Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyANGELINA
Highway US 59
From AT FM 2021
To .
CSJ 0176-02-102
Proj ID STP 2013(779)SB
Work Type CONSTRUCT GRADE SEPARATION
 
1.284 18772914.71 1589.14 18862305.99 99.9
Work Order 10-24-13
Work Began 11-11-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 515
Addl Days Granted 22
Working Days Charged 518
Percent Time Used 96
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-102
LOGGINS & SONS, ALLEN(3.28%)
SOUTH TEXAS ILLUMINATION, LLC(0.79%)
W. W. FOUNDATION DRILLING, LTD.(0.69%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.34%)
PINTO CONSTRUCTION CO., INC. (2.81%)
BREDA COMPANY, INC.(0.93%)
DUSTROL, INC.(0.72%)
WEBBER BARRIER SERVICES, LLC.(0.50%)
MOORE BROTHERS CONSTRUCTION COMPANY( 16.38%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.14%)
SCOTT DERR PAINTING CO (0.05%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18%)
ODUM SERVICES, L.P.(0.22%)
PEREZ CONSTRUCTION CO. (0.24%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.39%)
BRADCO, LLC(0.38%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.01%)
ROY LEE WALKER (0.01%)
SOUTHEAST GRINDING & GROOVING, LLC (0.10%)
Contract # 06133202
Totals 18772914.71 1589.14 18862305.99 99.9

CountyANGELINA
Highway US 59
From 0.7 MI S OF FM 2021 @ REDLAND
To 0.1 MI N OF FM 3439
CSJ 0176-02-113
Proj ID NH 1602(093)
Work Type HMA LEVEL - UP AND PFC SURFACE
 
1.289 1438279.24 1099079.24 1443072.04 99.9
Work Order 06-06-16
Work Began 09-07-16
Work Completed  
Time Computed 07-18-16
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 85
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-113
PANOLA SIGN & BARRICADE, INC.(0.39%)
STRIPE-A-ZONE, INC.(1.47%)
COWBELL TRAFFIC SERVICES, INC. (0.39%)
ALL AMERICAN MILLING, LLC(2.55%)
FREDONIA CONSTRUCTION SERVICES (0.69%)
TEX OP CONSTRUCTION, LP(4.43%)
Contract # 05163206
Totals 1438279.24 1099079.24 1443072.04 99.9

CountyPOLK
Highway US 59
From 0.47 MI S OF MILTON CREEK
To BU 59-J OVERPASS (SB LANES ONLY)
CSJ 0176-05-178
Proj ID NH 1602(034)
Work Type HMA LEVEL - UP AND PFC SURFACE
 
2.529 1250482.54 42711.08 1191043.72 95.3
Work Order 00-00-00
Work Began 08-02-16
Work Completed  
Time Computed 07-25-16
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 105
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0176-05-178
CEN TEX HYDROSEED, INC.(0.51%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.67%)
COWBELL TRAFFIC SERVICES, INC. (0.61%)
DUSTROL, INC.(6.19%)
WATERS CONSTRUCTION CO., INC.(9.67%)
Contract # 04163236
Totals 1250482.54 42711.08 1191043.72 95.3

CountyPOLK
Highway US 59
From AT FM 350
To '
CSJ 0176-05-179
Proj ID STP 1602(451)HES
Work Type INSTALL ADVANCE WARNING SIGNAL
 
0.600 89789.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-14-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0176-05-179
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163238
Totals 89789.50 0.00 0.00 0.0

CountySAN JACINTO
Highway US 59
From 1.00 MILE NORTH OF FM 2914
To 1.00 MILE SOUTH OF FM 2914
CSJ 0177-02-080
Proj ID STP 1102(058)HES
Work Type CNSTR INTRCHANGE & CLOSE CROSSOVERS
 
