Monthly State Let Construction Report For Lufkin District As Of Jan 11, 2017 Page 2 Of 4

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyANGELINA
HighwayUS 59
From.9 MILES N. OF LP 287 (N) (@ UP RR)
To.1 MILES N. OF LP 287 (N)
CSJ0176-02-090
Proj IDSTP 99(770)RGS
Work TypeREPLACE RAILROAD UNDERPASS
 
0.55413760249.9313002079.4094.6
CountyANGELINA
HighwayUS 59
From0.13 MI N OF FM 3439
ToLP 287/US 69
CSJ0176-02-105
Proj IDSTP 2012(501)HES
Work TypeCONSTRUCT INTERCHANGE
 
1.82938418975.2839254222.6899.9
Work Order08-20-12
Work Began09-10-12
Work Completed
Time Computed09-10-12
Contract Working Days764
Addl Days Granted104
Working Days Charged876
Percent Time Used100
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-090
HIGHWAY TECHNOLOGIES, INC. (0.12)
BATTERSON,LLP (0.57)
DUSTIN ALLEN, INC. (0.72)
A. H. BAKER SERVICES, INC. (10.54)
W. W. FOUNDATION DRILLING, LTD. (1.86)
MOORE BROTHERS CONSTRUCTION COMPANY (9.56)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.07)
DUSTROL, INC. (0.02)
DRILL TECH DRILLING & SHORING, INC. (1.56)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.17)
RAILWORKS TRACK SYSTEMS, INC. (0.14)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17)
A R BROTHERS CONSTRUCTION SERVICES, INC. (0.54)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (2.70)
ALLEN LOGGINGS & SONS, INC. (0.19)
FUGRO CONSULTANTS LP (0.07)
MESA ROD BUSTERS, INC. (0.80)
EROSION CONTROL, INC. (0.92)
EAST TEXAS LANDSCAPING, INC. (0.13)
TEX OP CONSTRUCTION, LP (0.42)
PINTO CONSTRUCTION CO., INC. (1.46)
SCOTT DERR PAINTING CO, LLC (0.30)
FARR FOUNDATION, INC. (1.39)
COX CONTRACTORS, INC. (0.65)
CURB PLANET INC. (0.00)
WEBBER BARRIER SERVICES, LLC. (0.76)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.07)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.22)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.88)
HEMPHILL PILE DRIVING CO., A CORP. (0.01)
SITAR CONSTRUCTION, LLC (0.11)
TX DOWN UNDER CONSTRUCTION, LLC (0.01)
ENCINO LANDSCAPE, INC. (0.17)
ROY LEE WALKER (0.01)
SOUTHEAST GRINDING & GROOVING, LLC (0.11)
Contract #06123008
Totals52179225.210.0052256302.0899.9

CountyANGELINA
HighwayBU 59-G
FromAT A&NR RR UNDERPASS
To.
CSJ0176-02-094
Proj IDSTP 2015(155)RGS
Work TypeREPLACE EXISTING RR STRUCTURE
 
0.36811387556.4611184491.7198.3
Work Order11-03-14
Work Began03-31-15
Work Completed
Time Computed01-05-15
Contract Working Days383
Addl Days Granted13
Working Days Charged407
Percent Time Used102
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-094
A R BROTHERS CONSTRUCTION SERVICES, INC. (13.15)
EROSION CONTROL MANAGEMENT SERVICES (0.76)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17)
LONE STAR RAILROAD CONTRACTORS, INC. (7.45)
MOORE BROTHERS CONSTRUCTION COMPANY (5.11)
PINTO CONSTRUCTION CO., INC. (0.81)
RDI FOUNDATION DRILLING (7.56)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.59)
S & S BRIDGE PAINTING, INC. (0.05)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.32)
TEX OP CONSTRUCTION, LP (0.35)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.88)
ALLEN LOGGINGS & SONS, INC. (4.98)
MESA ROD BUSTERS, INC. (0.34)
HEMPHILL PILE DRIVING CO., A CORP. (0.26)
FARR FOUNDATION, INC. (0.79)
VALLEY PLACERS, LLC (0.68)
COX CONTRACTORS, INC. (0.70)
CURB PLANET INC. (0.02)
Contract #09143008
Totals11387556.4614308.5011184491.7198.3

