Monthly State Let Construction Report For Lufkin District As Of Jan 11, 2016 Page 3 Of 4

Last Update: Tuesday, January 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPOLK
Highway US 287
From 2.50 MI W OF US 59
To 2.0 MI W OF US 59
CSJ 0341-02-046
Proj ID STP 1502(212)
Work Type ADD TURN LANES
 
0.593 1220777.00 57604.23 1157299.37 94.8
Work Order 07-22-15
Work Began 08-24-15
Work Completed  
Time Computed 08-22-15
Contract Working Days 55
Addl Days Granted 3
Working Days Charged 39
Percent Time Used 67
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0341-02-046
COWBELL TRAFFIC SERVICES, INC. (0.47%)
STRIPING TECHNOLOGY, L.P.(1.82%)
DREWERY & WHEATON, LLC (2.36%)
TEX OP CONSTRUCTION, LP(1.10%)
FLEX SUPPLY, LLC (0.34%)
J & M CONTRACTING, COMPANY (3.23%)
Contract # 05153252
Totals 1220777.00 57604.23 1157299.37 94.8

CountyPOLK
Highway US 287
From US 59
To TYLER COUNTY LINE
CSJ 0341-03-037
Proj ID STP 2014(925)HESG
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
23.125 928912.62 7430.00 901109.92 97.0
Work Order 09-09-14
Work Began 10-15-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 219
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 96
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0341-03-037
PANOLA SIGN & BARRICADE, INC.(1.55%)
RICE ENVIRONMENTAL SERVICES(7.74%)
J.P. ABNER STUMP GRINDING & TREE SERVICE (0.16%)
ACE CONTRACTORS, INC.(7.85%)
FREDONIA CONSTRUCTION SERVICES (0.00%)
Contract # 07143213
Totals 928912.62 7430.00 901109.92 97.0

CountyNACOGDOCHES
Highway SH 204
From CHEROKEE C/L (@ ANGELINA RIVER)
To 0.1 MI E OF FM 2783
CSJ 0450-04-044
Proj ID STP 2014(840)
Work Type OCST AND SUPERPAVE
 
2.556 1010920.03 0.00 989177.48 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-14
Work Began 09-30-14
Work Completed 03-25-15
Time Computed 08-29-14
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 167
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0450-04-044
AMERICAN REMEDIATION OPTIONS, INC. (7.72%)
L. S. EQUIPMENT CO., INC.( 16.08%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.44%)
STRIPING TECHNOLOGY, L.P.(2.38%)
EXPRESS PERSONNEL SERVICES (0.49%)
SPHERION (0.29%)
Contract # 06143031
Totals 1010920.03 0.00 989177.48 100.0

CountyNACOGDOCHES
Highway FM 95
From RUSK COUNTY LINE
To 0.5 MI W OF US 59 IN GARRISON
CSJ 0706-01-013
Proj ID STP 2013(519)HES
Work Type RECONSTRUCT AND WIDEN PAVEMENT
 
3.938 1382155.18 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-10-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0706-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153240
Totals 1382155.18 0.00 0.00 0.0

CountyNACOGDOCHES
Highway FM 95
From AT PARALLEL CREEK
To .
CSJ 0706-03-020
Proj ID BR 1502(622)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.289 1783241.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0706-03-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153239
Totals 1783241.53 0.00 0.00 0.0

CountySHELBY
Highway FM 139
From SH 7
To SH 87
CSJ 0742-01-052
Proj ID STP 2015(314)HRR
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
28.429 1987837.07 153428.46 1892554.27 95.2
Work Order 01-07-15
Work Began 02-18-15
Work Completed  
Time Computed 02-18-15
Contract Working Days 121
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 100
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0742-01-052
DUSTIN ALLEN, INC. ( 13.59%)
LONESTAR TRAFFIC SAFETY, LLC (0.59%)
LONGVIEW BRIDGE AND ROAD, LTD. ( 17.65%)
N-LINE TRAFFIC MAINTENANCE, L.P. (5.60%)
STRIPING TECHNOLOGY, L.P.(0.99%)
PINTO CONSTRUCTION CO., INC. (0.37%)
Contract # 11143218
Totals 1987837.07 153428.46 1892554.27 95.2

