Monthly State Let Construction Report For Lufkin District As Of May 15, 2013 Page 1 Of 3

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySAN AUGUSTINE
Highway SH 7 ETC
From NACOGDOCHES COUNTY LINE
To SHELBY COUNTY LINE
CSJ 0059-02-013
Proj ID STP 2012(111)
Work Type SEAL COAT
 
229.631 8597338.04 72460.30 7429590.09 86.4
Work Order 11-30-11
Work Began 06-11-12
Work Completed  
Time Computed 06-11-12
Contract Working Days 65
Addl Days Granted 5
Working Days Charged 65
Percent Time Used 92
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0059-02-013
D. I. J. CONSTRUCTION, INC.( 18.98%)
Contract # 11113015
Totals 8597338.04 72460.30 7429590.09 86.4

CountySHELBY
Highway US 59
From PANOLA COUNTY LINE
To SP RAILROAD OVERPASS IN TENAHA
CSJ 0063-06-094
Proj ID NH 2013(283)
Work Type REHABILITATE EXISTING PAVEMENT
 
2.163 3565080.07 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-31-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0063-06-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12123230
Totals 3565080.07 0.00 0.00 0.0

CountySHELBY
Highway SH 87 ETC
From FM 417
To SH 147
CSJ 0064-01-065
Proj ID STP 2013(167)
Work Type RESURFACE WITH SEAL COAT
 
245.917 9165319.80 175752.98 1127359.77 12.3
Work Order 01-04-13
Work Began 02-11-13
Work Completed  
Time Computed 02-01-13
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-01-065
INTERSTATE BARRICADES & MARKINGS, INC. ( 15.32%)
Contract # 11123221
Totals 9165319.80 175752.98 1127359.77 12.3

CountySABINE
Highway FM 201
From US 96
To FM 2343
CSJ 0064-15-006
Proj ID PLD 2013(065)
Work Type RESTORATION OF EXIST PVMT (IN SECTS)
 
7.422 620822.23 245939.23 544479.01 87.7
Work Order 10-18-12
Work Began 03-19-13
Work Completed  
Time Computed 01-16-13
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 51
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0064-15-006
AMERICAN REMEDIATION OPTIONS, INC. (0.49%)
CRABTREE BARRICADE SYSTEMS, INC. (4.17%)
PANOLA SIGN & BARRICADE, INC.(0.77%)
Contract # 09123240
Totals 620822.23 245939.23 544479.01 87.7

CountyNACOGDOCHES
Highway SH 21
From 0.40 MI W OF FM 226
To FM 3276
CSJ 0118-08-060
Proj ID C 118-8-60
Work Type GRADING, STRUT, BASE, HMAC SURFACE
 
4.231 7883681.86 393119.12 927738.28 11.7
Work Order 10-03-12
Work Began 01-11-13
Work Completed  
Time Computed 11-01-12
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 24
Contractor(s)
TRADECO INFRAESTRUCTURA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0118-08-060
N-LINE TRAFFIC MAINTENANCE, L.P. (0.17%)
AMERICAN REMEDIATION OPTIONS, INC. (1.62%)
VERITAS SUPPLY, INC. (1.03%)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (8.53%)
DUSTROL, INC.(0.42%)
TEXAS STAR TRANSPORT, LP (1.74%)
Contract # 07123023
Totals 7883681.86 393119.12 927738.28 11.7

CountySHELBY
Highway US 59 ETC
From CONCRETE PAVEMENT IN TENAHA
To 0.50 M S
CSJ 0175-02-082
Proj ID NH 2012(133)
Work Type RESURFACE WITH MICROSURFACING
 
29.959 2792818.80 0.00 529140.62 18.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-13-11
Work Began 00-00-00
Work Completed  
Time Computed 08-01-12
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 66
Contractor(s)
TNT'S PIPELINE, CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0175-02-082
DUSTROL, INC.(0.89%)
CRABTREE BARRICADE SYSTEMS, INC. (9.95%)
PANOLA SIGN & BARRICADE, INC.(0.70%)
NY-MAC ENTERPRISES, INC. ( 58.44%)
Contract # 11113221
Totals 2792818.80 0.00 529140.62 18.9

CountySHELBY
Highway US 84
From JUST E OF MORRIS CREEK
To SH 7 IN JOAQUIN
CSJ 0175-02-083
Proj ID STP 2012(714)
Work Type RECONSTRUCT EXISTING PAVEMENT
 
