Monthly Local Let Maintenance Report For Lufkin District As Of Jun 08, 2018 Page 2 Of 5

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSABINE COUNTY
CSJ6305-26-001
Proj IDSUP - 630526001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010100000.00147352.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-16
Work Began09-01-16
Work Completed09-01-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161141
Totals100000.000.00147352.00100.0

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS WITHIN THE
ToSABINE COUNTY MAINTENANCE SECTION
CSJ6308-42-001
Proj IDRMC - 630842001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010172470.0030463.0017.6
Work Order01-12-17
Work Began01-12-17
Work Completed
Time Computed01-12-17
Contract Working Days200
Addl Days Granted0
Working Days Charged10
Percent Time Used5
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6308-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161107
Totals172470.005735.0030463.0017.6

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6308-73-001
Proj IDRMC - 630873001
Work TypeINSTALLATION OF WATERBASE STRIPING
 
0.001294400.00123830.1242.0
Work Order12-08-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted365
Working Days Charged532
Percent Time Used72
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6308-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161103
Totals294400.0031512.78123830.1242.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6308-74-001
Proj IDRMC - 630874001
Work TypeINSTALLATION OF THERMOPLASTIC STRIPING
 
0.001274570.00417550.4899.9
Work Order12-08-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted365
Working Days Charged533
Percent Time Used73
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6308-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161104
Totals274570.000.00417550.4899.9

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE
ToSHELBY COUNTY MAINTENANCE SECTION
CSJ6309-67-001
Proj IDRMC - 630967001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010142140.0079133.5055.6
Work Order01-12-17
Work Began01-12-17
Work Completed
Time Computed01-12-17
Contract Working Days200
Addl Days Granted0
Working Days Charged21
Percent Time Used10
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6309-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161110
Totals142140.000.0079133.5055.6

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE
ToSAN AUGUSTINE COUNTY MAINTENANCE SECTION
CSJ6309-68-001
Proj IDRMC - 630968001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010146806.0048740.0033.2
Work Order00-00-00
Work Began01-26-17
Work Completed
Time Computed01-26-17
Contract Working Days200
Addl Days Granted0
Working Days Charged11
Percent Time Used5
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161109
Totals146806.004710.0048740.0033.2

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS WITHIN
ToLUFKIN DISTRICT
CSJ6310-18-001
Proj IDRMC - 631018001
Work TypeINSTALLATION OF SPECIALTY PVMNT MARKINGS
 
0.001179448.0052861.3029.4
Work Order08-09-17
Work Began08-16-17
Work Completed
Time Computed01-17-17
Contract Working Days365
Addl Days Granted0
Working Days Charged289
Percent Time Used79
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6310-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161108
Totals179448.000.0052861.3029.4

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN THE HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6312-52-001
Proj IDRMC - 631252001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010165108.10162175.0898.2
Work Order05-23-17
Work Began06-20-17
Work Completed
Time Computed06-20-17
Contract Working Days72
Addl Days Granted72
Working Days Charged56
Percent Time Used38
Contractor(s)
DON YATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171104
Totals165108.100.00162175.0898.2

CountyPOLK
HighwayUS0059
FromVARIOUS ROADWAYS IN THE POLK COUNTY
ToMAINTENANCE SECTION
CSJ6312-54-001
Proj IDRMC - 631254001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010244709.27230120.5194.0
Work Order00-00-00
Work Began06-12-17
Work Completed
Time Computed06-01-17
Contract Working Days99
Addl Days Granted99
Working Days Charged80
Percent Time Used40
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6312-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171103
Totals244709.270.00230120.5194.0

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN THE SAN JACINTO
ToMAINTENANCE SECTION
CSJ6312-58-001
Proj IDRMC - 631258001
Work TypeMOWING OF RIGHT-OF-WAY AND LITTER REMVAL
 
0.010132231.77124288.8193.9
Work Order06-01-17
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days54
Addl Days Granted54
Working Days Charged38
Percent Time Used35
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6312-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171106
Totals132231.770.00124288.8193.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIIONS IN
ToLUFKIN DISTRICT
CSJ6313-75-001
Proj IDRMC - 631375001
Work TypeDISTRICT WIDE TRAFFIC SIGNAL MAINTENANCE
 
