Monthly State Let Construction Report For Lufkin District As Of Feb 10, 2017 Page 3 Of 4

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN AUGUSTINE
HighwayUS 96
FromSHELBY COUNTY LINE
ToFM 3451
CSJ0809-03-038
Proj IDNH 2013(514)
Work TypeADD PASSING LANES AND RECONST PVMT
 
3.8047319958.623101523.6242.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-12-15
Work Began03-30-16
Work Completed
Time Computed00-00-00
Contract Working Days149
Addl Days Granted0
Working Days Charged110
Percent Time Used73
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0809-03-038
PANOLA SIGN & BARRICADE, INC. (0.19)
COLD CREEK CONSTRUCTION, LTD (1.64)
AMERICAN REMEDIATION OPTIONS, INC. (2.74)
A R BROTHERS CONSTRUCTION SERVICES, INC. (4.64)
DUSTROL, INC. (1.52)
LONGVIEW BRIDGE AND ROAD, LTD. (42.07)
STRIPING TECHNOLOGY, L.P. (1.93)
WEST TEXAS RUMBLE STRIP (0.06)
STRIPING SYSTEMS, INC. (0.02)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.89)
Contract #08153048
Totals7319958.620.003101523.6242.3

CountySAN AUGUSTINE
HighwayUS 96
FromAT AYISH BAYOU
To.
CSJ0809-04-046
Proj IDBR 1502(202)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.5453951203.543689444.3393.3
Work Order07-02-15
Work Began11-18-15
Work Completed
Time Computed08-02-15
Contract Working Days152
Addl Days Granted26
Working Days Charged160
Percent Time Used89
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0809-04-046
PANOLA SIGN & BARRICADE, INC. (0.26)
MOORE BROTHERS CONSTRUCTION COMPANY (13.90)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.73)
MCL CONTRACTING, LLC (0.14)
CRABTREE BARRICADE SYSTEMS, INC. (0.65)
AMERICAN REMEDIATION OPTIONS, INC. (2.06)
MAC TRANSPORTATION, LTD, L.L.P. (0.00)
Contract #05153241
Totals3951203.5474385.203689444.3393.3

CountySHELBY
HighwayFM 417
FromSH 87
ToFM 139
CSJ0810-02-019
Proj IDSTP 2016(808)
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
11.2925757568.552137252.0037.1
Work Order05-23-16
Work Began06-22-16
Work Completed
Time Computed06-22-16
Contract Working Days155
Addl Days Granted0
Working Days Charged68
Percent Time Used43
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0810-02-019
DREWERY BROS TREE SERVICE, INC. (3.09)
JE CASEY, LLC (1.42)
PANOLA SIGN & BARRICADE, INC. (0.77)
STRIPING TECHNOLOGY, L.P. (2.28)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.29)
FREDONIA CONSTRUCTION SERVICES (0.17)
STRIPING SYSTEMS, INC. (0.03)
AMERICAN REMEDIATION OPTIONS, INC. (1.85)
Contract #03163021
Totals5757568.555500.002137252.0037.1

CountyPOLK
HighwayCR
FromBLUEWATER RD OVER BLUE BRANCH
To.
CSJ0911-04-034
Proj IDBR 2001(480)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.231885751.00550756.4262.1
Work Order06-02-16
Work Began09-12-16
Work Completed
Time Computed09-01-16
Contract Working Days128
Addl Days Granted0
Working Days Charged73
Percent Time Used57
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-034
AMERICAN REMEDIATION OPTIONS, INC. (6.59)
PANOLA SIGN & BARRICADE, INC. (1.53)
Contract #04163212
Totals885751.0021310.50550756.4262.1

CountyPOLK
HighwayVA
FromWITHIN LAKE LIVINGSTON STATE PARK
To.
CSJ0911-04-054
Proj IDC 911-4-54
Work TypeREPAIR AND RESURFACE PAVED AREAS
 
0.1002009215.001834496.3991.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-16
Work Began04-04-16
Work Completed
Time Computed00-00-00
Contract Working Days127
Addl Days Granted0
Working Days Charged123
Percent Time Used96
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-054
DREWERY BROS TREE SERVICE, INC. (1.20)
AMERICAN REMEDIATION OPTIONS, INC. (4.01)
Contract #01163025
Totals2009215.000.001834496.3991.3

CountyPOLK
HighwayCR
FromUPPER LEGGETT RD
ToAT TRIB OF BIG SANDY CREEK
CSJ0911-04-060
Proj IDBR 1402(189)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.4411889227.891761731.2493.2
Work Order03-08-16
Work Began07-11-16
Work Completed
Time Computed07-11-16
Contract Working Days177
Addl Days Granted0
Working Days Charged109
Percent Time Used61
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-060
PANOLA SIGN & BARRICADE, INC. (0.46)
AMERICAN REMEDIATION OPTIONS, INC. (4.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.51)
Contract #08153046
Totals1889227.8986822.961761731.2493.2

