Monthly State Let Construction Report For Lufkin District As Of Feb 09, 2018 Page 1 Of 3

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNACOGDOCHES ETC
HighwaySH 7 ETC
FromSL 224
ToFM 2713
CSJ0059-01-060
Proj IDSTP 2017(249)
Work TypeRESURFACE WITH SEAL COAT
 
224.67411201892.3410574695.8994.4
Work Order01-04-17
Work Began04-04-17
Work Completed
Time Computed04-04-17
Contract Working Days91
Addl Days Granted31
Working Days Charged122
Percent Time Used100
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0059-01-060
INTERSTATE BARRICADES & MARKINGS, INC. (11.35)
BRYDL CONTRACTING, INC. (0.65)
MOORE BROTHERS CONSTRUCTION COMPANY (2.25)
DUSTROL, INC. (0.33)
Contract #11163025
Totals11201892.34293598.7810574695.8994.4

CountySHELBY
HighwaySH 7
FromSAN AUGUSTINE COUNTY LINE
ToMOUNT HERMON
CSJ0059-03-020
Proj IDSTP 2018(519)
Work TypeOVERLAY WITH PFC
 
7.0031821663.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days39
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0059-03-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183028
Totals1821663.850.000.000.0

CountySHELBY ETC
HighwaySH 7 ETC
From4.246 MI N OF FM 2913
To0.763 MI W OF US 96
CSJ0059-04-046
Proj IDSTP 1702(249)HESG
Work TypeTEXTURIZE SHOULDERS
 
432.7032926648.23288940.809.8
Work Order07-20-17
Work Began10-25-17
Work Completed
Time Computed08-21-17
Contract Working Days185
Addl Days Granted0
Working Days Charged60
Percent Time Used32
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0059-04-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173228
Totals2926648.23150290.80288940.809.8

CountySHELBY
HighwaySH 87
FromSH 7
ToSH 147
CSJ0064-01-067
Proj IDSTP 2018(154)HES
Work TypeIMPROVE GUARDRAIL AND SAFETY TREAT
 
12.9591118355.8383022.037.4
Work Order11-20-17
Work Began01-29-18
Work Completed
Time Computed12-20-17
Contract Working Days202
Addl Days Granted0
Working Days Charged18
Percent Time Used8
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-01-067
DUSTIN ALLEN, INC. (16.45)
FLEX SUPPLY, LLC (1.23)
Contract #10173212
Totals1118355.8383022.0383022.037.4

CountySAN AUGUSTINE
HighwaySH 21
FromSH 147
ToFM 1
CSJ0064-04-038
Proj IDSTP 2016(120)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
15.5671848256.101735303.5494.8
Work Order12-21-15
Work Began01-18-16
Work Completed
Time Computed01-18-17
Contract Working Days176
Addl Days Granted0
Working Days Charged198
Percent Time Used112
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0064-04-038
AMERICAN REMEDIATION OPTIONS, INC. (26.79)
Contract #10153002
Totals1848256.100.001735303.5494.8

CountyHOUSTON
HighwaySH 19
FromSH 7
To1.616 MI N OF FM 231
CSJ0109-05-040
Proj IDSTP 2017(045)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
17.231921752.50888795.9496.4
Work Order11-08-16
Work Began12-12-16
Work Completed
Time Computed12-08-16
Contract Working Days140
Addl Days Granted22
Working Days Charged158
Percent Time Used97
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0109-05-040
ODUM SERVICES, L.P. (10.76)
Contract #09163218
Totals921752.502757.75888795.9496.4

CountyHOUSTON ETC
HighwaySH 19 ETC
From0.524 MI S OF FM 230
ToTRINITY COUNTY LINE
CSJ0109-06-041
Proj IDSTP 2018(681)HES
Work TypeMILLED EDGELINE/CENTERLINE RUMBLE
 
38.519294820.390.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-06-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183230
Totals294820.390.000.000.0

CountyHOUSTON
HighwaySH 21
FromAT TRINITY RIVER
To.
CSJ0117-06-049
Proj IDBR 2018(030)
Work TypeBRIDGE REPAIR
 
