Monthly Local Let Maintenance Report For Lufkin District As Of Mar 13, 2024 Page 4 Of 6

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOUSTON
HighwaySL0304
FromHOUSTON COUNTY MAINTENANCE YARD
ToHOUSTON COUNTY MAINTENANCE YARD
CSJ6445-49-001
Proj IDMMC - 644549001
Work TypeHYDRAULIC CEMENT
 
0.01082220.9666056.1880.3
Work Order00-00-00
Work Began06-26-23
Work Completed
Time Computed06-26-23
Contract Working Days120
Addl Days Granted240
Working Days Charged249
Percent Time Used69
Contractor(s)
AKA-MATERIALS
SUBCONTRACTOR(S) FOR CCSJ: 6445-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231164
Totals82220.9637814.2666056.1880.3

CountyANGELINA
HighwaySL0287
FromANGELINA COUNTY MAINTENANCE YARD
ToANGELINA COUNTY MAINTENANCE YARD
CSJ6445-80-001
Proj IDMMC - 644580001
Work TypeCUTBACK
 
0.01048840.0040939.6883.8
Work Order00-00-00
Work Began06-26-23
Work Completed
Time Computed06-26-23
Contract Working Days120
Addl Days Granted240
Working Days Charged249
Percent Time Used69
Contractor(s)
CLEVELAND ASPHALT PRODUCTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6445-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231167
Totals48840.000.0040939.6883.8

CountyHOUSTON
HighwaySL0304
FromHOUSTON COUNTY MAINTENANCE YARD
ToHOUSTON COUNTY MAINTENANCE YARD
CSJ6445-84-001
Proj IDMMC - 644584001
Work TypeCUTBACK
 
0.010138950.00182382.2199.9
Work Order00-00-00
Work Began08-30-23
Work Completed
Time Computed08-30-23
Contract Working Days120
Addl Days Granted120
Working Days Charged184
Percent Time Used76
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6445-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07231160
Totals138950.000.00182382.2199.9

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY
ToVARIOUS LOCATIONS
CSJ6445-86-001
Proj IDSUP - 644586001
Work TypeCURB & GUTTER MAINT
 
0.01064219.920.000.0
Work Order00-00-00
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6445-86-001
OAK CREEK DAY HABILITATION/VOCATION CENTER (0.00)
Contract #07231137
Totals64219.920.000.000.0

CountySABINE
HighwayUS0096
FromSABINE COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6445-88-001
Proj IDSUP - 644588001
Work TypeGROUNDS MAINTENANCE
 
0.01055290.6622089.1239.9
Work Order08-01-23
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6445-88-001
OAK CREEK DAY HABILITATION/VOCATION CENTER (0.00)
Contract #07231138
Totals55290.664121.6522089.1239.9

CountyPOLK
HighwayUS0059
FromPOLK COUNTY MAINTENANCE YARD
ToPOLK COUNTY MAINTENANCE YARD
CSJ6445-92-001
Proj IDMMC - 644592001
Work TypeEMULSION
 
0.010131600.00216792.5299.9
Work Order00-00-00
Work Began06-23-23
Work Completed
Time Computed06-23-23
Contract Working Days120
Addl Days Granted240
Working Days Charged252
Percent Time Used70
Contractor(s)
CLEVELAND ASPHALT PRODUCTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6445-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231168
Totals131600.000.00216792.5299.9

CountyANGELINA
HighwayBU0069J
FromANGELINA COUNTY MAINTENANCE YARD
ToANGELINA COUNTY MAINTENANCE YARD
CSJ6446-02-001
Proj IDMMC - 644602001
Work TypeEMULSION
 
0.01030500.00520689.1699.9
Work Order00-00-00
Work Began06-26-23
Work Completed
Time Computed06-26-23
Contract Working Days120
Addl Days Granted240
Working Days Charged249
Percent Time Used69
Contractor(s)
CLEVELAND ASPHALT PRODUCTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6446-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231169
Totals30500.003198.83520689.1699.9

CountyPOLK
HighwayUS0059
FromPOLK COUNTY MAINTENANCE YARD
ToPOLK COUNTY MAINTENANCE YARD
CSJ6446-18-001
Proj IDMMC - 644618001
Work TypeHOT MIX
 
0.010217400.00189470.9087.1
Work Order00-00-00
Work Began07-03-23
Work Completed
Time Computed07-03-23
Contract Working Days120
Addl Days Granted240
Working Days Charged242
Percent Time Used67
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6446-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231170
Totals217400.0024951.18189470.9087.1

CountyHOUSTON
HighwaySL0304
FromHOUSTON COUNTY MAINTENANCE YARD
ToHOUSTON COUNTY MAINTENANCE YARD
CSJ6446-22-001
Proj IDMMC - 644622001
Work TypeAGGREGATE
 
