Monthly State Let Maintenance Report For Houston District As Of Apr 11, 2014 Page 3 Of 4

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway IH0610
From VARIOUS HWYS IN HOUSTON DISTRICT
To VARIOUS HWYS IN HOUSTON DISTRICT
CSJ 6255-63-001
Proj ID RMC - 625563001
Work Type MNT OF VIVDS
 
0.001 448185.00 0.00 207047.00 52.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-05-13
Work Began 08-05-13
Work Completed  
Time Computed 08-05-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 239
Percent Time Used 65
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6255-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134014
Totals 448185.00 0.00 207047.00 52.7

CountyHARRIS
Highway IH0610
From VARIOUS HWYS IN HOUSTON DISTRICT
To VARIOUS HWYS IN HOUSTON DISTRICT
CSJ 6256-17-001
Proj ID RMC - 625617001
Work Type MAINTNENANCE OF ILLUMINATION SYSTEMS
 
0.001 2100620.00 0.00 722911.20 39.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-28-13
Work Began 09-13-13
Work Completed  
Time Computed 09-03-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 210
Percent Time Used 28
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6256-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06134014
Totals 2100620.00 0.00 722911.20 39.1

CountyHARRIS
Highway US0059
From VARIOUS HWYS IN NORTH HARRIS COUNTY
To VARIOUS HWYS IN NORTH HARRIS COUNTY
CSJ 6256-44-001
Proj ID RMC - 625644001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 407919.75 29920.00 166770.00 40.8
Work Order 10-09-13
Work Began 10-14-13
Work Completed  
Time Computed 10-14-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 169
Percent Time Used 46
Contractor(s)
CROSBY RD CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6256-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08134013
Totals 407919.75 29920.00 166770.00 40.8

CountyBRAZORIA
Highway SH0288
From VARIOUS HWYS WITHIN BRAZORIA COUNTY
To VARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ 6256-51-001
Proj ID RMC - 625651001
Work Type JOINT AND CRACK SEAL
 
0.001 245000.00 0.00 110656.00 52.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-17-13
Work Began 12-01-13
Work Completed  
Time Computed 11-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 41
Contractor(s)
DELTA PRIME SPECIALTY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08134006
Totals 245000.00 0.00 110656.00 52.2

CountyWALLER
Highway FM1488
From VARIOUS ROADWAYS IN WALLER COUNTY
To VARIOUS ROADWAYS IN WALLER COUNTY
CSJ 6257-32-001
Proj ID RMC - 625732001
Work Type DELINEATOR, OBJ MRKR & MAILBOXES
 
0.001 351695.00 0.00 261945.69 89.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-19-13
Work Began 09-04-13
Work Completed  
Time Computed 08-19-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 225
Percent Time Used 61
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6257-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07134005
Totals 351695.00 0.00 261945.69 89.6

CountyGALVESTON
Highway SH0146
From VARIOUS HIGHWAYS IN GALVESTON
To VARIOUS HIGHWAYS IN GALVESTON
CSJ 6258-29-001
Proj ID RMC - 625829001
Work Type REFLECTIVE PAVEMENT MARKERS (GRAPHICS)
 
0.001 313880.44 0.00 143264.53 57.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-02-13
Work Began 10-28-13
Work Completed  
Time Computed 10-15-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 168
Percent Time Used 46
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08134014
Totals 313880.44 0.00 143264.53 57.9

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6258-71-001
Proj ID RMC - 625871001
Work Type FULL DEP CONC PVMT REP & MISC CONC
 
0.001 684575.00 0.00 2208.31 4.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-23-13
Work Began 09-23-13
Work Completed  
Time Computed 09-23-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 190
Percent Time Used 52
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6258-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07134017
Totals 684575.00 0.00 2208.31 4.9

CountyHARRIS
Highway LP0008
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6258-83-001
Proj ID RMC - 625883001
Work Type REFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.001 719813.70 25695.33 25695.33 3.5
Work Order 12-12-13
Work Began 01-02-14
Work Completed  
Time Computed 01-02-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 7
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09134004
Totals 719813.70 25695.33 25695.33 3.5

CountyMONTGOMERY
Highway US0059
From VARIOUS HWYS IN MONTGOMERY COUNTY
To VARIOUS HWYS IN MONTGOMERY COUNTY
CSJ 6258-91-001
Proj ID RMC - 625891001
Work Type CLEANING & SWEEPING HIGHWAYS
 
