Monthly State Let Construction Report For Bryan District As Of Apr 10, 2018 Page 2 Of 3

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZOS
HighwayFM 158
FromSH 6 NORTHBOUND FRONTAGE ROAD
ToSH 30
CSJ0212-03-057
Proj IDSTP 1602(409)TAPS
Work TypePEDESTRIAN SAFETY LIGHTING
 
3.9661380692.25694686.0650.3
Work Order09-15-16
Work Began01-10-17
Work Completed
Time Computed12-14-16
Contract Working Days177
Addl Days Granted0
Working Days Charged89
Percent Time Used50
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0212-03-057
N-LINE TRAFFIC MAINTENANCE, L.P. (0.54)
BRITTEN HYDROSEEDING (4.92)
SHAW DRILLING, LLC (3.24)
Contract #08163014
Totals1380692.250.00694686.0650.3

CountyGRIMES
HighwaySH 30
FromAT THE INTERSECTION OF SH 30
ToAND FM 244
CSJ0212-04-033
Proj IDSTP 1402(194)
Work TypeCONSTRUCT GRADE SEPARATION
 
0.8335718784.145737321.4699.9
Work Order09-30-14
Work Began11-12-15
Work Completed
Time Computed10-16-14
Contract Working Days251
Addl Days Granted36
Working Days Charged281
Percent Time Used97
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0212-04-033
TEXOP CONSTRUCTION (1.66)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.94)
PENHALL COMPANY (0.18)
MESA ROD BUSTERS, INC. (0.38)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.70)
WILLOW CITY SIGN & RAIL, INC. (2.17)
SCOTT DERR PAINTING CO (0.22)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.95)
CEN TEX HYDROSEED, INC. (2.61)
BRICK PAVING PLUS, INC. (0.51)
MCL CONTRACTING, LLC (0.14)
D. I. J. CONSTRUCTION, INC. (0.03)
BATTEN DRILLING, INC. (0.29)
AARON CONCRETE CONTRACTORS, L.P. (0.31)
Contract #07143023
Totals5718784.1444190.005737321.4699.9

CountyMILAM
HighwayFM 485
FromAT COW CREEK
To.
CSJ0262-07-033
Proj IDBR 1702(780)
Work TypeREPLACE EXISTING BRIDGE
 
0.161668667.60465937.0569.6
Work Order09-21-17
Work Began01-08-18
Work Completed
Time Computed12-20-17
Contract Working Days70
Addl Days Granted3
Working Days Charged47
Percent Time Used64
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0262-07-033
AWP, INC. DBA AREA WIDE PROTECTIVE (1.03)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.33)
ROADWAY SPECIALTIES, INC. (5.00)
D.I.J. CONSTRUCTION, INC (1.44)
BOWMAN ENGINEERING & CONSULTING, INC (0.33)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.45)
Contract #08173244
Totals668667.60192119.21465937.0569.6

CountyGRIMES
HighwaySH 90
From0.3 MILES S OF HOLLANDS CREEK
To0.5 MILES S OF HOLLANDS CREEK
CSJ0315-03-059
Proj IDSTP 1702(804)
Work TypeOVERLAY
 
4.8992078724.66235476.0011.3
Work Order09-21-17
Work Began11-28-17
Work Completed
Time Computed10-21-17
Contract Working Days90
Addl Days Granted0
Working Days Charged35
Percent Time Used38
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0315-03-059
D.I.J. CONSTRUCTION, INC (2.21)
WEST TX RUMBLE STRIP (0.46)
WILLOW CITY SIGN & RAIL, INC. (1.99)
AREA WIDE PROTECTIVE, INC. (0.29)
Contract #08173046
Totals2078724.6625704.00235476.0011.3

CountyBRAZOS
HighwaySH 105
FromAT THE BRAZOS RIVER
To.
CSJ0315-05-026
Proj IDBR 2014(643)
Work TypeGRADING, STRUCTURES, BASE AND SURF
 