2.497 5325125.48 319310.97 355110.97 6.6
Work Order 10-24-12
Work Began 03-28-13
Work Completed  
Time Computed 01-22-13
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 10
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0175-02-083
AMERICAN REMEDIATION OPTIONS, INC. (1.22%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.11%)
MOORE BROTHERS CONSTRUCTION COMPANY( 49.79%)
PANOLA SIGN & BARRICADE, INC.(0.21%)
RESONANT MACHINES(0.30%)
STRIPING TECHNOLOGY, L.P.(0.85%)
TEX OP CONSTRUCTION, LP(0.77%)
Contract # 08123035
Totals 5325125.48 319310.97 355110.97 6.6

CountySHELBY
Highway US 84
From SH 7
To JUST W OF FM 2787
CSJ 0175-02-085
Proj ID STP 2012(370)
Work Type REHAB EXIST PVMT & ADD LEFT TURN LN
 
1.724 3569846.90 977291.10 3591427.25 99.9
Work Order 05-10-12
Work Began 08-14-12
Work Completed  
Time Computed 08-08-12
Contract Working Days 96
Addl Days Granted 17
Working Days Charged 103
Percent Time Used 91
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0175-02-085
AMERICAN REMEDIATION OPTIONS, INC. (1.70%)
BANNER SIGN & BARRICADE, INC. (HOOKS)(0.25%)
MOORE BROTHERS CONSTRUCTION COMPANY( 28.47%)
STRIPING TECHNOLOGY, L.P.(1.70%)
TEX OP CONSTRUCTION, LP(0.53%)
P.R. PARKER COMPANY, INC.(0.15%)
L.S. EQUIPMENT CO., INC. (0.81%)
Contract # 03123219
Totals 3569846.90 977291.10 3591427.25 99.9

CountyNACOGDOCHES
Highway BU 59-F
From BOWIE ST
To MAIN ST (SH 21)
CSJ 0175-08-042
Proj ID STP 2013(676)
Work Type UPGRADE TRAFFIC SIGNALS
 
2.825 834399.31 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 194
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0175-08-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133234
Totals 834399.31 0.00 0.00 0.0

CountyNACOGDOCHES
Highway US 59
From 6.75 MI N OF ANGELINA RIVER BRIDGE
To ANGELINA RIVER BRIDGE_(NB ONLY)
CSJ 0176-01-097
Proj ID NH 2013(328)
Work Type HMA LEVEL - UP AND PFC SURFACE
 
6.746 2585770.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-097
J & M CONTRACTING, COMPANY (1.38%)
PANOLA SIGN & BARRICADE, INC.(0.20%)
STRIPING TECHNOLOGY, L.P.(1.62%)
Contract # 01133013
Totals 2585770.98 0.00 0.00 0.0

CountyANGELINA
Highway US 59
From .9 MILES N. OF LP 287 (N) (@ UP RR)
To .1 MILES N. OF LP 287 (N)
CSJ 0176-02-090
Proj ID STP 99(770)RGS
Work Type REPLACE RAILROAD UNDERPASS
 
0.554 13760249.93 1288092.08 4707020.97 34.2
CountyANGELINA
Highway US 59
From 0.13 MI N OF FM 3439
To LP 287/US 69
CSJ 0176-02-105
Proj ID STP 2012(501)HES
Work Type CONSTRUCT INTERCHANGE
 
1.829 38418975.28 610332.88 11097872.20 28.8
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 764
Addl Days Granted 11
Working Days Charged 160
Percent Time Used 20
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-090
HIGHWAY TECHNOLOGIES, INC. (0.12%)
BATTERSON,LLP(0.57%)
DUSTIN ALLEN, INC. (0.72%)
A. H. BAKER SERVICES, INC. ( 10.54%)
W. W. FOUNDATION DRILLING, LTD.(1.86%)
MOORE BROTHERS CONSTRUCTION COMPANY(9.56%)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.08%)
DUSTROL, INC.(0.02%)
DRILL TECH DRILLING & SHORING, INC.(1.56%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.17%)
RAILWORKS TRACK SYSTEMS, INC.(0.14%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (0.54%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(2.70%)
ALLEN LOGGINGS & SONS, INC.(0.19%)
FUGRO CONSULTANTS LP (0.07%)
MESA ROD BUSTERS, INC. (0.80%)
EROSION CONTROL, INC.(0.92%)
EAST TEXAS LANDSCAPING, INC. (0.13%)
TEX OP CONSTRUCTION, LP(0.42%)
PINTO CONSTRUCTION CO., INC. (1.46%)
SCOTT DERR PAINTING CO, LLC(0.30%)
FARR FOUNDATION, INC.(1.39%)
COX CONTRACTORS, INC.(0.65%)
CURB PLANET INC. (0.00%)
WEBBER BARRIER SERVICES, LLC.(0.76%)
Contract # 06123008
Totals 52179225.21 1898424.96 15804893.17 30.2

