Monthly State Let Construction Report For Lufkin District As Of May 10, 2016 Page 1 Of 4

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySHELBY
Highway SH 7
From 4.432 MI E OF FM 2913
To US 96
CSJ 0059-04-045
Proj ID STP 2016(419)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
9.550 1260125.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-31-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 123
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0059-04-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153026
Totals 1260125.90 0.00 0.00 0.0

CountySHELBY
Highway US 96
From 1.46 MI N OF SH 87 IN CENTER
To SH 87 IN CENTER
CSJ 0063-06-096
Proj ID NH 2016(271)
Work Type PLANE EXISTING SURFACE AND OVERLAY
 
3.275 2189250.49 643457.01 1198762.55 54.7
Work Order 02-22-16
Work Began 02-29-16
Work Completed  
Time Computed 02-24-16
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 60
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0063-06-096
DUSTROL, INC.(7.29%)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC( 12.57%)
PANOLA SIGN & BARRICADE, INC.(0.33%)
STRIPING TECHNOLOGY, L.P.(3.10%)
W.O.E. CONSTRUCTION(0.16%)
Contract # 11153027
Totals 2189250.49 643457.01 1198762.55 54.7

CountySAN AUGUSTINE
Highway SH 21 ETC
From SH 147
To FM 1
CSJ 0064-04-037
Proj ID STP 2016(274)
Work Type RESURFACE WITH SEAL COAT
 
177.815 7619981.14 0.00 733819.05 9.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 03-14-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 7
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-04-037
INTERSTATE BARRICADES & MARKINGS, INC. ( 14.26%)
Contract # 12153225
Totals 7619981.14 0.00 733819.05 9.6

CountySAN AUGUSTINE
Highway SH 21
From SH 147
To FM 1
CSJ 0064-04-038
Proj ID STP 2016(120)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
15.567 1848256.10 0.00 645281.02 34.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 01-18-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 27
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0064-04-038
AMERICAN REMEDIATION OPTIONS, INC. ( 26.79%)
Contract # 10153002
Totals 1848256.10 0.00 645281.02 34.9

CountySABINE
Highway FM 1
From SH 184
To 6.1 MI S OF SH 184
CSJ 0064-11-013
Proj ID STP 2014(737)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
21.014 1186968.00 1326.00 1156447.37 97.4
Work Order 07-22-14
Work Began 08-11-14
Work Completed  
Time Computed 08-07-14
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 88
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-11-013
PANOLA SIGN & BARRICADE, INC.(0.89%)
DUSTIN ALLEN, INC. ( 10.08%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.19%)
LUDCO, INC.(1.48%)
Contract # 06143037
Totals 1186968.00 1326.00 1156447.37 97.4

CountySABINE
Highway FM 1
From SH 184
To SS 1
CSJ 0064-11-014
Proj ID STP 1502(459)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
6.038 3634869.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 104
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-11-014
AMERICAN REMEDIATION OPTIONS, INC. (3.63%)
CRABTREE BARRICADE SYSTEMS, INC. (1.61%)
MOORE BROTHERS CONSTRUCTION COMPANY(4.76%)
PANOLA SIGN & BARRICADE, INC.(0.52%)
Contract # 07153245
Totals 3634869.32 0.00 0.00 0.0

CountyHOUSTON
Highway US 287
From 2.1 MI N OF FM 2663
To 0.761 MI S OF SL 304
CSJ 0109-04-029
Proj ID STP 2016(483)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
14.264 1611863.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-04-029
AMERICAN REMEDIATION OPTIONS, INC. (6.57%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 55.22%)
PANOLA SIGN & BARRICADE, INC.(0.87%)
Contract # 01163028
Totals 1611863.00 0.00 0.00 0.0

CountyTRINITY
Highway SH 19 ETC
From HOUSTON COUNTY LINE
To SH 94 IN TRINITY
CSJ 0109-07-050
Proj ID STP 2015(321)
Work Type RESURFACE WITH SEAL COAT
 
208.759 8618179.28 0.00 8231704.17 95.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-10-15
Work Began 02-28-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 65
Addl Days Granted 18
Working Days Charged 83
Percent Time Used 100
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-07-050
INTERSTATE BARRICADES & MARKINGS, INC. ( 14.05%)
Contract # 11143003
Totals 8618179.28 0.00 8231704.17 95.5

