Monthly State Let Construction Report For Lufkin District As Of Jun 10, 2015 Page 3 Of 3

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRINITY
Highway CR
From PORT BLVD AT MILL CREEK
To .
CSJ 0911-40-028
Proj ID BR 2013(408)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.105 604354.25 6000.00 598068.11 100.0
Work Order 06-12-14
Work Began 10-16-14
Work Completed 05-01-15
Time Computed 09-10-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 71
Percent Time Used 118
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-40-028
LONESTAR TRAFFIC SAFETY, LLC (0.51%)
SPECIALTY DRILLING, LTD. (8.60%)
AMERICAN REMEDIATION OPTIONS, INC. (9.42%)
Contract # 05143032
Totals 604354.25 6000.00 598068.11 100.0

CountyHOUSTON
Highway FM 227
From BU 287-V
To 0.5 MI E OF CR 1685
CSJ 0937-02-029
Proj ID STP 2013(546)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
11.160 4278380.79 0.00 4040100.49 94.6
Work Order 06-19-13
Work Began 07-10-13
Work Completed  
Time Computed 07-10-13
Contract Working Days 168
Addl Days Granted 18
Working Days Charged 196
Percent Time Used 105
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0937-02-029
STRIPING TECHNOLOGY, L.P.(2.43%)
ROBINSON CONSTRUCTION(4.56%)
ODUM SERVICES, L.P.(3.30%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.66%)
Contract # 04133219
Totals 4278380.79 0.00 4040100.49 94.6

CountyHOUSTON
Highway FM 227
From AT HICKORY CREEK
To .
CSJ 0937-03-013
Proj ID BR 1502(259)
Work Type REMOVE AND REPLACE EXISTING BRIDGE
 
0.503 2633662.02 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0937-03-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153037
Totals 2633662.02 0.00 0.00 0.0

CountySABINE
Highway FM 1592
From SH 103
To SH 184
CSJ 1510-01-019
Proj ID STP 2014(747)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
17.157 1226352.49 50731.25 992216.94 80.9
Work Order 08-29-14
Work Began 09-23-14
Work Completed  
Time Computed 09-14-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 73
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 1510-01-019
ODUM SERVICES, L.P.(7.05%)
Contract # 06143233
Totals 1226352.49 50731.25 992216.94 80.9

CountyHOUSTON
Highway FM 1280
From SH 21
To FM 230
CSJ 1676-02-015
Proj ID STP 2013(394)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
25.772 4387077.87 0.00 4012550.57 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-13
Work Began 05-20-13
Work Completed 11-21-14
Time Computed 04-26-13
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 228
Percent Time Used 89
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1676-02-015
COLD CREEK CONSTRUCTION, LTD (1.27%)
J & M CONTRACTING, COMPANY ( 13.60%)
MURRAY CONSTRUCTION(0.75%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.77%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.07%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.17%)
TRAFCO INDUSTRIES, INC.(0.03%)
NIXON ENGINEERING(0.00%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(0.29%)
Contract # 02133020
Totals 4387077.87 0.00 4012550.57 100.0

CountyHOUSTON
Highway FM 1733
From SH 21
To SH 7
CSJ 1677-01-015
Proj ID STP 2014(210)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
10.353 3771800.47 0.00 3642779.31 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-23-14
Work Began 02-17-14
Work Completed 12-16-14
Time Computed 02-08-14
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 149
Percent Time Used 89
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1677-01-015
ROADSAFE TRAFFIC SYSTEMS, INC. (2.27%)
ODUM SERVICES, L.P.(1.11%)
MURRAY CONSTRUCTION(0.75%)
J & M CONTRACTING, COMPANY (7.25%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.95%)
DREWERY & WHEATON, LLC (1.65%)
BERTLAND-HILL, LLC (0.89%)
Contract # 11133211
Totals 3771800.47 0.00 3642779.31 100.0

CountyNACOGDOCHES
Highway FM 1878
From NORTH STREET (BU 59-F)
To CLARK BOULEVARD
CSJ 1810-01-028
Proj ID STP 2015(618)
Work Type WIDEN FROM 2 TO 4 LANES AND ADD C & G
 
0.218 1448289.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1810-01-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153215
Totals 1448289.45 0.00 0.00 0.0