0.001 459000.00 22250.00 38125.00 8.3
Work Order 12-31-13
Work Began 01-06-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 14
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6258-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11134005
Totals 459000.00 22250.00 38125.00 8.3

CountyHARRIS
Highway US0059
From VARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
To VARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
CSJ 6259-00-001
Proj ID RMC - 625900001
Work Type FULL DEPTH CONCRETE & ASPHALT REPAIR
 
0.001 536250.00 0.00 0.00 0.0
Work Order 01-13-14
Work Began 01-17-14
Work Completed  
Time Computed 01-17-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 11
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6259-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10134002
Totals 536250.00 0.00 0.00 0.0

CountyGALVESTON
Highway FM0517
From VARIOUS HWYS IN GALVESTON COUNTY
To VARIOUS HWYS IN GALVESTON COUNTY
CSJ 6259-98-001
Proj ID RMC - 625998001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 354900.00 36186.56 334684.05 94.3
Work Order 12-30-13
Work Began 01-02-14
Work Completed  
Time Computed 01-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 22
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134033
Totals 354900.00 36186.56 334684.05 94.3

CountyHARRIS
Highway IH0045
From VARIOUS LOCATIONS AT
To IH-10, IH-45
CSJ 6260-77-001
Proj ID BPM - 626077001
Work Type BRIDGE PREVENTATIVE MAINTENANCE
 
0.001 498025.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134009
Totals 498025.00 0.00 0.00 0.0

CountyGALVESTON
Highway SH0087
From GALVESTON FERRY LANDING
To BOLIVAR FERRY LANDING
CSJ 6261-68-001
Proj ID RMC - 626168001
Work Type REPAIR OF MARINE EQUIPMENT
 
1.000 323055.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134008
Totals 323055.00 0.00 0.00 0.0

CountyHARRIS
Highway IH0010
From VARIOUS HIGHWAYS WITHIN THE HOUSTON
To DISTRICT
CSJ 6262-40-001
Proj ID RMC - 626240001
Work Type PAVEMENT MARKINGS AND OVERHEAD SIGNS
 
0.001 663840.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144022
Totals 663840.82 0.00 0.00 0.0

CountyHARRIS
Highway IH0610
From VARIOUS HIGHWAYS
To INSIDE LOOP 8
CSJ 6262-50-001
Proj ID RMC - 626250001
Work Type PERFORMANCE BASED TOTAL MAINTENANCE
 
0.001 23084824.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-03-14
Work Began 00-00-00
Work Completed  
Time Computed 06-01-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6262-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144042
Totals 23084824.00 0.00 0.00 0.0

CountyHARRIS
Highway SL0008
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6263-16-001
Proj ID RMC - 626316001
Work Type SPALL REPAIR / RAISING & UNDERSEALING JT / C
 
0.001 532350.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-19-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144030
Totals 532350.00 0.00 0.00 0.0

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6263-35-001
Proj ID RMC - 626335001
Work Type STORM SEWER SYSTEM CLEANING
 
0.001 374525.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-14
Work Began 03-19-14
Work Completed  
Time Computed 03-19-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLEANSERVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144036
Totals 374525.00 0.00 0.00 0.0

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6263-36-001
Proj ID RMC - 626336001
Work Type PAVEMENT MARKINGS
 
0.001 822207.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-14
Work Began 04-21-14
Work Completed  
Time Computed 04-21-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144021
Totals 822207.00 0.00 0.00 0.0

CountyHARRIS
Highway IH0610
From VARIOUS HWYS IN HOUSTON DISTRICT
To VARIOUS HWYS IN HOUSTON DISTRICT
CSJ 6264-07-001
Proj ID RMC - 626407001
Work Type LOOP DET REP AND / OR REPLCMNT
 
0.001 1241612.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-14
Work Began 03-17-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144037
Totals 1241612.50 0.00 0.00 0.0

CountyMONTGOMERY
Highway US0059
From VARIOUS HWYS IN MONTGOMERY
To VARIOUS HWYS IN MONTGOMERY
CSJ 6264-28-001
Proj ID RMC - 626428001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 437399.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-28-14
Work Began 00-00-00
Work Completed  
Time Computed 05-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144003
Totals 437399.00 0.00 0.00 0.0