Monthly State Let Construction Report For Bryan District As Of Jul 13, 2018 Page 3 Of 3

Last Update: Friday, July 13, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMILAM
HighwayFM 487
FromCOUNTY ROAD 402
To0.7 MILE NORTH OF COUNTY ROAD 235
CSJ0858-01-033
Proj IDSTP 1502(528)HES
Work TypePROVIDE ADDITIONAL PAVEMENT WIDTH
 
15.4095587641.645206667.0694.9
Work Order10-30-15
Work Began02-15-16
Work Completed
Time Computed01-28-16
Contract Working Days150
Addl Days Granted4
Working Days Charged242
Percent Time Used157
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0858-01-033
R K STEPHENS CONSTRUCTION, LLC (7.02)
ROADWAY SPECIALTIES, INC. (1.91)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45)
CEN TEX HYDROSEED, INC. (1.57)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.78)
NIXON ENGINEERING (0.00)
Contract #08153237
Totals5587641.640.005206667.0694.9

CountyMILAM
HighwayFM 908
FromUS 79
ToUS 77
CSJ0858-02-021
Proj IDSTP 2018(029)
Work TypeREHABILITATE EXISTING ROAD
 
1.5431428673.97797694.3855.8
Work Order11-20-17
Work Began02-05-18
Work Completed
Time Computed12-20-17
Contract Working Days87
Addl Days Granted0
Working Days Charged20
Percent Time Used22
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0858-02-021
AREA WIDE PROTECTIVE, INC. (1.95)
FLASHER LIMITED (0.90)
LUZ LERMA CONSTRUCTION, INC. (34.59)
ENVIRONMENTAL SAFETY SERVICES, INC. (4.12)
Contract #09173019
Totals1428673.974000.00797694.3855.8

CountyBRAZOS
HighwayVA
FromVAR. LOCATIONS IN BRAZOS, WALKER,
ToMADISON, LEON & FREESTONE COUNTIES
CSJ0917-00-042
Proj IDITS 2001(537)
Work TypeFY16 ITS DEVELOPMENT PROGRAM
 
0.001549299.80764782.4199.9
Work Order05-12-16
Work Began07-26-16
Work Completed
Time Computed06-11-16
Contract Working Days85
Addl Days Granted53
Working Days Charged100
Percent Time Used72
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-042
BUYER BARRICADES (2.30)
SPECIALTY DRILLING, LTD. (4.73)
Contract #04163239
Totals549299.800.00764782.4199.9

CountyMILAM
HighwayCR
FromON CR 398 - LOCAL CR 440
ToAT BRUSHY CREEK RELIEF
CSJ0917-12-080
Proj IDBR 2012(334)
Work TypeREPLACE AN EXISTING BRIDGE FACILITY
 
0.132447590.00440848.9598.4
Work Order07-11-17
Work Began08-21-17
Work Completed
Time Computed08-21-17
Contract Working Days82
Addl Days Granted0
Working Days Charged76
Percent Time Used92
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0917-12-080
VOGES DRILLING CO. (10.37)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.11)
SAN-ANN-CO., INC. (0.67)
HOUSTON SAWING & DRILLING (0.61)
Contract #06173019
Totals447590.001306.80440848.9598.4

CountyGRIMES
HighwayCR
FromON CR 251 - LOCAL CR 190
ToAT GIBBONS CREEK
CSJ0917-17-065
Proj IDBR 2012(273)
Work TypeREPLACE EXISTING BRIDGE
 
0.192905681.32895556.9198.8
Work Order07-21-17
Work Began10-19-17
Work Completed
Time Computed10-19-17
Contract Working Days196
Addl Days Granted0
Working Days Charged136
Percent Time Used69
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-065
LONESTAR TRAFFIC SAFETY, LLC (0.69)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.48)
HEMPHILL WBE PILE DRIVING CO. (3.82)
DIIBS SPECIALISTS (0.34)
MESA ROD BUSTERS, INC. (0.50)
A-1 EROSION CONTROL, LLC (0.14)
HOUSTON SAWING & DRILLING (0.32)
Contract #06173223
Totals905681.328249.10895556.9198.8

CountyWASHINGTON
HighwayCS
FromON TEXAS STREET
ToAT INDIAN CREEK
CSJ0917-19-050
Proj IDBR 2017(904)
Work TypeREPLACE EXISTING BRIDGE
 
