AVERAGE LOW BID UNIT PRICE - MAINTENANCE - STATEWIDE

Last Update: Monday, June 2, 2014
ITEMS 512 2061 TO 540 2041
Items Items Bid Code Range
0100 - 0169
0204 - 0292
0305 - 0361
0400 - 0496
0500 - 0560
0610 - 0690
0700 - 0788
1004 - 1138
2176 - 2199
3035 - 3281
4003 - 4568
5049 - 5953
6005 - 6986
7008 - 7649
8020 - 8987
500 2001 - 512 2059
512 2061 - 540 2041
540 2044 - 560 2044
Item No Description Units May 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
512 2061 PORT CTB (STKPL) (SNGL SLP) (TY J - J) LF     60.000 7.00000 1
512 2093 PORT CBR (DES SOURCE) LF     6,030.000 10.99502 2
512 2094 PORT CBR (MOVE) LF     9,000.000 5.66667 2
512 2095 PORT CBR (STOCKPILE) LF     6,030.000 4.59701 2
512 2097 REMOVE PRECAST PORTABLE TRAFFIC BARRIE LF     1,770.000 67.08000 1
514 2001 PERM CONC TRF BARR (SAFETY SH) (TY 1) LF     75.000 7.00000 1
514 2002 PERM CONC TRF BARR (SAFETY SH) (TY 2) LF     85.000 69.00000 1
514 2004 PERM CONC TRF BARR (SGL SLP) (TY 1) (42" LF     2,408.000 78.41570 2
514 2005 PERM CONC TRF BARR (SGL SLP) (TY 2) (42" LF     15.000 400.00000 1
514 2064 PERMCONCTRFBARR (SGL SLP) (TY1) (42") (RMA LF     1,000.000 50.00000 1
528 2004 LANDSCAPE PAVERS SY 250.000 30.00000 807.000 34.59727 4
529 2001 CONC CURB (TY I) LF     1,521.000 17.65105 3
529 2002 CONC CURB (TY II) LF 2,400.000 10.00000 11,584.000 15.12886 15
529 2003 CONC CURB & GUTTER (TY I) LF 55.000 28.00000 110.000 27.00000 2
529 2004 CONC CURB & GUTTER (TY II) LF 500.000 13.00000 16,210.000 25.87122 14
529 2005 CONC CURB (MONO) (TY I) LF     890.000 8.85393 4
529 2006 CONC CURB (MONO) (TY II) LF 125.000 21.00000 2,356.000 10.27589 9
529 2007 CONC CURB (DOWEL) LF 12.000 200.00000 11,457.500 13.42236 20
529 2008 CONC CURB & GUTTER (SPECIAL) LF     164.000 23.00000 1
529 2009 CONCRETE CURB (SPECIAL) LF 470.000 40.74000 880.000 31.07705 2
529 2010 CONC CURB AND GUTTER (TY II) (REINF) LF     611.000 26.29918 5
529 2011 CONC CURB & GUTTER (SAWTOOTH) LF     126.000 35.00000 1
529 2013 CONC CURB (TY A) (BARRIER) LF     1,500.000 7.36000 1
529 2015 CONC CURB (TY I) (REINF) LF     300.000 10.00000 1
529 2069 CONC CURB AND GUTTER (TY I) (REINF) LF     140.000 17.00000 1
529 2086 CONC CURB (DOWEL) (SLOTTED) LF     165.000 32.00000 1
530 2003 INTERSECTIONS (SURF TREAT) EA     16.000 2,625.60625 4
530 2005 INTERSECTIONS (ACP) SY     4,408.000 26.05471 2
530 2006 INTERSECTIONS (SURF TREAT) SY 12,581.000 1.50000 22,060.000 7.39717 14
530 2007 DRIVEWAYS (CONC) EA     16.000 2,808.25000 7
530 2008 DRIVEWAYS (ACP) EA     70.000 1,169.51429 13
530 2009 DRIVEWAYS (SURF TREAT) EA     268.000 334.98134 11
530 2010 DRIVEWAYS (CONC) SY     1,938.000 72.91303 18
530 2011 DRIVEWAYS (ACP) SY     10,912.000 31.51159 19
530 2012 DRIVEWAYS (SURF TREAT) SY 275.000 41.78000 13,446.000 18.10326 8
530 2015 TURNOUTS (SURF TREAT) EA     330.000 482.41861 14
530 2017 TURNOUTS (ACP) SY     252.000 10.63849 2
530 2018 TURNOUTS (SURF TREAT) SY     15,186.000 16.28917 9
530 2021 INTRSCT, DRVWAYS, & TURNOUT (SURF TREAT SY     3,235.000 34.97927 2
530 2057 TURNOUTS (RAP) SY     22,019.000 10.13814 2
530 2058 DRIVEWAYS (OTHER) EA     316.000 258.90823 14
530 2075 DRIVEWAYS (GRAVEL) SY     518.000 9.00000 1
531 2001 CONC SIDEWALKS (3') (6") LF     10.000 165.00000 1
531 2003 CONC SIDEWALKS (5') (6") LF     17.000 59.25000 1
531 2004 CONC SIDEWALKS (6") SY 100.000 60.00000 502.700 60.28148 10
531 2005 CURB RAMPS (TY 1) EA 8.000 1,250.00000 104.000 1,408.88154 21
531 2006 CURB RAMPS (TY 2) EA 8.000 1,325.00000 21.000 1,371.76190 8
531 2007 CURB RAMPS (TY 3) EA     2.000 1,685.00000 1