CountyANGELINA
HighwayUS 59
FromAT FM 2021
To.
CSJ0176-02-102
Proj IDSTP 2013(779)SB
Work TypeCONSTRUCT GRADE SEPARATION
 
1.28418772914.7118862305.9999.9
Work Order10-24-13
Work Began11-11-13
Work Completed
Time Computed12-01-13
Contract Working Days515
Addl Days Granted22
Working Days Charged518
Percent Time Used96
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-102
LOGGINS & SONS, ALLEN (3.28)
SOUTH TEXAS ILLUMINATION, LLC (0.79)
W. W. FOUNDATION DRILLING, LTD. (0.69)
PROFESSIONAL TRAFFIC CONTROL, LLC (1.34)
PINTO CONSTRUCTION CO., INC. (2.81)
BREDA COMPANY, INC. (0.93)
DUSTROL, INC. (0.72)
WEBBER BARRIER SERVICES, LLC. (0.50)
MOORE BROTHERS CONSTRUCTION COMPANY (16.38)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.14)
SCOTT DERR PAINTING CO (0.05)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18)
ODUM SERVICES, L.P. (0.22)
PEREZ CONSTRUCTION CO. (0.24)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.39)
BRADCO, LLC (0.38)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.01)
ROY LEE WALKER (0.01)
SOUTHEAST GRINDING & GROOVING, LLC (0.10)
Contract #06133202
Totals18772914.710.0018862305.9999.9

CountyPOLK
HighwayUS 59
FromAT BEAR CREEK
To.
CSJ0176-04-081
Proj IDBR 2017(481)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.314497647.500.000.0
CountyPOLK
HighwayUS 59
FromANGELINA COUNTY LINE
ToUS 287
CSJ0176-04-084
Proj IDSTP 2017(482)HES
Work TypeIMPROVE GUARDRAIL TO DES STANDARDS
 
9.508299158.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days114
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-04-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173221
Totals796806.250.000.000.0

CountyPOLK
HighwayUS 59
From0.47 MI S OF MILTON CREEK
ToBU 59-J OVERPASS (SB LANES ONLY)
CSJ0176-05-178
Proj IDNH 1602(034)
Work TypeHMA LEVEL-UP AND PFC SURFACE
 
2.5291250482.541198146.7295.9
Work Order00-00-00
Work Began08-02-16
Work Completed
Time Computed07-25-16
Contract Working Days37
Addl Days Granted0
Working Days Charged39
Percent Time Used105
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0176-05-178
CEN TEX HYDROSEED, INC. (0.51)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.67)
COWBELL TRAFFIC SERVICES, INC. (0.61)
DUSTROL, INC. (6.19)
WATERS CONSTRUCTION CO., INC. (9.67)
Contract #04163236
Totals1250482.540.001198146.7295.9

CountyPOLK
HighwayUS 59
FromAT FM 350
To'
CSJ0176-05-179
Proj IDSTP 1602(451)HES
Work TypeINSTALL ADVANCE WARNING SIGNAL
 
0.60089789.5036587.2540.7
Work Order09-14-16
Work Began12-12-16
Work Completed
Time Computed12-12-16
Contract Working Days20
Addl Days Granted0
Working Days Charged8
Percent Time Used40
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0176-05-179
N-LINE TRAFFIC MAINTENANCE, L.P. (1.95)
Contract #08163238
Totals89789.5036587.2536587.2540.7

CountySAN JACINTO
HighwayUS 59
From1.00 MILE NORTH OF FM 2914
To1.00 MILE SOUTH OF FM 2914
CSJ0177-02-080
Proj IDSTP 1102(058)HES
Work TypeCNSTR INTRCHANGE & CLOSE CROSSOVERS
 