0.068341287.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days69
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-19-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183245
Totals341287.960.000.000.0

CountyFREESTONE
HighwayPW
FromWITHIN FAIRFIELD STATE PARK IN THE
ToSPRINGFIELD AND POST OAK AREAS
CSJ0917-20-036
Proj IDC 917-20-36
Work TypeRECONSTRUCT ROADS AND CAMPSITES
 
1.0001862429.041956067.1099.9
Work Order03-15-17
Work Began05-01-17
Work Completed
Time Computed04-14-17
Contract Working Days175
Addl Days Granted45
Working Days Charged220
Percent Time Used100
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-036
AREA WIDE PROTECTIVE, INC. (0.44)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (3.22)
COLD CREEK CONSTRUCTION, LTD (0.66)
STRIPING TECHNOLOGY, L.P. (0.39)
MOORE PLUMBING REPAIR, LLC (0.89)
Contract #02173215
Totals1862429.04194525.411956067.1099.9

CountyWALKER
HighwayCR
FromON CR 667 - LOCAL BEAR CREEK ROAD
ToAT WHITES CREEK
CSJ0917-27-044
Proj IDBR 2016(317)
Work TypeGRADING, STRUCTURES AND BASE
 
0.104504029.64499483.8799.0
Work Order07-21-17
Work Began10-19-17
Work Completed
Time Computed10-19-17
Contract Working Days99
Addl Days Granted0
Working Days Charged66
Percent Time Used66
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-044
LONESTAR TRAFFIC SAFETY, LLC (0.60)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.95)
DIIBS SPECIALISTS (0.62)
BOWMAN ENGINEERING & CONSULTING, INC (0.56)
Contract #06173009
Totals504029.640.00499483.8799.0

CountyBRAZOS
HighwayCR
FromON CR 121 - LOCAL DILLY SHAW TAP RD
ToAT CEDAR CREEK
CSJ0917-29-120
Proj IDBR 2016(358)
Work TypeGRADING, STRUCTURE, BASE AND SURF
 
0.189772705.3711850.001.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-17-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days171
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-29-120
AREA WIDE PROTECTIVE, INC. (1.26)
Contract #04183208
Totals772705.370.0011850.001.5

CountyBRAZOS
HighwayVA
FromON SH 308 FROM FM 1179
ToINLOW STREET
CSJ0917-29-129
Proj IDSTP 2017(099)TAPS
Work TypePEDESTRIAN AND BICYCLE IMPROVMENTS
 
1.1641803581.231027237.0756.9
Work Order09-25-17
Work Began12-14-17
Work Completed
Time Computed10-25-17
Contract Working Days140
Addl Days Granted5
Working Days Charged133
Percent Time Used91
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-29-129
TEXAS ALTERNATIVE GRASSER, INC. (0.37)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (29.08)
CEN TEX HYDROSEED, INC. (1.57)
D. I. J. CONSTRUCTION, INC. (1.59)
SPEEDY PAVING (1.67)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
AREA WIDE PROTECTIVE, INC. (0.27)
Contract #08173012
Totals1803581.23199097.661027237.0756.9

CountyGRIMES
HighwayFM 1696
FromFM 39
ToSH 90
CSJ1562-03-018
Proj IDSTP 2017(349)
Work TypeREHABILITATE EXISTING ROADWAY
 
9.1145527215.435275386.8596.1
Work Order04-04-17
Work Began05-03-17
Work Completed
Time Computed05-03-17
Contract Working Days215
Addl Days Granted53
Working Days Charged261
Percent Time Used97
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1562-03-018
ROADSAFE TRAFFIC SYSTEMS, INC. (1.38)
CEN TEX HYDROSEED, INC. (0.56)
COLD CREEK CONSTRUCTION, LTD (1.99)
ODUM SERVICES, L.P. (1.06)
J & M CONTRACTING COMPANY (4.44)
AREA WIDE PROTECTIVE, INC. (1.38)
A. L. HELMCAMP, INC. (0.59)
ANGEL BROTHERS ENTERPRISES, LTD. (9.94)
Contract #01173017
Totals5527215.43154880.165275386.8596.1

page 1 | page 2 | page 3