Monthly State Let Construction Report For Lufkin District As Of Jul 13, 2015 Page 1 Of 3

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySHELBY
Highway SH 7
From SAN AUGUSTINE COUNTY LINE
To 4.429 MI N OF FM 2913
CSJ 0059-03-018
Proj ID STP 2014(851)HES
Work Type IMPROVE GUARDRAIL TO DES STANDARDS
 
16.929 839398.00 0.00 845709.10 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-29-14
Work Began 08-18-14
Work Completed 02-10-15
Time Computed 08-14-14
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 120
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0059-03-018
L.C. JORDAN & SON( 55.77%)
Contract # 06143047
Totals 839398.00 0.00 845709.10 100.0

CountySABINE
Highway US 96
From FM 1
To JASPER COUNTY LINE
CSJ 0064-06-052
Proj ID NH 2015(418)
Work Type RESURFACE WITH MICROSURFACING
 
29.170 1880399.04 0.00 1879037.79 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-13-15
Work Began 04-20-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 82
Contractor(s)
NY-MAC ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-06-052
PANOLA SIGN & BARRICADE, INC.(0.87%)
CRABTREE BARRICADE SYSTEMS, INC. (7.96%)
Contract # 12143022
Totals 1880399.04 0.00 1879037.79 99.9

CountySABINE
Highway FM 1
From SH 184
To 6.1 MI S OF SH 184
CSJ 0064-11-013
Proj ID STP 2014(737)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
21.014 1186968.00 1000.00 1069150.30 90.0
Work Order 07-22-14
Work Began 08-11-14
Work Completed  
Time Computed 08-07-14
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 135
Percent Time Used 65
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-11-013
PANOLA SIGN & BARRICADE, INC.(0.89%)
DUSTIN ALLEN, INC. ( 10.08%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.19%)
Contract # 06143037
Totals 1186968.00 1000.00 1069150.30 90.0

CountySABINE
Highway FM 1
From SH 184
To SS 1
CSJ 0064-11-014
Proj ID STP 1502(459)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
6.038 3634869.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 104
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-11-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153245
Totals 3634869.32 0.00 0.00 0.0

CountyTRINITY
Highway SH 19 ETC
From HOUSTON COUNTY LINE
To SH 94 IN TRINITY
CSJ 0109-07-050
Proj ID STP 2015(321)
Work Type RESURFACE WITH SEAL COAT
 
208.759 8618179.28 0.00 780269.99 9.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-10-15
Work Began 02-28-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-07-050
INTERSTATE BARRICADES & MARKINGS, INC. ( 14.05%)
Contract # 11143003
Totals 8618179.28 0.00 780269.99 9.0

CountyHOUSTON
Highway SH 21
From FM 1280
To 2.32 MI E OF FM 2967
CSJ 0117-06-044
Proj ID NH 1502(067)
Work Type RECONSTRUCT AND ADD PASSING LANES
 
7.337 11812489.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-01-15
Work Began 00-00-00
Work Completed  
Time Computed 07-02-15
Contract Working Days 314
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0117-06-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153055
Totals 11812489.64 0.00 0.00 0.0

CountyHOUSTON
Highway SH 21
From 2.32 MI E OF FM 2967
To SH 7
CSJ 0117-07-040
Proj ID NH 1502(460)
Work Type RECONST PVMNT & ADD PASSING LANES
 
5.724 11462865.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 408
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0117-07-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153209
Totals 11462865.25 0.00 0.00 0.0

CountyNACOGDOCHES
Highway SH 21
From 0.40 MI W OF FM 226
To FM 3276
CSJ 0118-08-060
Proj ID C 118-8-60
Work Type GRADING, STRUT, BASE, HMAC SURFACE
 
4.231 7883681.86 -5625.00 5602356.63 72.8
Work Order 10-03-12
Work Began 01-11-13
Work Completed  
Time Computed 11-01-12
Contract Working Days 235
Addl Days Granted 4
Working Days Charged 383
Percent Time Used 160
Contractor(s)
FEDERAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0118-08-060
N-LINE TRAFFIC MAINTENANCE, L.P. (0.17%)
AMERICAN REMEDIATION OPTIONS, INC. (1.62%)
VERITAS SUPPLY, INC. (1.03%)
DREWERY CONSTRUCTION COMPANY, INCORPORATED ( 32.69%)
DUSTROL, INC.(0.42%)
TEXAS STAR TRANSPORT, LP (1.74%)
STRIPING TECHNOLOGY, L.P.(0.76%)
O DIRT (1.25%)
Contract # 07123023
Totals 7883681.86 5625.00 5602356.63 72.8

