Monthly State Let Construction Report For Lufkin District As Of Oct 16, 2017 Page 2 Of 4

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyANGELINA
HighwayUS 59
From.9 MILES N. OF LP 287 (N) (@ UP RR)
To.1 MILES N. OF LP 287 (N)
CSJ0176-02-090
Proj IDSTP 99(770)RGS
Work TypeREPLACE RAILROAD UNDERPASS
 
0.55413760249.9313152130.0495.5
CountyANGELINA
HighwayUS 59
From0.13 MI N OF FM 3439
ToLP 287/US 69
CSJ0176-02-105
Proj IDSTP 2012(501)HES
Work TypeCONSTRUCT INTERCHANGE
 
1.82938418975.2839223271.7399.9
Work Order08-20-12
Work Began09-10-12
Work Completed
Time Computed09-10-12
Contract Working Days764
Addl Days Granted116
Working Days Charged876
Percent Time Used99
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-090
HIGHWAY TECHNOLOGIES, INC. (0.12)
BATTERSON,LLP (0.57)
DUSTIN ALLEN, INC. (0.72)
A. H. BAKER SERVICES, INC. (10.54)
W. W. FOUNDATION DRILLING, LTD. (1.86)
MOORE BROTHERS CONSTRUCTION COMPANY (9.56)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.07)
DUSTROL, INC. (0.02)
DRILL TECH DRILLING & SHORING, INC. (1.56)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.17)
RAILWORKS TRACK SYSTEMS, INC. (0.14)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17)
A R BROTHERS CONSTRUCTION SERVICES, INC. (0.54)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (2.70)
ALLEN LOGGINGS & SONS, INC. (0.19)
FUGRO CONSULTANTS LP (0.07)
MESA ROD BUSTERS, INC. (0.80)
EROSION CONTROL, INC. (0.92)
EAST TEXAS LANDSCAPING, INC. (0.13)
TEX OP CONSTRUCTION, LP (0.42)
PINTO CONSTRUCTION CO., INC. (1.46)
SCOTT DERR PAINTING CO, LLC (0.30)
FARR FOUNDATION, INC. (1.39)
COX CONTRACTORS, INC. (0.65)
CURB PLANET INC. (0.00)
WEBBER BARRIER SERVICES, LLC. (0.76)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.07)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.22)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.88)
HEMPHILL PILE DRIVING CO., A CORP. (0.01)
SITAR CONSTRUCTION, LLC (0.11)
TX DOWN UNDER CONSTRUCTION, LLC (0.01)
ENCINO LANDSCAPE, INC. (0.17)
ROY LEE WALKER (0.01)
SOUTHEAST GRINDING & GROOVING, LLC (0.11)
Contract #06123008
Totals52179225.210.0052375401.7799.9

CountyANGELINA
HighwayUS 59
FromAT FM 2021
To.
CSJ0176-02-102
Proj IDSTP 2013(779)SB
Work TypeCONSTRUCT GRADE SEPARATION
 
1.28418772914.7118863716.5299.9
Work Order10-24-13
Work Began11-11-13
Work Completed
Time Computed12-01-13
Contract Working Days515
Addl Days Granted22
Working Days Charged518
Percent Time Used96
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-102
LOGGINS & SONS, ALLEN (3.28)
SOUTH TEXAS ILLUMINATION, LLC (0.79)
W. W. FOUNDATION DRILLING, LTD. (0.69)
PROFESSIONAL TRAFFIC CONTROL, LLC (1.34)
PINTO CONSTRUCTION CO., INC. (2.81)
BREDA COMPANY, INC. (0.93)
DUSTROL, INC. (0.72)
WEBBER BARRIER SERVICES, LLC. (0.50)
MOORE BROTHERS CONSTRUCTION COMPANY (16.38)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.14)
SCOTT DERR PAINTING CO (0.05)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18)
ODUM SERVICES, L.P. (0.22)
PEREZ CONSTRUCTION CO. (0.24)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.39)
BRADCO, LLC (0.38)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.01)
ROY LEE WALKER (0.01)
SOUTHEAST GRINDING & GROOVING, LLC (0.10)
Contract #06133202
Totals18772914.710.0018863716.5299.9

