Monthly State Let Construction Report For Lufkin District As Of Apr 11, 2016 Page 3 Of 4

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySAN AUGUSTINE
Highway US 96
From SHELBY COUNTY LINE
To FM 3451
CSJ 0809-03-038
Proj ID NH 2013(514)
Work Type ADD PASSING LANES AND RECONST PVMT
 
3.804 7319958.62 0.00 34850.00 0.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 03-30-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 2
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0809-03-038
PANOLA SIGN & BARRICADE, INC.(0.19%)
COLD CREEK CONSTRUCTION, LTD (1.64%)
AMERICAN REMEDIATION OPTIONS, INC. (2.74%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (4.64%)
DUSTROL, INC.(1.52%)
LONGVIEW BRIDGE AND ROAD, LTD. ( 42.07%)
STRIPING TECHNOLOGY, L.P.(1.93%)
WEST TEXAS RUMBLE STRIP(0.06%)
Contract # 08153048
Totals 7319958.62 0.00 34850.00 0.4

CountySAN AUGUSTINE
Highway US 96
From AT AYISH BAYOU
To .
CSJ 0809-04-046
Proj ID BR 1502(202)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.545 3951203.54 378992.30 1774913.68 44.9
Work Order 07-02-15
Work Began 11-18-15
Work Completed  
Time Computed 08-02-15
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 32
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0809-04-046
PANOLA SIGN & BARRICADE, INC.(0.26%)
MOORE BROTHERS CONSTRUCTION COMPANY( 13.90%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.73%)
MCL CONTRACTING, LLC (0.14%)
CRABTREE BARRICADE SYSTEMS, INC. (0.65%)
AMERICAN REMEDIATION OPTIONS, INC. (2.06%)
MAC TRANSPORTATION, LTD, L.L.P.(0.00%)
Contract # 05153241
Totals 3951203.54 378992.30 1774913.68 44.9

CountySHELBY
Highway FM 417
From SH 87
To FM 139
CSJ 0810-02-019
Proj ID STP 2016(808)
Work Type RECONSTRUCT AND WIDEN PAVEMENT
 
11.292 5757568.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 155
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0810-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163021
Totals 5757568.55 0.00 0.00 0.0

CountyANGELINA
Highway VA
From AT VARIOUS LOCATIONS IN LUFKIN DIST
To .
CSJ 0911-00-074
Proj ID STP 1502(258)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1038185.70 0.00 962756.63 92.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-11-15
Work Began 01-05-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 88
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-00-074
N-LINE TRAFFIC MAINTENANCE, L.P. (1.80%)
STRIPE-A-ZONE, INC.(2.33%)
MELS ELECTRIC, L.P.( 19.30%)
JE CASEY, LLC(1.38%)
W.A. ROBBINS CONSTRUCTION CO., INC.( 10.91%)
FAASS TRUCKING, INC. (0.00%)
Contract # 07153263
Totals 1038185.70 0.00 962756.63 92.7

CountyPOLK
Highway CR
From BLUEWATER RD OVER BLUE BRANCH
To .
CSJ 0911-04-034
Proj ID BR 2001(480)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.231 885751.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163212
Totals 885751.00 0.00 0.00 0.0

CountyPOLK
Highway VA
From WITHIN LAKE LIVINGSTON STATE PARK
To .
CSJ 0911-04-054
Proj ID C 911-4-54
Work Type REPAIR AND RESURFACE PAVED AREAS
 
0.100 2009215.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 04-04-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-054
DREWERY BROS TREE SERVICE, INC.(1.20%)
AMERICAN REMEDIATION OPTIONS, INC. (4.01%)
Contract # 01163025
Totals 2009215.00 0.00 0.00 0.0

CountyPOLK
Highway CR
From KELLEY RD OVER MENARD CREEK
To .
CSJ 0911-04-056
Proj ID BR 2014(692)
Work Type BRIDGE REPLACEMENT
 
0.281 707623.10 0.00 676013.37 95.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-26-15
Work Began 09-14-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 39
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-056
PANOLA SIGN & BARRICADE, INC.(1.56%)
AMERICAN REMEDIATION OPTIONS, INC. (9.20%)
Contract # 02153220
Totals 707623.10 0.00 676013.37 95.5

