Monthly State Let Construction Report For Lufkin District As Of May 10, 2016 Page 3 Of 4

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPOLK
Highway FM 62
From AT DRAW CREEK
To .
CSJ 0654-01-026
Proj ID BR 2016(964)
Work Type BRIDGE REHABILITATION
 
0.090 495378.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 0654-01-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163229
Totals 495378.86 0.00 0.00 0.0

CountyNACOGDOCHES
Highway FM 95
From RUSK COUNTY LINE
To 0.5 MI W OF US 59 IN GARRISON
CSJ 0706-01-013
Proj ID STP 2013(519)HES
Work Type RECONSTRUCT AND WIDEN PAVEMENT
 
3.938 1382155.18 0.00 895387.97 64.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-10-15
Work Began 02-24-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 45
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0706-01-013
AMERICAN REMEDIATION OPTIONS, INC. (2.66%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 24.71%)
COLD CREEK CONSTRUCTION, LTD (3.59%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.00%)
PANOLA SIGN & BARRICADE, INC.(0.86%)
A. L. HELMCAMP, INC. (1.07%)
Contract # 06153240
Totals 1382155.18 0.00 895387.97 64.7

CountyNACOGDOCHES
Highway FM 95
From AT PARALLEL CREEK
To .
CSJ 0706-03-020
Proj ID BR 1502(622)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.289 1783241.53 0.00 267764.30 15.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-15
Work Began 03-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 12
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0706-03-020
AMERICAN REMEDIATION OPTIONS, INC. (5.48%)
PANOLA SIGN & BARRICADE, INC.(0.67%)
STRIPING TECHNOLOGY, L.P.(0.70%)
Contract # 08153239
Totals 1783241.53 0.00 267764.30 15.0

CountySHELBY
Highway FM 139
From SH 7
To SH 87
CSJ 0742-01-052
Proj ID STP 2015(314)HRR
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
28.429 1987837.07 16577.35 2000224.18 99.9
Work Order 01-07-15
Work Began 02-18-15
Work Completed  
Time Computed 02-18-15
Contract Working Days 121
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 100
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0742-01-052
DUSTIN ALLEN, INC. ( 13.59%)
LONESTAR TRAFFIC SAFETY, LLC (0.59%)
LONGVIEW BRIDGE AND ROAD, LTD. ( 17.65%)
N-LINE TRAFFIC MAINTENANCE, L.P. (5.60%)
STRIPING TECHNOLOGY, L.P.(0.99%)
PINTO CONSTRUCTION CO., INC. (0.37%)
FREDONIA CONSTRUCTION(0.07%)
Contract # 11143218
Totals 1987837.07 16577.35 2000224.18 99.9

CountySAN AUGUSTINE
Highway US 96
From SHELBY COUNTY LINE
To FM 3451
CSJ 0809-03-038
Proj ID NH 2013(514)
Work Type ADD PASSING LANES AND RECONST PVMT
 
3.804 7319958.62 0.00 373990.29 5.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 03-30-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 8
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0809-03-038
PANOLA SIGN & BARRICADE, INC.(0.19%)
COLD CREEK CONSTRUCTION, LTD (1.64%)
AMERICAN REMEDIATION OPTIONS, INC. (2.74%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (4.64%)
DUSTROL, INC.(1.52%)
LONGVIEW BRIDGE AND ROAD, LTD. ( 42.07%)
STRIPING TECHNOLOGY, L.P.(1.93%)
WEST TEXAS RUMBLE STRIP(0.06%)
Contract # 08153048
Totals 7319958.62 0.00 373990.29 5.1

CountySAN AUGUSTINE
Highway US 96
From AT AYISH BAYOU
To .
CSJ 0809-04-046
Proj ID BR 1502(202)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.545 3951203.54 177610.48 1952524.16 49.4
Work Order 07-02-15
Work Began 11-18-15
Work Completed  
Time Computed 08-02-15
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 38
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0809-04-046
PANOLA SIGN & BARRICADE, INC.(0.26%)
MOORE BROTHERS CONSTRUCTION COMPANY( 13.90%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.73%)
MCL CONTRACTING, LLC (0.14%)
CRABTREE BARRICADE SYSTEMS, INC. (0.65%)
AMERICAN REMEDIATION OPTIONS, INC. (2.06%)
MAC TRANSPORTATION, LTD, L.L.P.(0.00%)
Contract # 05153241
Totals 3951203.54 177610.48 1952524.16 49.4

