Monthly Local Let Maintenance Report For Lufkin District As Of Apr 12, 2024 Page 2 Of 6

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNACOGDOCHES
HighwaySH0007
FromNACOGDOCHES COUNTY
ToVARIOUS LOCATIONS
CSJ6429-92-001
Proj IDRMC - 642992001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
214075.00214581.50100.0
Work Order00-00-00
Work Began04-01-23
Work Completed04-04-24
Time Computed04-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6429-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03231102
Totals214075.0017920.00214581.50100.0

CountyPOLK
HighwayUS0059
FromPOLK COUNTY
ToVARIOUS LOCATIONS
CSJ6429-94-001
Proj IDRMC - 642994001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
216537.00114928.0053.0
Work Order00-00-00
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged244
Percent Time Used66
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6429-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03231103
Totals216537.0020065.00114928.0053.0

CountyNACOGDOCHES
HighwayUS0059
FromNACOGDOCHES COUNTY
ToVARIOUS LOCATIONS
CSJ6434-22-001
Proj IDRMC - 643422001
Work TypeTREE REMOVAL
 
0.01088650.00215255.0099.9
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged336
Percent Time Used92
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6434-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03231101
Totals88650.0034940.00215255.0099.9

CountySABINE
HighwaySH0021
FromSABINE COUNTY
ToVARIOUS LOCATIONS
CSJ6434-36-001
Proj IDRMC - 643436001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010230500.00255101.0099.9
Work Order05-08-23
Work Began05-15-23
Work Completed
Time Computed05-15-23
Contract Working Days365
Addl Days Granted0
Working Days Charged322
Percent Time Used88
Contractor(s)
AZA CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6434-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03231104
Totals230500.0055231.00255101.0099.9

CountyHOUSTON
HighwaySL0304
FromHOUSTON COUNTY
ToHOUSTON COUNTY
CSJ6436-37-001
Proj IDSUP - 643637001
Work TypePICNIC AREA MAINTENANCE
 
0.01082601.7663102.41100.0
Work Order00-00-00
Work Began03-01-23
Work Completed03-01-24
Time Computed03-01-23
Contract Working Days365
Addl Days Granted1
Working Days Charged366
Percent Time Used100
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6436-37-001
RUCON, INC. (0.00)
Contract #02231161
Totals82601.765135.8163102.41100.0

CountyANGELINA
HighwayFM0324
FromANGELINA COUNTY MAINTENANCE YARD
ToANGELINA COUNTY MAINTENANCE YARD
CSJ6436-88-001
Proj IDMMC - 643688001
Work TypeHOT MIX
 
0.010312222.001457410.1999.9
Work Order00-00-00
Work Began04-24-23
Work Completed
Time Computed04-24-23
Contract Working Days120
Addl Days Granted240
Working Days Charged343
Percent Time Used95
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6436-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03231160
Totals312222.005713.261457410.1999.9

CountyTRINITY
HighwayFM0357
FromTRINITY COUNTY
ToVARIOUS LOCATIONS
CSJ6437-00-001
Proj IDRMC - 643700001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010161750.0074338.0045.9
Work Order06-05-23
Work Began06-06-23
Work Completed
Time Computed06-06-23
Contract Working Days365
Addl Days Granted0
Working Days Charged245
Percent Time Used67
Contractor(s)
WAYLON BOYLES
SUBCONTRACTOR(S) FOR CCSJ: 6437-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231101
Totals161750.006780.0074338.0045.9

CountySAN JACINTO
HighwaySH0150
FromSAN JACINTO COUNTY MAINTENANCE YARD
ToSAN JACINTO COUNTY MAINTENANCE YARD
CSJ6437-23-001
Proj IDMMC - 643723001
Work TypeCUTBACK
 
0.010197500.003828.811.9
Work Order00-00-00
Work Began05-19-23
Work Completed
Time Computed05-19-23
Contract Working Days120
Addl Days Granted240
Working Days Charged328
Percent Time Used91
Contractor(s)
CLEVELAND ASPHALT PRODUCTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6437-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231163
Totals197500.000.003828.811.9

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY MAINTENANCE YARD
ToVARIOUS LOCATIONS
CSJ6438-29-001
Proj IDSUP - 643829001
Work TypeJANITORIAL MAINTENANCE
 
0.0107963.807300.1591.6
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged336
Percent Time Used92
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6438-29-001
BURKE CENTER (0.00)
Contract #04231130
Totals7963.80663.657300.1591.6

CountyHOUSTON
HighwayUS0287
FromHOUSTON COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6438-31-001
Proj IDSUP - 643831001
Work TypeJANITORIAL MAINTENANCE
 
