Monthly State Let Construction Report For Lufkin District As Of Apr 11, 2014 Page 1 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyNACOGDOCHES
Highway SH 7 ETC
From FM 2713
To 0.27 MI E OF TERRAPIN CREEK
CSJ 0059-01-058
Proj ID STP 2014(208)
Work Type SEAL COAT
 
243.717 8730174.21 0.00 1212166.30 13.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0059-01-058
INTERSTATE BARRICADES & MARKINGS, INC. ( 14.38%)
Contract # 11133216
Totals 8730174.21 0.00 1212166.30 13.8

CountySHELBY
Highway SH 7
From MOUNT HERMON
To US 96
CSJ 0059-04-044
Proj ID STP 2014(335)
Work Type RESURFACE WITH PFC
 
8.049 2145521.44 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-18-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0059-04-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143221
Totals 2145521.44 0.00 0.00 0.0

CountyHOUSTON
Highway US 287 ETC
From ANDERSON COUNTY LINE
To 3.992 MI S OF LP 531 (BU 287-V)
CSJ 0109-03-032
Proj ID STP 2014(025)HES
Work Type TEXTURIZE SHOULDERS
 
181.385 1142739.06 372346.13 453710.59 39.7
Work Order 01-06-14
Work Began 02-05-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 66
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-03-032
WEST TEXAS RUMBLE STRIP(9.12%)
Contract # 09133021
Totals 1142739.06 372346.13 453710.59 39.7

CountyNACOGDOCHES
Highway SH 21
From 0.40 MI W OF FM 226
To FM 3276
CSJ 0118-08-060
Proj ID C 118-8-60
Work Type GRADING, STRUT, BASE, HMAC SURFACE
 
4.231 7883681.86 0.00 3693529.46 46.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-03-12
Work Began 01-11-13
Work Completed  
Time Computed 11-01-12
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 197
Percent Time Used 83
Contractor(s)
TRADECO INFRAESTRUCTURA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0118-08-060
N-LINE TRAFFIC MAINTENANCE, L.P. (0.17%)
AMERICAN REMEDIATION OPTIONS, INC. (1.62%)
VERITAS SUPPLY, INC. (1.03%)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (8.53%)
DUSTROL, INC.(0.42%)
TEXAS STAR TRANSPORT, LP (1.74%)
STRIPING TECHNOLOGY, L.P.(0.76%)
O DIRT (1.25%)
Contract # 07123023
Totals 7883681.86 0.00 3693529.46 46.8

CountySHELBY
Highway US 84
From RUSK COUNTY LINE
To US 59 IN TIMPSON
CSJ 0123-07-018
Proj ID STP 2013(516)
Work Type RECONSTRUCT PAVEMENT
 
6.413 5459220.41 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0123-07-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143027
Totals 5459220.41 0.00 0.00 0.0

CountySHELBY
Highway US 84
From AT SABINE RIVER
To .
CSJ 0175-01-005
Proj ID BR 2005(5)
Work Type REPLACE BRIDGE
 
0.209 9916183.38 163784.10 2143048.02 21.6
CountySHELBY
Highway US 84
From 0.62 MI W OF SABINE RIVER
To SABINE RIVER BRIDGE
CSJ 0175-02-078
Proj ID BR 1302(051)
Work Type GRADING, STRUCTURE, BASE, SURFACING
 
0.479 4226063.48 40753.30 150712.90 3.5
CountySHELBY
Highway VA
From SABINE RIVER BRIDGE
To 0.1 MI E OF LOUISIANA 5
CSJ 0911-39-022
Proj ID CC 911-39-22
Work Type GRADING, STRUCTURE, BASE, SURFACING
 
0.543 6269852.76 636184.30 1355104.70 21.6
Work Order 09-26-13
Work Began 01-06-14
Work Completed  
Time Computed 12-27-13
Contract Working Days 611
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 9
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0175-01-005
SOUTHWEST ENVIRONMENT SERVICES LLC (2.06%)
DUSTROL, INC.(0.34%)
FBL & ASSOCIATES (0.67%)
HOUSTON SAWING & DRILLING(0.04%)
MOORE BROTHERS CONSTRUCTION COMPANY( 12.37%)
RDI FOUNDATION DRILLING(7.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.84%)
W.O.E. CONSTRUCTION(0.28%)
HIGHWAY 19 CONSTRUCTION, LLC (6.48%)
STRIPING TECHNOLOGY, L.P.(0.71%)
RICE ENVIRONMENTAL SERVICES(0.09%)
BRUMLEY DEVELOPMENT, LLC (0.00%)
MCL CONTRACTING, LLC (0.39%)
Contract # 07133206
Totals 20412099.62 840721.70 3648865.62 17.8