CountyANGELINA
HighwayUS 59
FromANGELINA RIVER BRIDGE
To0.520 MI NORTH OF FM 2021
CSJ0176-02-120
Proj IDNH 2017(826)
Work TypeHMA LEVEL UP, OCST AND PFC SURFACE
 
2.6902865623.761709229.1359.6
Work Order04-24-17
Work Began06-19-17
Work Completed
Time Computed05-24-17
Contract Working Days77
Addl Days Granted0
Working Days Charged43
Percent Time Used55
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-120
PANOLA SIGN & BARRICADE, INC. (0.20)
CLARK CONSTRUCTION OF TEXAS, INC. (8.56)
DUSTROL, INC. (6.64)
AMERICAN REMEDIATION OPTIONS, INC. (0.44)
STRIPE-A-ZONE, INC. (1.13)
NLG CONSTRUCTION, INC. (0.49)
Contract #03173220
Totals2865623.765457.601709229.1359.6

CountyPOLK
HighwayUS 59
FromAT BEAR CREEK
To.
CSJ0176-04-081
Proj IDBR 2017(481)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.314497647.50489275.7498.3
CountyPOLK
HighwayUS 59
FromANGELINA COUNTY LINE
ToUS 287
CSJ0176-04-084
Proj IDSTP 2017(482)HES
Work TypeIMPROVE GUARDRAIL TO DES STANDARDS
 
9.508299158.75300245.9899.9
Work Order02-07-17
Work Began03-09-17
Work Completed
Time Computed03-09-17
Contract Working Days114
Addl Days Granted3
Working Days Charged98
Percent Time Used83
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-04-081
AREA WIDE PROTECTIVE, INC. (12.94)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (21.92)
TEXAS CURB CUT, LP (1.12)
Contract #01173221
Totals796806.2510000.00789521.7299.0

CountyPOLK
HighwayUS 59
FromSL 393 S
ToTRINITY RIVER
CSJ0177-01-102
Proj IDNH 2017(641)
Work TypeHMA LEVEL-UP, OCST, & PFC
 
1.9702215251.081796209.2781.0
Work Order03-16-17
Work Began05-24-17
Work Completed
Time Computed05-08-17
Contract Working Days55
Addl Days Granted0
Working Days Charged53
Percent Time Used96
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0177-01-102
AWP, INC. (0.24)
CLARK CONSTRUCTION OF TEXAS, INC. (10.11)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.42)
DUSTROL, INC. (4.89)
STRIPING TECHNOLOGY, L.P. (1.85)
CHEROKEE SERVICES (0.36)
WEST TEXAS RUMBLE STRIP (0.18)
Contract #02173007
Totals2215251.08468731.361796209.2781.0

CountySAN JACINTO
HighwayUS 59
From1.00 MILE NORTH OF FM 2914
To1.00 MILE SOUTH OF FM 2914
CSJ0177-02-080
Proj IDSTP 1102(058)HES
Work TypeCNSTR INTRCHANGE & CLOSE CROSSOVERS
 
2.05912895988.9718253075.9699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-31-12
Work Began06-22-12
Work Completed
Time Computed04-02-12
Contract Working Days535
Addl Days Granted398
Working Days Charged933
Percent Time Used100
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-080
CRABTREE BARRICADE SYSTEMS, INC. (1.02)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.31)
MESA ROD BUSTERS, INC. (2.06)
WEBBER-BALKE FOUNDATION COMPANY, INC. (1.82)
ODUM SERVICES, L.P. (0.12)
KOSSMAN CONTRACTING CO., INC. (0.38)
ENVIRONMENTAL ALLIES, L.P. (0.09)
SCOTT DERR PAINTING CO, LLC (0.16)
TRAF-TEX, INC. (4.36)
DUSTROL, INC. (0.46)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.26)
WILLOW CITY SIGN & RAIL, INC. (0.12)
TRIPLE B SERVICES LLP (37.18)
SMITH & COMPANY (16.56)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.10)
GREY WOLF CLEARING INC. (0.52)
A & B CRUSHED CONCRETE (0.12)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.47)
SILVA, INC. (1.21)
INDUS CONSTRUCTION, L.P. (0.63)
JASSO"S SAWING & SEALING (0.36)
CURB PLANET INC. (0.08)
A-1 EROSION CONTROL, LLC (0.59)
WATERS CONSTRUCTION CO., INC. (0.31)
Contract #12113203
Totals12895988.970.0018253075.9699.9