3.28923601410.9219182363.8081.2
Work Order07-02-14
Work Began09-30-14
Work Completed
Time Computed09-30-14
Contract Working Days443
Addl Days Granted0
Working Days Charged354
Percent Time Used79
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0315-05-026
CHOCTAW ERECTORS, INC. (7.06)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.19)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.15)
ATS DRILLING, INC. (7.09)
HOUSTON SAWING & DRILLING (0.06)
BIG CREEK CONSTRUCTION, LTD. (6.72)
MINE SERVICE, INC. (5.33)
GEOSOURCE, INC. (0.94)
RICE ENVIRONMENTAL SERVICES (1.93)
PERFORMANCE EQUIPMENT (0.25)
MESA ROD BUSTERS, INC. (0.53)
EPCS ENVIRONMENTAL, LLC (1.52)
MCL CONTRACTING, LLC (0.25)
S & K TRUCKING (0.00)
TOM-MAC, INC. (1.03)
TNT CRANE & RIGGING, INC. (0.07)
CEN TEX HYDROSEED, INC. (0.41)
WILLOW CITY SIGN & RAIL, INC. (0.39)
Contract #05143202
Totals23601410.924356.2319182363.8081.2

CountyWASHINGTON
HighwayFM 389
From0.06 MILES WEST OF FM 332
ToUS 290
CSJ0315-08-037
Proj IDSTP 1602(156)
Work TypeREHABILITATE EXISTING ROADWAY
 
0.7454243520.681781833.6641.9
Work Order09-20-16
Work Began10-24-17
Work Completed
Time Computed10-20-16
Contract Working Days209
Addl Days Granted0
Working Days Charged74
Percent Time Used35
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0315-08-037
CANTU CONSTRUCTION, INC. (0.00)
ROADWAY SPECIALTIES, INC. (3.45)
CEN TEX HYDROSEED, INC. (1.12)
MURRAY CONSTRUCTION (0.29)
FARR FOUNDATION, INC. (1.06)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.54)
IVY ROSALVA CRUZ DBA IVY"S TRUCKING (0.00)
Contract #06163011
Totals4243520.68185438.701781833.6641.9

CountyLEON
HighwaySH 7
FromRUSK ST.
To3.8 MI EAST OF FM 1511
CSJ0335-01-031
Proj IDSTP 1602(317)
Work TypeREHABILITATE EXISTING ROAD
 
55.83825152378.8712224633.4248.6
Work Order09-20-16
Work Began10-31-16
Work Completed
Time Computed10-20-16
Contract Working Days522
Addl Days Granted42
Working Days Charged285
Percent Time Used50
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0335-01-031
COWBELL TRAFFIC SERVICES, INC. (0.33)
CHEROKEE SERVICES (0.07)
CEN TEX HYDROSEED, INC. (1.11)
FORTSON CONTRACTING, INC. (1.53)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.84)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.19)
W.S. CONSTRUCTION COMPANY (10.64)
COLD CREEK CONSTRUCTION, LTD (1.89)
SUPERIOR GROUTING SERVICES, INC. (0.38)
SAN-ANN-CO., INC. (0.00)
Contract #07163204
Totals25152378.87326208.4112224633.4248.6

CountyLEON
HighwaySH 7
FromAT BEAVER CREEK
To.
CSJ0335-03-042
Proj IDBR 2017(556)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1702256435.101504008.7866.6
Work Order06-07-17
Work Began09-11-17
Work Completed
Time Computed09-05-17
Contract Working Days137
Addl Days Granted3
Working Days Charged95
Percent Time Used67
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0335-03-042
CEN TEX HYDROSEED, INC. (1.23)
AREA WIDE PROTECTIVE, INC. (7.18)
SHINN AND GREGORY, INC. (3.41)
TEXAS ALTERNATIVE GRASSER, INC. (0.28)
D.I.J. CONSTRUCTION, INC (1.60)
BIG CREEK CONSTRUCTION, LTD. (13.29)
Contract #05173026
Totals2256435.10199106.041504008.7866.6

CountyGRIMES
HighwaySH 105
FromAT THE INTERSECTION OF SH 105
ToAND FM 1774
CSJ0338-01-052
Proj IDNH 1502(237)
Work TypeCONSTRUCT AT-GRADE INTERSECT IMPROV
 
1.7506022301.01722596.4411.9
Work Order06-14-17
Work Began10-12-17
Work Completed
Time Computed01-10-18
Contract Working Days254
Addl Days Granted0
Working Days Charged36
Percent Time Used14
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0338-01-052
CEN TEX HYDROSEED, INC. (2.81)
BATTEN DRILLING, INC. (0.26)
BRICK PAVING PLUS, INC. (0.98)
STRIPE LINES, INC. (0.95)
THIRD COAST SERVICES LLC (4.32)
STRIPE-A-ZONE, INC. (0.19)
MURRAY CONSTRUCTION (0.28)
POTTER TRUCKING (0.00)
AREA WIDE PROTECTIVE, INC. (1.47)
Contract #05173234
Totals6022301.01178777.79722596.4411.9