CountySAN AUGUSTINE
Highway SH 21
From AT US 96
To .
CSJ 0118-10-055
Proj ID STP 2015(154)
Work Type INTERSECTION IMPROVEMENTS
 
0.300 3381562.15 440066.43 1811993.46 53.5
Work Order 11-06-14
Work Began 03-16-15
Work Completed  
Time Computed 11-22-14
Contract Working Days 90
Addl Days Granted 2
Working Days Charged 45
Percent Time Used 48
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0118-10-055
A R BROTHERS CONSTRUCTION SERVICES, INC. (9.78%)
PANOLA SIGN & BARRICADE, INC.(0.30%)
STRIPING TECHNOLOGY, L.P.(1.07%)
DREWERY & WHEATON, LLC (1.60%)
SOUTH TEXAS ILLUMINATION, LLC(4.34%)
Contract # 09143230
Totals 3381562.15 440066.43 1811993.46 53.5

CountySHELBY
Highway US 84
From RUSK COUNTY LINE
To US 59 IN TIMPSON
CSJ 0123-07-018
Proj ID STP 2013(516)
Work Type RECONSTRUCT PAVEMENT
 
6.413 5459220.41 0.00 5302123.72 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-25-14
Work Began 05-12-14
Work Completed 06-24-15
Time Computed 05-11-14
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 155
Percent Time Used 98
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0123-07-018
ACU CONSTRUCTION LLC (0.40%)
A.J.J.A . TRUCKING, INC. (1.00%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.42%)
DREWERY"S TREE SERVICE AND CONSTRUCTION CO., INC.(0.27%)
DREWERY & WHEATON, LLC (0.11%)
J & M CONTRACTING, COMPANY (1.90%)
MURRAY CONSTRUCTION(0.45%)
ODUM SERVICES, L.P.(0.89%)
PANOLA SIGN & BARRICADE, INC.(0.38%)
STRIPING TECHNOLOGY, L.P.(1.39%)
COWBELL TRAFFIC SERVICE, INC.(0.19%)
FREDONIA CONSTRUCTION SERVICES (0.16%)
Contract # 02143027
Totals 5459220.41 0.00 5302123.72 100.0

CountySHELBY
Highway US 84
From AT SABINE RIVER
To .
CSJ 0175-01-005
Proj ID BR 2005(5)
Work Type REPLACE BRIDGE
 
0.209 9916183.38 507996.17 5055602.61 50.9
CountySHELBY
Highway US 84
From 0.62 MI W OF SABINE RIVER
To SABINE RIVER BRIDGE
CSJ 0175-02-078
Proj ID BR 1302(051)
Work Type GRADING, STRUCTURE, BASE, SURFACING
 
0.479 4226063.48 2862.50 1334897.98 31.5
CountySHELBY
Highway VA
From SABINE RIVER BRIDGE
To 0.1 MI E OF LOUISIANA 5
CSJ 0911-39-022
Proj ID CC 911-39-22
Work Type GRADING, STRUCTURE, BASE, SURFACING
 
0.543 6269852.76 87474.20 3534371.53 56.3
Work Order 09-26-13
Work Began 01-06-14
Work Completed  
Time Computed 12-27-13
Contract Working Days 611
Addl Days Granted 0
Working Days Charged 376
Percent Time Used 61
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0175-01-005
SOUTHWEST ENVIRONMENT SERVICES LLC (2.06%)
DUSTROL, INC.(0.34%)
FBL & ASSOCIATES (0.67%)
HOUSTON SAWING & DRILLING(0.04%)
MOORE BROTHERS CONSTRUCTION COMPANY( 12.37%)
RDI FOUNDATION DRILLING(7.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.84%)
W.O.E. CONSTRUCTION(0.28%)
HIGHWAY 19 CONSTRUCTION, LLC (6.48%)
STRIPING TECHNOLOGY, L.P.(0.71%)
RICE ENVIRONMENTAL SERVICES(0.09%)
BRUMLEY DEVELOPMENT, LLC (0.00%)
MCL CONTRACTING, LLC (0.39%)
MILLER TRANSPORTATION(0.00%)
DAVID LAWLER CONSTRUCTION(0.07%)
Contract # 07133206
Totals 20412099.62 598332.87 9924872.12 48.6

CountyNACOGDOCHES
Highway US 59
From 0.24 MI S OF FM 95 W
To US 259
CSJ 0175-07-056
Proj ID NH 2014(686)
Work Type MILL & INLAY SECTIONS AND SEAL
 
