Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway US0059
From VARIOUS ROADS IN COASTAL DISTRICT
To VARIOUS ROADS IN COASTAL DISTRICT
CSJ 6193-73-001
Proj ID RMC - 619373001
Work Type CALLOUT DEBRIS REMOVAL AND DISPOSAL
 
0.100 3689600.00 0.00 0.00 0.0
Work Order 07-21-09
Work Began 00-00-00
Work Completed  
Time Computed 07-21-09
Contract Working Days 730
Addl Days Granted 730
Working Days Charged 985
Percent Time Used 67
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6193-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06094012
Totals 3689600.00 0.00 0.00 0.0

CountyWALLER
Highway US0290
From VARIOUS HIGHWAYS IN WALLER COUNTY
To VARIOUS HIGHWAYS IN WALLER COUNTY
CSJ 6194-99-001
Proj ID RMC - 619499001
Work Type BRIDGE DECK REPAIR
 
0.001 313750.00 0.00 297730.55 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-06-10
Work Began 06-21-10
Work Completed  
Time Computed 04-12-10
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 750
Percent Time Used 102
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6194-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01104003
Totals 313750.00 0.00 297730.55 99.9

CountyGALVESTON
Highway SH0087
From GALVESTON FERRY LANDING
To BOLIVAR FERRY LANDING
CSJ 6195-11-001
Proj ID EMC - 619511001
Work Type EMERGENCY DOLPHIN REPAIRS
 
1.000 2872775.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6195-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06091240
Totals 2872775.00 0.00 0.00 0.0

CountyHARRIS
Highway IH0610
From VARIOUS HIGHWAYS IN HARRIS COUNTY
To VARIOUS HIGHWAYS IN HARRIS COUNTY
CSJ 6198-62-001
Proj ID RMC - 619862001
Work Type MAINTENANCE OF TRAFFIC SIGNALS
 
0.001 1425200.00 101880.90 911628.55 63.9
Work Order 03-24-11
Work Began 06-19-11
Work Completed  
Time Computed 04-19-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 348
Percent Time Used 47
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6198-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12104020
Totals 1425200.00 101880.90 911628.55 63.9

CountyHARRIS
Highway IH0010
From VARIOUS HWYS IN HOUSTON DISTRICT
To VARIOUS HWYS IN HOUSTON DISTRICT
CSJ 6198-68-001
Proj ID RMC - 619868001
Work Type MAINTENANCE OF ILLUMINATION SYSTEMS
 
0.001 1836751.87 0.00 1136845.90 65.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-09-10
Work Began 01-03-11
Work Completed  
Time Computed 01-03-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 484
Percent Time Used 66
Contractor(s)
CREACOM, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6198-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10104004
Totals 1836751.87 0.00 1136845.90 65.7

CountyHARRIS
Highway IH0010
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6204-48-001
Proj ID RMC - 620448001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 600175.20 0.00 271072.70 49.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-10
Work Began 07-01-10
Work Completed  
Time Computed 07-01-10
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 670
Percent Time Used 91
Contractor(s)
SURETEC INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6204-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04104003
Totals 600175.20 0.00 271072.70 49.2

CountyGALVESTON
Highway IH0045
From GALVESTON CAUSEWAY
To GALVESTON CAUSEWAY
CSJ 6204-78-001
Proj ID RMC - 620478001
Work Type FENDER SYSTEM REPAIR
 
0.001 632077.00 0.00 244595.52 38.6
Work Order 04-06-10
Work Began 08-15-11
Work Completed  
Time Computed 05-01-10
Contract Working Days 730
Addl Days Granted 120
Working Days Charged 704
Percent Time Used 82
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6204-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01104022
Totals 632077.00 0.00 244595.52 38.6

CountyHARRIS
Highway IH0045
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6204-89-001
Proj ID RMC - 620489001
Work Type ROADSIDE MOWING
 
0.001 285065.15 0.00 142282.05 49.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-07-10
Work Began 05-02-11
Work Completed  
Time Computed 05-02-11
Contract Working Days 155
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 39
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6204-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10104014
Totals 285065.15 0.00 142282.05 49.9

CountyHARRIS
Highway IH0610
From VARIOUS HWYS IN HOUSTON DISTRICT
To VARIOUS HWYS IN HOUSTON DISTRICT
CSJ 6205-75-001
Proj ID RMC - 620575001
Work Type LOOP DETECTOR REPAIR AND REPLACEMENT
 
0.001 1358820.00 0.00 0.00 3.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-28-12
Work Began 03-05-12
Work Completed  
Time Computed 03-05-12
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 7
Contractor(s)
REPUBLIC INTELLIGENT TRANSPORTATION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6205-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10114029
Totals 1358820.00 0.00 0.00 3.2

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6208-61-001
Proj ID RMC - 620861001
Work Type CLEANING & SWEEPING HWYS.
 
