Monthly State Let Construction Report For Bryan District As Of Aug 16, 2018 Page 1 Of 3

Last Update: Thursday, August 16, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROBERTSON ETC
HighwaySH 6 ETC
From0.6 MILES NORTH OF FM 979
To0.35 MILES SOUTH OF FM 1644 WEST
CSJ0049-06-078
Proj IDNH 2018(395)
Work TypeASPHALT RUBBER SEAL
 
31.2892287795.202680472.2999.9
Work Order02-26-18
Work Began05-07-18
Work Completed
Time Computed05-07-18
Contract Working Days53
Addl Days Granted3
Working Days Charged42
Percent Time Used75
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-078
INTERSTATE BARRICADES & MARKINGS, INC. (10.45)
Contract #01183227
Totals2287795.2037390.652680472.2999.9

CountyROBERTSON ETC
HighwayUS 79 ETC
From0.145 MILES NORTH OF FM 485
ToWEST EVANS STREET
CSJ0049-07-063
Proj IDSTP 1702(018)HESG
Work TypeMILLED EDGE/CTR LINE RUMBLE STRIPS
 
312.0571388888.891368511.65100.0
Work Order06-14-17
Work Began09-11-17
Work Completed08-14-18
Time Computed07-14-17
Contract Working Days157
Addl Days Granted12
Working Days Charged169
Percent Time Used100
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-07-063
RED SIXTEEN CONSTRUCTION, INC (7.80)
Contract #05173230
Totals1388888.8911025.921368511.65100.0

CountyROBERTSON
HighwayUS 190
From0.27 MI NORTH OF CR 226 (ABBOTT RD)
To0.45 MILES S OF CR806 (SADBERRY RD)
CSJ0049-08-065
Proj IDNH 2018(615)
Work TypeRIGHT TURN DECEL / ACCEL LANES
 
12.3277241078.320.000.0
CountyROBERTSON
HighwayUS 190
From0.45 MI S OF CR 806 (SADBERRY RD)
ToOSR (COUNTY LINE)
CSJ0049-08-067
Proj IDC 49-8-67
Work TypeMILLING AND HMA OVERLAY
 
2.4651046311.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-31-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days298
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183239
Totals8287389.920.000.000.0

CountyBRAZOS ETC
HighwayUS 190 ETC
FromON SH 6 EFR 0.2 MI NORTH OF FM 2818
To0.55 MILES SOUTH OF FM 2818
CSJ0049-09-073
Proj IDNH 2017(179)
Work TypeSEAL COAT
 
479.94217282629.3215789904.2691.3
Work Order12-28-16
Work Began05-08-17
Work Completed
Time Computed05-01-17
Contract Working Days104
Addl Days Granted0
Working Days Charged99
Percent Time Used95
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-073
D.I.J. CONSTRUCTION, INC (14.49)
WATERS CONSTRUCTION CO., INC. (1.35)
BRYDL CONTRACTING, INC. (1.17)
Contract #10163001
Totals17282629.320.0015789904.2691.3

CountyBRAZOS
HighwayUS 190
FromAT FM 2818
To.
CSJ0049-09-079
Proj IDSTP 1802(486)HESG
Work TypeINSTALL TRAFFIC SIGNAL
 
0.200388060.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183241
Totals388060.000.000.000.0

CountyBRAZOS
HighwaySH 6
FromSH 21
ToFM 158
CSJ0049-12-096
Proj IDNH 1502(234)
Work TypeUPGRADE FREEWAY RAMPS
 
2.4597542870.376727255.3689.2
CountyZERO COUNTIES
Highway
From
To
CSJ0049-12-111
Proj ID
Work Type
 
0.00726261.700.0
Work Order08-20-15
Work Began02-29-16
Work Completed
Time Computed02-17-16
Contract Working Days308
Addl Days Granted55
Working Days Charged366
Percent Time Used100
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-096
ALLSTATE SIGNAL & CONSTRUCTION, LLC (4.25)
A BROTHERS MILLING, LLC (1.71)
CEN TEX HYDROSEED, INC. (4.03)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.58)
WILLOW CITY SIGN & RAIL, INC. (4.34)
COWBELL TRAFFIC SERVICES, INC. (0.16)
BEAR CREEK CONSTRUCTION, LLC (0.37)
AREA WIDE PROTECTIVE, INC. (0.53)
AARON CONCRETE CONTRACTORS, L.P. (0.61)
Contract #06153011
Totals7542870.37147459.997453517.0698.8

CountyROBERTSON ETC
HighwaySH 14 ETC
FromFM 46
ToSH 6
CSJ0049-15-013
Proj IDSTP 2018(131)HES
Work TypeTEXTURIZE SHOULDERS AND CENTERLINE
 
220.821918845.70849927.3892.4
Work Order11-13-17
Work Began01-29-18
Work Completed
Time Computed12-13-17
Contract Working Days93
Addl Days Granted0
Working Days Charged82
Percent Time Used88
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-15-013
RED SIXTEEN CONSTRUCTION, INC (5.32)
Contract #10173210
Totals918845.702150.21849927.3892.4