CountySAN JACINTO
HighwayUS 59
FromJUST S OF UPRR IN SHEPHERD
ToJUST N OF FM 2914
CSJ0177-02-089
Proj IDSTP 2013(916)
Work TypeADD SB FRTG RD & RECONST MAIN LANES
 
1.6428948536.8510596914.6399.9
Work Order05-14-14
Work Began08-15-14
Work Completed
Time Computed05-30-14
Contract Working Days230
Addl Days Granted148
Working Days Charged387
Percent Time Used102
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-089
FLORIDA TRAFFIC CONTROL DEVICES, INC. (0.88)
DOUBLE OAK CONSTRUCTION, INC. (0.67)
CRABTREE BARRICADE SYSTEMS, INC. (0.91)
SMITH & COMPANY (20.62)
WILLOW CITY SIGN & RAIL, INC. (0.59)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.20)
BREDA COMPANY, INC. (0.92)
CPAVE, INC. (1.78)
ROY LEE WALKER (0.13)
THOMAS TRACTOR WORKS, INC. (0.16)
NORWEST SERVICES, LLC (0.06)
SOUTHERN CRUSHED CONCRETE LLC (0.86)
SOUTHEAST GRINDING & GROOVING, LLC (0.37)
HOUSTON SAWING & DRILLING (0.03)
DUSTROL, INC. (0.22)
TEXOP CONSTRUCTION (0.23)
WEST TX RUMBLE STRIP (0.09)
Contract #02143221
Totals8948536.85809094.0810596914.6399.9

CountySAN JACINTO
HighwayUS 59
From0.50 MI S OF FM 2914
ToLIBERTY COUNTY LINE
CSJ0177-02-091
Proj IDNH 2016(734)
Work TypeHMA LEVEL-UP AND PFC SURFACE
 
16.4612971066.403045271.0199.9
Work Order04-19-16
Work Began05-23-16
Work Completed
Time Computed05-23-16
Contract Working Days94
Addl Days Granted12
Working Days Charged103
Percent Time Used97
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-091
STRIPING TECHNOLOGY, L.P. (1.46)
INTERSTATE BARRICADES & MARKINGS, INC. (0.60)
COWBELL TRAFFIC SERVICES, INC. (0.39)
CLARK CONSTRUCTION OF TEXAS, INC. (9.33)
AMERICAN REMEDIATION OPTIONS, INC. (6.84)
DUSTROL, INC. (1.05)
NLG CONSTRUCTION, INC. (0.13)
Contract #02163033
Totals2971066.4093210.803045271.0199.9

CountyANGELINA
HighwayBU 69-J
FromAT FM 58
To'
CSJ0200-01-090
Proj IDSTP 2017(642)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.200255255.15304276.1599.9
Work Order03-22-17
Work Began06-30-17
Work Completed
Time Computed06-20-17
Contract Working Days30
Addl Days Granted0
Working Days Charged30
Percent Time Used100
Contractor(s)
SIGNAL SERVICES GROUP INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-01-090
DUSTROL, INC. (7.11)
MOORE BROTHERS CONSTRUCTION COMPANY (21.95)
STRIPE-A-ZONE, INC. (4.42)
TIGER CREEK ENTERPRISES, INC. (2.68)
Contract #02173025
Totals255255.150.00304276.1599.9

CountyANGELINA
HighwayUS 69
FromHUNTINGTON
ToFM 844
CSJ0200-02-031
Proj IDNH 2013(513)
Work TypeGR STRS BASE & SURF
 