531 2008 CURB RAMPS (TY 4) EA     5.000 2,195.46000 2
531 2010 CURB RAMPS (TY 7) EA     42.000 1,337.94286 15
531 2011 CURB RAMPS (TY 8) EA 4.000 2,350.00000 12.000 1,991.66667 5
531 2012 CURB RAMPS (TY 9) EA     2.000 1,400.00000 1
531 2013 CURB RAMPS (TY 20) EA     2.000 2,500.00000 1
531 2015 CONC SIDEWALKS (4") SY 113.000 55.75221 1,354.000 48.78434 16
531 2016 CONC SIDEWALKS (6') (6") LF     50.000 46.00000 1
531 2017 CURB RAMPS (TY 21) EA     4.000 1,493.75000 3
531 2022 CURB RAMPS (TY 7) (MOD) EA     1.000 2,000.00000 1
531 2024 CONC SIDEWALK (5") SY     2,428.333 30.59000 1
531 2029 CONC SIDEWALKS (5") LF     30.000 90.00000 1
531 2040 CURB RAMPS (TY 5) EA     5.000 1,511.04000 3
531 2041 CURB RAMPS (TY 10) EA     21.000 1,439.52381 2
531 2054 CURB RAMPS SY     70.000 102.68000 1
531 2062 CURB RAMPS (TY 21) (MOD) EA     5.000 3,135.26000 1
531 2084 CONC SIDEWALKS (4') (4") LF     400.000 22.00000 1
531 2103 CONC SIDEWALKS (6") (RMA) SY     550.000 10.00000 1
533 2006 SHOULDER TEXTURING (MILLED) (ASPHALT) LF 173,980.000 0.12500 2,332,351.000 0.15666 13
536 2001 CONC MEDIAN LF     100.000 61.41000 1
536 2002 CONC MEDIAN SY     243.000 65.62189 3
536 2004 CONC DIRECTIONAL ISLAND SY     491.000 73.01477 4
540 2001 MTL W - BEAM GD FEN (TIM POST) LF 21,076.500 18.49122 66,357.640 17.79685 79
540 2002 MTL W - BEAM GD FEN (STEEL POST) LF     13,974.000 16.17099 23
540 2003 MTL THRIE - BEAM GD FEN (TIM POST) LF 50.000 20.00000 1,365.000 9.85348 10
540 2004 MTL THRIE - BEAM GD FEN (STEEL POST) LF     375.000 3.33333 2
540 2005 TERMINAL ANCHOR SECTION EA 26.000 22.76923 227.000 255.74476 36
540 2007 MTL W - BEAM GD FEN ADJUSTMENT LF 665.000 5.98496 35,563.000 2.16106 21
540 2008 MTL THRIE - BEAM GD FEN ADJUSTMENT LF     1,082.000 4.32948 7
540 2009 TERMINAL ANCHOR SECTION ADJUSTMENT EA     57.000 61.40351 4
540 2010 TRANSITION ADJUSTMENT EA 9.000 1.00000 46.000 546.41304 12
540 2011 MTL BEAM GD FEN TRANS (THRIE - BEAM) EA 44.000 686.36364 464.000 878.31881 58
540 2012 MTL BEAM GD FEN TRANS (TL2) EA     21.000 377.38095 5
540 2013 MTL BEAM GD FEN TRANS (T101) EA 16.000 850.00000 187.000 488.94230 20
540 2014 MTL W - BEAM GD FEN (LOW FILL CULVERT) LF 150.000 3.00000 654.000 20.20489 9
540 2015 MTL W - BEAM GD FEN (TIM POST) RADIUS RAIL LF 600.000 6.00000 4,900.000 15.40204 11
540 2016 MTL BM GD FN TRANS (THRIE) (RND TIM POST EA     44.000 671.18182 7
540 2017 MTL W - BEAM GD FEN (ROUND TIMBER POST) LF     11,700.000 19.50000 1
540 2019 MTL BEAM GD FEN TRANS (THRIE) (STL POST EA     27.000 1,279.07407 6
540 2021 MTL BEAM GD FEN TRANS (T101) (STL POST) EA     75.000 50.00000 2
540 2022 MTL W - BEAM GD FEN (STL POST) RADIUS RAIL LF     595.000 11.65882 5
540 2025 TERMINAL ANCHOR SECTION (DRWY) (SPCL) EA 1.000 400.00000 8.000 188.12500 3
540 2027 MTL W - BEAM GD FEN (STEEL POST) (TY IV) LF     1,437.500 36.85000 1
540 2030 MTL BEAM GD FEN (MOVE AND RESET) LF 200.000 3.00000 450.000 1.88889 4
540 2031 MTL BM GD FN (REMOVE & RESET) LF     5,612.000 7.34587 4
540 2032 MTL BM GD FN TRANSITION (REMOVE & RESET) EA     31.000 550.00000 3
540 2034 MTL W - BEAM GD FEN (SPECIAL) LF     125.000 25.00000 1
540 2036 DRIVEWAY TERMINAL ANCHOR SECTION EA 4.000 3.00000 13.000 235.15385 7
540 2037 MTL W - BEAM GD FEN (CRT POST) (SHRT RAD LF 100.000 18.00000 250.000 7.80000 4
540 2038 MTL BM GD FN (TIM POST) (W - BEAM FURN) LF 100.000 3.00000 450.000 5.92222 5
540 2039 MTL BEAM GD FEN TRANS (THRIE - BEAM) (OPT1 EA     4.000 1,500.00000 1
540 2040 MTL BEAM GD FEN TRANS (THRIE - BEAM) (OPT2 EA     8.000 3,462.50000 2
540 2041 MTL W - BEAM GD FEN (STEEL POST) (OPT2) LF     18.750 38.96000 1