CountyBRAZOS
HighwayBS 6-R ETC
FromON BS 6-R
ToAT THE INTERSECTION WITH 29TH ST
CSJ0050-01-079
Proj IDSTP 2017(914)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
2.6411474037.571297965.4488.0
Work Order06-26-17
Work Began11-27-17
Work Completed
Time Computed09-22-17
Contract Working Days190
Addl Days Granted0
Working Days Charged161
Percent Time Used84
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-079
STRIPE LINES, INC. (4.71)
TRAF-TEX, INC. (48.61)
AREA WIDE PROTECTIVE, INC. (0.68)
Contract #04173004
Totals1474037.573533.001297965.4488.0

CountyBRAZOS
HighwayBS 6-R
FromFM 2818
To0.7 MILES SOUTH OF FM 2818
CSJ0050-01-080
Proj IDSTP 1802(407)HES
Work TypeINSTALL RAISED MEDIAN
 
1.5301137292.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days79
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183216
Totals1137292.260.000.000.0

CountyGRIMES
HighwaySH 6
From0.70 MILES N OF CR 413
ToWALLER COUNTY LINE
CSJ0050-03-095
Proj IDNH 1602(408)
Work TypeIMPROVE CROSSOVERS AND TURN LANES
 
9.5925968699.795803562.1397.2
Work Order10-06-16
Work Began01-05-17
Work Completed
Time Computed11-05-16
Contract Working Days222
Addl Days Granted69
Working Days Charged273
Percent Time Used93
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-095
CEN TEX HYDROSEED, INC. (0.74)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.98)
D. I. J. CONSTRUCTION, INC. (3.47)
ANGEL BROTHERS ENTERPRISES, LTD. (36.14)
WEST TEXAS RUMBLE STRIP (0.06)
J & M CONTRACTING, COMPANY (10.10)
ODUM SERVICES, L.P. (2.08)
Contract #08163236
Totals5968699.79100274.815803562.1397.2

CountyGRIMES
HighwaySH 6
FromBRAZOS COUNTY LINE
ToWALLER COUNTY LINE
CSJ0050-03-100
Proj IDC 50-3-100
Work TypeOVERLAY
 
14.3835798125.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183040
Totals5798125.910.000.000.0

CountyFREESTONE ETC
HighwayBU 84-R ETC
FromUS 84
ToSH 179
CSJ0057-02-037
Proj IDSTP 2018(232)
Work TypeSEAL COAT
 
385.07412525077.008823600.6870.4
Work Order12-04-17
Work Began05-14-18
Work Completed
Time Computed05-01-18
Contract Working Days75
Addl Days Granted1
Working Days Charged47
Percent Time Used61
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0057-02-037
D. I. J. CONSTRUCTION, INC. (17.61)
BRYDL CONTRACTING, INC. (0.81)
Contract #10173003
Totals12525077.003502976.558823600.6870.4

CountyBURLESON
HighwaySH 21
FromN BROADWAY ST
ToLOOP 83
CSJ0116-03-060
Proj IDNH 2017(346)
Work TypeSIDEWALKS AND LANDSCAPE DEV
 
1.290323412.25317232.1699.9
Work Order03-22-17
Work Began05-23-17
Work Completed
Time Computed05-16-17
Contract Working Days91
Addl Days Granted10
Working Days Charged120
Percent Time Used118
Contractor(s)
OPPORTUNITY EXCAVATION/CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0116-03-060
D.I.J. CONSTRUCTION, INC (1.86)
SCOTT DERR PAINTING CO, LLC (4.81)
BATTEN DRILLING, INC. (0.46)
Contract #12163020
Totals323412.250.00317232.1699.9

CountyBRAZOS
HighwaySH 21
FromBURLESON COUNTY LINE
To1.35 MILES W OF FM 2818
CSJ0116-04-100
Proj IDNH 2018(317)
Work TypeOVERLAY
 
21.0425427954.284533162.2183.5
Work Order02-05-18
Work Began03-06-18
Work Completed
Time Computed03-06-18
Contract Working Days135
Addl Days Granted11
Working Days Charged92
Percent Time Used63
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0116-04-100
AREA WIDE PROTECTIVE, INC. (0.50)
WEST TEXAS RUMBLE STRIP (0.21)
WILLOW CITY SIGN & RAIL, INC. (3.42)
FLASHER LIMITED (4.99)
CHEROKEE SERVICES (1.53)
Contract #12173213
Totals5427954.282156573.884533162.2183.5

CountyBRAZOS
HighwayUS 190
FromON US 190 (SH 21)
ToAT MARINO ROAD
CSJ0117-01-052
Proj IDSTP 1802(744)HES
Work TypeMODERNIZE INTERSECT TRAFFIC SIGNAL
 
0.003321352.990.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0117-01-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183056
Totals321352.990.000.000.0

CountyWASHINGTON
HighwaySH 36
FromAT WOLF CREEK (1.81 MI NW OF FM390)
To.
CSJ0186-05-040
Proj IDBR 1702(193)
Work TypeREPLACE EXISTING BRIDGE
 