0.8981384827.00441149.8531.8
Work Order11-13-17
Work Began01-08-18
Work Completed
Time Computed12-13-17
Contract Working Days76
Addl Days Granted0
Working Days Charged12
Percent Time Used15
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0117-06-049
PANOLA SIGN & BARRICADE, INC. (0.67)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.20)
Contract #10173225
Totals1384827.00426406.80441149.8531.8

CountyHOUSTON
HighwaySH 21
From2.32 MI E OF FM 2967
ToSH 7
CSJ0117-07-040
Proj IDNH 1502(460)
Work TypeRECONST PVMNT & ADD PASSING LANES
 
5.72411462865.258234307.4571.8
Work Order10-06-15
Work Began11-10-15
Work Completed
Time Computed11-05-15
Contract Working Days408
Addl Days Granted75
Working Days Charged372
Percent Time Used77
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0117-07-040
DREWERY BROS TREE SERVICE, INC. (0.49)
DUSTY ALLEN, INC. (0.56)
J&M CONTRACTING COMPANY (8.44)
PANOLA SIGN & BARRICADE, INC. (0.34)
TEXOP CONSTRUCTION (0.95)
WEST TEXAS RUMBLE STRIP (0.06)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.39)
FREDONIA CONSTRUCTION SERVICES (0.10)
BATTEN DRILLING, INC. (0.01)
STRIPING TECHNOLOGY, L.P. (0.90)
Contract #07153209
Totals11462865.25158229.928234307.4571.8

CountyHOUSTON ETC
HighwaySH 7 ETC
FromSH 21
To0.072 MILES W. OF SL 304
CSJ0117-07-041
Proj IDNH 2018(252)
Work TypeRESURFACE WITH SEAL COAT
 
222.07610385539.170.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0117-07-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173011
Totals10385539.170.000.000.0

CountyHOUSTON
HighwaySH 21
From0.65 MI S OF SL 304
To2.567 MI S OF FM 1733
CSJ0118-01-019
Proj IDSTP 2017(307)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
25.3462981766.602687577.2190.1
Work Order02-14-17
Work Began03-08-17
Work Completed
Time Computed03-08-17
Contract Working Days211
Addl Days Granted0
Working Days Charged192
Percent Time Used90
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0118-01-019
ODUM SERVICES, L.P. (5.63)
PIPE WHOLESALERS OF TEXAS, INC. (0.00)
Contract #01173016
Totals2981766.60260881.892687577.2190.1

CountyNACOGDOCHES
HighwaySH 21
FromSH 7
ToSAN AUGUSTINE COUNTY LINE
CSJ0118-08-074
Proj IDSTP 2018(366)HES
Work TypeIMPROVE GUARDRAIL AND SAFETY TREAT
 
23.8641578551.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days205
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0118-08-074
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173023
Totals1578551.000.000.000.0

CountySAN AUGUSTINE
HighwaySH 21
FromAT ATTOYAC RIVER RELIEF
To.
CSJ0118-10-057
Proj IDBR 1702(518)
Work TypeREMOVE & REPLACE 2 STRUCTURES
 
0.5865292158.61200453.043.7
Work Order08-16-17
Work Began00-00-00
Work Completed
Time Computed11-14-17
Contract Working Days198
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0118-10-057
CRABTREE BARRICADE SYSTEMS, INC. (0.18)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.22)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.74)
WEST TEXAS RUMBLE STRIP (0.07)
STRIPING TECHNOLOGY, L.P. (0.38)
AMERICAN REMEDIATION OPTIONS, INC. (2.02)
Contract #07173009
Totals5292158.6156190.35200453.043.7