2.05912895988.9716337088.8499.9
Work Order01-31-12
Work Began06-22-12
Work Completed
Time Computed04-02-12
Contract Working Days535
Addl Days Granted236
Working Days Charged892
Percent Time Used115
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-080
CRABTREE BARRICADE SYSTEMS, INC. (1.02)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.31)
MESA ROD BUSTERS, INC. (2.06)
WEBBER-BALKE FOUNDATION COMPANY, INC. (1.82)
ODUM SERVICES, L.P. (0.12)
KOSSMAN CONTRACTING CO., INC. (0.38)
ENVIRONMENTAL ALLIES, L.P. (0.09)
SCOTT DERR PAINTING CO, LLC (0.16)
TRAF-TEX, INC. (4.36)
DUSTROL, INC. (0.46)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.26)
WILLOW CITY SIGN & RAIL, INC. (0.12)
TRIPLE B SERVICES LLP (37.18)
SMITH & COMPANY (16.56)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.10)
GREY WOLF CLEARING INC. (0.52)
A & B CRUSHED CONCRETE (0.12)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.47)
SILVA, INC. (1.21)
INDUS CONSTRUCTION, L.P. (0.63)
JASSO"S SAWING & SEALING (0.36)
CURB PLANET INC. (0.08)
A-1 EROSION CONTROL, LLC (0.59)
Contract #12113203
Totals12895988.97228244.6716337088.8499.9

CountySAN JACINTO
HighwayUS 59
FromJUST S OF UPRR IN SHEPHERD
ToJUST N OF FM 2914
CSJ0177-02-089
Proj IDSTP 2013(916)
Work TypeADD SB FRTG RD & RECONST MAIN LANES
 
1.6428948536.854213011.2447.0
Work Order05-14-14
Work Began08-15-14
Work Completed
Time Computed05-30-14
Contract Working Days230
Addl Days Granted0
Working Days Charged219
Percent Time Used95
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-089
FLORIDA TRAFFIC CONTROL DEVICES, INC. (0.88)
DOUBLE OAK CONSTRUCTION, INC. (0.67)
CRABTREE BARRICADE SYSTEMS, INC. (0.91)
SMITH & COMPANY (20.62)
WILLOW CITY SIGN & RAIL, INC. (0.59)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.20)
BREDA COMPANY, INC. (0.92)
CPAVE, INC. (1.78)
ROY LEE WALKER (0.13)
THOMAS TRACTOR WORKS, INC. (0.16)
NORWEST SERVICES, LLC (0.06)
Contract #02143221
Totals8948536.85295446.134213011.2447.0

CountySAN JACINTO
HighwayUS 59
From0.50 MI S OF FM 2914
ToLIBERTY COUNTY LINE
CSJ0177-02-091
Proj IDNH 2016(734)
Work TypeHMA LEVEL-UP AND PFC SURFACE
 
16.4612971066.402776032.4093.4
Work Order04-19-16
Work Began05-23-16
Work Completed
Time Computed05-23-16
Contract Working Days94
Addl Days Granted0
Working Days Charged93
Percent Time Used98
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-091
STRIPING TECHNOLOGY, L.P. (1.46)
INTERSTATE BARRICADES & MARKINGS, INC. (0.60)
COWBELL TRAFFIC SERVICES, INC. (0.39)
CLARK CONSTRUCTION OF TEXAS, INC. (9.33)
AMERICAN REMEDIATION OPTIONS, INC. (6.84)
DUSTROL, INC. (1.05)
NLG CONSTRUCTION, INC. (0.13)
Contract #02163033
Totals2971066.400.002776032.4093.4

