Monthly State Let Construction Report For Lufkin District As Of Aug 16, 2016 Page 1 Of 4

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySHELBY
Highway SH 7
From 4.432 MI E OF FM 2913
To US 96
CSJ 0059-04-045
Proj ID STP 2016(419)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
9.550 1260125.90 130601.20 336539.00 26.7
Work Order 03-31-16
Work Began 05-23-16
Work Completed  
Time Computed 05-02-16
Contract Working Days 123
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 38
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0059-04-045
ODUM SERVICES, L.P.( 14.14%)
Contract # 12153026
Totals 1260125.90 130601.20 336539.00 26.7

CountySHELBY
Highway US 96
From 1.46 MI N OF SH 87 IN CENTER
To SH 87 IN CENTER
CSJ 0063-06-096
Proj ID NH 2016(271)
Work Type PLANE EXISTING SURFACE AND OVERLAY
 
3.275 2189250.49 2475.00 2186665.09 99.8
Work Order 02-22-16
Work Began 02-29-16
Work Completed  
Time Computed 02-24-16
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 86
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0063-06-096
DUSTROL, INC.(7.29%)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC( 12.57%)
PANOLA SIGN & BARRICADE, INC.(0.33%)
STRIPING TECHNOLOGY, L.P.(3.10%)
W.O.E. CONSTRUCTION(0.16%)
STRIPING SYSTEMS, INC. (0.06%)
Contract # 11153027
Totals 2189250.49 2475.00 2186665.09 99.8

CountySAN AUGUSTINE
Highway SH 21 ETC
From SH 147
To FM 1
CSJ 0064-04-037
Proj ID STP 2016(274)
Work Type RESURFACE WITH SEAL COAT
 
177.815 7619981.14 0.00 2647499.65 34.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 03-14-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 55
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-04-037
INTERSTATE BARRICADES & MARKINGS, INC. ( 14.26%)
Contract # 12153225
Totals 7619981.14 0.00 2647499.65 34.7

CountySAN AUGUSTINE
Highway SH 21
From SH 147
To FM 1
CSJ 0064-04-038
Proj ID STP 2016(120)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
15.567 1848256.10 0.00 1029433.16 55.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 01-18-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 57
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0064-04-038
AMERICAN REMEDIATION OPTIONS, INC. ( 26.79%)
Contract # 10153002
Totals 1848256.10 0.00 1029433.16 55.6

CountySABINE
Highway FM 1
From SH 184
To SS 1
CSJ 0064-11-014
Proj ID STP 1502(459)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
6.038 3634869.32 0.00 2017880.90 55.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-15
Work Began 05-03-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 104
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 52
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-11-014
AMERICAN REMEDIATION OPTIONS, INC. (3.63%)
CRABTREE BARRICADE SYSTEMS, INC. (1.61%)
MOORE BROTHERS CONSTRUCTION COMPANY(4.76%)
PANOLA SIGN & BARRICADE, INC.(0.52%)
Contract # 07153245
Totals 3634869.32 0.00 2017880.90 55.5

CountyHOUSTON
Highway US 287
From 2.1 MI N OF FM 2663
To 0.761 MI S OF SL 304
CSJ 0109-04-029
Proj ID STP 2016(483)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
14.264 1611863.00 149042.34 742232.90 46.0
Work Order 03-29-16
Work Began 05-09-16
Work Completed  
Time Computed 05-09-16
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 30
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-04-029
AMERICAN REMEDIATION OPTIONS, INC. (6.57%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 55.22%)
PANOLA SIGN & BARRICADE, INC.(0.87%)
Contract # 01163028
Totals 1611863.00 149042.34 742232.90 46.0

CountyTRINITY
Highway SH 19 ETC
From HOUSTON COUNTY LINE
To SH 94 IN TRINITY
CSJ 0109-07-050
Proj ID STP 2015(321)
Work Type RESURFACE WITH SEAL COAT
 
208.759 8618179.28 0.00 8231704.17 95.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-10-15
Work Began 02-28-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 65
Addl Days Granted 18
Working Days Charged 83
Percent Time Used 100
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-07-050
INTERSTATE BARRICADES & MARKINGS, INC. ( 14.05%)
Contract # 11143003
Totals 8618179.28 0.00 8231704.17 95.5

CountyHOUSTON
Highway SH 21
From FM 1280
To 2.32 MI E OF FM 2967
CSJ 0117-06-044
Proj ID NH 1502(067)
Work Type RECONSTRUCT AND ADD PASSING LANES
 