CountySAN AUGUSTINE
HighwaySH 21
FromAT PERKINS CREEK
To.
CSJ0118-10-058
Proj IDBR 2016(484)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.0585229087.953880651.6574.2
Work Order03-08-16
Work Began02-15-17
Work Completed
Time Computed05-09-16
Contract Working Days263
Addl Days Granted12
Working Days Charged176
Percent Time Used64
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0118-10-058
AMERICAN REMEDIATION OPTIONS, INC. (3.88)
COWBELL TRAFFIC SERVICES, INC. (0.09)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.14)
MCL CONTRACTING, LLC (0.13)
MOORE BROTHERS CONSTRUCTION COMPANY (7.53)
PANOLA SIGN & BARRICADE, INC. (0.17)
STRIPING TECHNOLOGY, L.P. (0.46)
TEXOP CONSTRUCTION (1.42)
ISAACS CONSTRUCTION SERVICES, LLC. (0.18)
Contract #01163207
Totals5229087.951200.003880651.6574.2

CountySAN AUGUSTINE
HighwaySH 21
FromAT NICIPER CREEK
To.
CSJ0118-10-060
Proj IDBR 2017(825)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.4822474844.691052401.0142.5
Work Order04-26-17
Work Began07-10-17
Work Completed
Time Computed07-10-17
Contract Working Days177
Addl Days Granted0
Working Days Charged90
Percent Time Used50
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0118-10-060
AMERICAN REMEDIATION OPTIONS, INC. (3.73)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.55)
PANOLA SIGN & BARRICADE, INC. (0.49)
TEXOP CONSTRUCTION (1.00)
STRIPING TECHNOLOGY, L.P. (0.81)
BOWMAN ENGINEERING & CONSULTING, INC (0.23)
Contract #03173027
Totals2474844.69152335.711052401.0142.5

CountySHELBY ETC
HighwayUS 84 ETC
FromRUSK COUNTY LINE
ToUS 59
CSJ0123-07-019
Proj IDSTP 2017(310)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
24.2951254729.101128405.0389.9
Work Order02-22-17
Work Began04-10-17
Work Completed
Time Computed03-27-17
Contract Working Days211
Addl Days Granted15
Working Days Charged178
Percent Time Used78
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0123-07-019
JE CASEY, LLC (4.77)
PANOLA SIGN & BARRICADE, INC. (1.86)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.15)
Contract #01173026
Totals1254729.1041110.901128405.0389.9

CountySHELBY
HighwayUS 84
FromAT SABINE RIVER
To.
CSJ0175-01-005
Proj IDBR 2005(5)
Work TypeREPLACE BRIDGE
 
0.2099916183.389877345.8599.9
CountySHELBY
HighwayUS 84
From0.62 MI W OF SABINE RIVER
ToSABINE RIVER BRIDGE
CSJ0175-02-078
Proj IDBR 1302(051)
Work TypeGRADING, STRUCTURE, BASE, SURFACING
 
0.4794226063.484087276.0796.7
CountySHELBY
HighwayVA
FromSABINE RIVER BRIDGE
To0.1 MI E OF LOUISIANA 5
CSJ0911-39-022
Proj IDCC 911-39-22
Work TypeGRADING, STRUCTURE, BASE, SURFACING
 
0.5436269852.766810579.2599.9
Work Order09-26-13
Work Began01-06-14
Work Completed
Time Computed12-27-13
Contract Working Days611
Addl Days Granted227
Working Days Charged883
Percent Time Used105
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0175-01-005
SOUTHWEST ENVIRONMENT SERVICES LLC (2.06)
DUSTROL, INC. (0.34)
FBL & ASSOCIATES (0.67)
HOUSTON SAWING & DRILLING (0.04)
MOORE BROTHERS CONSTRUCTION COMPANY (12.37)
RDI FOUNDATION DRILLING (7.41)
TOTAL HIGHWAY MAINTENANCE, LLC (0.84)
W.O.E. CONSTRUCTION (0.28)
HIGHWAY 19 CONSTRUCTION, LLC (6.48)
STRIPING TECHNOLOGY, L.P. (0.71)
RICE ENVIRONMENTAL SERVICES (0.09)
BRUMLEY DEVELOPMENT, LLC (0.00)
MCL CONTRACTING, LLC (0.39)
MILLER TRANSPORTATION (0.00)
DAVID LAWLER CONSTRUCTION (0.07)
LFI FT PIERCE, INC (0.04)
ODUM SERVICES, L.P. (0.23)
PROTECTION SERVICES INC. (0.03)
DYKON BLASTING CORP (0.54)
AGGREGATE TECHNOLOGIES, INC. (0.08)
VALLEY PLACERS, LLC (0.22)
JEFF WILSON BORING (0.01)
FRAMERS OF TENNESSEE, LLC (0.04)
L. S. EQUIPMENT CO., INC. (0.39)
ALPHA SERVICE AND PRODUCTS, INC. (0.02)
Contract #07133206
Totals20412099.6215814.6020775201.1799.9

