Monthly State Let Construction Report For Lufkin District As Of Dec 9, 2016 Page 3 Of 4

Last Update: Friday, December 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySHELBY
Highway FM 417
From SH 87
To FM 139
CSJ 0810-02-019
Proj ID STP 2016(808)
Work Type RECONSTRUCT AND WIDEN PAVEMENT
 
11.292 5757568.55 75670.74 2046358.32 35.5
Work Order 05-23-16
Work Began 06-22-16
Work Completed  
Time Computed 06-22-16
Contract Working Days 155
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 42
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0810-02-019
DREWERY BROS TREE SERVICE, INC.(3.09%)
JE CASEY, LLC(1.42%)
PANOLA SIGN & BARRICADE, INC.(0.77%)
STRIPING TECHNOLOGY, L.P.(2.28%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.29%)
FREDONIA CONSTRUCTION SERVICES (0.17%)
STRIPING SYSTEMS, INC. (0.03%)
AMERICAN REMEDIATION OPTIONS, INC. (1.85%)
Contract # 03163021
Totals 5757568.55 75670.74 2046358.32 35.5

CountyPOLK
Highway CR
From BLUEWATER RD OVER BLUE BRANCH
To .
CSJ 0911-04-034
Proj ID BR 2001(480)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.231 885751.00 77800.73 529445.92 59.7
Work Order 06-02-16
Work Began 09-12-16
Work Completed  
Time Computed 09-01-16
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 44
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-034
AMERICAN REMEDIATION OPTIONS, INC. (6.59%)
PANOLA SIGN & BARRICADE, INC.(1.53%)
Contract # 04163212
Totals 885751.00 77800.73 529445.92 59.7

CountyPOLK
Highway VA
From WITHIN LAKE LIVINGSTON STATE PARK
To .
CSJ 0911-04-054
Proj ID C 911-4-54
Work Type REPAIR AND RESURFACE PAVED AREAS
 
0.100 2009215.00 0.00 1606180.91 79.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 04-04-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 86
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-054
DREWERY BROS TREE SERVICE, INC.(1.20%)
AMERICAN REMEDIATION OPTIONS, INC. (4.01%)
Contract # 01163025
Totals 2009215.00 0.00 1606180.91 79.9

CountyPOLK
Highway CR
From UPPER LEGGETT RD
To AT TRIB OF BIG SANDY CREEK
CSJ 0911-04-060
Proj ID BR 1402(189)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.441 1889227.89 255163.63 1619285.19 85.7
Work Order 03-08-16
Work Began 07-11-16
Work Completed  
Time Computed 07-11-16
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 49
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-060
PANOLA SIGN & BARRICADE, INC.(0.46%)
AMERICAN REMEDIATION OPTIONS, INC. (4.65%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.51%)
Contract # 08153046
Totals 1889227.89 255163.63 1619285.19 85.7

CountyPOLK
Highway CR
From CARMONA RD AT BRUSHY CREEK
To .
CSJ 0911-04-067
Proj ID BR 1502(205)
Work Type BRIDGE REPLACEMENT
 
0.225 1019437.73 163820.63 163820.63 16.0
Work Order 08-03-16
Work Began 00-00-00
Work Completed  
Time Computed 10-26-16
Contract Working Days 121
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 1
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-067
AMERICAN REMEDIATION OPTIONS, INC. (6.28%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.88%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.00%)
MCL CONTRACTING, LLC (0.78%)
Contract # 06163027
Totals 1019437.73 163820.63 163820.63 16.0

CountyPOLK
Highway CR
From NINE BRIDGE ROAD
To AT PINEY CREEK RELIEF NO. 1
CSJ 0911-04-068
Proj ID BR 1502(206)
Work Type BRIDGE REPLACEMENT
 
0.124 740248.00 131041.61 713039.61 96.3
Work Order 07-11-16
Work Began 08-08-16
Work Completed  
Time Computed 08-08-16
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 78
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-068
TEXAS ALTERNATIVE GRASSER, INC.(0.65%)
LONESTAR TRAFFIC SAFETY, LLC (0.41%)
PENHALL COMPANY (AUSTIN) (0.47%)
MORRIS COUNTY CONTRACTORS, L.L.C.(4.42%)
Contract # 05163212
Totals 740248.00 131041.61 713039.61 96.3

