| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | HOUSTON |
| Highway |
FM 1280 |
| From |
AT WHITE ROCK CREEK & 2 RELIEFS |
| To |
. |
| CSJ |
0931-02-016 |
| Proj ID |
BR 2007(407) |
| Work Type |
REPLACE BRIDGES AND APPROACHES |
| |
|
6.039 |
4068148.33 |
0.00 |
2631527.46 |
64.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
06-14-07 |
| Work Began |
09-06-07 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
458 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0931-02-016 AMERICAN REMEDIATION OPTIONS, INC. (1.60%) J & M CONTRACTING, COMPANY (4.48%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.22%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.22%) QUALITY TRAFFIC SERVICES, L.L.C. (0.74%) ODUM SERVICES, L.P.(2.06%) HIGHWAY TECHNOLOGIES, L.P. (0.93%)
|
| Contract # |
04073226 |
|
Totals |
4068148.33 |
0.00 |
2631527.46 |
64.6 |
|
| County | ANGELINA |
| Highway |
FM 842 |
| From |
SH 103 |
| To |
JACK NERREN ROAD (END OF PAVEMENT) |
| CSJ |
1165-01-022 |
| Proj ID |
STP 2008(671)HES |
| Work Type |
SAFETY TREAT FIXED OBJECTS |
| |
|
11.547 |
646998.61 |
28528.39 |
543774.92 |
84.0 |
| Work Order |
07-14-08 |
| Work Began |
07-28-08 |
| Work Completed |
|
| Time Computed |
07-30-08 |
| Contract Working Days |
148 |
| Addl Days Granted |
0 |
| Working Days Charged |
82 |
| Percent Time Used |
55 |
| Contractor(s) |
| A R BROTHERS CONSTRUCTION SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1165-01-022 TLS FARM SERVICES OF EAST TEXAS, LLC ( 12.90%) BANNER SIGN & BARRICADE, INC. (HOOKS)(1.17%) COLD CREEK CONSTRUCTION, LTD (9.03%) ODUM SERVICES, L.P.( 12.90%)
|
| Contract # |
06083018 |
|
Totals |
646998.61 |
28528.39 |
543774.92 |
84.0 |
|
| County | ANGELINA |
| Highway |
FM 844 |
| From |
US 69 |
| To |
4.62 MI S OF FM 1818 (END PAVEMENT) |
| CSJ |
1166-01-017 |
| Proj ID |
STP 2008(443)HES |
| Work Type |
SAFETY TREAT FIXED OBJECTS |
| |
|
15.823 |
1571479.21 |
62787.75 |
1067641.28 |
67.9 |
| Work Order |
05-05-08 |
| Work Began |
05-15-08 |
| Work Completed |
|
| Time Computed |
05-21-08 |
| Contract Working Days |
307 |
| Addl Days Granted |
0 |
| Working Days Charged |
130 |
| Percent Time Used |
42 |
| Contractor(s) |
| AJAX EQUIPMENT COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1166-01-017 JORDAN SERVICES(2.39%) D. B. INDUSTRIES, INC. (3.13%) RED-GAP CONTRACTORS, L.L.C.(9.43%) STRIPING TECHNOLOGY, L.P.(0.82%)
|
| Contract # |
03083015 |
|
Totals |
1571479.21 |
62787.75 |
1067641.28 |
67.9 |
|
| County | NACOGDOCHES |
| Highway |
FM 343 |
| From |
FM 225 |
| To |
LP 224 |
| CSJ |
2300-01-017 |
| Proj ID |
STP 2008(841)HES |
| Work Type |
SAFETY TREAT FIXED OBJECTS |
| |
|
14.229 |
796260.64 |
0.00 |
70753.23 |
8.8 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-12-08 |
| Work Began |
11-13-08 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
268 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| A R BROTHERS CONSTRUCTION SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2300-01-017 PANOLA SIGN & BARRICADE, INC.(1.45%)
|
| Contract # |
08083020 |
|
Totals |
796260.64 |
0.00 |
70753.23 |
8.8 |
|
| County | HOUSTON |
| Highway |
FM 2160 |
| From |
3.07 MI W OF US 287 (END PAVEMENT) |
| To |
US 287 |
| CSJ |
2357-01-010 |
| Proj ID |
STP 2007(773)HES |
| Work Type |
SAFETY TREAT FIXED OBJECTS |
| |
|
3.075 |
379359.70 |
0.00 |
339537.00 |
99.1 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-14-07 |
| Work Began |
10-16-07 |
| Work Completed |
|
| Time Computed |
09-30-07 |
| Contract Working Days |
149 |
| Addl Days Granted |
0 |
| Working Days Charged |
210 |
| Percent Time Used |
140 |
| Contractor(s) |
| STONERIDGE CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2357-01-010 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08073034 |
|
Totals |
379359.70 |
0.00 |
339537.00 |
99.1 |
|
| County | NACOGDOCHES |
| Highway |
FM 2609 |
| From |
FM 941 |
| To |
LP 224 |
| CSJ |
2590-01-022 |
| Proj ID |
STP 2007(691)SB |
| Work Type |
SFTY TRT FXD OBJS & CNSTR PVD SHLDR |
| |
|
6.078 |
7284403.89 |
16241.72 |
2738562.32 |
34.5 |
| Work Order |
01-23-08 |
| Work Began |
02-05-08 |
| Work Completed |
|
| Time Computed |
02-08-08 |
| Contract Working Days |
453 |
| Addl Days Granted |
0 |
| Working Days Charged |
126 |
| Percent Time Used |
27 |
| Contractor(s) |
| A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2590-01-022 BUILDER SERVICES (0.64%) JV ENVIRONMENTAL SERVICES(1.26%) HIGHWAY TECHNOLOGIES (0.74%) N-LINE TRAFFIC MAINTENANCE, L.P. (1.41%) STRIPING TECHNOLOGY, L.P.(0.09%) A R BROTHERS CONSTRUCTION SERVICES, INC. ( 13.34%)
|
| Contract # |
07073006 |
|
Totals |
7284403.89 |
16241.72 |
2738562.32 |
34.5 |
|