CountyPOLK
Highway US 59
From UP RR OVERPASS @ CHOATES CREEK
To 0.3 MI S OF MORGAN CREEK BRIDGE
CSJ 0177-01-097
Proj ID NH 2013(329)
Work Type REHABILITATE EXISTING PAVEMENT
 
4.793 3822937.37 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0177-01-097
COWBELL TRAFFIC SERVICES, INC. (0.30%)
C PAVE, INC. (2.14%)
DUSTIN ALLEN, INC. (1.85%)
HIGHWAY TECHNOLOGIES, INC. (0.22%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.06%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.49%)
TEX OP CONSTRUCTION, LP(3.00%)
WATERS CONSTRUCTION CO., INC.(6.00%)
Contract # 02133223
Totals 3822937.37 0.00 0.00 0.0

CountySAN JACINTO
Highway US 59
From SH 150
To S OF UP RR
CSJ 0177-02-053
Proj ID STP 2009(574)SB
Work Type GR, STR & SURF
 
3.436 33439437.65 389608.53 32150606.52 96.1
CountySAN JACINTO
Highway US 59
From AT UPRR IN SHEPHERD
To .
CSJ 0177-02-072
Proj ID RW 177-2-72
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
0.001 683821.20 0.00 593394.94 86.7
Work Order 03-24-10
Work Began 04-01-10
Work Completed  
Time Computed 04-09-10
Contract Working Days 839
Addl Days Granted 34
Working Days Charged 809
Percent Time Used 92
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-053
SCOTT DERR PAINTING CO (0.04%)
INDUS CONSTRUCTION, L.P. ( 11.65%)
PFEIFFER & SON LTD.(0.04%)
VICON SERVICES, INC. (0.29%)
ARTEX ELECTRIC, INC. (3.80%)
BASE CONSTRUCTION, L.L.P.(5.22%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.54%)
BATTERSON, L.L.P.(0.60%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.37%)
CENTRAL NORTH CONSTRUCTION, LLC(0.73%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.17%)
FOSTER FENCE, LTD. (0.00%)
BELL BOTTOM FOUNDATION CO. (0.87%)
DORAN STEEL, INC.(0.03%)
WEST TEXAS RUMBLE STRIP(0.07%)
Contract # 02103001
Totals 34123258.85 389608.53 32744001.46 95.9

CountySAN JACINTO
Highway US 59
From 1.00 MILE NORTH OF FM 2914
To 1.00 MILE SOUTH OF FM 2914
CSJ 0177-02-080
Proj ID STP 1102(058)HES
Work Type CNSTR INTRCHANGE & CLOSE CROSSOVERS
 
2.059 12895988.97 4000.00 2222439.76 17.2
Work Order 01-31-12
Work Began 06-22-12
Work Completed  
Time Computed 04-02-12
Contract Working Days 535
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 6
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-080
CRABTREE BARRICADE SYSTEMS, INC. (1.01%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.31%)
MESA ROD BUSTERS, INC. (2.31%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.44%)
ODUM SERVICES, L.P.(0.12%)
KOSSMAN CONTRACTING CO., INC.(0.38%)
ENVIRONMENTAL ALLIES, L.P. (0.07%)
SCOTT DERR PAINTING CO, LLC(0.16%)
TRAF-TEX, INC. (4.31%)
DUSTROL, INC.(0.07%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.27%)
WILLOW CITY SIGN & RAIL, INC.(0.12%)
TRIPLE B SERVICES, L.L.P.( 23.16%)
SMITH & COMPANY( 14.27%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.10%)
GREY WOLF CLEARING INC.(0.52%)
A & B CRUSHED CONCRETE (0.12%)
Contract # 12113203
Totals 12895988.97 4000.00 2222439.76 17.2