0.01011797.6810596.0689.8
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged336
Percent Time Used92
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6438-31-001
BURKE CENTER (0.00)
Contract #04231131
Totals11797.68983.1410596.0689.8

CountySAN JACINTO
HighwaySH0150
FromSAN JACINTO COUNTY MAINTENANCE YARD
ToVARIOUS LOCATIONS
CSJ6438-33-001
Proj IDSUP - 643833001
Work TypeGROUNDS MAINTENANCE
 
0.010114250.8448931.9942.8
Work Order00-00-00
Work Began04-01-23
Work Completed
Time Computed04-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6438-33-001
RUCON, INC. (0.00)
Contract #03231130
Totals114250.845459.6648931.9942.8

CountyNACOGDOCHES
HighwayUS0059
FromNACOGDOCHES COUNTY MAINT & DISTRICT
ToVARIOUS LOCATIONS
CSJ6438-35-001
Proj IDSUP - 643835001
Work TypeJANITORIAL MAINTENANCE
 
0.01039790.449177.4423.0
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged336
Percent Time Used92
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6438-35-001
OAK CREEK DAY HABILITATION/VOCATION CENTER (0.00)
Contract #04231132
Totals39790.44743.849177.4423.0

CountySAN AUGUSTINE
HighwayUS0096
FromSAN AUGUSTINE COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6438-37-001
Proj IDSUP - 643837001
Work TypeJANITORIAL MAINTENANCE
 
0.01011780.766792.1557.6
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged333
Percent Time Used91
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6438-37-001
BURKE CENTER (0.00)
Contract #04231133
Totals11780.76480.876792.1557.6

CountySHELBY
HighwayUS0096
FromSHELBY COUNTY
ToVARIOUS LOCATIONS
CSJ6438-39-001
Proj IDSUP - 643839001
Work TypeJANITORIAL MAINTENANCE
 
0.01017248.8014254.7182.6
Work Order05-01-23
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged336
Percent Time Used92
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6438-39-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #04231134
Totals17248.801437.4014254.7182.6

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6438-41-001
Proj IDSUP - 643841001
Work TypeJANITORIAL MAINTENANCE
 
0.01017319.8016060.4192.7
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged336
Percent Time Used92
Contractor(s)
WORKQUEST
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6438-41-001
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT (0.00)
Contract #04231135
Totals17319.802362.9516060.4192.7

CountyTRINITY
HighwayUS0287
FromTRINITY COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6438-43-001
Proj IDSUP - 643843001
Work TypeJANITORIAL MAINTENANCE
 
0.01019868.6417853.6389.8
Work Order04-26-23
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged336
Percent Time Used92
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6438-43-001
BURKE CENTER (0.00)
Contract #04231136
Totals19868.641655.7217853.6389.8

CountyNACOGDOCHES
HighwayFM0343
FromNACOGDOCHES COUNTY MAINTENANCE YARD
ToNACOGDOCHES COUNTY MAINTENANCE YARD
CSJ6438-85-001
Proj IDMMC - 643885001
Work TypeFLEXIBLE BASE
 
0.010200000.00235506.5099.9
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days120
Addl Days Granted240
Working Days Charged336
Percent Time Used93
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6438-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231161
Totals200000.000.00235506.5099.9

CountyTRINITY
HighwayUS0287
FromVARIOUS LIMITS IN TRINITY
ToCOUNTY MAINTENANCE SECTIONS
CSJ6439-84-001
Proj IDRMC - 643984001
Work TypeCULVERT CLEANING
 
0.010228040.00247813.5099.9
Work Order09-25-23
Work Began09-25-23
Work Completed
Time Computed09-25-23
Contract Working Days47
Addl Days Granted0
Working Days Charged33
Percent Time Used70
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6439-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231103
Totals228040.000.00247813.5099.9

CountySHELBY
HighwayFM3343
FromSHELBY COUNTY MAINTENANCE YARD
ToSHELBY COUNTY MAINTENANCE YARD
CSJ6439-96-001
Proj IDMMC - 643996001
Work TypeFLEXIBLE BASE
 
0.010299460.00774140.3799.9
Work Order06-14-23
Work Began06-15-23
Work Completed
Time Computed06-15-23
Contract Working Days120
Addl Days Granted240
Working Days Charged291
Percent Time Used80
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6439-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231160
Totals299460.000.00774140.3799.9

CountySAN JACINTO
HighwaySH0150
FromSAN JACINTO COUNTY MAINTENANCE YARD
ToSAN JACINTO COUNTY MAINTENANCE YARD
CSJ6440-10-001
Proj IDMMC - 644010001
Work TypeHYDRAULIC CEMENT
 
0.01060180.000.000.0
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days120
Addl Days Granted240
Working Days Charged305
Percent Time Used84
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6440-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231161
Totals60180.000.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6