Monthly State Let Maintenance Report For Houston District As Of Jan 11, 2017 Page 3 Of 7

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS COUNTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6282-55-001
Proj IDRMC - 628255001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0011041195.001098397.0899.9
Work Order05-21-15
Work Began06-01-15
Work Completed
Time Computed06-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged578
Percent Time Used79
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6282-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154203
Totals1041195.0065233.091098397.0899.9

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6283-14-001
Proj IDRMC - 628314001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.001498974.00455239.19100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-30-15
Work Began07-01-15
Work Completed06-30-16
Time Computed07-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6283-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04154022
Totals498974.000.00455239.19100.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS IN BRAZORIA COUNTY
ToVARIOUS HWYS IN BRAZORIA COUNTY
CSJ6283-15-001
Proj IDRMC - 628315001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
0.0011701140.001312955.0077.1
Work Order06-08-15
Work Began07-01-15
Work Completed
Time Computed07-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6283-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04154223
Totals1701140.0041100.001312955.0077.1

CountyGALVESTON
HighwaySH0087
FromGALVESTON FERRY LANDING
ToBOLIVAR FERRY LANDING
CSJ6283-37-001
Proj IDRMC - 628337001
Work TypeMARINE EQUIPMENT MAINTENACE AND
 
0.100975375.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164004
Totals975375.000.000.000.0

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6283-47-001
Proj IDRMC - 628347001
Work TypeREFLECTIVE PAVEMENT MARKINGS (LONG
 
0.001619401.05532802.62100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-15
Work Completed07-31-16
Time Computed08-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6283-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05154208
Totals619401.050.00532802.62100.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6283-77-001
Proj IDRMC - 628377001
Work TypeMETAL BEAM GUARD FENCE UPGRADE
 
0.0011232199.30623476.5654.7
Work Order02-11-16
Work Began02-15-16
Work Completed
Time Computed02-15-16
Contract Working Days110
Addl Days Granted0
Working Days Charged185
Percent Time Used168
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-77-001
TINMAN ENTERPRISES (92.61)
Contract #09154003
Totals1232199.3034641.54623476.5654.7

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6283-86-001
Proj IDRMC - 628386001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001683590.00660372.91100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-15
Work Completed07-31-16
Time Computed08-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6283-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05154004
Totals683590.000.00660372.91100.0

CountyBRAZORIA
HighwayFM0524
From019 MILES NORTH OF CR 360
ToSH 35
CSJ6284-15-001
Proj IDRMC - 628415001
Work TypeACP OVERLAY, SEAL COAT AND PAVEMENT
 
2.0402183127.302234262.7499.9
Work Order06-30-15
Work Began07-06-15
Work Completed
Time Computed07-06-15
Contract Working Days91
Addl Days Granted2
Working Days Charged95
Percent Time Used102
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6284-15-001
INTERSTATE BARRICADES & MARKINGS, INC. (3.57)
COX PAVING COMPANY OF TEXAS, INC. (9.36)
THIRD COAST SERVICES LLC (0.16)
WEST TEXAS RUMBLE STRIP (0.18)
RICE ENVIRONMENTAL SERVICES (2.21)
BLACKTOPPER TECHNOLOGY, INC. (8.32)
Contract #05154206
Totals2183127.300.002234262.7499.9

CountyGALVESTON
HighwayIH0045
FromIH 45 GALVESTON CAUSEWAY BRIDGE
ToIH 45 GALVESTON CAUSEWAY BRIDGE
CSJ6284-41-001
Proj IDRMC - 628441001
Work TypeILLUMINATION REPAIR/REPLACEMENT
 
0.0011382456.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days210
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6284-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164205
Totals1382456.000.000.000.0

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6284-84-001
Proj IDRMC - 628484001
Work TypeMNT OF ILLUMINATION SYS
 
0.0011832670.001050971.6057.3
Work Order02-05-16
Work Began02-08-16
Work Completed
Time Computed02-08-16
Contract Working Days731
Addl Days Granted0
Working Days Charged313
Percent Time Used42
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6284-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154206
Totals1832670.0093228.601050971.6057.3

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6284-85-001
Proj IDRMC - 628485001
Work TypePREV MNT OF SGNL EQUIP
 