CountyHOUSTON
Highway FM 2022
From ANDERSON COUNTY LINE
To 0.1 MI N OF FM 3313
CSJ 1875-02-021
Proj ID STP 2013(677)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
38.913 4505244.42 0.00 4597685.30 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-23-13
Work Began 08-13-13
Work Completed 02-02-15
Time Computed 08-13-13
Contract Working Days 168
Addl Days Granted 12
Working Days Charged 179
Percent Time Used 99
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1875-02-021
MURRAY CONSTRUCTION(0.64%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.61%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.91%)
ODUM SERVICES, L.P.(3.30%)
COLD CREEK CONSTRUCTION, LTD (2.18%)
PANOLA SIGN & BARRICADE, INC.(0.98%)
MOORE BROTHERS CONSTRUCTION COMPANY( 30.94%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 20.26%)
SAND HILL FOUNDATION, LLC(0.11%)
Contract # 05133020
Totals 4505244.42 0.00 4597685.30 100.0

CountyPOLK
Highway FM 1988
From AT LONG KING CREEK
To .
CSJ 1876-01-030
Proj ID BR 1502(017)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.509 3278223.27 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1876-01-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153032
Totals 3278223.27 0.00 0.00 0.0

CountyNACOGDOCHES
Highway LP 224
From SH 7
To US 59 SOUTH
CSJ 2560-01-072
Proj ID STP 2014(750)HESG
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
11.764 1620204.50 47930.82 1573677.13 97.1
Work Order 09-09-14
Work Began 10-10-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 100
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2560-01-072
DREWERY & WHEATON, LLC ( 21.10%)
RICE ENVIRONMENTAL SERVICES( 19.52%)
DREWERY"S TREE SERVICE AND CONSTRUCTION CO., INC.(1.57%)
ODUM SERVICES, L.P.(4.07%)
PANOLA SIGN & BARRICADE, INC.(0.62%)
Contract # 06143228
Totals 1620204.50 47930.82 1573677.13 97.1

CountyANGELINA
Highway FM 706
From US 69
To SH 103
CSJ 2959-01-009
Proj ID STP 1502(185)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
4.914 638068.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2959-01-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153011
Totals 638068.30 0.00 0.00 0.0

CountySHELBY
Highway LP 500
From US 96 (N)
To SH 7 EAST OF CENTER
CSJ 3315-01-016
Proj ID STP 2012(648)
Work Type GR, STR, BASE & SURF
 
3.338 11879175.22 710523.18 12036182.58 99.9
Work Order 09-24-12
Work Began 11-01-12
Work Completed  
Time Computed 11-01-12
Contract Working Days 462
Addl Days Granted 224
Working Days Charged 644
Percent Time Used 93
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 3315-01-016
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. (0.89%)
MOORE BROTHERS CONSTRUCTION COMPANY( 21.73%)
NORTH TEXAS REBAR, LLC (0.62%)
RICE ENVIRONMENTAL SERVICES(0.31%)
S & S PAINTING (0.11%)
TEX OP CONSTRUCTION, LP(0.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.46%)
W. W. FOUNDATION DRILLING, LTD.(1.07%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.32%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
FBL & ASSOCIATES (0.79%)
S & R DOZER, INC.(0.73%)
SILVA CONTRACTING COMPANY, INC.(2.02%)
MCL CONTRACTING, LLC (0.68%)
L. S. EQUIPMENT CO., INC.(0.19%)
Contract # 07123206
Totals 11879175.22 710523.18 12036182.58 99.9

CountyNACOGDOCHES
Highway FM 3314
From 0.9 MI W OF US 59
To US 59 RAMP
CSJ 3490-01-003
Proj ID STP 2015(619)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
0.874 548619.07 295966.60 393991.60 71.8
Work Order 03-23-15
Work Began 04-21-15
Work Completed  
Time Computed 04-08-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 22
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3490-01-003
AMERICAN REMEDIATION OPTIONS, INC. (5.18%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (6.06%)
MOORE BROTHERS CONSTRUCTION COMPANY( 34.92%)
PANOLA SIGN & BARRICADE, INC.(0.73%)
SANDHILL FOUNDATION, LLC (0.91%)
STRIPING TECHNOLOGY, L.P.(3.90%)
Contract # 02153013
Totals 548619.07 295966.60 393991.60 71.8