2.059 12895988.97 1749504.68 15958824.33 99.9
Work Order 01-31-12
Work Began 06-22-12
Work Completed  
Time Computed 04-02-12
Contract Working Days 535
Addl Days Granted 236
Working Days Charged 853
Percent Time Used 110
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-080
CRABTREE BARRICADE SYSTEMS, INC. (1.02%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.31%)
MESA ROD BUSTERS, INC. (2.06%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.82%)
ODUM SERVICES, L.P.(0.12%)
KOSSMAN CONTRACTING CO., INC.(0.38%)
ENVIRONMENTAL ALLIES, L.P. (0.09%)
SCOTT DERR PAINTING CO, LLC(0.16%)
TRAF-TEX, INC. (4.36%)
DUSTROL, INC.(0.46%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.26%)
WILLOW CITY SIGN & RAIL, INC.(0.12%)
TRIPLE B SERVICES LLP( 37.18%)
SMITH & COMPANY( 16.56%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.10%)
GREY WOLF CLEARING INC.(0.52%)
A & B CRUSHED CONCRETE (0.12%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.47%)
SILVA, INC.(1.21%)
INDUS CONSTRUCTION, L.P. (0.63%)
JASSO"S SAWING & SEALING (0.36%)
CURB PLANET INC. (0.08%)
A-1 EROSION CONTROL, LLC (0.59%)
Contract # 12113203
Totals 12895988.97 1749504.68 15958824.33 99.9

CountySAN JACINTO
Highway US 59
From JUST S OF UPRR IN SHEPHERD
To JUST N OF FM 2914
CSJ 0177-02-089
Proj ID STP 2013(916)
Work Type ADD SB FRTG RD & RECONST MAIN LANES
 
1.642 8948536.85 504036.96 2765387.06 30.9
Work Order 05-14-14
Work Began 08-15-14
Work Completed  
Time Computed 05-30-14
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 79
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-089
FLORIDA TRAFFIC CONTROL DEVICES, INC.(0.88%)
DOUBLE OAK CONSTRUCTION, INC.(0.67%)
CRABTREE BARRICADE SYSTEMS, INC. (0.91%)
SMITH & COMPANY( 20.62%)
WILLOW CITY SIGN & RAIL, INC.(0.59%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.20%)
BREDA COMPANY, INC.(0.92%)
CPAVE, INC.(1.78%)
ROY LEE WALKER (0.13%)
THOMAS TRACTOR WORKS, INC. (0.16%)
NORWEST SERVICES, LLC(0.06%)
Contract # 02143221
Totals 8948536.85 504036.96 2765387.06 30.9

CountySAN JACINTO
Highway US 59
From 0.50 MI S OF FM 2914
To LIBERTY COUNTY LINE
CSJ 0177-02-091
Proj ID NH 2016(734)
Work Type HMA LEVEL - UP AND PFC SURFACE
 
16.461 2971066.40 1183147.37 2517909.34 84.7
Work Order 04-19-16
Work Began 05-23-16
Work Completed  
Time Computed 05-23-16
Contract Working Days 94
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 85
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-091
STRIPING TECHNOLOGY, L.P.(1.46%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.60%)
COWBELL TRAFFIC SERVICES, INC. (0.39%)
CLARK CONSTRUCTION OF TEXAS, INC.(9.33%)
AMERICAN REMEDIATION OPTIONS, INC. (6.84%)
DUSTROL, INC.(1.05%)
NLG CONSTRUCTION, INC. (0.13%)
Contract # 02163033
Totals 2971066.40 1183147.37 2517909.34 84.7

CountyANGELINA
Highway US 69
From SL 287
To 0.202 MI N OF HUNTINGTON SCL
CSJ 0200-01-082
Proj ID STP 2016(423)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
8.849 861310.50 165602.44 741076.82 86.6
Work Order 03-31-16
Work Began 05-17-16
Work Completed  
Time Computed 05-17-16
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 109
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0200-01-082
ODUM SERVICES, L.P.( 16.22%)
Contract # 01163210
Totals 861310.50 165602.44 741076.82 86.6

CountyANGELINA
Highway US 69
From HUNTINGTON
To FM 844
CSJ 0200-02-040
Proj ID NH 2017(162)
Work Type PREP ROW
 
2.253 359054.46 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-02-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10163206
Totals 359054.46 0.00 0.00 0.0