CountySHELBY
Highway FM 417
From SH 87
To FM 139
CSJ 0810-02-019
Proj ID STP 2016(808)
Work Type RECONSTRUCT AND WIDEN PAVEMENT
 
11.292 5757568.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 155
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0810-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163021
Totals 5757568.55 0.00 0.00 0.0

CountyANGELINA
Highway VA
From AT VARIOUS LOCATIONS IN LUFKIN DIST
To .
CSJ 0911-00-074
Proj ID STP 1502(258)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1038185.70 0.00 962756.63 92.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-11-15
Work Began 01-05-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 88
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-00-074
N-LINE TRAFFIC MAINTENANCE, L.P. (1.80%)
STRIPE-A-ZONE, INC.(2.33%)
MELS ELECTRIC, L.P.( 19.30%)
JE CASEY, LLC(1.38%)
W.A. ROBBINS CONSTRUCTION CO., INC.( 10.91%)
FAASS TRUCKING, INC. (0.00%)
Contract # 07153263
Totals 1038185.70 0.00 962756.63 92.7

CountyPOLK
Highway CR
From BLUEWATER RD OVER BLUE BRANCH
To .
CSJ 0911-04-034
Proj ID BR 2001(480)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.231 885751.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163212
Totals 885751.00 0.00 0.00 0.0

CountyPOLK
Highway VA
From WITHIN LAKE LIVINGSTON STATE PARK
To .
CSJ 0911-04-054
Proj ID C 911-4-54
Work Type REPAIR AND RESURFACE PAVED AREAS
 
0.100 2009215.00 0.00 117470.50 5.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 04-04-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 9
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-054
DREWERY BROS TREE SERVICE, INC.(1.20%)
AMERICAN REMEDIATION OPTIONS, INC. (4.01%)
Contract # 01163025
Totals 2009215.00 0.00 117470.50 5.8

CountyPOLK
Highway CR
From KELLEY RD OVER MENARD CREEK
To .
CSJ 0911-04-056
Proj ID BR 2014(692)
Work Type BRIDGE REPLACEMENT
 
0.281 707623.10 0.00 678250.17 95.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-26-15
Work Began 09-14-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 39
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-056
PANOLA SIGN & BARRICADE, INC.(1.56%)
AMERICAN REMEDIATION OPTIONS, INC. (9.20%)
Contract # 02153220
Totals 707623.10 0.00 678250.17 95.8

CountyPOLK
Highway CR
From DICK SKINNER RD AT TRIB OF NECHES R
To .
CSJ 0911-04-059
Proj ID BR 1402(188)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.413 1215872.88 112807.85 420301.80 34.5
Work Order 08-26-15
Work Began 02-29-16
Work Completed  
Time Computed 11-24-15
Contract Working Days 151
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 13
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-059
PANOLA SIGN & BARRICADE, INC.(1.09%)
AMERICAN REMEDIATION OPTIONS, INC. (5.52%)
Contract # 07153052
Totals 1215872.88 112807.85 420301.80 34.5

CountyPOLK
Highway CR
From UPPER LEGGETT RD
To AT TRIB OF BIG SANDY CREEK
CSJ 0911-04-060
Proj ID BR 1402(189)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.441 1889227.89 0.00 9913.44 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153046
Totals 1889227.89 0.00 9913.44 0.5

CountyPOLK
Highway CR
From NINE BRIDGE ROAD
To AT PINEY CREEK RELIEF NO. 1
CSJ 0911-04-068
Proj ID BR 1502(206)
Work Type BRIDGE REPLACEMENT
 
0.124 740248.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163212
Totals 740248.00 0.00 0.00 0.0

CountyHOUSTON
Highway CR
From CR 3480 AT BIG CREEK TRIBUTARY
To .
CSJ 0911-28-031
Proj ID BR 2014(433)
Work Type BRIDGE REPLACEMENT
 