CountyBRAZOS
HighwayFM 60
FromAT THE INTERCHANGE OF FM 60 WITH
ToFM 2818
CSJ0506-01-105
Proj IDNH 1602(416)
Work TypeIMPROVE INTERCHANGE
 
0.48513863443.805660311.7040.8
Work Order12-12-16
Work Began03-06-17
Work Completed
Time Computed01-11-17
Contract Working Days396
Addl Days Granted2
Working Days Charged184
Percent Time Used46
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0506-01-105
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.66)
FLASHER EQUIPMENT COMPANY (1.25)
SCOTT DERR PAINTING CO, LLC (0.22)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.74)
BRICK PAVING PLUS, INC. (3.07)
BOENIGK MASONRY (0.28)
FORTSON CONTRACTING, INC. (0.18)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (6.90)
SCR CIVIL CONSTRUCTION, LLC (0.47)
AREA WIDE PROTECTIVE, INC. (0.53)
CEN TEX HYDROSEED, INC. (0.01)
HURRICANE FENCE CO. OF BRYAN, C.S. (0.05)
Contract #10163002
Totals13863443.80182688.915660311.7040.8

CountyBURLESON
HighwayFM 2155
FromAT BETHEL DRAW
To.
CSJ0506-04-022
Proj IDBR 2016(579)
Work TypeREPLACE EXISTING BRIDGE
 
0.2981647283.551723005.1199.9
Work Order03-29-16
Work Began06-16-16
Work Completed
Time Computed06-16-16
Contract Working Days212
Addl Days Granted6
Working Days Charged218
Percent Time Used100
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0506-04-022
CEN TEX HYDROSEED, INC. (2.37)
DUSTIN ALLEN, INC. (3.44)
FLASHER EQUIPMENT COMPANY (0.87)
JUST GROOVING, LTD. (0.27)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.09)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27)
MESA ROD BUSTERS, INC. (0.42)
BROCK CONSTRUCTION, LLC (0.87)
Contract #01163213
Totals1647283.550.001723005.1199.9

CountyBRAZOS
HighwayFM 2154
FromON FM 2154
ToAT GREENS PRAIRIE TRAIL
CSJ0540-04-072
Proj IDSTP 2016(837)
Work TypeINTERSECTION IMPROVEMENTS
 
0.4812056099.021858515.1690.3
Work Order09-23-16
Work Began10-24-16
Work Completed
Time Computed10-23-16
Contract Working Days97
Addl Days Granted11
Working Days Charged98
Percent Time Used90
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0540-04-072
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (9.51)
BRICK PAVING PLUS, INC. (0.07)
CEN TEX HYDROSEED, INC. (0.82)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.65)
PEDRO CARLOS CONSTRUCTION CO. (1.23)
TEXAS ALTERNATIVE GRASSER, INC. (0.72)
FLASHER EQUIPMENT COMPANY (1.99)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
Contract #05163209
Totals2056099.022695.841858515.1690.3

CountyBRAZOS
HighwayFM 159
FromSH 6
ToSH 105
CSJ0540-05-046
Proj IDSTP 1602(417)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
34.1772209014.251770088.3880.1
Work Order12-20-16
Work Began01-17-17
Work Completed
Time Computed01-17-17
Contract Working Days203
Addl Days Granted18
Working Days Charged217
Percent Time Used98
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0540-05-046
COMEN ENTERPRISE LLC (2.18)
PIPE WHOLESALERS OF TEXAS, INC. (0.00)
Contract #08163213
Totals2209014.2595271.761770088.3880.1

CountyBURLESON
HighwayFM 60
From1.2 MILES WEST OF FM 2039
To0.62 MILE EAST OF OLD RIVER
CSJ0648-03-050
Proj IDC 648-3-50
Work TypeGRADING, STRUCTURES, BASE AND SURFA
 
3.98410487720.8710778211.4299.9
Work Order02-19-14
Work Began04-07-14
Work Completed
Time Computed04-07-14
Contract Working Days227
Addl Days Granted34
Working Days Charged280
Percent Time Used107
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0648-03-050
BLUE STAR BARRICADES, INC. (0.26)
COWBELL TRAFFIC SERVICES, INC. (0.07)
D. I. J. CONSTRUCTION, INC. (0.65)
LONE STAR HIGHWAY PRODUCTS, INC. (0.52)
MURRAY CONSTRUCTION (0.38)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.16)
TEXAS ALTERNATIVE GRASSER, INC. (0.30)
PRIME ECO GROUP, INC. (0.00)
PIPE WHOLESALERS OF TEXAS, INC. (0.00)
COMEN ENTERPRISE (0.36)
Contract #12133003
Totals10487720.877710.0010778211.4299.9