0.001327765.00587491.5299.9
Work Order05-02-17
Work Began05-09-17
Work Completed
Time Computed05-09-17
Contract Working Days365
Addl Days Granted365
Working Days Charged388
Percent Time Used53
Contractor(s)
BAY CITY TRAFFIC
SUBCONTRACTOR(S) FOR CCSJ: 6313-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171101
Totals327765.0015055.00587491.5299.9

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS IN THE SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6314-24-001
Proj IDRMC - 631424001
Work TypeDITCH AND CULVERT CLEANING
 
0.010169650.00297017.3699.9
Work Order04-17-17
Work Began04-20-17
Work Completed
Time Computed04-20-17
Contract Working Days45
Addl Days Granted45
Working Days Charged40
Percent Time Used44
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171106
Totals169650.000.00297017.3699.9

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN POLK COUNTY
ToMAINTENANCE SECTION
CSJ6315-48-001
Proj IDRMC - 631548001
Work TypeTREE & BRUSH REMOVAL AND TREE TRIMMING
 
0.010217735.00109640.0050.3
Work Order12-04-17
Work Began12-01-17
Work Completed
Time Computed12-01-17
Contract Working Days200
Addl Days Granted0
Working Days Charged65
Percent Time Used32
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6315-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171103
Totals217735.0031398.00109640.0050.3

CountySAN AUGUSTINE
HighwaySH0103
FromVARIOUS LOCATIONS IN SAN AUGUSTINE
ToCOUNTY MAINTENANCE SECTION
CSJ6315-93-001
Proj IDRMC - 631593001
Work TypeTREE & BRUSH REMOVAL
 
0.010209120.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6315-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171101
Totals209120.000.000.000.0

CountySABINE
HighwaySH0021
FromVARIOUS LOCATIONS IN SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6316-67-001
Proj IDRMC - 631667001
Work TypeTREE & BRUSH REMOVAL AND TREE TRIMMING
 
0.010251150.0057934.0023.0
Work Order10-06-17
Work Began11-06-17
Work Completed
Time Computed11-01-17
Contract Working Days200
Addl Days Granted0
Working Days Charged38
Percent Time Used19
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6316-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171102
Totals251150.0029201.0057934.0023.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN THE_HOUSTON_COUNTY
ToMAINTENANCE SECTION
CSJ6317-63-001
Proj IDRMC - 631763001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010356050.0032761.009.2
Work Order07-20-17
Work Began10-23-17
Work Completed
Time Computed08-01-17
Contract Working Days200
Addl Days Granted0
Working Days Charged3
Percent Time Used1
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171101
Totals356050.0015375.0032761.009.2

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS IN THE SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6317-92-001
Proj IDSUP - 631792001
Work TypePICNIC AREA GRNDS & C&G MAINTENANCE
 
0.01082720.2254205.7565.5
Work Order07-01-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171111
Totals82720.224860.2654205.7565.5

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN POLK COUNTY
ToMAINTENANCE SECTION
CSJ6317-93-001
Proj IDSUP - 631793001
Work TypePICNIC & GROUNDS MAINT IN POLK COUNTY
 
0.01036967.1226258.1971.0
Work Order06-27-17
Work Began07-10-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6317-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171110
Totals36967.122190.4026258.1971.0

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS IN SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6317-94-001
Proj IDSUP - 631794001
Work TypeDELINEATOR, MBOX, SIGN STR. AND C&G MNT.
 
0.010213500.0039415.8018.4
Work Order07-01-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171102
Totals213500.000.0039415.8018.4

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN HOUSTON COUNTY
ToMAINTENANCE SECTION
CSJ6317-95-001
Proj IDSUP - 631795001
Work TypeCURB & GUTTER MAINT. HOUSTON COUNTY
 
0.01028500.0012952.5945.4
Work Order06-27-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171106
Totals28500.000.0012952.5945.4