CountySHELBY
Highway US 84
From JUST E OF MORRIS CREEK
To SH 7 IN JOAQUIN
CSJ 0175-02-083
Proj ID STP 2012(714)
Work Type RECONSTRUCT EXISTING PAVEMENT
 
2.497 5325125.48 363210.80 4793239.23 90.0
Work Order 10-24-12
Work Began 03-28-13
Work Completed  
Time Computed 01-22-13
Contract Working Days 167
Addl Days Granted 55
Working Days Charged 181
Percent Time Used 81
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0175-02-083
AMERICAN REMEDIATION OPTIONS, INC. (1.22%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.11%)
MOORE BROTHERS CONSTRUCTION COMPANY( 49.79%)
PANOLA SIGN & BARRICADE, INC.(0.21%)
RESONANT MACHINES(0.30%)
STRIPING TECHNOLOGY, L.P.(0.85%)
TEX OP CONSTRUCTION, LP(0.77%)
MAC TRANSPORTATION, LTD, L.L.P.(0.16%)
F. J. BURNELL, INC.(0.03%)
Contract # 08123035
Totals 5325125.48 363210.80 4793239.23 90.0

CountyNACOGDOCHES
Highway US 59
From 0.24 MI S OF FM 95 W
To US 259
CSJ 0175-07-056
Proj ID NH 2014(686)
Work Type MILL & INLAY SECTIONS AND SEAL
 
13.421 3335178.93 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0175-07-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143219
Totals 3335178.93 0.00 0.00 0.0

CountyNACOGDOCHES
Highway BU 59-F
From BOWIE ST
To MAIN ST (SH 21)
CSJ 0175-08-042
Proj ID STP 2013(676)
Work Type UPGRADE TRAFFIC SIGNALS
 
2.825 834399.31 0.00 390082.66 46.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 12-10-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 194
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 48
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0175-08-042
B & B UNDERGROUND, LLC (2.25%)
Contract # 05133234
Totals 834399.31 0.00 390082.66 46.7

CountyANGELINA
Highway US 59
From .9 MILES N. OF LP 287 (N) (@ UP RR)
To .1 MILES N. OF LP 287 (N)
CSJ 0176-02-090
Proj ID STP 99(770)RGS
Work Type REPLACE RAILROAD UNDERPASS
 
0.554 13760249.93 131432.30 8160970.29 59.3
CountyANGELINA
Highway US 59
From 0.13 MI N OF FM 3439
To LP 287/US 69
CSJ 0176-02-105
Proj ID STP 2012(501)HES
Work Type CONSTRUCT INTERCHANGE
 
1.829 38418975.28 1534473.83 23410294.92 60.9
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 764
Addl Days Granted 16
Working Days Charged 384
Percent Time Used 49
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-090
HIGHWAY TECHNOLOGIES, INC. (0.12%)
BATTERSON,LLP(0.57%)
DUSTIN ALLEN, INC. (0.72%)
A. H. BAKER SERVICES, INC. ( 10.54%)
W. W. FOUNDATION DRILLING, LTD.(1.86%)
MOORE BROTHERS CONSTRUCTION COMPANY(9.56%)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.08%)
DUSTROL, INC.(0.02%)
DRILL TECH DRILLING & SHORING, INC.(1.56%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.17%)
RAILWORKS TRACK SYSTEMS, INC.(0.14%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (0.54%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(2.70%)
ALLEN LOGGINGS & SONS, INC.(0.19%)
FUGRO CONSULTANTS LP (0.07%)
MESA ROD BUSTERS, INC. (0.80%)
EROSION CONTROL, INC.(0.92%)
EAST TEXAS LANDSCAPING, INC. (0.13%)
TEX OP CONSTRUCTION, LP(0.42%)
PINTO CONSTRUCTION CO., INC. (1.46%)
SCOTT DERR PAINTING CO, LLC(0.30%)
FARR FOUNDATION, INC.(1.39%)
COX CONTRACTORS, INC.(0.65%)
CURB PLANET INC. (0.00%)
WEBBER BARRIER SERVICES, LLC.(0.76%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.07%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.22%)
Contract # 06123008
Totals 52179225.21 1665906.13 31571265.21 60.5