7.337 11812489.64 967377.93 5659321.91 47.9
Work Order 06-01-15
Work Began 09-02-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 314
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 58
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0117-06-044
AMERICAN REMEDIATION OPTIONS, INC. (3.78%)
BIG CREEK CONSTRUCTION, LTD. ( 18.95%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.95%)
J & M CONTRACTING, COMPANY ( 22.49%)
PANOLA SIGN & BARRICADE, INC.(0.31%)
WEST TEXAS RUMBLE STRIP(0.06%)
Contract # 04153055
Totals 11812489.64 967377.93 5659321.91 47.9

CountyHOUSTON
Highway SH 21
From 2.32 MI E OF FM 2967
To SH 7
CSJ 0117-07-040
Proj ID NH 1502(460)
Work Type RECONST PVMNT & ADD PASSING LANES
 
5.724 11462865.25 0.00 3615694.06 31.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-15
Work Began 11-10-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 408
Addl Days Granted 8
Working Days Charged 134
Percent Time Used 32
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0117-07-040
DREWERY BROS TREE SERVICE, INC.(0.49%)
DUSTY ALLEN, INC.(0.56%)
J&M CONTRACTING COMPANY(8.44%)
PANOLA SIGN & BARRICADE, INC.(0.34%)
TEXOP CONSTRUCTION (0.95%)
WEST TEXAS RUMBLE STRIP(0.06%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.39%)
FREDONIA CONSTRUCTION SERVICES (0.10%)
BATTEN DRILLING, INC.(0.01%)
Contract # 07153209
Totals 11462865.25 0.00 3615694.06 31.5

CountySAN AUGUSTINE
Highway SH 21
From AT PERKINS CREEK
To .
CSJ 0118-10-058
Proj ID BR 2016(484)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.058 5229087.95 90720.00 90720.00 1.7
Work Order 03-08-16
Work Began 00-00-00
Work Completed  
Time Computed 05-09-16
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0118-10-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163207
Totals 5229087.95 90720.00 90720.00 1.7

CountySABINE
Highway SH 21 ETC
From SAN AUGUSTINE CO LINE
To FM 330
CSJ 0119-02-020
Proj ID STP 1602(450)HES
Work Type RUMBLE STRIPS
 
83.672 684933.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 23
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0119-02-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163042
Totals 684933.24 0.00 0.00 0.0

CountySHELBY
Highway FM 415
From AT BEAR BAYOU
To .
CSJ 0123-08-010
Proj ID BR 1502(621)
Work Type BRIDGE REPLACEMENT
 
0.165 1352960.21 120492.75 223722.80 16.5
Work Order 10-30-15
Work Began 07-19-16
Work Completed  
Time Computed 03-01-16
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 6
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0123-08-010
PANOLA SIGN & BARRICADE, INC.(0.71%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.75%)
AMERICAN REMEDIATION OPTIONS, INC. (4.69%)
STRIPING TECHNOLOGY, L.P.(1.22%)
Contract # 08153242
Totals 1352960.21 120492.75 223722.80 16.5

CountySHELBY
Highway US 84
From AT SABINE RIVER
To .
CSJ 0175-01-005
Proj ID BR 2005(5)
Work Type REPLACE BRIDGE
 
0.209 9916183.38 262590.00 7365925.02 74.2
CountySHELBY
Highway US 84
From 0.62 MI W OF SABINE RIVER
To SABINE RIVER BRIDGE
CSJ 0175-02-078
Proj ID BR 1302(051)
Work Type GRADING, STRUCTURE, BASE, SURFACING
 
0.479 4226063.48 28680.00 2419379.37 57.2
CountySHELBY
Highway VA
From SABINE RIVER BRIDGE
To 0.1 MI E OF LOUISIANA 5
CSJ 0911-39-022
Proj ID CC 911-39-22
Work Type GRADING, STRUCTURE, BASE, SURFACING
 
0.543 6269852.76 210195.11 5248990.12 83.7
Work Order 09-26-13
Work Began 01-06-14
Work Completed  
Time Computed 12-27-13
Contract Working Days 611
Addl Days Granted 53
Working Days Charged 631
Percent Time Used 95
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0175-01-005
SOUTHWEST ENVIRONMENT SERVICES LLC (2.06%)
DUSTROL, INC.(0.34%)
FBL & ASSOCIATES (0.67%)
HOUSTON SAWING & DRILLING(0.04%)
MOORE BROTHERS CONSTRUCTION COMPANY( 12.37%)
RDI FOUNDATION DRILLING(7.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.84%)
W.O.E. CONSTRUCTION(0.28%)
HIGHWAY 19 CONSTRUCTION, LLC (6.48%)
STRIPING TECHNOLOGY, L.P.(0.71%)
RICE ENVIRONMENTAL SERVICES(0.09%)
BRUMLEY DEVELOPMENT, LLC (0.00%)
MCL CONTRACTING, LLC (0.39%)
MILLER TRANSPORTATION(0.00%)
DAVID LAWLER CONSTRUCTION(0.07%)
LFI FT PIERCE, INC (0.04%)
ODUM SERVICES, L.P.(0.23%)
PROTECTION SERVICES INC. (0.03%)
DYKON BLASTING CORP(0.54%)
AGGREGATE TECHNOLOGIES, INC. (0.08%)
Contract # 07133206
Totals 20412099.62 501465.11 15034294.51 73.6

