Monthly State Let Construction Report For Lufkin District As Of Apr 11, 2014 Page 2 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPOLK
Highway PR 56
From US 190
To 1.317 MI S
CSJ 0213-12-009
Proj ID PLD 2014(053)
Work Type RECONSTRUCT & WIDEN EXISTING PVMT
 
1.317 1144070.43 233454.38 233454.38 20.4
Work Order 01-17-14
Work Began 03-12-14
Work Completed  
Time Computed 03-12-14
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 28
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0213-12-009
LONESTAR TRAFFIC SAFETY, LLC (0.32%)
MOORE BROTHERS CONSTRUCTION COMPANY( 29.10%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 13.34%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.52%)
AMERICAN REMEDIATION OPTIONS, INC. (5.88%)
Contract # 10133218
Totals 1144070.43 233454.38 233454.38 20.4

CountySABINE
Highway SH 87
From 1.61 MI S OF FM 944
To 0.2 MI SE OF FM 2928
CSJ 0304-04-042
Proj ID STP 2013(463)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
7.996 1937298.95 6167.50 1578953.53 81.5
Work Order 05-23-13
Work Began 07-01-13
Work Completed  
Time Computed 06-08-13
Contract Working Days 62
Addl Days Granted 22
Working Days Charged 76
Percent Time Used 90
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0304-04-042
AMERICAN REMEDIATION OPTIONS, INC. (6.78%)
CRABTREE BARRICADE SYSTEMS, INC. (2.64%)
LONE STAR EQUIPMENT CO. INC. (INACTIVE--SEE 12687) ( 21.75%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
EXPRESS PERSONNEL SERVICES (0.25%)
Contract # 03133229
Totals 1937298.95 6167.50 1578953.53 81.5

CountyHOUSTON
Highway SH 7
From LEON COUNTY LINE
To 1.32 MI W OF SH 21
CSJ 0335-02-028
Proj ID STP 2013(330)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
21.317 5778013.18 3620.56 5426638.90 93.9
CountyHOUSTON
Highway SH 7
From 1.32 MI W OF SH 21
To SH 21
CSJ 0335-02-029
Proj ID STP 2013(331)
Work Type RESURFACE WITH HMA PAVEMENT
 
1.050 310422.64 105.00 240391.39 77.4
Work Order 03-22-13
Work Began 04-04-13
Work Completed  
Time Computed 04-04-13
Contract Working Days 202
Addl Days Granted 0
Working Days Charged 191
Percent Time Used 94
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0335-02-028
A R BROTHERS CONSTRUCTION SERVICES, INC. (8.97%)
BATTERSON,LLP(0.67%)
MURRAY CONSTRUCTION(0.44%)
STRIPING TECHNOLOGY, L.P.(1.72%)
TEXAS LAND CLEARING, INC.(0.92%)
WATERS CONSTRUCTION CO., INC.( 18.08%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.77%)
DUSTIN ALLEN, INC. (5.75%)
Contract # 01133202
Totals 6088435.82 3725.56 5667030.29 93.0

CountyANGELINA
Highway SP 339
From LP 36
To SH 94
CSJ 0336-04-014
Proj ID STP 2013(120)
Work Type PLANE, SEAL AND OVERLAY
 
1.166 778694.77 73487.43 263365.93 33.8
CountyANGELINA
Highway SP 339
From LP 287
To LP 36
CSJ 0336-04-015
Proj ID PLD 1102(545)
Work Type RESURF & WIDEN FOR CTWLTL W / C & G
 
1.110 2633618.29 33171.99 1852541.06 70.3
Work Order 12-04-12
Work Began 02-08-13
Work Completed  
Time Computed 02-04-13
Contract Working Days 231
Addl Days Granted 1
Working Days Charged 171
Percent Time Used 73
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0336-04-014
HIGHWAY TECHNOLOGIES, INC. (1.80%)
AMERICAN REMEDIATION OPTIONS, INC. (1.48%)
J & M CONTRACTING, COMPANY ( 31.01%)
DUSTROL, INC.(2.89%)
LONE STAR EQUIPMENT CO. INC. (INACTIVE--SEE 12687) (6.61%)
M BROCK INC(0.46%)
PINTO CONSTRUCTION CO., INC. (5.74%)
CRABTREE BARRICADE SYSTEMS, INC. (1.81%)
Contract # 10123006
Totals 3412313.06 106659.42 2115906.99 62.0