CountyANGELINA
HighwayUS 69
FromSL 287
To0.202 MI N OF HUNTINGTON SCL
CSJ0200-01-082
Proj IDSTP 2016(423)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
8.849861310.50834384.7798.0
Work Order03-31-16
Work Began05-17-16
Work Completed
Time Computed05-17-16
Contract Working Days85
Addl Days Granted5
Working Days Charged107
Percent Time Used118
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0200-01-082
ODUM SERVICES, L.P. (16.22)
Contract #01163210
Totals861310.508680.00834384.7798.0

CountyANGELINA
HighwayUS 69
FromHUNTINGTON
ToFM 844
CSJ0200-02-040
Proj IDNH 2017(162)
Work TypePREP ROW
 
2.253359054.460.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-22-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-02-040
N-LINE TRAFFIC MAINTENANCE, L.P. (1.27)
Contract #10163206
Totals359054.460.000.000.0

CountySAN JACINTO
HighwayUS 190
FromWALKER COUNTY LINE
ToPOLK COUNTY LINE
CSJ0213-02-043
Proj IDSTP 1602(080)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
14.0372543073.001082199.8242.5
Work Order06-27-16
Work Began07-26-16
Work Completed
Time Computed07-26-16
Contract Working Days246
Addl Days Granted0
Working Days Charged82
Percent Time Used33
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0213-02-043
ODUM SERVICES, L.P. (9.53)
B-N-T SERVICES, LLC (12.07)
Contract #05163008
Totals2543073.00208620.921082199.8242.5

CountyPOLK
HighwayUS 190
FromONALASKA
ToFM 2457
CSJ0213-03-097
Proj IDSTP 2013(515)
Work TypeADD PASSING LANES
 
21.94313913635.967766191.6055.8
Work Order11-24-15
Work Began02-01-16
Work Completed
Time Computed12-24-15
Contract Working Days223
Addl Days Granted0
Working Days Charged175
Percent Time Used78
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0213-03-097
ROADSAFE TRAFFIC SYSTEMS, INC. (0.65)
WILLOW CITY SIGN & RAIL, INC. (0.48)
WATERS CONSTRUCTION CO., INC. (4.26)
TEXOP CONSTRUCTION (0.87)
TEXAS LAND CLEARING SERVICE (1.42)
LUDCO, INC. (0.21)
DUSTIN ALLEN, INC. (5.72)
COWBELL TRAFFIC SERVICES, INC. (0.14)
J & M CONTRACTING, COMPANY (20.43)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.53)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.01)
Contract #09153004
Totals13913635.961203219.207766191.6055.8

CountyPOLK
HighwayUS 190
FromUS 59
To0.12 MI W OF FM 1276
CSJ0213-04-046
Proj IDSTP 2016(708)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
22.8521486579.001243444.1083.6
Work Order04-12-16
Work Began04-26-16
Work Completed
Time Computed04-26-16
Contract Working Days124
Addl Days Granted0
Working Days Charged124
Percent Time Used100
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0213-04-046
L.C. JORDAN & SON (17.75)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.57)
Contract #02163030
Totals1486579.0065733.801243444.1083.6

CountyTRINITY
HighwayUS 287
FromHARRISON ST IN GROVETON
ToFM 355 IN GROVETON
CSJ0319-01-062
Proj IDSTP 1502(608)
Work TypeRECONSTRUCT PAVEMENT
 
0.9784457994.944285528.9596.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-12-15
Work Began01-11-16
Work Completed
Time Computed00-00-00
Contract Working Days98
Addl Days Granted59
Working Days Charged135
Percent Time Used85
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0319-01-062
INTERSTATE BARRICADES & MARKINGS, INC. (0.23)
DUSTROL, INC. (4.30)
J & M CONTRACTING, COMPANY (30.95)
WATERS CONSTRUCTION CO., INC. (0.78)
WILLOW CITY SIGN & RAIL, INC. (0.43)
STRIPE-A-ZONE, INC. (0.43)
Contract #08153053
Totals4457994.940.004285528.9596.1

CountyHOUSTON
HighwaySH 7
From0.2 MI E OF FM 232
ToKENNARD
CSJ0336-01-046
Proj IDNH 2015(156)
Work TypeGRADING, STRUT, BASE, HMAC SURFACE
 