CountyPOLK
HighwayCR
FromCARMONA RD AT BRUSHY CREEK
To.
CSJ0911-04-067
Proj IDBR 1502(205)
Work TypeBRIDGE REPLACEMENT
 
0.2251019437.73560499.1754.9
Work Order08-03-16
Work Began11-29-16
Work Completed
Time Computed10-26-16
Contract Working Days121
Addl Days Granted0
Working Days Charged35
Percent Time Used28
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-067
AMERICAN REMEDIATION OPTIONS, INC. (6.28)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.88)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.00)
MCL CONTRACTING, LLC (0.78)
Contract #06163027
Totals1019437.73184000.04560499.1754.9

CountyPOLK
HighwayCR
FromWELLS LANDING RD AT KICKAPOO CREEK
To.
CSJ0911-04-072
Proj IDBR 2016(770)
Work TypeBRIDGE REPLACEMENT
 
0.2041452873.790.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days252
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-072
SOUTHWEST ENVIRONMENT SERVICES LLC (1.03)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.31)
COMEN ENTERPRISE LLC (4.90)
W. W. FOUNDATION DRILLING, LTD. (13.49)
Contract #11163213
Totals1452873.790.000.000.0

CountyPOLK
HighwayCR
FromROCK ISLAND RD AT BUNDIX CREEK
To.
CSJ0911-04-080
Proj IDBR 2016(778)
Work TypeBRIDGE REPLACEMENT
 
0.1661091491.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-22-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-080
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
AMERICAN REMEDIATION OPTIONS, INC. (4.37)
HEMPHILL WBE PILE DRIVING CO. (4.50)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.47)
Contract #10163220
Totals1091491.650.000.000.0

CountyPOLK
HighwayCR
FromOLD HWY 35 N
ToAT TRIB OF LONG KING CREEK
CSJ0911-04-083
Proj IDBR 2016(781)
Work TypeBRIDGE REPLACEMENT
 
0.067351199.3259128.0016.8
CountyPOLK
HighwayCR
FromOAKDALE LOOP AT KIBBLE CREEK
To.
CSJ0911-04-084
Proj IDBR 2016(782)
Work TypeBRIDGE REPLACEMENT
 
0.096460983.4635644.477.7
Work Order08-18-16
Work Began11-25-16
Work Completed
Time Computed11-16-16
Contract Working Days83
Addl Days Granted0
Working Days Charged17
Percent Time Used20
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-083
AMERICAN REMEDIATION OPTIONS, INC. (6.37)
LONESTAR TRAFFIC SAFETY, LLC (0.46)
Contract #07163229
Totals812182.781200.0094772.4711.6

CountySAN JACINTO
HighwayVA
FromVARIOUS LOCATIONS
ToWITHIN THE CITY OF COLDSPRING
CSJ0911-07-038
Proj IDSTP 2017(251)
Work TypeCONSTRUCT CURB RAMPS
 
0.100646827.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days116
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-07-038
INTERSTATE BARRICADES & MARKINGS, INC. (1.21)
LONESTAR TRAFFIC SAFETY, LLC (0.63)
HOUSTON TREE & LAWN SERVICE (0.46)
Contract #11163021
Totals646827.000.000.000.0

CountyHOUSTON
HighwayCR
FromCR 1585 AT SAN PEDRO CREEK
To.
CSJ0911-28-036
Proj IDBR 2014(436)
Work TypeBRIDGE REPLACEMENT
 
0.146763544.08332509.5243.5
Work Order07-28-16
Work Began12-09-16
Work Completed
Time Computed10-26-16
Contract Working Days88
Addl Days Granted0
Working Days Charged31
Percent Time Used35
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-036
AMERICAN REMEDIATION OPTIONS, INC. (6.74)
FLEX SUPPLY, LLC (0.85)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.32)
Contract #06163019
Totals763544.0890055.82332509.5243.5

CountyHOUSTON
HighwayVA
FromWITHIN MISSION TEJAS ST HIST SITE
To.
CSJ0911-28-037
Proj IDC 911-28-37
Work TypeCNSTR NEW ENTRANCE RD & PARKING LOT
 
0.100746460.56161165.5821.5
Work Order12-06-16
Work Began01-03-17
Work Completed
Time Computed01-03-17
Contract Working Days164
Addl Days Granted8
Working Days Charged16
Percent Time Used9
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-037
PANOLA SIGN & BARRICADE, INC. (1.11)
AMERICAN REMEDIATION OPTIONS, INC. (1.10)
MOORE BROTHERS CONSTRUCTION COMPANY (24.42)
STRIPING TECHNOLOGY, L.P. (1.07)
COX CONTRACTORS, INC. (12.79)
Contract #11163018
Totals746460.56161165.58161165.5821.5

CountyHOUSTON
HighwayCR
FromCR 1765 AT RICH CREEK
To.
CSJ0911-28-040
Proj IDBR 1602(206)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.066461059.2097489.6621.1
CountyHOUSTON
HighwayCR
FromCR 1680 AT SILVER CREEK
To.
CSJ0911-28-044
Proj IDBR 1602(212)
Work TypeBRIDGE REPLACEMENT
 