CountyNACOGDOCHES
Highway SH 7
From 1.6 MI NE OF ANGELINA RIVER
To 0.3 MI W OF FM 2782
CSJ 0553-03-022
Proj ID C 553-3-22
Work Type GRADING, STRUTURES, BASE, SURFACING
 
2.756 5437705.41 17849.90 5166882.07 95.3
Work Order 10-11-12
Work Began 11-07-12
Work Completed  
Time Computed 11-07-12
Contract Working Days 158
Addl Days Granted 12
Working Days Charged 188
Percent Time Used 110
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0553-03-022
AMERICAN REMEDIATION OPTIONS, INC. (0.20%)
M BROCK INC(0.84%)
MOORE BROTHERS CONSTRUCTION COMPANY( 19.75%)
PANOLA SIGN & BARRICADE, INC.(0.15%)
TEX OP CONSTRUCTION, LP(0.45%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.81%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.07%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (9.18%)
Contract # 08123232
Totals 5437705.41 17849.90 5166882.07 95.3

CountySHELBY
Highway FM 711
From SH 7
To SAN AUGUSTINE COUNTY LINE
CSJ 0895-01-014
Proj ID STP 2013(243)
Work Type RECONSTRUCT AND WIDEN PAVEMENT
 
8.686 3099169.73 1729.75 2780877.52 89.7
Work Order 01-31-13
Work Began 03-14-13
Work Completed  
Time Computed 03-14-13
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 132
Percent Time Used 95
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0895-01-014
AMERICAN REMEDIATION OPTIONS, INC. (0.82%)
M BROCK INC(4.90%)
ODUM SERVICES, L.P.(0.23%)
PANOLA SIGN & BARRICADE, INC.(0.52%)
STRIPING TECHNOLOGY, L.P.(3.10%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.45%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (0.05%)
Contract # 12123221
Totals 3099169.73 1729.75 2780877.52 89.7

CountyPOLK
Highway VA
From AT LAKE LIVINGSTON STATE PARK
To .
CSJ 0911-04-053
Proj ID C 911-4-53
Work Type REPAIR AND RESURFACE PAVED AREAS
 
0.818 819806.93 0.00 774037.38 94.4
Work Order 06-14-13
Work Began 07-25-13
Work Completed  
Time Computed 06-03-13
Contract Working Days 35
Addl Days Granted 5
Working Days Charged 30
Percent Time Used 75
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-053
PANOLA SIGN & BARRICADE, INC.(0.36%)
CCC BLACKTOPPING, LLC( 26.67%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.76%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.40%)
Contract # 04133024
Totals 819806.93 0.00 774037.38 94.4

CountySABINE
Highway CR
From ROCK CREEK RD AT ROCK CREEK
To .
CSJ 0911-29-036
Proj ID BR 2012(488)
Work Type BRIDGE REPLACEMENT
 
0.129 436864.83 0.00 230523.24 52.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-13
Work Began 03-04-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 25
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-29-036
AMERICAN REMEDIATION OPTIONS, INC. (6.81%)
CRABTREE BARRICADE SYSTEMS, INC. (2.02%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 10.92%)
MESA ROD BUSTERS, INC. (0.59%)
Contract # 04133226
Totals 436864.83 0.00 230523.24 52.7

CountySABINE
Highway CR
From CENTERVIEW RD AT BEAR CREEK
To .
CSJ 0911-29-038
Proj ID BR 2012(490)
Work Type BRIDGE REPLACEMENT
 
0.126 437819.77 11678.43 485980.73 99.9
Work Order 05-28-13
Work Began 07-25-13
Work Completed  
Time Computed 07-24-13
Contract Working Days 125
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 74
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-29-038
PANOLA SIGN & BARRICADE, INC.(0.92%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.72%)
AMERICAN REMEDIATION OPTIONS, INC. (6.19%)
NORTH TEXAS REBAR, LLC (0.38%)
Contract # 03133026
Totals 437819.77 11678.43 485980.73 99.9

