Time Computed01-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged244
Percent Time Used66
Contractor(s)
WORKQUEST
SAUMYA, INC
SUBCONTRACTOR(S) FOR CCSJ: 6462-51-001
SAUMYA, INC (0.00)
Contract #12231130
Totals25577.802692.4010096.5039.4

CountyTRINITY
HighwayFM0357
FromTRINITY COUNTY
ToVARIOUS LOCATIONS
CSJ6462-83-001
Proj IDRMC - 646283001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010168000.06284161.2099.9
Work Order04-10-24
Work Began04-10-24
Work Completed
Time Computed04-10-24
Contract Working Days365
Addl Days Granted0
Working Days Charged144
Percent Time Used39
Contractor(s)
FLORES TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6462-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02241105
Totals168000.0631070.00284161.2099.9

CountySABINE
HighwaySH0021
FromSABINE COUNTY
ToVARIOUS LOCATIONS
CSJ6462-84-001
Proj IDRMC - 646284001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010244255.00261370.0099.9
Work Order04-17-24
Work Began04-18-24
Work Completed
Time Computed04-18-24
Contract Working Days365
Addl Days Granted0
Working Days Charged136
Percent Time Used37
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03241103
Totals244255.0089700.00261370.0099.9

CountyNACOGDOCHES
HighwaySH0007
FromNACOGDOCHES COUNTY
ToVARIOUS LOCATIONS
CSJ6462-96-001
Proj IDRMC - 646296001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010161130.0022005.0013.6
Work Order00-00-00
Work Began04-01-24
Work Completed
Time Computed04-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02241106
Totals161130.000.0022005.0013.6

CountyNACOGDOCHES
HighwayUS0059
FromNACOGDOCHES COUNTY
ToVARIOUS LOCATIONS
CSJ6462-97-001
Proj IDRMC - 646297001
Work TypeTREE REMOVAL
 
0.01092775.00185710.0099.9
Work Order00-00-00
Work Began05-01-24
Work Completed
Time Computed05-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6462-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02241107
Totals92775.0045800.00185710.0099.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6