2.1039969131.13429870.504.3
Work Order07-14-17
Work Began08-17-17
Work Completed
Time Computed08-14-17
Contract Working Days310
Addl Days Granted0
Working Days Charged17
Percent Time Used5
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-02-031
STRIPING TECHNOLOGY, L.P. (1.60)
A R BROTHERS CONSTRUCTION SERVICES, INC. (11.45)
AMERICAN REMEDIATION OPTIONS, INC. (1.33)
MOORE BROTHERS CONSTRUCTION COMPANY (31.91)
TEXAS ALTERNATIVE GRASSER, INC. (0.86)
PANOLA SIGN & BARRICADE, INC. (0.33)
DUSTROL, INC. (1.07)
STRIPING SYSTEMS, INC. (0.01)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.09)
Contract #06173006
Totals9969131.13371570.08429870.504.3

CountyANGELINA
HighwayUS 69
FromFM 844
ToZAVALLA
CSJ0200-02-042
Proj IDNH 1702(519)
Work TypeCLEARING AND GRUBBING
 
10.835890456.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-23-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days109
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0200-02-042
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.06)
Contract #07173216
Totals890456.220.000.000.0

CountySAN JACINTO
HighwayUS 190
FromWALKER COUNTY LINE
ToPOLK COUNTY LINE
CSJ0213-02-043
Proj IDSTP 1602(080)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
14.0372543073.002143049.5084.2
Work Order06-27-16
Work Began07-26-16
Work Completed
Time Computed07-26-16
Contract Working Days246
Addl Days Granted0
Working Days Charged214
Percent Time Used86
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0213-02-043
ODUM SERVICES, L.P. (9.53)
B-N-T SERVICES, LLC (12.07)
Contract #05163008
Totals2543073.004030.002143049.5084.2

CountyPOLK
HighwayUS 190
FromONALASKA
ToFM 2457
CSJ0213-03-097
Proj IDSTP 2013(515)
Work TypeADD PASSING LANES
 
21.94313913635.9613321987.3395.7
Work Order11-24-15
Work Began02-01-16
Work Completed
Time Computed12-24-15
Contract Working Days223
Addl Days Granted0
Working Days Charged222
Percent Time Used99
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0213-03-097
ROADSAFE TRAFFIC SYSTEMS, INC. (0.65)
WILLOW CITY SIGN & RAIL, INC. (0.48)
WATERS CONSTRUCTION CO., INC. (4.26)
TEXOP CONSTRUCTION (0.87)
TEXAS LAND CLEARING SERVICE (1.42)
LUDCO, INC. (0.21)
DUSTIN ALLEN, INC. (5.72)
COWBELL TRAFFIC SERVICES, INC. (0.14)
J & M CONTRACTING, COMPANY (20.43)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.53)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.01)
Contract #09153004
Totals13913635.9659308.5013321987.3395.7

CountyTRINITY
HighwayUS 287
FromSH 94
ToHARRISON AVE IN GROVETON
CSJ0319-01-064
Proj IDSTP 2017(827)
Work TypeRECONSTRUCT EXISTING PAVEMENT
 
4.7001947390.021319307.0967.7
Work Order04-19-17
Work Began05-31-17
Work Completed
Time Computed05-22-17
Contract Working Days80
Addl Days Granted0
Working Days Charged55
Percent Time Used68
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0319-01-064
A R BROTHERS CONSTRUCTION SERVICES, INC. (9.98)
AWP, INC. (0.93)
STRIPE-A-ZONE, INC. (1.05)
WEST TEXAS RUMBLE STRIP (0.29)
NIXON ENGINEERING, L.L.C. (0.07)
Contract #03173009
Totals1947390.02120252.001319307.0967.7

CountyHOUSTON
HighwaySH 7
From0.2 MI E OF FM 232
ToKENNARD
CSJ0336-01-046
Proj IDNH 2015(156)
Work TypeGRADING, STRUT, BASE, HMAC SURFACE
 