CountySAN JACINTO
Highway US 190
From WALKER COUNTY LINE
To POLK COUNTY LINE
CSJ 0213-02-043
Proj ID STP 1602(080)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
14.037 2543073.00 146767.82 691986.62 27.2
Work Order 06-27-16
Work Began 07-26-16
Work Completed  
Time Computed 07-26-16
Contract Working Days 246
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 19
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0213-02-043
ODUM SERVICES, L.P.(9.53%)
B-N-T SERVICES, LLC( 12.07%)
Contract # 05163008
Totals 2543073.00 146767.82 691986.62 27.2

CountyPOLK
Highway US 190
From ONALASKA
To FM 2457
CSJ 0213-03-097
Proj ID STP 2013(515)
Work Type ADD PASSING LANES
 
21.943 13913635.96 567710.04 6065526.23 43.5
Work Order 11-24-15
Work Began 02-01-16
Work Completed  
Time Computed 12-24-15
Contract Working Days 223
Addl Days Granted 0
Working Days Charged 146
Percent Time Used 65
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0213-03-097
ROADSAFE TRAFFIC SYSTEMS, INC. (0.65%)
WILLOW CITY SIGN & RAIL, INC.(0.48%)
WATERS CONSTRUCTION CO., INC.(4.26%)
TEXOP CONSTRUCTION (0.87%)
TEXAS LAND CLEARING SERVICE(1.42%)
LUDCO, INC.(0.21%)
DUSTIN ALLEN, INC. (5.72%)
COWBELL TRAFFIC SERVICES, INC. (0.14%)
J & M CONTRACTING, COMPANY ( 20.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.53%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.01%)
Contract # 09153004
Totals 13913635.96 567710.04 6065526.23 43.5

CountyPOLK
Highway US 190
From US 59
To 0.12 MI W OF FM 1276
CSJ 0213-04-046
Proj ID STP 2016(708)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
22.852 1486579.00 83489.00 778487.50 52.3
Work Order 04-12-16
Work Began 04-26-16
Work Completed  
Time Computed 04-26-16
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 81
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0213-04-046
L.C. JORDAN & SON( 17.75%)
Contract # 02163030
Totals 1486579.00 83489.00 778487.50 52.3

CountyTRINITY
Highway US 287
From HARRISON ST IN GROVETON
To FM 355 IN GROVETON
CSJ 0319-01-062
Proj ID STP 1502(608)
Work Type RECONSTRUCT PAVEMENT
 
0.978 4457994.94 0.00 3091482.54 69.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 01-11-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 98
Addl Days Granted 59
Working Days Charged 106
Percent Time Used 67
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0319-01-062
INTERSTATE BARRICADES & MARKINGS, INC. (0.23%)
DUSTROL, INC.(4.30%)
J & M CONTRACTING, COMPANY ( 30.95%)
WATERS CONSTRUCTION CO., INC.(0.78%)
WILLOW CITY SIGN & RAIL, INC.(0.43%)
STRIPE-A-ZONE, INC.(0.43%)
Contract # 08153053
Totals 4457994.94 0.00 3091482.54 69.3

CountyHOUSTON
Highway SH 7
From 0.2 MI E OF FM 232
To KENNARD
CSJ 0336-01-046
Proj ID NH 2015(156)
Work Type GRADING, STRUT, BASE, HMAC SURFACE
 
7.057 10296162.55 773554.45 7641681.58 74.2
Work Order 10-28-14
Work Began 01-07-15
Work Completed  
Time Computed 11-13-14
Contract Working Days 390
Addl Days Granted 17
Working Days Charged 267
Percent Time Used 65
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0336-01-046
INTERSTATE BARRICADES & MARKINGS, INC. (0.87%)
TEX OP CONSTRUCTION, LP(0.06%)
WEST TEXAS RUMBLE STRIP(0.04%)
PANOLA SIGN & BARRICADE, INC.(0.43%)
RICE ENVIRONMENTAL SERVICES(1.77%)
J & M CONTRACTING, COMPANY (9.35%)
SANDHILL FOUNDATION, LLC (1.69%)
MOORE BROTHERS CONSTRUCTION COMPANY( 26.16%)
AMERICAN REMEDIATION OPTIONS, INC. (0.55%)
Contract # 09143203
Totals 10296162.55 773554.45 7641681.58 74.2