13.421 3335178.93 220436.27 2898933.27 86.9
Work Order 05-20-14
Work Began 07-28-14
Work Completed  
Time Computed 06-05-14
Contract Working Days 39
Addl Days Granted 14
Working Days Charged 51
Percent Time Used 96
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0175-07-056
ACU CONSTRUCTION LLC (3.02%)
PANOLA SIGN & BARRICADE, INC.(0.14%)
STRIPING TECHNOLOGY, L.P.(4.11%)
Contract # 04143219
Totals 3335178.93 220436.27 2898933.27 86.9

CountyNACOGDOCHES
Highway BU 59-F
From BOWIE ST
To MAIN ST (SH 21)
CSJ 0175-08-042
Proj ID STP 2013(676)
Work Type UPGRADE TRAFFIC SIGNALS
 
2.825 834399.31 0.00 900168.97 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 12-10-13
Work Completed 03-02-15
Time Computed 00-00-00
Contract Working Days 194
Addl Days Granted 36
Working Days Charged 230
Percent Time Used 100
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0175-08-042
B & B UNDERGROUND, LLC (2.25%)
COX CONTRACTORS, INC.(2.11%)
STRIPING TECHNOLOGY, L.P.(5.01%)
Contract # 05133234
Totals 834399.31 0.00 900168.97 100.0

CountyNACOGDOCHES
Highway US 59
From LP 224
To 1.255 MI S OF LP 224
CSJ 0176-01-094
Proj ID STP 2014(918)HES
Work Type INSTALL RAISED MEDIAN
 
1.672 14030469.72 104014.83 2519535.44 17.9
Work Order 09-12-14
Work Began 01-07-15
Work Completed  
Time Computed 01-05-15
Contract Working Days 532
Addl Days Granted 0
Working Days Charged 124
Percent Time Used 23
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-094
BRADCO, LLC(2.45%)
DUSTIN ALLEN, INC. (0.64%)
DUSTROL, INC.(1.29%)
ECM ENVIRONMENTAL SERVICES, INC. (0.32%)
MOORE BROTHERS CONSTRUCTION COMPANY( 17.80%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.23%)
PINTO CONSTRUCTION CO., INC. (7.28%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.41%)
STRIPING TECHNOLOGY, L.P.(2.01%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(1.36%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.80%)
STEEL EFFECTS(0.00%)
L MOBLEY CONCRETE CONSTRUCTION (6.95%)
Contract # 07143005
Totals 14030469.72 104014.83 2519535.44 17.9

CountyANGELINA
Highway US 59
From .9 MILES N. OF LP 287 (N) (@ UP RR)
To .1 MILES N. OF LP 287 (N)
CSJ 0176-02-090
Proj ID STP 99(770)RGS
Work Type REPLACE RAILROAD UNDERPASS
 
0.554 13760249.93 114618.20 11602669.74 84.3
CountyANGELINA
Highway US 59
From 0.13 MI N OF FM 3439
To LP 287/US 69
CSJ 0176-02-105
Proj ID STP 2012(501)HES
Work Type CONSTRUCT INTERCHANGE
 
1.829 38418975.28 301850.55 32790120.12 85.3
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 764
Addl Days Granted 32
Working Days Charged 691
Percent Time Used 86
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-090
HIGHWAY TECHNOLOGIES, INC. (0.12%)
BATTERSON,LLP(0.57%)
DUSTIN ALLEN, INC. (0.72%)
A. H. BAKER SERVICES, INC. ( 10.54%)
W. W. FOUNDATION DRILLING, LTD.(1.86%)
MOORE BROTHERS CONSTRUCTION COMPANY(9.56%)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.08%)
DUSTROL, INC.(0.02%)
DRILL TECH DRILLING & SHORING, INC.(1.56%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.17%)
RAILWORKS TRACK SYSTEMS, INC.(0.14%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (0.54%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(2.70%)
ALLEN LOGGINGS & SONS, INC.(0.19%)
FUGRO CONSULTANTS LP (0.07%)
MESA ROD BUSTERS, INC. (0.80%)
EROSION CONTROL, INC.(0.92%)
EAST TEXAS LANDSCAPING, INC. (0.13%)
TEX OP CONSTRUCTION, LP(0.42%)
PINTO CONSTRUCTION CO., INC. (1.46%)
SCOTT DERR PAINTING CO, LLC(0.30%)
FARR FOUNDATION, INC.(1.39%)
COX CONTRACTORS, INC.(0.65%)
CURB PLANET INC. (0.00%)
WEBBER BARRIER SERVICES, LLC.(0.76%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.07%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.22%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.88%)
Contract # 06123008
Totals 52179225.21 416468.75 44392789.86 85.0