0.137 748567.80 0.00 366209.24 48.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-15
Work Began 01-20-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 70
Contractor(s)
HARTBEAT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-031
DUSTIN ALLEN, INC. (5.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.51%)
HEMPHILL PILE DRIVING CO., A CORP. (4.20%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.75%)
CANNON STEEL, INC(4.14%)
REID CONSTRUCTION, INC.(0.38%)
Contract # 06153231
Totals 748567.80 0.00 366209.24 48.9

CountySHELBY
Highway CR
From CR 4323 AT FLAT FORK CR RELIEF NO 2
To .
CSJ 0911-39-042
Proj ID BR 2014(429)
Work Type BRIDGE REPLACEMENT
 
0.379 1170264.70 26809.36 1117317.05 95.4
Work Order 03-26-15
Work Began 08-03-15
Work Completed  
Time Computed 06-24-15
Contract Working Days 174
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 56
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-042
AMERICAN REMEDIATION OPTIONS, INC. (9.13%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.76%)
PANOLA SIGN & BARRICADE, INC.(0.63%)
MESA ROD BUSTERS, INC. (0.85%)
Contract # 02153021
Totals 1170264.70 26809.36 1117317.05 95.4

CountyHOUSTON
Highway FM 227
From AT HICKORY CREEK
To .
CSJ 0937-03-013
Proj ID BR 1502(259)
Work Type REMOVE AND REPLACE EXISTING BRIDGE
 
0.503 2633662.02 46453.18 225639.58 8.5
Work Order 07-22-15
Work Began 00-00-00
Work Completed  
Time Computed 11-20-15
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0937-03-013
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.87%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64%)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (4.27%)
DUSTIN ALLEN, INC. (1.31%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.65%)
DUSTROL, INC.(0.69%)
PENHALL COMPANY(0.25%)
STRIPING TECHNOLOGY, L.P.(0.68%)
MESA ROD BUSTERS, INC. (0.32%)
Contract # 06153037
Totals 2633662.02 46453.18 225639.58 8.5

CountySAN AUGUSTINE
Highway FM 705
From SH 147
To 2.49 MI S OF FM 83
CSJ 1079-01-031
Proj ID STP 2015(420)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
22.379 1266570.98 0.00 458493.20 36.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-02-15
Work Began 12-09-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 336
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 19
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1079-01-031
DUSTIN ALLEN, INC. ( 12.83%)
PANOLA SIGN & BARRICADE, INC.(1.57%)
Contract # 09153226
Totals 1266570.98 0.00 458493.20 36.1

CountySABINE
Highway FM 1592
From SH 103
To SH 184
CSJ 1510-01-019
Proj ID STP 2014(747)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
17.157 1226352.49 1800.00 1135694.94 92.6
Work Order 08-29-14
Work Began 09-23-14
Work Completed  
Time Computed 09-14-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 157
Percent Time Used 98
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 1510-01-019
ODUM SERVICES, L.P.(7.05%)
Contract # 06143233
Totals 1226352.49 1800.00 1135694.94 92.6

CountyNACOGDOCHES
Highway FM 1878
From NORTH STREET (BU 59-F)
To CLARK BOULEVARD
CSJ 1810-01-028
Proj ID STP 2015(618)
Work Type WIDEN FROM 2 TO 4 LANES AND ADD C & G
 
0.218 1448289.45 0.00 1387002.86 95.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-30-15
Work Began 12-07-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 59
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1810-01-028
BRADCO, LLC(6.76%)
DUSTROL, INC.(0.58%)
G & L FLOWERS TRUCKING (4.87%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.82%)
SOUTH TEXAS ILLUMINATION, LLC( 14.35%)
STRIPING TECHNOLOGY, L.P.(1.35%)
FLOWERS TRUCKING (0.00%)
TEXOP CONSTRUCTION (0.58%)
FREDONIA CONSTRUCTION SERVICES (0.82%)
Contract # 02153215
Totals 1448289.45 0.00 1387002.86 95.7

page 1 | page 2 | page 3 | page 4