0.061346469.10229548.8066.2
CountyHOUSTON
HighwayCR
FromCR 1750 AT RICH CREEK
To.
CSJ0911-28-045
Proj IDBR 1602(205)
Work TypeBRIDGE REPLACEMENT
 
0.073273448.9014900.005.4
Work Order08-29-16
Work Began12-12-16
Work Completed
Time Computed11-28-16
Contract Working Days168
Addl Days Granted0
Working Days Charged27
Percent Time Used16
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-040
MORRIS COUNTY CONTRACTORS, L.L.C. (5.17)
LONE STAR TRAFFIC SERVICE, INC. (0.63)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.94)
Contract #07163221
Totals1080977.20174401.33341938.4631.6

CountyANGELINA
HighwayCR
FromOLD HOMER ALTO HWY AT BODEN CR
To.
CSJ0911-38-070
Proj IDBR 1602(274)
Work TypeBRIDGE REPLACEMENT
 
0.068460227.88151549.2932.9
Work Order08-19-16
Work Began12-01-16
Work Completed
Time Computed11-17-16
Contract Working Days59
Addl Days Granted0
Working Days Charged14
Percent Time Used23
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-38-070
MORRIS COUNTY CONTRACTORS, L.L.C. (3.42)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.32)
HEMPHILL WBE PILE DRIVING CO. (3.36)
Contract #07163020
Totals460227.8873402.64151549.2932.9

CountySHELBY
HighwayCR
FromACCESS RD AT TOLEDO BEND RESERVOIR
To.
CSJ0911-39-046
Proj IDBR 2016(605)
Work TypeBRIDGE REPLACEMENT
 
0.2141129593.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-06-16
Work Began02-06-17
Work Completed
Time Computed00-00-00
Contract Working Days220
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-046
PANOLA SIGN & BARRICADE, INC. (1.24)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.48)
HEMPHILL WBE PILE DRIVING CO. (4.30)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.49)
ISAACS CONSTRUCTION SERVICES, LLC. (1.24)
MORRIS COUNTY CONTRACTORS, L.L.C. (5.40)
Contract #10163209
Totals1129593.900.000.000.0

CountySHELBY
HighwayCR
FromCR 3564 AT HILLIARD CREEK
To.
CSJ0911-39-051
Proj IDBR 2016(598)
Work TypeBRIDGE REPLACEMENT
 
0.133844617.78328815.0038.9
Work Order08-18-16
Work Began11-16-16
Work Completed
Time Computed11-16-16
Contract Working Days150
Addl Days Granted0
Working Days Charged35
Percent Time Used23
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-051
PANOLA SIGN & BARRICADE, INC. (1.20)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.22)
FREDONIA CONSTRUCTION SERVICES (0.95)
AMERICAN REMEDIATION OPTIONS, INC. (7.11)
MCL CONTRACTING, LLC (0.57)
Contract #06163226
Totals844617.78104776.50328815.0038.9

CountySHELBY
HighwayCR
FromCR 4256 AT TRIB OF FLAT FORK CREEK
To.
CSJ0911-39-054
Proj IDBR 2016(601)
Work TypeBRIDGE REPLACEMENT
 
0.070281906.66215726.2576.5
CountySHELBY
HighwayCR
FromCR 4670 AT MCFADDEN CREEK
To.
CSJ0911-39-056
Proj IDBR 2016(603)
Work TypeBRIDGE REPLACEMENT
 
0.066270140.58215919.5079.9
Work Order09-15-16
Work Began10-13-16
Work Completed
Time Computed10-13-16
Contract Working Days77
Addl Days Granted0
Working Days Charged50
Percent Time Used64
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-054
HEMPHILL WBE PILE DRIVING CO. (4.78)
PANOLA SIGN & BARRICADE, INC. (1.19)
ODUM SERVICES, L.P. (5.78)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.71)
ISAACS CONSTRUCTION SERVICES, LLC. (1.72)
Contract #07163230
Totals552047.2419193.00431645.7578.1

CountyNACOGDOCHES
HighwayFM 343
FromCHEROKEE COUNTY LINE
ToFM 225
CSJ0926-02-010
Proj IDSTP 2017(315)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
13.6881213495.600.000.0
CountyNACOGDOCHES
HighwayFM 343
FromCHEROKEE COUNTY LINE
ToFM 225
CSJ0926-02-011
Proj IDSTP 2017(314)
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
6.8443510530.020.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-17-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0926-02-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163028
Totals4724025.620.000.000.0

CountyNACOGDOCHES
HighwayFM 1087
FromUS 259
ToFM 95
CSJ0926-05-008
Proj IDSTP 2017(643)HES
Work TypeSFT FIXED OBJ
 
10.916775621.060.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days137
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0926-05-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173004
Totals775621.060.000.000.0

page 1 | page 2 | page 3 | page 4