CountyNACOGDOCHES
Highway US 59
From LP 224
To 1.255 MI S OF LP 224
CSJ 0176-01-094
Proj ID STP 2014(918)HES
Work Type INSTALL RAISED MEDIAN
 
1.672 14030469.72 1272874.47 8577786.75 61.1
Work Order 09-12-14
Work Began 01-07-15
Work Completed  
Time Computed 01-05-15
Contract Working Days 532
Addl Days Granted 0
Working Days Charged 387
Percent Time Used 72
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-094
BRADCO, LLC(6.00%)
DUSTIN ALLEN, INC. (0.64%)
DUSTROL, INC.(1.29%)
ECM ENVIRONMENTAL SERVICES, INC. (0.32%)
MOORE BROTHERS CONSTRUCTION COMPANY( 17.80%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.23%)
PINTO CONSTRUCTION CO., INC. (7.29%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.41%)
STRIPING TECHNOLOGY, L.P.(2.01%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(1.36%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.80%)
STEEL EFFECTS(0.00%)
L MOBLEY CONCRETE CONSTRUCTION (6.95%)
CARTHAGE DRILLING, INC.(0.07%)
Contract # 07143005
Totals 14030469.72 1272874.47 8577786.75 61.1

CountyNACOGDOCHES
Highway US 59
From GRASS MEDIAN S OF SL 224
To ANGELINA RIVER BRIDGE
CSJ 0176-01-107
Proj ID NH 1602(177)
Work Type OVERLAY WITH PFC
 
6.632 1598523.47 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-107
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163032
Totals 1598523.47 0.00 0.00 0.0

CountyNACOGDOCHES
Highway US 59 ETC
From AT ANGELINA RIVER
To .
CSJ 0176-01-109
Proj ID BR 2016(696)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
9.588 2458818.05 60968.50 345636.68 14.0
Work Order 04-19-16
Work Began 06-15-16
Work Completed  
Time Computed 05-19-16
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 45
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-109
DUSTIN ALLEN, INC. (6.89%)
J & M CONTRACTING, COMPANY ( 13.30%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.03%)
STRIPING TECHNOLOGY, L.P.(0.74%)
STRIPING SYSTEMS, INC. (0.06%)
Contract # 02163227
Totals 2458818.05 60968.50 345636.68 14.0

CountyANGELINA
Highway US 59
From .9 MILES N. OF LP 287 (N) (@ UP RR)
To .1 MILES N. OF LP 287 (N)
CSJ 0176-02-090
Proj ID STP 99(770)RGS
Work Type REPLACE RAILROAD UNDERPASS
 
0.554 13760249.93 17993.60 13003124.13 94.6
CountyANGELINA
Highway US 59
From 0.13 MI N OF FM 3439
To LP 287/US 69
CSJ 0176-02-105
Proj ID STP 2012(501)HES
Work Type CONSTRUCT INTERCHANGE
 
1.829 38418975.28 29381.25 39176611.37 99.9
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 764
Addl Days Granted 104
Working Days Charged 876
Percent Time Used 100
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-090
HIGHWAY TECHNOLOGIES, INC. (0.12%)
BATTERSON,LLP(0.57%)
DUSTIN ALLEN, INC. (0.72%)
A. H. BAKER SERVICES, INC. ( 10.54%)
W. W. FOUNDATION DRILLING, LTD.(1.86%)
MOORE BROTHERS CONSTRUCTION COMPANY(9.56%)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.07%)
DUSTROL, INC.(0.02%)
DRILL TECH DRILLING & SHORING, INC.(1.56%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.17%)
RAILWORKS TRACK SYSTEMS, INC.(0.14%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (0.54%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(2.70%)
ALLEN LOGGINGS & SONS, INC.(0.19%)
FUGRO CONSULTANTS LP (0.07%)
MESA ROD BUSTERS, INC. (0.80%)
EROSION CONTROL, INC.(0.92%)
EAST TEXAS LANDSCAPING, INC. (0.13%)
TEX OP CONSTRUCTION, LP(0.42%)
PINTO CONSTRUCTION CO., INC. (1.46%)
SCOTT DERR PAINTING CO, LLC(0.30%)
FARR FOUNDATION, INC.(1.39%)
COX CONTRACTORS, INC.(0.65%)
CURB PLANET INC. (0.00%)
WEBBER BARRIER SERVICES, LLC.(0.76%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.07%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.22%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.88%)
HEMPHILL PILE DRIVING CO., A CORP. (0.01%)
SITAR CONSTRUCTION, LLC(0.11%)
TX DOWN UNDER CONSTRUCTION, LLC(0.01%)
ENCINO LANDSCAPE, INC. (0.17%)
ROY LEE WALKER (0.01%)
SOUTHEAST GRINDING & GROOVING, LLC (0.11%)
Contract # 06123008
Totals 52179225.21 47374.85 52179735.50 99.9