7.05710296162.557900231.8976.7
Work Order10-28-14
Work Began01-07-15
Work Completed
Time Computed11-13-14
Contract Working Days390
Addl Days Granted17
Working Days Charged293
Percent Time Used71
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0336-01-046
INTERSTATE BARRICADES & MARKINGS, INC. (0.87)
TEX OP CONSTRUCTION, LP (0.06)
WEST TEXAS RUMBLE STRIP (0.04)
PANOLA SIGN & BARRICADE, INC. (0.43)
RICE ENVIRONMENTAL SERVICES (1.77)
J & M CONTRACTING, COMPANY (9.35)
SANDHILL FOUNDATION, LLC (1.69)
MOORE BROTHERS CONSTRUCTION COMPANY (26.16)
AMERICAN REMEDIATION OPTIONS, INC. (0.55)
Contract #09143203
Totals10296162.55177413.287900231.8976.7

CountyTRINITY
HighwayUS 287
FromHOUSTON COUNTY LINE
ToSH 94
CSJ0340-02-025
Proj IDSTP 1602(082)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
22.2511687891.22376594.0022.3
Work Order07-11-16
Work Began09-26-16
Work Completed
Time Computed08-10-16
Contract Working Days178
Addl Days Granted1
Working Days Charged46
Percent Time Used25
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0340-02-025
N-LINE TRAFFIC MAINTENANCE, L.P. (0.84)
DUSTIN ALLEN, INC. (6.67)
COLD CREEK CONSTRUCTION, LTD (7.93)
Contract #05163028
Totals1687891.221200.00376594.0022.3

CountyPOLK
HighwayFM 356
From1.12 MI N OF US 190
ToUS 190
CSJ0475-11-031
Proj IDSTP 1602(273)
Work TypeGR,STR,CURB,GUTTER,BASE,SURF
 
1.0797653712.001015797.6513.2
Work Order09-15-16
Work Began11-14-16
Work Completed
Time Computed10-17-16
Contract Working Days162
Addl Days Granted0
Working Days Charged20
Percent Time Used12
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0475-11-031
CEN TEX HYDROSEED, INC. (1.83)
J & M CONTRACTING, COMPANY (42.30)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.62)
WATERS CONSTRUCTION CO., INC. (1.41)
WILLOW CITY SIGN & RAIL, INC. (1.53)
THIRD COAST SERVICES LLC (1.23)
TEXAS LAND CLEARING SERVICE (0.97)
Contract #07163039
Totals7653712.00519429.591015797.6513.2

CountyPOLK
HighwayFM 62
FromAT DRAW CREEK
To.
CSJ0654-01-026
Proj IDBR 2016(964)
Work TypeBRIDGE REHABILITATION
 
0.090495378.86273493.8255.2
Work Order07-15-16
Work Began09-13-16
Work Completed
Time Computed08-15-16
Contract Working Days65
Addl Days Granted0
Working Days Charged61
Percent Time Used93
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 0654-01-026
MORRIS COUNTY CONTRACTORS, L.L.C. (4.41)
FLEX SUPPLY, LLC (0.76)
JM YANEZ CONSTRUCTION (13.21)
A K CONTRACTING, LLC (1.11)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.06)
Contract #04163229
Totals495378.8663238.35273493.8255.2

CountyNACOGDOCHES
HighwayFM 95
FromAT PARALLEL CREEK
To.
CSJ0706-03-020
Proj IDBR 1502(622)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2891783241.531530963.6485.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-30-15
Work Began03-01-16
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted2
Working Days Charged124
Percent Time Used101
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0706-03-020
AMERICAN REMEDIATION OPTIONS, INC. (5.48)
PANOLA SIGN & BARRICADE, INC. (0.67)
STRIPING TECHNOLOGY, L.P. (0.70)
Contract #08153239
Totals1783241.530.001530963.6485.9