CountyANGELINA
Highway US 69
From AT US 59/LP 287 IN LUFKIN
To .
CSJ 0200-01-075
Proj ID NH 2013(393)
Work Type INTERSECTION IMPROVEMENTS
 
0.050 943447.64 0.00 0.00 0.0
CountyANGELINA
Highway US 69
From LP 287
To 0.18 MI W OF FM 841
CSJ 0200-01-079
Proj ID NH 2013(393)
Work Type REPAIR CONC JTS AND RESURFACE W / PFC
 
2.604 2634126.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-26-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0200-01-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133006
Totals 3577573.72 0.00 0.00 0.0

CountyANGELINA
Highway BU 69-J
From FM 58
To US 59/LP 287
CSJ 0200-01-081
Proj ID STP 2013(242)
Work Type RESURFACE WITH MICROSURFACING
 
14.969 1167447.12 108334.46 108334.46 9.2
Work Order 02-12-13
Work Began 04-30-13
Work Completed  
Time Computed 04-30-13
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 4
Contractor(s)
NY-MAC ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-01-081
PANOLA SIGN & BARRICADE, INC.(0.72%)
CRABTREE BARRICADE SYSTEMS, INC. (8.17%)
Contract # 12123007
Totals 1167447.12 108334.46 108334.46 9.2

CountySABINE
Highway SH 87
From 0.2 MI N OF FM 276
To SH 21 IN MILAM
CSJ 0304-02-038
Proj ID PLD 2012(187)
Work Type PROVIDE ADDL PAV SURF WID & TURN LN
 
5.479 3199990.60 436506.40 861758.46 26.9
Work Order 01-04-13
Work Began 02-18-13
Work Completed  
Time Computed 02-18-13
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 37
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0304-02-038
AMERICAN REMEDIATION OPTIONS, INC. (2.23%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 11.61%)
CRABTREE BARRICADE SYSTEMS, INC. (1.31%)
EXPRESS PERSONNEL SERVICES (0.15%)
M BROCK INC(1.70%)
PINTO CONSTRUCTION CO., INC. ( 13.01%)
Contract # 11123220
Totals 3199990.60 436506.40 861758.46 26.9

CountySABINE
Highway SH 87
From 1.61 MI S OF FM 944
To 0.2 MI SE OF FM 2928
CSJ 0304-04-042
Proj ID STP 2013(463)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
7.996 1937298.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0304-04-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133229
Totals 1937298.95 0.00 0.00 0.0

CountyTRINITY
Highway SH 94
From AT NECHES RIVER RELIEFS
To .
CSJ 0319-03-048
Proj ID BR 2009(221)
Work Type REPLACE BRIDGES AND APPROACHES
 
3.068 10888820.53 52506.36 10888391.52 99.9
Work Order 03-09-10
Work Began 04-16-10
Work Completed  
Time Computed 03-25-10
Contract Working Days 783
Addl Days Granted 5
Working Days Charged 780
Percent Time Used 98
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0319-03-048
AMERICAN REMEDIATION OPTIONS, INC. (2.03%)
COWBELL TRAFFIC SERVICES, INC. (0.19%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.11%)
MOORE BROTHERS CONSTRUCTION COMPANY( 13.73%)
STRIPING TECHNOLOGY, L.P.(0.13%)
TREVCON, INC.(2.24%)
MESA ROD BUSTERS, INC. (0.18%)
LONE STAR HIGHWAY PRODUCTS, INC. (2.83%)
TEX OP CONSTRUCTION, LP(0.31%)
Contract # 01103002
Totals 10888820.53 52506.36 10888391.52 99.9

CountyHOUSTON
Highway SH 7
From AT SH 21
To .
CSJ 0335-02-027
Proj ID STP 2013(119)HES
Work Type REALIGN INTERSECTION
 
0.510 976008.54 219775.88 818463.52 83.8
Work Order 12-14-12
Work Began 01-21-13
Work Completed  
Time Computed 01-21-13
Contract Working Days 70
Addl Days Granted 4
Working Days Charged 51
Percent Time Used 68
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0335-02-027
AMERICAN REMEDIATION OPTIONS, INC. (3.91%)
ROAD SAFE(2.79%)
THIRD COAST SERVICES LLC (6.46%)
TEX OP CONSTRUCTION, LP(1.17%)
Contract # 10123221
Totals 976008.54 219775.88 818463.52 83.8

page 1 | page 2 | page 3