CountySAN AUGUSTINE
Highway US 96
From SHELBY COUNTY LINE
To FM 3451
CSJ 0809-03-038
Proj ID NH 2013(514)
Work Type ADD PASSING LANES AND RECONST PVMT
 
3.804 7319958.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0809-03-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153048
Totals 7319958.62 0.00 0.00 0.0

CountySAN AUGUSTINE
Highway US 96
From AT AYISH BAYOU
To .
CSJ 0809-04-046
Proj ID BR 1502(202)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.545 3951203.54 159038.29 910672.55 23.0
Work Order 07-02-15
Work Began 11-18-15
Work Completed  
Time Computed 08-02-15
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 5
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0809-04-046
PANOLA SIGN & BARRICADE, INC.(0.26%)
MOORE BROTHERS CONSTRUCTION COMPANY( 13.90%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.73%)
MCL CONTRACTING, LLC (0.14%)
CRABTREE BARRICADE SYSTEMS, INC. (0.65%)
AMERICAN REMEDIATION OPTIONS, INC. (2.06%)
Contract # 05153241
Totals 3951203.54 159038.29 910672.55 23.0

CountyANGELINA
Highway VA
From AT VARIOUS LOCATIONS IN LUFKIN
To DISTRICT
CSJ 0911-00-073
Proj ID STP 2014(928)
Work Type CONSTRUCT CURB RAMPS
 
0.001 556965.00 21000.00 567183.75 100.0
Work Order 09-12-14
Work Began 10-07-14
Work Completed 07-21-15
Time Computed 09-28-14
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 66
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-00-073
STRIPING TECHNOLOGY, L.P.(2.25%)
CLASSIC TEJAS CONSTRUCTION, INC. (2.80%)
Contract # 07143009
Totals 556965.00 21000.00 567183.75 100.0

CountyANGELINA
Highway VA
From AT VARIOUS LOCATIONS IN LUFKIN DIST
To .
CSJ 0911-00-074
Proj ID STP 1502(258)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1038185.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-11-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 43
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-00-074
N-LINE TRAFFIC MAINTENANCE, L.P. (1.80%)
STRIPE-A-ZONE, INC.(2.33%)
Contract # 07153263
Totals 1038185.70 0.00 0.00 0.0

CountyPOLK
Highway VA
From WITHIN LAKE LIVINGSTON STATE PARK
To .
CSJ 0911-04-054
Proj ID C 911-4-54
Work Type REPAIR AND RESURFACE PAVED AREAS
 
0.100 2009215.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163025
Totals 2009215.00 0.00 0.00 0.0

CountyPOLK
Highway CR
From KELLEY RD OVER MENARD CREEK
To .
CSJ 0911-04-056
Proj ID BR 2014(692)
Work Type BRIDGE REPLACEMENT
 
0.281 707623.10 0.00 583830.25 82.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-26-15
Work Began 09-14-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 25
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-056
PANOLA SIGN & BARRICADE, INC.(1.56%)
AMERICAN REMEDIATION OPTIONS, INC. (9.20%)
Contract # 02153220
Totals 707623.10 0.00 583830.25 82.5

CountyPOLK
Highway CR
From DICK SKINNER RD AT TRIB OF NECHES R
To .
CSJ 0911-04-059
Proj ID BR 1402(188)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.413 1215872.88 24572.16 24572.16 2.0
Work Order 08-26-15
Work Began 00-00-00
Work Completed  
Time Computed 11-24-15
Contract Working Days 151
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153052
Totals 1215872.88 24572.16 24572.16 2.0

CountyPOLK
Highway CR
From UPPER LEGGETT RD
To AT TRIB OF BIG SANDY CREEK
CSJ 0911-04-060
Proj ID BR 1402(189)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.441 1889227.89 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153046
Totals 1889227.89 0.00 0.00 0.0