CountyPOLK
Highway CR
From WELLS LANDING RD AT KICKAPOO CREEK
To .
CSJ 0911-04-072
Proj ID BR 2016(770)
Work Type BRIDGE REPLACEMENT
 
0.204 1452873.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 252
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11163213
Totals 1452873.79 0.00 0.00 0.0

CountyPOLK
Highway CR
From ROCK ISLAND RD AT BUNDIX CREEK
To .
CSJ 0911-04-080
Proj ID BR 2016(778)
Work Type BRIDGE REPLACEMENT
 
0.166 1091491.65 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-22-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10163220
Totals 1091491.65 0.00 0.00 0.0

CountyPOLK
Highway CR
From OLD HWY 35 N
To AT TRIB OF LONG KING CREEK
CSJ 0911-04-083
Proj ID BR 2016(781)
Work Type BRIDGE REPLACEMENT
 
0.067 351199.32 55150.00 55150.00 15.7
CountyPOLK
Highway CR
From OAKDALE LOOP AT KIBBLE CREEK
To .
CSJ 0911-04-084
Proj ID BR 2016(782)
Work Type BRIDGE REPLACEMENT
 
0.096 460983.46 28690.12 28690.12 6.2
Work Order 08-18-16
Work Began 11-25-16
Work Completed  
Time Computed 11-16-16
Contract Working Days 83
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 8
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-083
AMERICAN REMEDIATION OPTIONS, INC. (6.37%)
LONESTAR TRAFFIC SAFETY, LLC (0.46%)
Contract # 07163229
Totals 812182.78 83840.12 83840.12 10.3

CountySAN JACINTO
Highway VA
From VARIOUS LOCATIONS
To WITHIN THE CITY OF COLDSPRING
CSJ 0911-07-038
Proj ID STP 2017(251)
Work Type CONSTRUCT CURB RAMPS
 
0.100 646827.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 116
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-07-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11163021
Totals 646827.00 0.00 0.00 0.0

CountyHOUSTON
Highway CR
From CR 1585 AT SAN PEDRO CREEK
To .
CSJ 0911-28-036
Proj ID BR 2014(436)
Work Type BRIDGE REPLACEMENT
 
0.146 763544.08 15552.84 93679.28 12.2
Work Order 07-28-16
Work Began 00-00-00
Work Completed  
Time Computed 10-26-16
Contract Working Days 88
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 1
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-036
AMERICAN REMEDIATION OPTIONS, INC. (6.74%)
FLEX SUPPLY, LLC (0.85%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.32%)
Contract # 06163019
Totals 763544.08 15552.84 93679.28 12.2

CountyHOUSTON
Highway VA
From WITHIN MISSION TEJAS ST HIST SITE
To .
CSJ 0911-28-037
Proj ID C 911-28-37
Work Type CNSTR NEW ENTRANCE RD & PARKING LOT
 
0.100 746460.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-06-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11163018
Totals 746460.56 0.00 0.00 0.0

CountyHOUSTON
Highway CR
From CR 1765 AT RICH CREEK
To .
CSJ 0911-28-040
Proj ID BR 1602(206)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 461059.20 0.00 0.00 0.0
CountyHOUSTON
Highway CR
From CR 1680 AT SILVER CREEK
To .
CSJ 0911-28-044
Proj ID BR 1602(212)
Work Type BRIDGE REPLACEMENT
 
0.061 346469.10 0.00 0.00 0.0
CountyHOUSTON
Highway CR
From CR 1750 AT RICH CREEK
To .
CSJ 0911-28-045
Proj ID BR 1602(205)
Work Type BRIDGE REPLACEMENT
 
0.073 273448.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-040
MORRIS COUNTY CONTRACTORS, L.L.C.(5.17%)
LONE STAR TRAFFIC SERVICE, INC.(0.63%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.94%)
Contract # 07163221
Totals 1080977.20 0.00 0.00 0.0

CountyANGELINA
Highway CR
From OLD HOMER ALTO HWY AT BODEN CR
To .
CSJ 0911-38-070
Proj ID BR 1602(274)
Work Type BRIDGE REPLACEMENT
 
0.068 460227.88 0.00 48655.65 10.5
Work Order 08-19-16
Work Began 12-01-16
Work Completed  
Time Computed 11-17-16
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 5
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-38-070
MORRIS COUNTY CONTRACTORS, L.L.C.(3.42%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.32%)
HEMPHILL WBE PILE DRIVING CO.(3.36%)
Contract # 07163020
Totals 460227.88 0.00 48655.65 10.5