CountyPOLK
Highway CR
From DICK SKINNER RD AT TRIB OF NECHES R
To .
CSJ 0911-04-059
Proj ID BR 1402(188)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.413 1215872.88 142612.64 307493.95 25.2
Work Order 08-26-15
Work Began 02-29-16
Work Completed  
Time Computed 11-24-15
Contract Working Days 151
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 6
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-059
PANOLA SIGN & BARRICADE, INC.(1.09%)
AMERICAN REMEDIATION OPTIONS, INC. (5.52%)
Contract # 07153052
Totals 1215872.88 142612.64 307493.95 25.2

CountyPOLK
Highway CR
From UPPER LEGGETT RD
To AT TRIB OF BIG SANDY CREEK
CSJ 0911-04-060
Proj ID BR 1402(189)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.441 1889227.89 0.00 9913.44 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153046
Totals 1889227.89 0.00 9913.44 0.5

CountyHOUSTON
Highway CR
From CR 3480 AT BIG CREEK TRIBUTARY
To .
CSJ 0911-28-031
Proj ID BR 2014(433)
Work Type BRIDGE REPLACEMENT
 
0.137 748567.80 0.00 290070.95 38.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-15
Work Began 01-20-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 50
Contractor(s)
HARTBEAT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-031
DUSTIN ALLEN, INC. (5.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.51%)
HEMPHILL PILE DRIVING CO., A CORP. (4.20%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.75%)
CANNON STEEL, INC(4.14%)
Contract # 06153231
Totals 748567.80 0.00 290070.95 38.7

CountySHELBY
Highway CR
From CR 4323 AT FLAT FORK CR RELIEF NO 2
To .
CSJ 0911-39-042
Proj ID BR 2014(429)
Work Type BRIDGE REPLACEMENT
 
0.379 1170264.70 24370.74 1090507.69 93.1
Work Order 03-26-15
Work Began 08-03-15
Work Completed  
Time Computed 06-24-15
Contract Working Days 174
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 51
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-042
AMERICAN REMEDIATION OPTIONS, INC. (9.13%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.76%)
PANOLA SIGN & BARRICADE, INC.(0.63%)
MESA ROD BUSTERS, INC. (0.85%)
Contract # 02153021
Totals 1170264.70 24370.74 1090507.69 93.1

CountyHOUSTON
Highway FM 227
From AT HICKORY CREEK
To .
CSJ 0937-03-013
Proj ID BR 1502(259)
Work Type REMOVE AND REPLACE EXISTING BRIDGE
 
0.503 2633662.02 0.00 179186.40 6.8
Work Order 07-22-15
Work Began 00-00-00
Work Completed  
Time Computed 11-20-15
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0937-03-013
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.87%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64%)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (4.27%)
DUSTIN ALLEN, INC. (1.31%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.65%)
DUSTROL, INC.(0.69%)
PENHALL COMPANY(0.25%)
STRIPING TECHNOLOGY, L.P.(0.68%)
MESA ROD BUSTERS, INC. (0.32%)
Contract # 06153037
Totals 2633662.02 0.00 179186.40 6.8

CountySAN AUGUSTINE
Highway FM 705
From SH 147
To 2.49 MI S OF FM 83
CSJ 1079-01-031
Proj ID STP 2015(420)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
22.379 1266570.98 0.00 405420.20 32.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-02-15
Work Began 12-09-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 336
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 16
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1079-01-031
DUSTIN ALLEN, INC. ( 12.83%)
PANOLA SIGN & BARRICADE, INC.(1.57%)
Contract # 09153226
Totals 1266570.98 0.00 405420.20 32.0

CountySABINE
Highway FM 1592
From SH 103
To SH 184
CSJ 1510-01-019
Proj ID STP 2014(747)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
17.157 1226352.49 0.00 1133894.94 92.4
Work Order 08-29-14
Work Began 09-23-14
Work Completed  
Time Computed 09-14-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 157
Percent Time Used 98
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 1510-01-019
ODUM SERVICES, L.P.(7.05%)
Contract # 06143233
Totals 1226352.49 0.00 1133894.94 92.4