CountySAN AUGUSTINE
Highway CR
From CR 4320 AT CHIAMON BAYOU
To .
CSJ 0911-30-021
Proj ID BR 2013(435)
Work Type BRIDGE REPLACEMENT
 
0.176 510181.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-30-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143019
Totals 510181.60 0.00 0.00 0.0

CountySAN AUGUSTINE
Highway CR
From CR 201 AT BIG IRON ORE CREEK
To .
CSJ 0911-30-028
Proj ID BR 2013(437)
Work Type BRIDGE REPLACEMENT
 
0.211 644984.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-30-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143023
Totals 644984.12 0.00 0.00 0.0

CountyHOUSTON
Highway FM 227
From BU 287-V
To 0.5 MI E OF CR 1685
CSJ 0937-02-029
Proj ID STP 2013(546)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
11.160 4278380.79 1000.00 2001478.68 46.7
Work Order 06-19-13
Work Began 07-10-13
Work Completed  
Time Computed 07-10-13
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 33
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0937-02-029
STRIPING TECHNOLOGY, L.P.(2.43%)
ROBINSON CONSTRUCTION(4.56%)
ODUM SERVICES, L.P.(3.30%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.66%)
Contract # 04133219
Totals 4278380.79 1000.00 2001478.68 46.7

CountyHOUSTON
Highway FM 1280
From SH 21
To FM 230
CSJ 1676-02-015
Proj ID STP 2013(394)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
25.772 4387077.87 0.00 1888553.37 43.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-13
Work Began 05-20-13
Work Completed  
Time Computed 04-26-13
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 40
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1676-02-015
COLD CREEK CONSTRUCTION, LTD (1.27%)
J & M CONTRACTING, COMPANY ( 13.60%)
MURRAY CONSTRUCTION(0.75%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.77%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.07%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.17%)
TRAFCO INDUSTRIES, INC.(0.03%)
Contract # 02133020
Totals 4387077.87 0.00 1888553.37 43.0

CountyHOUSTON
Highway FM 1733
From SH 21
To SH 7
CSJ 1677-01-015
Proj ID STP 2014(210)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
10.353 3771800.47 280975.51 495203.96 13.1
Work Order 01-23-14
Work Began 02-17-14
Work Completed  
Time Computed 02-08-14
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 14
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1677-01-015
ROADSAFE TRAFFIC SYSTEMS, INC. (2.27%)
ODUM SERVICES, L.P.(1.11%)
MURRAY CONSTRUCTION(0.75%)
J & M CONTRACTING, COMPANY (7.25%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.95%)
DREWERY & WHEATON, LLC (1.65%)
Contract # 11133211
Totals 3771800.47 280975.51 495203.96 13.1

CountyNACOGDOCHES
Highway FM 225
From 0.07 MI WEST OF CR 715
To LOOP 224
CSJ 1810-02-013
Proj ID HP 62(2)
Work Type CONSTRUCT PAVED SHLDRS & OVERLAY
 
2.374 3291831.37 0.00 3561338.09 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-16-11
Work Began 03-06-12
Work Completed  
Time Computed 03-06-12
Contract Working Days 257
Addl Days Granted 32
Working Days Charged 288
Percent Time Used 99
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1810-02-013
CF SOUTHWEST ENVIRONMENT SERVICES LLC(2.40%)
DUSTROL, INC.(0.50%)
J & M CONTRACTING, COMPANY ( 16.64%)
PANOLA SIGN & BARRICADE, INC.(0.27%)
STRIPING TECHNOLOGY, L.P.(1.18%)
MOORE"S CONCRETE CONTRACTORS, LLC(2.87%)
Contract # 11113218
Totals 3291831.37 0.00 3561338.09 99.9