0.01093200.0053460.7557.3
Work Order00-00-00
Work Began07-21-23
Work Completed
Time Computed07-21-23
Contract Working Days120
Addl Days Granted120
Working Days Charged224
Percent Time Used93
Contractor(s)
ARCOSA LWS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231171
Totals93200.0053460.7553460.7557.3

CountySAN AUGUSTINE
HighwaySH0103
FromSAN AUG COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6447-00-001
Proj IDRMC - 644700001
Work TypeTREE REMOVAL
 
0.010123131.00129616.0099.9
Work Order00-00-00
Work Began12-11-23
Work Completed
Time Computed12-11-23
Contract Working Days365
Addl Days Granted0
Working Days Charged81
Percent Time Used22
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6447-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231102
Totals123131.0024915.00129616.0099.9

CountySHELBY
HighwaySH0087
FromVARIOUS LOCATIONS IN THE SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6447-78-001
Proj IDRMC - 644778001
Work TypeDITCH CLEANING AND RESHAPING
 
151451.00105675.4069.7
Work Order10-02-23
Work Began10-02-23
Work Completed
Time Computed10-02-23
Contract Working Days45
Addl Days Granted0
Working Days Charged26
Percent Time Used57
Contractor(s)
RHINO EQUITY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6447-78-001
J&H EXCAVATION INC. (0.00)
Contract #08231105
Totals151451.000.00105675.4069.7

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY
ToVARIOUS LOCATIONS
CSJ6448-05-001
Proj IDRMC - 644805001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010168850.0086800.0051.4
Work Order00-00-00
Work Began09-14-23
Work Completed
Time Computed09-14-23
Contract Working Days365
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
BA NEWTON'S ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6448-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231106
Totals168850.001230.0086800.0051.4

CountySABINE
HighwayUS0096
FromSABINE COUNTY
ToVARIOUS LOCATIONS
CSJ6449-61-001
Proj IDRMC - 644961001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010292599.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-11-24
Work Began00-00-00
Work Completed
Time Computed06-01-24
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6449-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01241114
Totals292599.180.000.000.0

CountySAN AUGUSTINE
HighwayUS0096
FromSAN AUGUSTINE COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6449-63-001
Proj IDRMC - 644963001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010181625.110.000.0
Work Order00-00-00
Work Began02-15-24
Work Completed
Time Computed02-15-24
Contract Working Days37
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6449-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01241115
Totals181625.110.000.000.0

CountyTRINITY
HighwayUS0287
FromTRINITY COUNTY
ToVARIOUS LOCATIONS
CSJ6449-67-001
Proj IDRMC - 644967001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010144472.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days33
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6449-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01241116
Totals144472.200.000.000.0

CountyANGELINA
HighwayUS0059
FromDISTRICTWIDE COUNTY MAINTENANCE YARDS
ToDISTRICTWIDE COUNTY MAINTENANCE YARDS
CSJ6449-95-001
Proj IDMMC - 644995001
Work TypeWINTER WEATHER MATERIAL
 
0.01062160.00107076.0099.9
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days210
Addl Days Granted0
Working Days Charged121
Percent Time Used57
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6449-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231162
Totals62160.000.00107076.0099.9

CountyANGELINA
HighwayBU0069J
FromANGELINA COUNTY
ToANGELINA COUNTY
CSJ6450-43-001
Proj IDSUP - 645043001
Work TypeGROUNDS MAINTENANCE
 
0.01044591.4812251.5027.4
Work Order00-00-00
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6450-43-001
OAK CREEK DAY HABILITATION/VOCATION CENTER (0.00)
Contract #07231130
Totals44591.482338.8212251.5027.4

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY
ToVARIOUS LOCATIONS
CSJ6450-45-001
Proj IDSUP - 645045001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.01016905.000.000.0
Work Order00-00-00
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6450-45-001
OAK CREEK DAY HABILITATION/VOCATION CENTER (0.00)
Contract #07231131
Totals16905.000.000.000.0

CountyPOLK
HighwayUS0059
FromPOLK COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6450-47-001
Proj IDSUP - 645047001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.01028980.007459.2025.7
Work Order00-00-00
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6450-47-001
OAK CREEK DAY HABILITATION/VOCATION CENTER (0.00)
Contract #07231132
Totals28980.004670.407459.2025.7

CountySAN AUGUSTINE
HighwayUS0096
FromSAN AUGUSTINE COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6450-49-001
Proj IDSUP - 645049001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.01091155.751848.002.0
Work Order00-00-00
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
OAK CREEK DAY HABILITATION/VOCATIONAL CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6450-49-001
OAK CREEK DAY HABILITATION/VOCATION CENTER (0.00)
Contract #07231133
Totals91155.751848.001848.002.0