CountySHELBY
Highway CR
From ACCESS RD AT TOLEDO BEND RESERVOIR
To .
CSJ 0911-39-046
Proj ID BR 2016(605)
Work Type BRIDGE REPLACEMENT
 
0.214 1129593.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-06-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10163209
Totals 1129593.90 0.00 0.00 0.0

CountySHELBY
Highway CR
From CR 3564 AT HILLIARD CREEK
To .
CSJ 0911-39-051
Proj ID BR 2016(598)
Work Type BRIDGE REPLACEMENT
 
0.133 844617.78 115233.44 115233.44 13.6
Work Order 08-18-16
Work Began 11-16-16
Work Completed  
Time Computed 11-16-16
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 3
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-051
PANOLA SIGN & BARRICADE, INC.(1.20%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.22%)
FREDONIA CONSTRUCTION SERVICES (0.95%)
AMERICAN REMEDIATION OPTIONS, INC. (7.11%)
Contract # 06163226
Totals 844617.78 115233.44 115233.44 13.6

CountySHELBY
Highway CR
From CR 4256 AT TRIB OF FLAT FORK CREEK
To .
CSJ 0911-39-054
Proj ID BR 2016(601)
Work Type BRIDGE REPLACEMENT
 
0.070 281906.66 87317.25 196777.25 69.8
CountySHELBY
Highway CR
From CR 4670 AT MCFADDEN CREEK
To .
CSJ 0911-39-056
Proj ID BR 2016(603)
Work Type BRIDGE REPLACEMENT
 
0.066 270140.58 67502.20 172511.25 63.8
Work Order 09-15-16
Work Began 10-13-16
Work Completed  
Time Computed 10-13-16
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 41
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-054
HEMPHILL WBE PILE DRIVING CO.(4.78%)
PANOLA SIGN & BARRICADE, INC.(1.19%)
ODUM SERVICES, L.P.(5.78%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.71%)
ISAACS CONSTRUCTION SERVICES, LLC. (1.72%)
Contract # 07163230
Totals 552047.24 154819.45 369288.50 66.8

CountyNACOGDOCHES
Highway FM 343
From CHEROKEE COUNTY LINE
To FM 225
CSJ 0926-02-010
Proj ID STP 2017(315)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
13.688 1213495.60 0.00 0.00 0.0
CountyNACOGDOCHES
Highway FM 343
From CHEROKEE COUNTY LINE
To FM 225
CSJ 0926-02-011
Proj ID STP 2017(314)
Work Type RECONSTRUCT AND WIDEN PAVEMENT
 
6.844 3510530.02 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0926-02-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12163028
Totals 4724025.62 0.00 0.00 0.0

CountyHOUSTON
Highway FM 227
From AT HICKORY CREEK
To .
CSJ 0937-03-013
Proj ID BR 1502(259)
Work Type REMOVE AND REPLACE EXISTING BRIDGE
 
0.503 2633662.02 157111.83 1425505.39 54.1
Work Order 07-22-15
Work Began 05-11-16
Work Completed  
Time Computed 05-11-16
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 55
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0937-03-013
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.87%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64%)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (4.27%)
DUSTIN ALLEN, INC. (1.31%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.65%)
DUSTROL, INC.(0.69%)
PENHALL COMPANY(0.25%)
STRIPING TECHNOLOGY, L.P.(0.68%)
MESA ROD BUSTERS, INC. (0.32%)
JOHN L. BILLINGSLEY LOGGING, LLC (0.94%)
DAVIS MOTOR CRANE SERVICE, INC.(1.79%)
Contract # 06153037
Totals 2633662.02 157111.83 1425505.39 54.1

CountySAN AUGUSTINE
Highway FM 705
From SH 147
To 2.49 MI S OF FM 83
CSJ 1079-01-031
Proj ID STP 2015(420)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
22.379 1266570.98 0.00 760536.90 60.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-02-15
Work Began 12-09-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 336
Addl Days Granted 0
Working Days Charged 185
Percent Time Used 55
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1079-01-031
DUSTIN ALLEN, INC. ( 12.83%)
PANOLA SIGN & BARRICADE, INC.(1.57%)
Contract # 09153226
Totals 1266570.98 0.00 760536.90 60.0

page 1 | page 2 | page 3 | page 4