CountyNACOGDOCHES
HighwayUS 59
FromLP 224
To1.255 MI S OF LP 224
CSJ0176-01-094
Proj IDSTP 2014(918)HES
Work TypeINSTALL RAISED MEDIAN
 
1.67214030469.7214171964.0299.9
Work Order09-12-14
Work Began01-07-15
Work Completed
Time Computed01-05-15
Contract Working Days532
Addl Days Granted37
Working Days Charged562
Percent Time Used98
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-094
BRADCO, LLC (6.00)
DUSTIN ALLEN, INC. (0.64)
DUSTROL, INC. (1.29)
ECM ENVIRONMENTAL SERVICES, INC. (0.32)
MOORE BROTHERS CONSTRUCTION COMPANY (17.80)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.23)
PINTO CONSTRUCTION CO., INC. (7.29)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.41)
STRIPING TECHNOLOGY, L.P. (2.01)
TEXAS TRAFFIC CONTROL SYSTEMS, INC. (1.36)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.80)
STEEL EFFECTS (0.00)
L MOBLEY CONCRETE CONSTRUCTION (6.95)
CARTHAGE DRILLING, INC. (0.07)
BREDA COMPANY, INC. (0.49)
CPAVE, INC. (0.17)
PEREZ CONSTRUCTION CO. (0.35)
ADCOCK 4 INVESTMENTS, LLC, DBA BRADCO (5.91)
SCOTT DERR PAINTING CO, LLC (0.05)
Contract #07143005
Totals14030469.7276327.8614171964.0299.9

CountyANGELINA
HighwayUS 59
FromANGELINA RIVER BRIDGE
To0.520 MI NORTH OF FM 2021
CSJ0176-02-120
Proj IDNH 2017(826)
Work TypeHMA LEVEL UP, OCST AND PFC SURFACE
 
2.6902865623.763144485.1499.9
Work Order04-24-17
Work Began06-19-17
Work Completed
Time Computed05-24-17
Contract Working Days77
Addl Days Granted0
Working Days Charged76
Percent Time Used98
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-120
PANOLA SIGN & BARRICADE, INC. (0.20)
CLARK CONSTRUCTION OF TEXAS, INC. (8.56)
DUSTROL, INC. (6.64)
AMERICAN REMEDIATION OPTIONS, INC. (0.44)
STRIPE-A-ZONE, INC. (1.13)
NLG CONSTRUCTION, INC. (0.49)
Contract #03173220
Totals2865623.760.003144485.1499.9

CountyPOLK
HighwayUS 59
FromSL 393 S
ToTRINITY RIVER
CSJ0177-01-102
Proj IDNH 2017(641)
Work TypeHMA LEVEL-UP, OCST, & PFC
 
1.9702215251.082316083.2199.9
Work Order03-16-17
Work Began05-24-17
Work Completed
Time Computed05-08-17
Contract Working Days55
Addl Days Granted15
Working Days Charged69
Percent Time Used98
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0177-01-102
AWP, INC. (0.24)
CLARK CONSTRUCTION OF TEXAS, INC. (10.11)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.42)
DUSTROL, INC. (4.89)
STRIPING TECHNOLOGY, L.P. (1.85)
CHEROKEE SERVICES (0.36)
WEST TEXAS RUMBLE STRIP (0.18)
HIGHWAY DATA SERVICES (0.05)
Contract #02173007
Totals2215251.0821.582316083.2199.9

page 1 | page 2 | page 3