CountyTRINITY
Highway US 287
From HOUSTON COUNTY LINE
To SH 94
CSJ 0340-02-025
Proj ID STP 1602(082)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
22.251 1687891.22 119980.00 339904.00 20.1
Work Order 07-11-16
Work Began 09-26-16
Work Completed  
Time Computed 08-10-16
Contract Working Days 178
Addl Days Granted 1
Working Days Charged 42
Percent Time Used 23
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0340-02-025
N-LINE TRAFFIC MAINTENANCE, L.P. (0.84%)
DUSTIN ALLEN, INC. (6.67%)
COLD CREEK CONSTRUCTION, LTD (7.93%)
Contract # 05163028
Totals 1687891.22 119980.00 339904.00 20.1

CountyPOLK
Highway FM 356
From 1.12 MI N OF US 190
To US 190
CSJ 0475-11-031
Proj ID STP 1602(273)
Work Type GR, STR, CURB, GUTTER, BASE, SURF
 
1.079 7653712.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-15-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 162
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0475-11-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163039
Totals 7653712.00 0.00 0.00 0.0

CountyPOLK
Highway FM 62
From AT DRAW CREEK
To .
CSJ 0654-01-026
Proj ID BR 2016(964)
Work Type BRIDGE REHABILITATION
 
0.090 495378.86 63012.92 165977.62 33.5
Work Order 07-15-16
Work Began 09-13-16
Work Completed  
Time Computed 08-15-16
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 63
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 0654-01-026
MORRIS COUNTY CONTRACTORS, L.L.C.(4.41%)
FLEX SUPPLY, LLC (0.76%)
JM YANEZ CONSTRUCTION( 13.21%)
Contract # 04163229
Totals 495378.86 63012.92 165977.62 33.5

CountyNACOGDOCHES
Highway FM 95
From AT PARALLEL CREEK
To .
CSJ 0706-03-020
Proj ID BR 1502(622)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.289 1783241.53 0.00 1215062.19 68.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-15
Work Began 03-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 85
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0706-03-020
AMERICAN REMEDIATION OPTIONS, INC. (5.48%)
PANOLA SIGN & BARRICADE, INC.(0.67%)
STRIPING TECHNOLOGY, L.P.(0.70%)
Contract # 08153239
Totals 1783241.53 0.00 1215062.19 68.1

CountySAN AUGUSTINE
Highway US 96
From SHELBY COUNTY LINE
To FM 3451
CSJ 0809-03-038
Proj ID NH 2013(514)
Work Type ADD PASSING LANES AND RECONST PVMT
 
3.804 7319958.62 0.00 2501621.17 34.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 03-30-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 71
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0809-03-038
PANOLA SIGN & BARRICADE, INC.(0.19%)
COLD CREEK CONSTRUCTION, LTD (1.64%)
AMERICAN REMEDIATION OPTIONS, INC. (2.74%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (4.64%)
DUSTROL, INC.(1.52%)
LONGVIEW BRIDGE AND ROAD, LTD. ( 42.07%)
STRIPING TECHNOLOGY, L.P.(1.93%)
WEST TEXAS RUMBLE STRIP(0.06%)
STRIPING SYSTEMS, INC. (0.02%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.89%)
Contract # 08153048
Totals 7319958.62 0.00 2501621.17 34.1

CountySAN AUGUSTINE
Highway US 96
From AT AYISH BAYOU
To .
CSJ 0809-04-046
Proj ID BR 1502(202)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.545 3951203.54 288541.82 3093133.16 78.2
Work Order 07-02-15
Work Began 11-18-15
Work Completed  
Time Computed 08-02-15
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 152
Percent Time Used 100
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0809-04-046
PANOLA SIGN & BARRICADE, INC.(0.26%)
MOORE BROTHERS CONSTRUCTION COMPANY( 13.90%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.73%)
MCL CONTRACTING, LLC (0.14%)
CRABTREE BARRICADE SYSTEMS, INC. (0.65%)
AMERICAN REMEDIATION OPTIONS, INC. (2.06%)
MAC TRANSPORTATION, LTD, L.L.P.(0.00%)
Contract # 05153241
Totals 3951203.54 288541.82 3093133.16 78.2