CountyANGELINA
Highway US 59
From AT FM 2021
To .
CSJ 0176-02-102
Proj ID STP 2013(779)SB
Work Type CONSTRUCT GRADE SEPARATION
 
1.284 18772914.71 504033.29 4533942.40 24.1
Work Order 10-24-13
Work Began 11-11-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 515
Addl Days Granted 1
Working Days Charged 63
Percent Time Used 12
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-102
LOGGINS & SONS, ALLEN(3.28%)
SOUTH TEXAS ILLUMINATION, LLC(0.79%)
W. W. FOUNDATION DRILLING, LTD.(0.69%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.34%)
PINTO CONSTRUCTION CO., INC. (2.81%)
BREDA COMPANY, INC.(0.93%)
DUSTROL, INC.(0.72%)
WEBBER BARRIER SERVICES, LLC.(0.50%)
MOORE BROTHERS CONSTRUCTION COMPANY( 16.38%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.14%)
SCOTT DERR PAINTING CO (0.05%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18%)
Contract # 06133202
Totals 18772914.71 504033.29 4533942.40 24.1

CountyPOLK
Highway US 59
From US 287
To US 190
CSJ 0176-05-173
Proj ID STP 2014(028)HES
Work Type IMPROVE GUARDRAIL TO DES STANDARDS
 
32.084 738985.26 26768.66 732113.53 99.0
Work Order 10-15-13
Work Began 11-12-13
Work Completed  
Time Computed 10-31-13
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 100
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0176-05-173
PANOLA SIGN & BARRICADE, INC.(0.05%)
JUNIOR CONSTRUCTION COMPANY, INC.( 17.56%)
JOSE SANTOS CONSTRUCTION COMPANY, INC. ( 14.24%)
Contract # 09133227
Totals 738985.26 26768.66 732113.53 99.0

CountyPOLK
Highway US 59
From 0.47 MI S OF MILTON CREEK
To BU 59-J OVERPASS (SB LANES ONLY)
CSJ 0176-05-175
Proj ID NH 2014(292)
Work Type RESURFACE WITH MICROSURFACING
 
20.831 1316346.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
VIKING CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0176-05-175
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12133220
Totals 1316346.55 0.00 0.00 0.0

CountyPOLK
Highway US 59
From MC & SA RR OVERPASS
To GRASS MEDIAN S OF LEGGETT
CSJ 0176-05-176
Proj ID NH 2014(815)
Work Type HMA LEVEL - UP, OCST & PFC
 
8.594 5586536.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0176-05-176
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143034
Totals 5586536.64 0.00 0.00 0.0

CountyANGELINA
Highway FM 324 ETC
From LP 287
To US 59
CSJ 0176-08-021
Proj ID STP 2014(260)HES
Work Type TEXTURIZE SHOULDERS
 
77.753 569824.32 0.00 552967.28 97.0
Work Order 01-06-14
Work Began 01-20-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 27
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 40
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0176-08-021
BRYDL CONTRACTING, INC.(3.13%)
Contract # 11133014
Totals 569824.32 0.00 552967.28 97.0

CountyPOLK
Highway US 59
From JUST N OF KNIGHT STREET
To 0.5 MI SOUTH
CSJ 0177-01-099
Proj ID NH 2013(915)
Work Type REMOVE X - OVERS & CONST TURN - AROUNDS
 
0.610 1577675.45 334486.14 558845.91 35.4
Work Order 12-19-13
Work Began 02-03-14
Work Completed  
Time Computed 02-03-14
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 46
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0177-01-099
A R BROTHERS CONSTRUCTION SERVICES, INC. (9.12%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.07%)
PINTO CONSTRUCTION CO., INC. ( 15.26%)
AMERICAN REMEDIATION OPTIONS, INC. (2.17%)
COWBELL TRAFFIC SERVICES, INC. (0.31%)
M BROCK INC(1.73%)
DUSTROL, INC.(0.82%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.30%)
LUDCO, INC.(1.75%)
Contract # 09133028
Totals 1577675.45 334486.14 558845.91 35.4

CountySAN JACINTO
Highway US 59
From SH 150
To S OF UP RR
CSJ 0177-02-053
Proj ID STP 2009(574)SB
Work Type GR, STR & SURF
 