CountyHOUSTON
Highway SH 21
From FM 1280
To 2.32 MI E OF FM 2967
CSJ 0117-06-044
Proj ID NH 1502(067)
Work Type RECONSTRUCT AND ADD PASSING LANES
 
7.337 11812489.64 722799.83 3334407.38 28.2
Work Order 06-01-15
Work Began 09-02-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 314
Addl Days Granted 0
Working Days Charged 131
Percent Time Used 41
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0117-06-044
AMERICAN REMEDIATION OPTIONS, INC. (3.78%)
BIG CREEK CONSTRUCTION, LTD. ( 18.95%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.95%)
J & M CONTRACTING, COMPANY ( 22.49%)
PANOLA SIGN & BARRICADE, INC.(0.31%)
WEST TEXAS RUMBLE STRIP(0.06%)
Contract # 04153055
Totals 11812489.64 722799.83 3334407.38 28.2

CountyHOUSTON
Highway SH 21
From 2.32 MI E OF FM 2967
To SH 7
CSJ 0117-07-040
Proj ID NH 1502(460)
Work Type RECONST PVMNT & ADD PASSING LANES
 
5.724 11462865.25 0.00 2373109.53 20.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-15
Work Began 11-10-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 408
Addl Days Granted 8
Working Days Charged 88
Percent Time Used 21
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0117-07-040
DREWERY BROS TREE SERVICE, INC.(0.49%)
DUSTY ALLEN, INC.(0.56%)
J&M CONTRACTING COMPANY(8.44%)
PANOLA SIGN & BARRICADE, INC.(0.34%)
TEXOP CONSTRUCTION (0.95%)
WEST TEXAS RUMBLE STRIP(0.06%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.39%)
FREDONIA CONSTRUCTION SERVICES (0.10%)
Contract # 07153209
Totals 11462865.25 0.00 2373109.53 20.7

CountyNACOGDOCHES
Highway SH 21
From 0.40 MI W OF FM 226
To FM 3276
CSJ 0118-08-060
Proj ID C 118-8-60
Work Type GRADING, STRUT, BASE, HMAC SURFACE
 
4.231 7883681.86 19737.60 7692292.70 100.0
Work Order 10-03-12
Work Began 01-11-13
Work Completed 04-20-16
Time Computed 11-01-12
Contract Working Days 235
Addl Days Granted 79
Working Days Charged 429
Percent Time Used 136
Contractor(s)
FEDERAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0118-08-060
N-LINE TRAFFIC MAINTENANCE, L.P. (0.17%)
AMERICAN REMEDIATION OPTIONS, INC. (1.62%)
VERITAS SUPPLY, INC. (1.03%)
DREWERY CONSTRUCTION COMPANY, INCORPORATED ( 32.69%)
DUSTROL, INC.(0.42%)
TEXAS STAR TRANSPORT, LP (1.74%)
STRIPING TECHNOLOGY, L.P.(0.76%)
O DIRT (1.25%)
Contract # 07123023
Totals 7883681.86 19737.60 7692292.70 100.0

CountySAN AUGUSTINE
Highway SH 21
From AT US 96
To .
CSJ 0118-10-055
Proj ID STP 2015(154)
Work Type INTERSECTION IMPROVEMENTS
 
0.300 3381562.15 0.00 3311162.49 97.9
Work Order 11-06-14
Work Began 03-16-15
Work Completed  
Time Computed 11-22-14
Contract Working Days 90
Addl Days Granted 36
Working Days Charged 124
Percent Time Used 98
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0118-10-055
A R BROTHERS CONSTRUCTION SERVICES, INC. (9.78%)
PANOLA SIGN & BARRICADE, INC.(0.30%)
STRIPING TECHNOLOGY, L.P.(1.07%)
DREWERY & WHEATON, LLC (1.60%)
SOUTH TEXAS ILLUMINATION, LLC(4.34%)
FREDONIA CONSTRUCTION SERVICES (0.27%)
ADCOCK 4 INVESTMENTS, LLC(4.72%)
AMERICAN REMEDIATION OPTIONS, INC. (0.29%)
Contract # 09143230
Totals 3381562.15 0.00 3311162.49 97.9