CountyHOUSTON
Highway FM 2022
From ANDERSON COUNTY LINE
To 0.1 MI N OF FM 3313
CSJ 1875-02-021
Proj ID STP 2013(677)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
38.913 4505244.42 132169.19 2461728.16 54.6
Work Order 07-23-13
Work Began 08-13-13
Work Completed  
Time Computed 08-13-13
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 55
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1875-02-021
MURRAY CONSTRUCTION(0.64%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.61%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.91%)
ODUM SERVICES, L.P.(3.30%)
COLD CREEK CONSTRUCTION, LTD (2.18%)
PANOLA SIGN & BARRICADE, INC.(0.98%)
MOORE BROTHERS CONSTRUCTION COMPANY( 30.94%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 20.26%)
SAND HILL FOUNDATION, LLC(0.11%)
Contract # 05133020
Totals 4505244.42 132169.19 2461728.16 54.6

CountySHELBY
Highway FM 2026
From FM 1645
To US 96
CSJ 1879-01-022
Proj ID STP 2013(068)
Work Type RECONSTRUCT AND WIDEN PAVEMENT
 
10.501 4032481.94 1000.00 3710104.84 92.0
Work Order 10-12-12
Work Began 11-26-12
Work Completed  
Time Computed 11-26-12
Contract Working Days 210
Addl Days Granted 1
Working Days Charged 211
Percent Time Used 100
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1879-01-022
SOUTHWEST ENVIRONMENT SERVICES LLC (0.49%)
ODUM SERVICES, L.P.(0.40%)
ROBINSON CONSTRUCTION(1.87%)
STRIPING TECHNOLOGY, L.P.(2.23%)
Contract # 09123230
Totals 4032481.94 1000.00 3710104.84 92.0

CountyHOUSTON
Highway FM 2423
From BU 287-V
To FM 2022
CSJ 2299-01-007
Proj ID STP 2014(336)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
5.970 1440516.50 167210.87 167210.87 11.6
Work Order 02-27-14
Work Began 03-18-14
Work Completed  
Time Computed 03-15-14
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 11
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2299-01-007
SOUTHWEST ENVIRONMENT SERVICES LLC (1.42%)
AMERICAN REMEDIATION OPTIONS, INC. (1.15%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 18.69%)
BATTERSON,LLP(2.42%)
EROSION CONTROL MANAGEMENT SERVICES(1.24%)
COLD CREEK CONSTRUCTION, LTD (6.12%)
PANOLA SIGN & BARRICADE, INC.(0.76%)
Contract # 01143014
Totals 1440516.50 167210.87 167210.87 11.6

CountyANGELINA
Highway FM 1194
From FM 3150
To SH 94
CSJ 2960-01-010
Proj ID STP 2013(876)
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
1.742 1209728.83 247740.19 1023756.27 84.6
Work Order 10-17-13
Work Began 11-11-13
Work Completed  
Time Computed 11-02-13
Contract Working Days 88
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 68
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2960-01-010
M BROCK INC(2.06%)
L. S. EQUIPMENT CO., INC.(5.20%)
PANOLA SIGN & BARRICADE, INC.(0.59%)
STRIPING TECHNOLOGY, L.P.(1.48%)
AMERICAN REMEDIATION OPTIONS, INC. (3.63%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 14.70%)
DUSTROL, INC.(1.36%)
Contract # 07133006
Totals 1209728.83 247740.19 1023756.27 84.6

CountyANGELINA
Highway FM 1475
From FM 841
To FM 326
CSJ 3264-01-007
Proj ID STP 2013(780)
Work Type REHAB & WIDEN EXISTING PAVEMENT
 
1.542 1164539.45 292393.78 701823.95 60.2
Work Order 08-21-13
Work Began 01-27-14
Work Completed  
Time Computed 09-06-13
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 53
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3264-01-007
PANOLA SIGN & BARRICADE, INC.(0.57%)
STRIPING TECHNOLOGY, L.P.(2.62%)
MOORE BROTHERS CONSTRUCTION COMPANY( 22.78%)
M BROCK INC(1.37%)
AMERICAN REMEDIATION OPTIONS, INC. (2.67%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (1.23%)
Contract # 06133006
Totals 1164539.45 292393.78 701823.95 60.2