0.0011205985.00726363.0060.2
Work Order12-10-15
Work Began12-14-15
Work Completed
Time Computed12-11-15
Contract Working Days731
Addl Days Granted0
Working Days Charged372
Percent Time Used50
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6284-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09154005
Totals1205985.0058097.50726363.0060.2

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6284-86-001
Proj IDRMC - 628486001
Work TypeMNT OF VIVDS
 
0.001623012.50622892.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-27-15
Work Began08-27-15
Work Completed
Time Computed08-27-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
SOUTHWEST SIGNAL SUPPLY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07154203
Totals623012.500.00622892.0099.9

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS COUNTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6284-97-001
Proj IDRMC - 628497001
Work TypePUMP STATION & DRAINAGE SYSTEM
 
0.001538300.00467946.2586.9
Work Order07-09-15
Work Began08-18-15
Work Completed
Time Computed07-08-15
Contract Working Days731
Addl Days Granted0
Working Days Charged540
Percent Time Used73
Contractor(s)
CLEAN SERVE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6284-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05154005
Totals538300.0010920.25467946.2586.9

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6285-73-001
Proj IDRMC - 628573001
Work TypeLOOP DET REP AND/OR REPLCMNT
 
0.0011276050.00445025.6034.8
Work Order03-29-16
Work Began04-04-16
Work Completed
Time Computed04-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged265
Percent Time Used36
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6285-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164007
Totals1276050.0029183.00445025.6034.8

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6285-98-001
Proj IDRMC - 628598001
Work TypeMNT OF TRAFFIC SGNLS
 
0.0011852065.00666812.5036.0
Work Order05-24-16
Work Began05-25-16
Work Completed
Time Computed05-25-16
Contract Working Days730
Addl Days Granted0
Working Days Charged206
Percent Time Used28
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6285-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164018
Totals1852065.0085934.00666812.5036.0

CountyHARRIS
HighwaySH0249
FromVARIOUS HIGHWAYS IN N. HARRIS COUNTY
ToVARIOUS HIGHWAYS IN N. HARRIS COUNTY
CSJ6286-42-001
Proj IDRMC - 628642001
Work TypeGUARDRAIL REPAIR
 
0.001290225.00293046.6299.9
Work Order01-15-16
Work Began01-25-16
Work Completed
Time Computed01-22-16
Contract Working Days366
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09154004
Totals290225.0050176.11293046.6299.9

CountyGALVESTON
HighwayFM1764
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GLAVESTON COUNTY
CSJ6286-49-001
Proj IDRMC - 628649001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001485300.00470500.0096.9
Work Order11-19-15
Work Began12-03-15
Work Completed
Time Computed12-01-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6286-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09154002
Totals485300.000.00470500.0096.9

CountyHARRIS
HighwayUS0059
FromVARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
ToVARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
CSJ6286-98-001
Proj IDRMC - 628698001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001476500.00443256.6593.0
Work Order01-12-16
Work Began01-18-16
Work Completed
Time Computed01-19-16
Contract Working Days366
Addl Days Granted0
Working Days Charged336
Percent Time Used91
Contractor(s)
CROSBY RD CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6286-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154005
Totals476500.0044359.30443256.6593.0

CountyHARRIS
HighwayIH0010
FromSPUR 330
ToHARRIS COUNTY LINE
CSJ6286-99-001
Proj IDRMC - 628699001
Work TypeRETRACE/REPLACE PAVEMENT MRK AND
 
8.305532519.36565483.6099.9
Work Order00-00-00
Work Began05-17-16
Work Completed
Time Computed05-17-16
Contract Working Days108
Addl Days Granted0
Working Days Charged78
Percent Time Used72
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6286-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164203
Totals532519.362040.00565483.6099.9

CountyHARRIS
HighwaySH0006
FromVARIOUS HIGHWAYS IN WEST HARRIS CO.
To.
CSJ6287-37-001
Proj IDRMC - 628737001
Work TypeASPHALT AND POTHOLE REPAIR
 
0.001349800.00145790.1141.6
Work Order00-00-00
Work Began02-03-16
Work Completed
Time Computed02-03-16
Contract Working Days731
Addl Days Granted0
Working Days Charged324
Percent Time Used44
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6287-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154012
Totals349800.000.00145790.1141.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7