Monthly State Let Maintenance Report For Houston District As Of Jul 11, 2014 Page 3 Of 4

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway US0059
From VARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
To VARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
CSJ 6259-00-001
Proj ID RMC - 625900001
Work Type FULL DEPTH CONCRETE & ASPHALT REPAIR
 
0.001 536250.00 0.00 58121.68 10.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-13-14
Work Began 01-17-14
Work Completed  
Time Computed 01-17-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 124
Percent Time Used 33
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6259-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10134002
Totals 536250.00 0.00 58121.68 10.8

CountyGALVESTON
Highway FM0517
From VARIOUS HWYS IN GALVESTON COUNTY
To VARIOUS HWYS IN GALVESTON COUNTY
CSJ 6259-98-001
Proj ID RMC - 625998001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 354900.00 0.00 419213.54 99.9
Work Order 12-30-13
Work Began 01-02-14
Work Completed  
Time Computed 01-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 39
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134033
Totals 354900.00 0.00 419213.54 99.9

CountyHARRIS
Highway IH0045
From VARIOUS LOCATIONS AT
To IH-10, IH-45
CSJ 6260-77-001
Proj ID BPM - 626077001
Work Type BRIDGE PREVENTATIVE MAINTENANCE
 
0.001 498025.00 0.00 187726.95 37.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-25-14
Work Began 05-09-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 27
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134009
Totals 498025.00 0.00 187726.95 37.6

CountyGALVESTON
Highway SH0087
From GALVESTON FERRY LANDING
To BOLIVAR FERRY LANDING
CSJ 6261-68-001
Proj ID RMC - 626168001
Work Type REPAIR OF MARINE EQUIPMENT
 
1.000 323055.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134008
Totals 323055.00 0.00 0.00 0.0

CountyHARRIS
Highway IH0010
From VARIOUS HIGHWAYS WITHIN THE HOUSTON
To DISTRICT
CSJ 6262-40-001
Proj ID RMC - 626240001
Work Type PAVEMENT MARKINGS AND OVERHEAD SIGNS
 
0.001 663840.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-04-14
Work Began 00-00-00
Work Completed  
Time Computed 04-12-14
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144022
Totals 663840.82 0.00 0.00 0.0

CountyHARRIS
Highway IH0610
From VARIOUS HIGHWAYS
To INSIDE LOOP 8
CSJ 6262-50-001
Proj ID RMC - 626250001
Work Type PERFORMANCE BASED TOTAL MAINTENANCE
 
0.001 23084824.00 1297295.58 1297295.58 5.6
Work Order 03-03-14
Work Began 00-00-00
Work Completed  
Time Computed 06-01-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 4
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6262-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144042
Totals 23084824.00 1297295.58 1297295.58 5.6

CountyHARRIS
Highway SL0008
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6263-16-001
Proj ID RMC - 626316001
Work Type SPALL REPAIR / RAISING & UNDERSEALING JT / C
 
0.001 532350.00 0.00 184243.14 34.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-19-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 14
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144030
Totals 532350.00 0.00 184243.14 34.6

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6263-35-001
Proj ID RMC - 626335001
Work Type STORM SEWER SYSTEM CLEANING
 
0.001 374525.00 0.00 52702.75 14.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-14
Work Began 03-19-14
Work Completed  
Time Computed 03-19-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 9
Contractor(s)
CLEANSERVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144036
Totals 374525.00 0.00 52702.75 14.0

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6263-36-001
Proj ID RMC - 626336001
Work Type PAVEMENT MARKINGS
 
0.001 822207.00 0.00 97370.04 11.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-14
Work Began 04-18-14
Work Completed  
Time Computed 04-18-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 5
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144021
Totals 822207.00 0.00 97370.04 11.8

CountyHARRIS
Highway IH0610
From VARIOUS HWYS IN HOUSTON DISTRICT
To VARIOUS HWYS IN HOUSTON DISTRICT
CSJ 6264-07-001
Proj ID RMC - 626407001
Work Type LOOP DET REP AND / OR REPLCMNT
 
0.001 1241612.50 47703.50 117713.55 9.4
Work Order 03-12-14
Work Began 03-17-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 14
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144037
Totals 1241612.50 47703.50 117713.55 9.4