CountySAN AUGUSTINE
Highway SH 21
From AT PERKINS CREEK
To .
CSJ 0118-10-058
Proj ID BR 2016(484)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.058 5229087.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0118-10-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163207
Totals 5229087.95 0.00 0.00 0.0

CountySHELBY
Highway FM 415
From AT BEAR BAYOU
To .
CSJ 0123-08-010
Proj ID BR 1502(621)
Work Type BRIDGE REPLACEMENT
 
0.165 1352960.21 0.00 0.00 0.0
Work Order 10-30-15
Work Began 00-00-00
Work Completed  
Time Computed 03-01-16
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0123-08-010
PANOLA SIGN & BARRICADE, INC.(0.71%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.75%)
AMERICAN REMEDIATION OPTIONS, INC. (4.69%)
STRIPING TECHNOLOGY, L.P.(1.22%)
Contract # 08153242
Totals 1352960.21 0.00 0.00 0.0

CountySHELBY
Highway US 84
From AT SABINE RIVER
To .
CSJ 0175-01-005
Proj ID BR 2005(5)
Work Type REPLACE BRIDGE
 
0.209 9916183.38 490500.00 6686845.02 67.4
CountySHELBY
Highway US 84
From 0.62 MI W OF SABINE RIVER
To SABINE RIVER BRIDGE
CSJ 0175-02-078
Proj ID BR 1302(051)
Work Type GRADING, STRUCTURE, BASE, SURFACING
 
0.479 4226063.48 26410.00 2375898.27 56.2
CountySHELBY
Highway VA
From SABINE RIVER BRIDGE
To 0.1 MI E OF LOUISIANA 5
CSJ 0911-39-022
Proj ID CC 911-39-22
Work Type GRADING, STRUCTURE, BASE, SURFACING
 
0.543 6269852.76 81892.54 4945915.94 78.8
Work Order 09-26-13
Work Began 01-06-14
Work Completed  
Time Computed 12-27-13
Contract Working Days 611
Addl Days Granted 0
Working Days Charged 573
Percent Time Used 93
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0175-01-005
SOUTHWEST ENVIRONMENT SERVICES LLC (2.06%)
DUSTROL, INC.(0.34%)
FBL & ASSOCIATES (0.67%)
HOUSTON SAWING & DRILLING(0.04%)
MOORE BROTHERS CONSTRUCTION COMPANY( 12.37%)
RDI FOUNDATION DRILLING(7.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.84%)
W.O.E. CONSTRUCTION(0.28%)
HIGHWAY 19 CONSTRUCTION, LLC (6.48%)
STRIPING TECHNOLOGY, L.P.(0.71%)
RICE ENVIRONMENTAL SERVICES(0.09%)
BRUMLEY DEVELOPMENT, LLC (0.00%)
MCL CONTRACTING, LLC (0.39%)
MILLER TRANSPORTATION(0.00%)
DAVID LAWLER CONSTRUCTION(0.07%)
LFI FT PIERCE, INC (0.04%)
ODUM SERVICES, L.P.(0.23%)
PROTECTION SERVICES INC. (0.03%)
DYKON BLASTING CORP(0.54%)
AGGREGATE TECHNOLOGIES, INC. (0.08%)
Contract # 07133206
Totals 20412099.62 598802.54 14008659.23 68.6

CountyNACOGDOCHES
Highway US 59
From 2.59 MI S OF RUSK COUNTY LINE
To US 259
CSJ 0175-07-057
Proj ID STP 2016(420)HES
Work Type IMPROVE GUARDRAIL TO DES STANDARDS
 
22.534 295401.65 0.00 159048.10 53.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 03-29-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 44
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0175-07-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153023
Totals 295401.65 0.00 159048.10 53.8

CountyNACOGDOCHES
Highway US 59
From LP 224
To 1.255 MI S OF LP 224
CSJ 0176-01-094
Proj ID STP 2014(918)HES
Work Type INSTALL RAISED MEDIAN
 