CountyNACOGDOCHES
Highway CR
From CR 706 AT YSELETA CREEK
To .
CSJ 0911-08-044
Proj ID BR 2013(438)
Work Type BRIDGE REPLACEMENT
 
0.041 217515.25 0.00 213932.92 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-14
Work Began 01-05-15
Work Completed 06-08-15
Time Computed 11-11-14
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 92
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-08-044
AMERICAN REMEDIATION OPTIONS, INC. (5.95%)
BANNER SIGN & BARRICADE, INC. (HOOKS)(0.91%)
Contract # 07143032
Totals 217515.25 0.00 213932.92 100.0

CountyHOUSTON
Highway CR
From CR 3480 AT BIG CREEK TRIBUTARY
To .
CSJ 0911-28-031
Proj ID BR 2014(433)
Work Type BRIDGE REPLACEMENT
 
0.137 748567.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HARTBEAT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-031
DUSTIN ALLEN, INC. (5.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.51%)
HEMPHILL PILE DRIVING CO., A CORP. (4.20%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.75%)
Contract # 06153231
Totals 748567.80 0.00 0.00 0.0

CountySABINE
Highway CR
From ROCK CREEK RD AT ROCK CREEK
To .
CSJ 0911-29-036
Proj ID BR 2012(488)
Work Type BRIDGE REPLACEMENT
 
0.129 436864.83 0.00 466017.52 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-13
Work Began 03-04-14
Work Completed 09-15-14
Time Computed 00-00-00
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 85
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-29-036
AMERICAN REMEDIATION OPTIONS, INC. (6.81%)
CRABTREE BARRICADE SYSTEMS, INC. (2.02%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 10.92%)
MESA ROD BUSTERS, INC. (0.59%)
Contract # 04133226
Totals 436864.83 0.00 466017.52 100.0

CountySAN AUGUSTINE
Highway CR
From CR 4320 AT CHIAMON BAYOU
To .
CSJ 0911-30-021
Proj ID BR 2013(435)
Work Type BRIDGE REPLACEMENT
 
0.176 510181.60 0.00 494027.64 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-14
Work Began 07-07-14
Work Completed 07-23-15
Time Computed 06-10-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 105
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-30-021
DUSTY ALLEN, INC.(7.41%)
PANOLA SIGN & BARRICADE, INC.(0.68%)
TEXAS ALTERNATIVE GRASSER, INC.(1.70%)
LONE STAR HIGHWAY PRODUCTS, INC. (2.39%)
Contract # 01143019
Totals 510181.60 0.00 494027.64 100.0

CountySAN AUGUSTINE
Highway CR
From CR 201 AT BIG IRON ORE CREEK
To .
CSJ 0911-30-028
Proj ID BR 2013(437)
Work Type BRIDGE REPLACEMENT
 
0.211 644984.12 0.00 644262.35 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 07-21-14
Work Completed 02-26-15
Time Computed 07-14-14
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 91
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-30-028
AMERICAN REMEDIATION OPTIONS, INC. (8.54%)
BANNER SIGN & BARRICADE, INC. (HOOKS)(0.44%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.50%)
MESA ROD BUSTERS, INC. (0.30%)
Contract # 02143023
Totals 644984.12 0.00 644262.35 100.0

CountySHELBY
Highway CR
From CR 4323 AT FLAT FORK CR RELIEF NO 2
To .
CSJ 0911-39-042
Proj ID BR 2014(429)
Work Type BRIDGE REPLACEMENT
 
0.379 1170264.70 74479.15 805091.45 68.7
Work Order 03-26-15
Work Began 08-03-15
Work Completed  
Time Computed 06-24-15
Contract Working Days 174
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 25
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-042
AMERICAN REMEDIATION OPTIONS, INC. (9.13%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.76%)
PANOLA SIGN & BARRICADE, INC.(0.63%)
MESA ROD BUSTERS, INC. (0.85%)
Contract # 02153021
Totals 1170264.70 74479.15 805091.45 68.7

page 1 | page 2 | page 3 | page 4