CountyMONTGOMERY
Highway US0059
From VARIOUS HWYS IN MONTGOMERY
To VARIOUS HWYS IN MONTGOMERY
CSJ 6264-28-001
Proj ID RMC - 626428001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 437399.00 0.00 264590.95 60.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-16-14
Work Began 04-16-14
Work Completed  
Time Computed 04-16-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 12
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144003
Totals 437399.00 0.00 264590.95 60.4

CountyBRAZORIA
Highway SH0288
From VARIOUS HWYS IN BRAZORIA COUNTY
To VARIOUS HWYS IN BRAZORIA COUNTY
CSJ 6264-83-001
Proj ID RMC - 626483001
Work Type SPALL REPAIR
 
0.001 416279.07 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144020
Totals 416279.07 0.00 0.00 0.0

CountyWALLER
Highway US0290
From VARIOUS ROADWAYS IN WALLER COUNTY
To VARIOUS ROADWAYS IN WALLER COUNTY
CSJ 6265-49-001
Proj ID RMC - 626549001
Work Type REFLECTIVE PAVEMENT MARKINGS
 
0.001 358791.73 59002.00 59002.00 16.4
Work Order 05-13-14
Work Began 05-20-14
Work Completed  
Time Computed 05-20-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 3
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6265-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144005
Totals 358791.73 59002.00 59002.00 16.4

CountyFORT BEND
Highway US0059
From VARIOUS HIGHWAYS IN FORT BEND COUNTY
To VARIOUS HIGHWAYS IN FORT BEND COUNTY
CSJ 6265-80-001
Proj ID RMC - 626580001
Work Type CLEANING AND SEALING JOINTS AND CRACKS
 
0.001 190000.00 0.00 181298.00 95.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 15
Contractor(s)
KUNTZ CONTRACTING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6265-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144029
Totals 190000.00 0.00 181298.00 95.4

CountyGALVESTON
Highway FM2094
From CONSTELLATION BLVD
To SOUTH SHORE BLVD
CSJ 6266-04-001
Proj ID RMC - 626604001
Work Type FULL DEPTH REPAIR
 
0.663 786000.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-22-14
Work Began 06-11-14
Work Completed  
Time Computed 06-09-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6266-04-001
KOSSMAN CONTRACTING CO., INC.(0.43%)
Contract # 02144004
Totals 786000.78 0.00 0.00 0.0

CountyHARRIS
Highway IH0610
From VARIOUS HWYS IN HOUSTON DIST
To VARIOUS HWYS IN HOUSTON DIST
CSJ 6266-11-001
Proj ID RMC - 626611001
Work Type MAINT OF VIVDS
 
0.001 499320.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SOUTHWEST SIGNAL SUPPLY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144006
Totals 499320.50 0.00 0.00 0.0

CountyHARRIS
Highway IH0610
From VARIOUS HWYS HARRIS COUNTY
To VARIOUS HWYS HARRIS COUNTY
CSJ 6266-38-001
Proj ID RMC - 626638001
Work Type RETRACE & REPL PAVEMENT MARKINGS
 
1.000 385641.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6266-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144025
Totals 385641.00 0.00 0.00 0.0

CountyHARRIS
Highway SH0225
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6266-42-001
Proj ID RMC - 626642001
Work Type PUMP STATION & DRAINAGE SYSTEM CLEANING
 
0.001 236000.00 0.00 1602.50 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 8
Contractor(s)
CLEANSERVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144020
Totals 236000.00 0.00 1602.50 0.6

CountyFORT BEND
Highway SH0006
From HARRIS COUNTY LINE
To VOSS ROAD
CSJ 6266-67-001
Proj ID RMC - 626667001
Work Type BASE REPAIR, PFC OVERLAY, PAV MARKS
 
3.097 1815127.06 101117.86 101117.86 5.5
Work Order 05-07-14
Work Began 05-07-14
Work Completed  
Time Computed 05-07-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 21
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6266-67-001
THIRD COAST SERVICES LLC (1.40%)
WEST TEXAS RUMBLE STRIP(0.25%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.29%)
BATTERSON,LLP(7.98%)
Contract # 03144024
Totals 1815127.06 101117.86 101117.86 5.5

CountyGALVESTON
Highway LP0108
From SH 87
To SH 87
CSJ 6266-85-001
Proj ID RMC - 626685001
Work Type ACP OVERLAY
 
4.296 696650.54 698224.94 698224.94 99.9
Work Order 05-01-14
Work Began 05-12-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 33
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6266-85-001
BATTERSON,LLP( 17.48%)
Contract # 03144005
Totals 696650.54 698224.94 698224.94 99.9