1.672 14030469.72 368760.69 6423546.05 45.7
Work Order 09-12-14
Work Began 01-07-15
Work Completed  
Time Computed 01-05-15
Contract Working Days 532
Addl Days Granted 0
Working Days Charged 326
Percent Time Used 61
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-094
BRADCO, LLC(6.00%)
DUSTIN ALLEN, INC. (0.64%)
DUSTROL, INC.(1.29%)
ECM ENVIRONMENTAL SERVICES, INC. (0.32%)
MOORE BROTHERS CONSTRUCTION COMPANY( 17.80%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.23%)
PINTO CONSTRUCTION CO., INC. (7.29%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.41%)
STRIPING TECHNOLOGY, L.P.(2.01%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(1.36%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.80%)
STEEL EFFECTS(0.00%)
L MOBLEY CONCRETE CONSTRUCTION (6.95%)
CARTHAGE DRILLING, INC.(0.07%)
Contract # 07143005
Totals 14030469.72 368760.69 6423546.05 45.7

CountyNACOGDOCHES
Highway US 59
From GRASS MEDIAN S OF SL 224
To ANGELINA RIVER BRIDGE
CSJ 0176-01-107
Proj ID NH 1602(177)
Work Type OVERLAY WITH PFC
 
6.632 1598523.47 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-107
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163032
Totals 1598523.47 0.00 0.00 0.0

CountyNACOGDOCHES
Highway US 59 ETC
From AT ANGELINA RIVER
To .
CSJ 0176-01-109
Proj ID BR 2016(696)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
9.588 2458818.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-19-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-109
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163227
Totals 2458818.05 0.00 0.00 0.0

CountyANGELINA
Highway US 59
From .9 MILES N. OF LP 287 (N) (@ UP RR)
To .1 MILES N. OF LP 287 (N)
CSJ 0176-02-090
Proj ID STP 99(770)RGS
Work Type REPLACE RAILROAD UNDERPASS
 
0.554 13760249.93 20180.00 12978182.21 94.4
CountyANGELINA
Highway US 59
From 0.13 MI N OF FM 3439
To LP 287/US 69
CSJ 0176-02-105
Proj ID STP 2012(501)HES
Work Type CONSTRUCT INTERCHANGE
 
1.829 38418975.28 32355.97 39100161.27 99.9
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 764
Addl Days Granted 104
Working Days Charged 876
Percent Time Used 100
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-090
HIGHWAY TECHNOLOGIES, INC. (0.12%)
BATTERSON,LLP(0.57%)
DUSTIN ALLEN, INC. (0.72%)
A. H. BAKER SERVICES, INC. ( 10.54%)
W. W. FOUNDATION DRILLING, LTD.(1.86%)
MOORE BROTHERS CONSTRUCTION COMPANY(9.56%)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.07%)
DUSTROL, INC.(0.02%)
DRILL TECH DRILLING & SHORING, INC.(1.56%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.17%)
RAILWORKS TRACK SYSTEMS, INC.(0.14%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (0.54%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(2.70%)
ALLEN LOGGINGS & SONS, INC.(0.19%)
FUGRO CONSULTANTS LP (0.07%)
MESA ROD BUSTERS, INC. (0.80%)
EROSION CONTROL, INC.(0.92%)
EAST TEXAS LANDSCAPING, INC. (0.13%)
TEX OP CONSTRUCTION, LP(0.42%)
PINTO CONSTRUCTION CO., INC. (1.46%)
SCOTT DERR PAINTING CO, LLC(0.30%)
FARR FOUNDATION, INC.(1.39%)
COX CONTRACTORS, INC.(0.65%)
CURB PLANET INC. (0.00%)
WEBBER BARRIER SERVICES, LLC.(0.76%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.07%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.22%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.88%)
HEMPHILL PILE DRIVING CO., A CORP. (0.01%)
SITAR CONSTRUCTION, LLC(0.11%)
TX DOWN UNDER CONSTRUCTION, LLC(0.01%)
ENCINO LANDSCAPE, INC. (0.17%)
ROY LEE WALKER (0.01%)
Contract # 06123008
Totals 52179225.21 52535.97 52078343.48 99.8

page 1 | page 2 | page 3 | page 4