7.05710296162.5510548821.7299.9
Work Order10-28-14
Work Began01-07-15
Work Completed
Time Computed11-13-14
Contract Working Days390
Addl Days Granted17
Working Days Charged355
Percent Time Used87
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0336-01-046
INTERSTATE BARRICADES & MARKINGS, INC. (0.87)
TEX OP CONSTRUCTION, LP (0.06)
WEST TEXAS RUMBLE STRIP (0.04)
PANOLA SIGN & BARRICADE, INC. (0.43)
RICE ENVIRONMENTAL SERVICES (1.77)
J & M CONTRACTING, COMPANY (9.35)
SANDHILL FOUNDATION, LLC (1.69)
MOORE BROTHERS CONSTRUCTION COMPANY (26.16)
AMERICAN REMEDIATION OPTIONS, INC. (0.55)
Contract #09143203
Totals10296162.550.0010548821.7299.9

CountyNACOGDOCHES
HighwaySH 103
FromANGELINA COUNTY LINE
ToSAN AUGUSTINE COUNTY LINE
CSJ0336-06-028
Proj IDSTP 2018(156)HES
Work TypeIMPROVE GUARDRAIL TO DES STANDARDS
 
20.681597891.990.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days74
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0336-06-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173013
Totals597891.990.000.000.0

CountyTRINITY
HighwayUS 287
FromHOUSTON COUNTY LINE
ToSH 94
CSJ0340-02-025
Proj IDSTP 1602(082)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
22.2511687891.221188855.3870.4
Work Order07-11-16
Work Began09-26-16
Work Completed
Time Computed08-10-16
Contract Working Days178
Addl Days Granted1
Working Days Charged119
Percent Time Used66
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0340-02-025
N-LINE TRAFFIC MAINTENANCE, L.P. (0.84)
DUSTIN ALLEN, INC. (6.67)
COLD CREEK CONSTRUCTION, LTD (7.93)
USA LANDSCAPE SERVICES EAST TEAST (1.94)
Contract #05163028
Totals1687891.2222943.801188855.3870.4

CountyPOLK
HighwayFM 356
From1.12 MI N OF US 190
ToUS 190
CSJ0475-11-031
Proj IDSTP 1602(273)
Work TypeGR,STR,CURB,GUTTER,BASE,SURF
 
1.0797653712.004384960.9957.2
Work Order09-15-16
Work Began11-14-16
Work Completed
Time Computed10-17-16
Contract Working Days162
Addl Days Granted0
Working Days Charged144
Percent Time Used88
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0475-11-031
CEN TEX HYDROSEED, INC. (1.83)
J & M CONTRACTING, COMPANY (42.30)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.62)
WATERS CONSTRUCTION CO., INC. (1.41)
WILLOW CITY SIGN & RAIL, INC. (1.53)
THIRD COAST SERVICES LLC (1.23)
TEXAS LAND CLEARING SERVICE (0.97)
TEXOP CONSTRUCTION (0.93)
Contract #07163039
Totals7653712.00429038.984384960.9957.2

CountyNACOGDOCHES
HighwaySH 7
FromAT FM 2782
To.
CSJ0553-03-033
Proj IDSTP 1702(111)HES
Work TypeINSTALL FLASHING BEACON
 
0.20044900.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LUDCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0553-03-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173008
Totals44900.000.000.000.0

CountyNACOGDOCHES
HighwayFM 95
FromAT PARALLEL CREEK
To.
CSJ0706-03-020
Proj IDBR 1502(622)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2891783241.531763540.3799.2
Work Order10-30-15
Work Began03-01-16
Work Completed
Time Computed03-01-16
Contract Working Days120
Addl Days Granted18
Working Days Charged147
Percent Time Used106
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0706-03-020
AMERICAN REMEDIATION OPTIONS, INC. (5.48)
PANOLA SIGN & BARRICADE, INC. (0.67)
STRIPING TECHNOLOGY, L.P. (0.70)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.29)
Contract #08153239
Totals1783241.530.001763540.3799.2

page 1 | page 2 | page 3 | page 4