0.0421448042.291425392.2298.4
Work Order06-14-17
Work Began09-05-17
Work Completed
Time Computed09-05-17
Contract Working Days70
Addl Days Granted1
Working Days Charged72
Percent Time Used101
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0186-05-040
CEN TEX HYDROSEED, INC. (1.00)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.29)
HUNTER DEMOLITION & WRECKING CORPORATION (3.24)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.11)
WILLOW CITY SIGN & RAIL, INC. (1.06)
STRIPE LINES, INC. (1.85)
TEXAS ALTERNATIVE GRASSER, INC. (0.19)
AREA WIDE PROTECTIVE, INC. (0.28)
DFW REBAR, INC. (0.27)
Contract #05173042
Totals1448042.290.001425392.2298.4

CountyWASHINGTON
HighwaySH 36
FromSH 36 NORTH
ToUS 290 WEST
CSJ0186-06-065
Proj IDNH 2013(761)
Work TypeWIDEN TO 4-LANE DIVIDED ROADWAY
 
2.92614327538.0414510626.6999.9
Work Order03-12-16
Work Began05-09-16
Work Completed
Time Computed04-10-16
Contract Working Days328
Addl Days Granted39
Working Days Charged384
Percent Time Used104
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0186-06-065
ROADSAFE TRAFFIC SYSTEMS, INC. (0.86)
CEN TEX HYDROSEED, INC. (0.46)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.40)
MESA ROD BUSTERS, INC. (0.82)
WILLOW CITY SIGN & RAIL, INC. (0.94)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.99)
LINDAMOOD DEMOLITION, INC. (1.02)
BRICK PAVING PLUS, INC. (0.07)
WEBBER BARRIER SERVICES, LLC. (0.89)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (1.10)
MESA ROD BUSTERS, INC. (0.09)
PEDRO CARLOS CONSTRUCTION CO. (0.60)
JEFFERY BAILEY TRUCKING, INC. (0.00)
PRIMATE CONSTRUCTION, INC. (0.29)
WEST TEXAS RUMBLE STRIP (0.03)
Contract #11153204
Totals14327538.04317689.9214510626.6999.9

CountyLEON
HighwayUS 79
FromFREESTONE COUNTY LINE
To2.7 MILES SW OF FM 542
CSJ0205-05-048
Proj IDNH 2017(758)
Work TypeOVERLAY
 
7.9942951399.983614268.4599.9
Work Order03-16-17
Work Began05-09-17
Work Completed
Time Computed04-15-17
Contract Working Days190
Addl Days Granted6
Working Days Charged196
Percent Time Used100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-05-048
COMEN ENTERPRISE LLC (5.86)
FLASHER EQUIPMENT COMPANY (0.86)
TOTAL HIGHWAY MAINTENANCE, LLC (1.94)
LONE STAR HIGHWAY PRODUCTS, INC. (0.80)
NIXON ENGINEERING (0.00)
Contract #02173028
Totals2951399.9840678.553614268.4599.9

CountyMILAM
HighwayUS 77
FromAT US 79
To.
CSJ0210-02-024
Proj IDSTP 2018(354)HESG
Work TypeINSTALL FLASHING BEACON
 
0.20057717.2529542.0051.1
Work Order02-05-18
Work Began06-04-18
Work Completed
Time Computed05-06-18
Contract Working Days36
Addl Days Granted0
Working Days Charged26
Percent Time Used72
Contractor(s)
SOUTH RANGER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0210-02-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173207
Totals57717.252850.0029542.0051.1

CountyWALKER
HighwaySH 30
FromTHE GRIMES COUNTY LINE
To0.8 MILE WEST OF FM 1791
CSJ0212-02-035
Proj IDSTP 2013(760)
Work TypeWIDEN ROADWAY TO SUPER 2 HIGHWAY
 
13.12716587457.2516425300.2499.0
Work Order08-20-15
Work Began02-15-16
Work Completed
Time Computed02-16-16
Contract Working Days240
Addl Days Granted45
Working Days Charged290
Percent Time Used101
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0212-02-035
AR DANIEL CONSTRUCTION SERVICES, INC. (1.25)
MURRAY CONSTRUCTION (0.37)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.76)
WILLOW CITY SIGN & RAIL, INC. (2.22)
WEST TEXAS RUMBLE STRIP (0.09)
CEN TEX HYDROSEED, INC. (0.17)
ALPHA EROSION PRODUCTS, LLC (0.19)
LONE STAR HIGHWAY PRODUCTS, INC. (0.21)
LONE STAR HIGHWAY PRODUCTS, INC. (0.01)
PIPE WHOLESALERS OF TEXAS, INC. (0.63)
RIOS TRUCKING CO. (3.08)
NIXON ENGINEERING (0.05)
AARON CONCRETE CONTRACTORS, L.P. (0.11)
Contract #06153205
Totals16587457.2574807.7016425300.2499.0

page 1 | page 2 | page 3