0.001 988080.00 0.00 614951.19 64.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-01-10
Work Began 10-03-10
Work Completed  
Time Computed 10-01-10
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6208-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07104004
Totals 988080.00 0.00 614951.19 64.1

CountyHARRIS
Highway IH0045
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6209-54-001
Proj ID RMC - 620954001
Work Type GUARDRAIL REPAIR
 
0.001 454585.00 0.00 395897.39 90.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-30-10
Work Began 09-01-10
Work Completed  
Time Computed 09-01-10
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 608
Percent Time Used 83
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6209-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07104005
Totals 454585.00 0.00 395897.39 90.9

CountyHARRIS
Highway IH0045
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6210-62-001
Proj ID RMC - 621062001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 838350.00 0.00 589181.73 74.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-10
Work Began 11-01-10
Work Completed  
Time Computed 11-01-10
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 547
Percent Time Used 74
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6210-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08104007
Totals 838350.00 0.00 589181.73 74.1

CountyHARRIS
Highway IH0045
From WITHIN NORTH HARRIS AREA
To WITHIN MONTGOMERY AREA
CSJ 6211-63-001
Proj ID RMC - 621163001
Work Type GENERAL ROUTINE MAINTENANCE OF IH45
 
1.000 899608.29 0.00 912505.21 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-20-10
Work Began 01-03-11
Work Completed  
Time Computed 01-03-11
Contract Working Days 365
Addl Days Granted 242
Working Days Charged 484
Percent Time Used 79
Contractor(s)
TEXAS HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6211-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11104015
Totals 899608.29 0.00 912505.21 99.9

CountyFORT BEND
Highway SH0099
From VARIOUS HWYS IN FORT BEND COUNTY
To VARIOUS HWYS IN FORT BEND COUNTY
CSJ 6211-80-001
Proj ID RMC - 621180001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 363336.46 0.00 149713.50 44.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-31-11
Work Began 05-31-11
Work Completed  
Time Computed 05-31-11
Contract Working Days 285
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 16
Contractor(s)
L. M. TRACTOR, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6211-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02114003
Totals 363336.46 0.00 149713.50 44.1

CountyHARRIS
Highway IH0010
From VARIOUS HWYS IN HOUSTON DISTRICT
To VARIOUS HWYS IN HOUSTON DISTRICT
CSJ 6212-14-001
Proj ID RMC - 621214001
Work Type LOOP DETECTOR
 
0.010 1447850.00 0.00 893670.60 68.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-15-10
Work Began 01-03-11
Work Completed  
Time Computed 01-03-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 484
Percent Time Used 66
Contractor(s)
REPUBLIC INTELLIGENT TRANSPORTATION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6212-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10104005
Totals 1447850.00 0.00 893670.60 68.0

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6214-64-001
Proj ID RMC - 621464001
Work Type GUARDRAIL REPAIR
 
0.001 873715.50 0.00 195254.75 28.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-01-10
Work Began 12-01-10
Work Completed  
Time Computed 12-01-10
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 517
Percent Time Used 70
Contractor(s)
TEXAS HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6214-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10104015
Totals 873715.50 0.00 195254.75 28.8

CountyHARRIS
Highway IH0010
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6215-45-001
Proj ID RMC - 621545001
Work Type FULL DEPTH CONCRETE REPAIR
 
0.001 847029.20 0.00 868235.09 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-31-11
Work Began 04-01-11
Work Completed  
Time Computed 04-01-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 396
Percent Time Used 54
Contractor(s)
TEXAS HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6215-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02114024
Totals 847029.20 0.00 868235.09 99.9

CountyMONTGOMERY
Highway US0059
From VARIOUS HWYS IN MONTGOMERY COUNTY
To VARIOUS HWYS IN MONTGOMERY COUNTY
CSJ 6219-04-001
Proj ID RMC - 621904001
Work Type ROADSIDE MOWING
 
0.001 314566.12 0.00 256720.18 81.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-12-11
Work Began 05-23-11
Work Completed  
Time Computed 05-30-11
Contract Working Days 125
Addl Days Granted 48
Working Days Charged 52
Percent Time Used 30
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6219-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01114016
Totals 314566.12 0.00 256720.18 81.6

CountyBRAZORIA
Highway SH0288
From VARIOUS HYWS IN SOUTH BRAZORIA COUNTY
To VARIOUS HYWS IN SOUTH BRAZORIA COUNTY
CSJ 6219-97-001
Proj ID RMC - 621997001
Work Type MOWING SOUTH
 
0.001 501932.94 0.00 168833.22 33.6
Work Order 08-04-11
Work Began 08-08-11
Work Completed  
Time Computed 08-08-11
Contract Working Days 243
Addl Days Granted 2
Working Days Charged 52
Percent Time Used 21
Contractor(s)
LANGFORD CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6219-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04114023
Totals 501932.94 0.00 168833.22 33.6

CountyWALLER
Highway US0290
From VARIOUS ROADWAYS IN WALLER COUNTY
To VARIOUS ROADWAYS IN WALLER COUNTY
CSJ 6220-04-001
Proj ID RMC - 622004001
Work Type MOWING RIGHT OF WAY
 
0.001 265489.20 0.00 135628.41 51.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-11
Work Began 05-26-11
Work Completed  
Time Computed 06-01-11
Contract Working Days 162
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 32
Contractor(s)
BEN E. SMITH TRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6220-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04114007
Totals 265489.20 0.00 135628.41 51.0