CountyNACOGDOCHES
Highway FM 1878
From NORTH STREET (BU 59-F)
To CLARK BOULEVARD
CSJ 1810-01-028
Proj ID STP 2015(618)
Work Type WIDEN FROM 2 TO 4 LANES AND ADD C & G
 
0.218 1448289.45 0.00 1197538.61 82.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-30-15
Work Began 12-07-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 48
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1810-01-028
BRADCO, LLC(6.76%)
DUSTROL, INC.(0.58%)
G & L FLOWERS TRUCKING (4.87%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.82%)
SOUTH TEXAS ILLUMINATION, LLC( 14.35%)
STRIPING TECHNOLOGY, L.P.(1.35%)
FLOWERS TRUCKING (0.00%)
TEXOP CONSTRUCTION (0.58%)
FREDONIA CONSTRUCTION SERVICES (0.82%)
Contract # 02153215
Totals 1448289.45 0.00 1197538.61 82.6

CountyHOUSTON
Highway FM 3151
From FM 1280
To FM 230
CSJ 1875-03-022
Proj ID C 1875-3-22
Work Type RECONSTRUCT AND WIDEN PAVEMENT
 
4.590 3146993.47 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 114
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1875-03-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153043
Totals 3146993.47 0.00 0.00 0.0

CountyPOLK
Highway FM 1988
From AT LONG KING CREEK
To .
CSJ 1876-01-030
Proj ID BR 1502(017)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.509 3278223.27 338736.24 1854425.36 56.5
Work Order 06-11-15
Work Began 09-23-15
Work Completed  
Time Computed 07-12-15
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 40
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1876-01-030
LONESTAR TRAFFIC SAFETY, LLC (0.19%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.13%)
MOORE BROTHERS CONSTRUCTION COMPANY(4.90%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.38%)
AMERICAN REMEDIATION OPTIONS, INC. (0.75%)
MCL CONTRACTING, LLC (0.24%)
Contract # 04153032
Totals 3278223.27 338736.24 1854425.36 56.5

CountyNACOGDOCHES
Highway LP 224
From SH 7
To US 59 SOUTH
CSJ 2560-01-072
Proj ID STP 2014(750)HESG
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
11.764 1620204.50 3888.34 1962475.97 99.9
Work Order 09-09-14
Work Began 10-10-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 95
Addl Days Granted 69
Working Days Charged 160
Percent Time Used 97
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2560-01-072
DREWERY & WHEATON, LLC ( 21.10%)
RICE ENVIRONMENTAL SERVICES( 19.52%)
DREWERY"S TREE SERVICE AND CONSTRUCTION CO., INC.(1.57%)
ODUM SERVICES, L.P.(4.07%)
PANOLA SIGN & BARRICADE, INC.(0.62%)
HEMPHILL PILE DRIVING CO., A CORP. (1.45%)
Contract # 06143228
Totals 1620204.50 3888.34 1962475.97 99.9

CountyNACOGDOCHES
Highway SL 224
From SH 7
To FM 2259
CSJ 2560-01-076
Proj ID STP 2016(425)
Work Type RESURFACE WITH THIN OVERLAY MIXTURE
 
5.189 789787.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-09-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 15
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2560-01-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163033
Totals 789787.24 0.00 0.00 0.0

CountyANGELINA
Highway FM 706
From US 69
To SH 103
CSJ 2959-01-009
Proj ID STP 1502(185)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
4.914 638068.30 7163.00 647314.39 99.9
Work Order 06-30-15
Work Began 08-19-15
Work Completed  
Time Computed 07-31-15
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 97
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2959-01-009
PANOLA SIGN & BARRICADE, INC.(1.29%)
FREDONIA CONSTRUCTION SERVICES (0.00%)
J.P. ABNER STUMP GRINDING & TREE SERVICE (0.19%)
Contract # 05153011
Totals 638068.30 7163.00 647314.39 99.9

page 1 | page 2 | page 3 | page 4