CountyFREESTONE
HighwayIH 45
FromON IH 45 EFR & WFR FROM US 84
ToFM 27
CSJ0675-01-066
Proj IDNH 2017(348)
Work TypeREHABILITATE EXISTING ROAD
 
0.8712450487.602557851.2899.9
Work Order01-25-17
Work Began03-13-17
Work Completed
Time Computed02-24-17
Contract Working Days110
Addl Days Granted11
Working Days Charged169
Percent Time Used139
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-01-066
COMEN ENTERPRISE LLC (0.93)
R K STEPHENS CONSTRUCTION, LLC (5.06)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.84)
TEXAS ALTERNATIVE GRASSER, INC. (0.23)
AREA WIDE PROTECTIVE, INC. (0.51)
NIXON ENGINEERING (0.00)
Contract #12163027
Totals2450487.600.002557851.2899.9

CountyFREESTONE ETC
HighwayIH 45
FromUS 84
ToNAVARRO COUNTY LINE
CSJ0675-01-070
Proj IDSTP 2018(751)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
113.1563593926.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0675-01-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183013
Totals3593926.000.000.000.0

CountyLEON
HighwayIH 45
From1.5 MILES SOUTH OF US 79
To1.0 MILES NORTH OF US 79
CSJ0675-03-081
Proj IDNH 1702(563)
Work TypeRAMP RELOCATION
 
2.5008878806.513846259.8343.3
Work Order10-03-17
Work Began11-13-17
Work Completed
Time Computed11-02-17
Contract Working Days240
Addl Days Granted9
Working Days Charged62
Percent Time Used24
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-03-081
COMEN ENTERPRISE LLC (2.07)
TEXAS ALTERNATIVE GRASSER, INC. (1.13)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67)
THIRD COAST SERVICES LLC (4.95)
BOWMAN ENGINEERING & CONSULTING, INC (0.30)
UNDER CONSTRUCTION INC. (0.17)
LONE STAR HIGHWAY PRODUCTS, INC. (0.21)
PIPE WHOLESALERS OF TEXAS, INC. (2.89)
AREA WIDE PROTECTIVE, INC. (0.52)
Contract #08173231
Totals8878806.511203477.583846259.8343.3

CountyWALKER
HighwayIH 45
FromSH 75 ON SBML
To0.08 MILES S OF MADISON C/L
CSJ0675-06-096
Proj IDC 675-6-96
Work TypeHMA OVERLAY
 
14.8886333633.620.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0675-06-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183226
Totals6333633.620.000.000.0

CountyBURLESON
HighwayFM 60
FromSH 21 W
ToFM 111
CSJ0713-01-032
Proj IDSTP 1602(321)
Work TypeREHABILITATE EXISTING ROAD
 
2.4982429597.652087197.2088.0
Work Order10-14-16
Work Began12-08-16
Work Completed
Time Computed11-13-16
Contract Working Days100
Addl Days Granted0
Working Days Charged167
Percent Time Used167
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0713-01-032
J & M CONTRACTING, COMPANY (30.56)
CEN TEX HYDROSEED, INC. (2.05)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.86)
BROCK CONSTRUCTION, LLC (1.44)
ODUM SERVICES, L.P. (0.77)
Contract #07163228
Totals2429597.6571882.252087197.2088.0

CountyMILAM
HighwayFM 487
FromCOUNTY ROAD 402
To0.7 MILE NORTH OF COUNTY ROAD 235
CSJ0858-01-033
Proj IDSTP 1502(528)HES
Work TypePROVIDE ADDITIONAL PAVEMENT WIDTH
 
15.4095587641.645206667.0694.9
Work Order10-30-15
Work Began02-15-16
Work Completed
Time Computed01-28-16
Contract Working Days150
Addl Days Granted4
Working Days Charged242
Percent Time Used157
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0858-01-033
R K STEPHENS CONSTRUCTION, LLC (7.02)
ROADWAY SPECIALTIES, INC. (1.91)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45)
CEN TEX HYDROSEED, INC. (1.57)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.78)
NIXON ENGINEERING (0.00)
Contract #08153237
Totals5587641.640.005206667.0694.9

page 1 | page 2 | page 3