Monthly State Let Construction Report For Lufkin District As Of Apr 10, 2015 Page 3 Of 3

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOUSTON
Highway FM 1733
From SH 21
To SH 7
CSJ 1677-01-015
Proj ID STP 2014(210)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
10.353 3771800.47 1655.93 3642779.31 100.0
Work Order 01-23-14
Work Began 02-17-14
Work Completed 12-16-14
Time Computed 02-08-14
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 149
Percent Time Used 89
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1677-01-015
ROADSAFE TRAFFIC SYSTEMS, INC. (2.27%)
ODUM SERVICES, L.P.(1.11%)
MURRAY CONSTRUCTION(0.75%)
J & M CONTRACTING, COMPANY (7.25%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.95%)
DREWERY & WHEATON, LLC (1.65%)
BERTLAND-HILL, LLC (0.89%)
Contract # 11133211
Totals 3771800.47 1655.93 3642779.31 100.0

CountyNACOGDOCHES
Highway FM 1878
From NORTH STREET (BU 59-F)
To CLARK BOULEVARD
CSJ 1810-01-028
Proj ID STP 2015(618)
Work Type WIDEN FROM 2 TO 4 LANES AND ADD C & G
 
0.218 1448289.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1810-01-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153215
Totals 1448289.45 0.00 0.00 0.0

CountyHOUSTON
Highway FM 2022
From ANDERSON COUNTY LINE
To 0.1 MI N OF FM 3313
CSJ 1875-02-021
Proj ID STP 2013(677)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
38.913 4505244.42 0.00 4572110.26 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-23-13
Work Began 08-13-13
Work Completed 02-02-15
Time Computed 08-13-13
Contract Working Days 168
Addl Days Granted 12
Working Days Charged 179
Percent Time Used 99
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1875-02-021
MURRAY CONSTRUCTION(0.64%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.61%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.91%)
ODUM SERVICES, L.P.(3.30%)
COLD CREEK CONSTRUCTION, LTD (2.18%)
PANOLA SIGN & BARRICADE, INC.(0.98%)
MOORE BROTHERS CONSTRUCTION COMPANY( 30.94%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 20.26%)
SAND HILL FOUNDATION, LLC(0.11%)
Contract # 05133020
Totals 4505244.42 0.00 4572110.26 100.0

CountyPOLK
Highway FM 1988
From AT LONG KING CREEK
To .
CSJ 1876-01-030
Proj ID BR 1502(017)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.509 3278223.27 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1876-01-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153032
Totals 3278223.27 0.00 0.00 0.0

CountyNACOGDOCHES
Highway LP 224
From SH 7
To US 59 SOUTH
CSJ 2560-01-072
Proj ID STP 2014(750)HESG
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
11.764 1620204.50 151512.07 1366890.89 84.3
Work Order 09-09-14
Work Began 10-10-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 87
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2560-01-072
DREWERY & WHEATON, LLC ( 21.10%)
RICE ENVIRONMENTAL SERVICES( 19.52%)
DREWERY"S TREE SERVICE AND CONSTRUCTION CO., INC.(1.57%)
ODUM SERVICES, L.P.(4.07%)
PANOLA SIGN & BARRICADE, INC.(0.62%)
Contract # 06143228
Totals 1620204.50 151512.07 1366890.89 84.3

CountySHELBY
Highway LP 500
From US 96 (N)
To SH 7 EAST OF CENTER
CSJ 3315-01-016
Proj ID STP 2012(648)
Work Type GR, STR, BASE & SURF
 
3.338 11879175.22 70781.28 10682675.65 89.9
Work Order 09-24-12
Work Began 11-01-12
Work Completed  
Time Computed 11-01-12
Contract Working Days 462
Addl Days Granted 224
Working Days Charged 603
Percent Time Used 87
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 3315-01-016
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. (0.89%)
MOORE BROTHERS CONSTRUCTION COMPANY( 21.73%)
NORTH TEXAS REBAR, LLC (0.62%)
RICE ENVIRONMENTAL SERVICES(0.31%)
S & S PAINTING (0.11%)
TEX OP CONSTRUCTION, LP(0.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.46%)
W. W. FOUNDATION DRILLING, LTD.(1.07%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.32%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
FBL & ASSOCIATES (0.79%)
S & R DOZER, INC.(0.73%)
SILVA CONTRACTING COMPANY, INC.(2.02%)
MCL CONTRACTING, LLC (0.68%)
L. S. EQUIPMENT CO., INC.(0.19%)
Contract # 07123206
Totals 11879175.22 70781.28 10682675.65 89.9

CountyNACOGDOCHES
Highway FM 3314
From 0.9 MI W OF US 59
To US 59 RAMP
CSJ 3490-01-003
Proj ID STP 2015(619)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
0.874 548619.07 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-23-15
Work Began 00-00-00
Work Completed  
Time Computed 04-08-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3490-01-003
AMERICAN REMEDIATION OPTIONS, INC. (5.18%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (6.06%)
MOORE BROTHERS CONSTRUCTION COMPANY( 34.92%)
PANOLA SIGN & BARRICADE, INC.(0.73%)
SANDHILL FOUNDATION, LLC (0.91%)
STRIPING TECHNOLOGY, L.P.(3.90%)
Contract # 02153013
Totals 548619.07 0.00 0.00 0.0

page 1 | page 2 | page 3