3.436 33439437.65 9104.62 33287259.77 99.5
CountySAN JACINTO
Highway US 59
From AT UPRR IN SHEPHERD
To .
CSJ 0177-02-072
Proj ID RW 177-2-72
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
0.001 683821.20 0.00 593394.94 86.7
Work Order 03-24-10
Work Began 04-01-10
Work Completed  
Time Computed 04-09-10
Contract Working Days 839
Addl Days Granted 76
Working Days Charged 910
Percent Time Used 99
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-053
SCOTT DERR PAINTING CO (0.04%)
INDUS CONSTRUCTION, L.P. ( 11.65%)
PFEIFFER & SON LTD.(0.04%)
VICON SERVICES, INC. (0.29%)
ARTEX ELECTRIC, INC. (3.80%)
BASE CONSTRUCTION, L.L.P.(5.22%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.54%)
BATTERSON, L.L.P.(0.60%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.37%)
CENTRAL NORTH CONSTRUCTION, LLC(0.73%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.17%)
FOSTER FENCE, LTD. (0.00%)
BELL BOTTOM FOUNDATION CO. (0.87%)
DORAN STEEL, INC.(0.03%)
WEST TEXAS RUMBLE STRIP(0.07%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.18%)
Contract # 02103001
Totals 34123258.85 9104.62 33880654.71 99.2

CountySAN JACINTO
Highway US 59
From 1.00 MILE NORTH OF FM 2914
To 1.00 MILE SOUTH OF FM 2914
CSJ 0177-02-080
Proj ID STP 1102(058)HES
Work Type CNSTR INTRCHANGE & CLOSE CROSSOVERS
 
2.059 12895988.97 208027.07 3631018.02 28.1
Work Order 01-31-12
Work Began 06-22-12
Work Completed  
Time Computed 04-02-12
Contract Working Days 535
Addl Days Granted 36
Working Days Charged 205
Percent Time Used 35
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-080
CRABTREE BARRICADE SYSTEMS, INC. (1.01%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.31%)
MESA ROD BUSTERS, INC. (2.31%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.44%)
ODUM SERVICES, L.P.(0.12%)
KOSSMAN CONTRACTING CO., INC.(0.38%)
ENVIRONMENTAL ALLIES, L.P. (0.07%)
SCOTT DERR PAINTING CO, LLC(0.16%)
TRAF-TEX, INC. (4.31%)
DUSTROL, INC.(0.07%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.27%)
WILLOW CITY SIGN & RAIL, INC.(0.12%)
TRIPLE B SERVICES, L.L.P.( 23.16%)
SMITH & COMPANY( 14.27%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.10%)
GREY WOLF CLEARING INC.(0.52%)
A & B CRUSHED CONCRETE (0.12%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.47%)
Contract # 12113203
Totals 12895988.97 208027.07 3631018.02 28.1

CountySAN JACINTO
Highway US 59
From JUST S OF UPRR IN SHEPHERD
To JUST N OF FM 2914
CSJ 0177-02-089
Proj ID STP 2013(916)
Work Type ADD SB FRTG RD & RECONST MAIN LANES
 
1.642 8948536.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143221
Totals 8948536.85 0.00 0.00 0.0

CountyANGELINA
Highway US 69
From AT US 59/LP 287 IN LUFKIN
To .
CSJ 0200-01-075
Proj ID NH 2013(393)
Work Type INTERSECTION IMPROVEMENTS
 
0.050 943447.64 0.00 891815.17 94.9
CountyANGELINA
Highway US 69
From LP 287
To 0.18 MI W OF FM 841
CSJ 0200-01-079
Proj ID NH 2013(393)
Work Type REPAIR CONC JTS AND RESURFACE W / PFC
 
2.604 2634126.08 0.00 2371474.80 90.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-26-13
Work Began 05-22-13
Work Completed  
Time Computed 05-22-13
Contract Working Days 76
Addl Days Granted 7
Working Days Charged 87
Percent Time Used 104
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0200-01-075
AMERICAN REMEDIATION OPTIONS, INC. (0.51%)
DUSTROL, INC.(0.84%)
HIGHWAY TECHNOLOGIES, INC. (0.13%)
J & M CONTRACTING, COMPANY (4.63%)
PINTO CONSTRUCTION CO., INC. (1.05%)
LONE STAR EQUIPMENT CO. INC. (INACTIVE--SEE 12687) (6.52%)
STRIPING TECHNOLOGY, L.P.(7.65%)
CRABTREE BARRICADE SYSTEMS, INC. (0.20%)
JAMES HILLIARD AND SONS LANDSCAPING, LLC (0.39%)
Contract # 02133006
Totals 3577573.72 0.00 3263289.97 91.3

page 1 | page 2 | page 3