CountyANGELINA
Highway BU 59-G
From AT A&NR RR UNDERPASS
To .
CSJ 0176-02-094
Proj ID STP 2015(155)RGS
Work Type REPLACE EXISTING RR STRUCTURE
 
0.368 11387556.46 377100.18 1980676.57 17.3
Work Order 11-03-14
Work Began 03-31-15
Work Completed  
Time Computed 01-05-15
Contract Working Days 383
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 15
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-094
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 13.15%)
EROSION CONTROL MANAGEMENT SERVICES(0.76%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17%)
LONE STAR RAILROAD CONTRACTORS, INC. (7.45%)
MOORE BROTHERS CONSTRUCTION COMPANY(5.11%)
PINTO CONSTRUCTION CO., INC. (0.81%)
RDI FOUNDATION DRILLING(7.56%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.59%)
S & S BRIDGE PAINTING, INC.(0.05%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.32%)
TEX OP CONSTRUCTION, LP(0.35%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.88%)
ALLEN LOGGINGS & SONS, INC.(4.98%)
MESA ROD BUSTERS, INC. (0.34%)
HEMPHILL PILE DRIVING CO., A CORP. (0.26%)
Contract # 09143008
Totals 11387556.46 377100.18 1980676.57 17.3

CountyANGELINA
Highway US 59
From AT FM 2021
To .
CSJ 0176-02-102
Proj ID STP 2013(779)SB
Work Type CONSTRUCT GRADE SEPARATION
 
1.284 18772914.71 517805.16 15215571.15 81.0
Work Order 10-24-13
Work Began 11-11-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 515
Addl Days Granted 11
Working Days Charged 377
Percent Time Used 71
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-102
LOGGINS & SONS, ALLEN(3.28%)
SOUTH TEXAS ILLUMINATION, LLC(0.79%)
W. W. FOUNDATION DRILLING, LTD.(0.69%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.34%)
PINTO CONSTRUCTION CO., INC. (2.81%)
BREDA COMPANY, INC.(0.93%)
DUSTROL, INC.(0.72%)
WEBBER BARRIER SERVICES, LLC.(0.50%)
MOORE BROTHERS CONSTRUCTION COMPANY( 16.38%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.14%)
SCOTT DERR PAINTING CO (0.05%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18%)
ODUM SERVICES, L.P.(0.22%)
PEREZ CONSTRUCTION CO. (0.24%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.39%)
Contract # 06133202
Totals 18772914.71 517805.16 15215571.15 81.0

CountyPOLK
Highway US 59
From 0.47 MI S OF MILTON CREEK
To BU 59-J OVERPASS (SB LANES ONLY)
CSJ 0176-05-175
Proj ID NH 2014(292)
Work Type RESURFACE WITH MICROSURFACING
 
20.831 1316346.55 478887.46 1124210.38 87.2
Work Order 01-17-14
Work Began 04-30-15
Work Completed  
Time Computed 08-01-14
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 225
Contractor(s)
VIKING CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0176-05-175
PANOLA SIGN & BARRICADE, INC.(0.67%)
CRABTREE BARRICADE SYSTEMS, INC. (7.07%)
Contract # 12133220
Totals 1316346.55 478887.46 1124210.38 87.2

CountyPOLK
Highway US 59
From MC & SA RR OVERPASS
To GRASS MEDIAN S OF LEGGETT
CSJ 0176-05-176
Proj ID NH 2014(815)
Work Type HMA LEVEL - UP, OCST & PFC
 
8.594 5586536.64 246172.66 3383302.44 60.9
Work Order 06-11-14
Work Began 06-30-14
Work Completed  
Time Computed 06-27-14
Contract Working Days 84
Addl Days Granted 6
Working Days Charged 111
Percent Time Used 123
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0176-05-176
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20%)
W.O.E. CONSTRUCTION(0.98%)
J & M CONTRACTING, COMPANY (5.38%)
DUSTROL, INC.(1.28%)
AMERICAN REMEDIATION OPTIONS, INC. (0.27%)
CLARK CONSTRUCTION OF TEXAS, INC.(9.45%)
SPHERION (0.00%)
STRIPING TECHNOLOGY, L.P.(1.21%)
Contract # 04143034
Totals 5586536.64 246172.66 3383302.44 60.9

CountyPOLK
Highway US 59
From GRASS MEDIAN S OF LEGGETT
To 0.47 MI S OF MILTON CREEK
CSJ 0176-05-177
Proj ID NH 2015(533)
Work Type PLANE, SEAL AND RESURFACE WITH PFC
 
5.368 1700521.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-18-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0176-05-177
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153020
Totals 1700521.55 0.00 0.00 0.0

page 1 | page 2 | page 3