CountyANGELINA
Highway BU 59-G
From AT A&NR RR UNDERPASS
To .
CSJ 0176-02-094
Proj ID STP 2015(155)RGS
Work Type REPLACE EXISTING RR STRUCTURE
 
0.368 11387556.46 235398.72 10071302.04 88.4
Work Order 11-03-14
Work Began 03-31-15
Work Completed  
Time Computed 01-05-15
Contract Working Days 383
Addl Days Granted 13
Working Days Charged 331
Percent Time Used 83
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-094
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 13.15%)
EROSION CONTROL MANAGEMENT SERVICES(0.76%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17%)
LONE STAR RAILROAD CONTRACTORS, INC. (7.45%)
MOORE BROTHERS CONSTRUCTION COMPANY(5.11%)
PINTO CONSTRUCTION CO., INC. (0.81%)
RDI FOUNDATION DRILLING(7.56%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.59%)
S & S BRIDGE PAINTING, INC.(0.05%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.32%)
TEX OP CONSTRUCTION, LP(0.35%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.88%)
ALLEN LOGGINGS & SONS, INC.(4.98%)
MESA ROD BUSTERS, INC. (0.34%)
HEMPHILL PILE DRIVING CO., A CORP. (0.26%)
FARR FOUNDATION, INC.(0.79%)
VALLEY PLACERS, LLC(0.68%)
COX CONTRACTORS, INC.(0.70%)
CURB PLANET INC. (0.02%)
Contract # 09143008
Totals 11387556.46 235398.72 10071302.04 88.4

CountyANGELINA
Highway US 59
From AT FM 2021
To .
CSJ 0176-02-102
Proj ID STP 2013(779)SB
Work Type CONSTRUCT GRADE SEPARATION
 
1.284 18772914.71 2994.94 18796915.90 99.9
Work Order 10-24-13
Work Began 11-11-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 515
Addl Days Granted 22
Working Days Charged 518
Percent Time Used 96
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-102
LOGGINS & SONS, ALLEN(3.28%)
SOUTH TEXAS ILLUMINATION, LLC(0.79%)
W. W. FOUNDATION DRILLING, LTD.(0.69%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.34%)
PINTO CONSTRUCTION CO., INC. (2.81%)
BREDA COMPANY, INC.(0.93%)
DUSTROL, INC.(0.72%)
WEBBER BARRIER SERVICES, LLC.(0.50%)
MOORE BROTHERS CONSTRUCTION COMPANY( 16.38%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.14%)
SCOTT DERR PAINTING CO (0.05%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18%)
ODUM SERVICES, L.P.(0.22%)
PEREZ CONSTRUCTION CO. (0.24%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.39%)
BRADCO, LLC(0.38%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.01%)
ROY LEE WALKER (0.01%)
SOUTHEAST GRINDING & GROOVING, LLC (0.10%)
Contract # 06133202
Totals 18772914.71 2994.94 18796915.90 99.9

CountyANGELINA
Highway US 59
From 0.7 MI S OF FM 2021 @ REDLAND
To 0.1 MI N OF FM 3439
CSJ 0176-02-113
Proj ID NH 1602(093)
Work Type HMA LEVEL - UP AND PFC SURFACE
 
1.289 1438279.24 0.00 0.00 0.0
Work Order 06-06-16
Work Began 00-00-00
Work Completed  
Time Computed 07-18-16
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-113
PANOLA SIGN & BARRICADE, INC.(0.39%)
STRIPE-A-ZONE, INC.(1.47%)
COWBELL TRAFFIC SERVICES, INC. (0.39%)
ALL AMERICAN MILLING, LLC(2.55%)
FREDONIA CONSTRUCTION SERVICES (0.69%)
Contract # 05163206
Totals 1438279.24 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4