Monthly State Let Maintenance Report For Houston District As Of Apr 10, 2015 Page 4 Of 6

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway SH0035
From SH 0035 AT AIRPORT BLVD TO
To IPSWICK RD.
CSJ 6270-40-001
Proj ID RMC - 627040001
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
0.001 927439.58 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6270-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04154216
Totals 927439.58 0.00 0.00 0.0

CountyHARRIS
Highway IH0010
From AT SJOLANDER
To .
CSJ 6270-41-001
Proj ID RMC - 627041001
Work Type ACCEL / DECEL LANES WIDENING
 
0.001 779525.24 191176.00 791027.25 99.9
Work Order 00-00-00
Work Began 01-05-15
Work Completed  
Time Computed 01-05-15
Contract Working Days 45
Addl Days Granted 4
Working Days Charged 47
Percent Time Used 95
Contractor(s)
MAR-CON SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-41-001
GMJ PAVING CO. (9.46%)
REGIONAL TRAFFIC SERVICES LLC(5.91%)
SEAMARCK LANDSCAPE SERVICES, INC (0.28%)
Contract # 09144003
Totals 779525.24 191176.00 791027.25 99.9

CountyMONTGOMERY
Highway SH0105
From HIGHLAND HOLLOW_DRIVE
To INDIAN HILLS DRIVE
CSJ 6271-21-001
Proj ID RMC - 627121001
Work Type INSTALL BOX CULVERTS
 
0.170 398305.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTH TEXAS CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02154005
Totals 398305.00 0.00 0.00 0.0

CountyHARRIS
Highway IH0610
From VARIOUS HWYS HARRIS COUNTY
To VARIOUS HWYS HARRIS COUNTY
CSJ 6271-38-001
Proj ID RMC - 627138001
Work Type RETRACE & REPL PAVEMENT MARKINGS
 
1.000 692325.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6271-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02154212
Totals 692325.00 0.00 0.00 0.0

CountyHARRIS
Highway SL0008
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6271-43-001
Proj ID RMC - 627143001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 609950.00 23625.00 128328.36 21.0
Work Order 10-14-14
Work Began 11-01-14
Work Completed  
Time Computed 11-01-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 146
Percent Time Used 19
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6271-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08144003
Totals 609950.00 23625.00 128328.36 21.0

CountyHARRIS
Highway SH0225
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6271-49-001
Proj ID RMC - 627149001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 699600.00 19052.67 183558.62 26.2
Work Order 00-00-00
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 238
Percent Time Used 32
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6271-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144207
Totals 699600.00 19052.67 183558.62 26.2

CountyHARRIS
Highway BU0290H
From WALLER C/L
To WEST OF BADTKE ROAD
CSJ 6271-71-001
Proj ID RMC - 627171001
Work Type PLN, SL CT, THIN O - L MIX (TOM) , PV MRK
 
5.635 1675064.21 0.00 1956145.46 100.0
Work Order 07-07-14
Work Began 07-08-14
Work Completed 03-03-15
Time Computed 07-07-14
Contract Working Days 45
Addl Days Granted 7
Working Days Charged 50
Percent Time Used 96
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6271-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05144024
Totals 1675064.21 0.00 1956145.46 100.0

CountyGALVESTON
Highway SH0275
From 1.238 MI WEST OF 51ST ST.
To 0.2 MI WEST OF 51ST ST.
CSJ 6271-72-001
Proj ID RMC - 627172001
Work Type ACP OVERLAY
 
2.423 844959.99 0.00 1153496.46 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-25-14
Work Began 07-23-14
Work Completed 11-03-14
Time Computed 07-09-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 100
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6271-72-001
BATTERSON,LLP(7.12%)
Contract # 05144025
Totals 844959.99 0.00 1153496.46 100.0

CountyHARRIS
Highway SH0225
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6271-91-001
Proj ID RMC - 627191001
Work Type FULL DEPTH CONCRETE REPAIR
 
0.001 1133300.00 0.00 623171.47 54.9
Work Order 00-00-00
Work Began 08-21-14
Work Completed  
Time Computed 08-21-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 218
Percent Time Used 29
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-91-001
SCR CONSTRUCTION CO., INC. ( 29.55%)
Contract # 06144206
Totals 1133300.00 0.00 623171.47 54.9

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6271-97-001
Proj ID RMC - 627197001
Work Type FULL DEPTH CONCRETE REPAIR & MISC CONC
 
0.001 864550.00 45050.28 189539.95 21.9
Work Order 09-25-14
Work Began 10-01-14
Work Completed  
Time Computed 10-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 176
Percent Time Used 48
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144014
Totals 864550.00 45050.28 189539.95 21.9

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6272-65-001
Proj ID RMC - 627265001
Work Type CRACK & SPALL REPAIR
 
0.001 474200.00 0.00 296562.35 62.5
Work Order 11-19-14
Work Began 11-23-14
Work Completed  
Time Computed 11-23-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 123
Percent Time Used 16
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144205
Totals 474200.00 0.00 296562.35 62.5

CountyHARRIS
Highway US0059
From VARIOUS HWYS IN NORTH HARRIS COUNTY
To VARIOUS HWYS IN NORTH HARRIS COUNTY
CSJ 6272-77-001
Proj ID RMC - 627277001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 447413.00 25400.00 147650.00 33.0
Work Order 10-13-14
Work Began 10-20-14
Work Completed  
Time Computed 10-20-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 152
Percent Time Used 41
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08144201
Totals 447413.00 25400.00 147650.00 33.0

CountyFORT BEND
Highway SH0006
From 500' SOUTH OF VOSS ROAD
To 0.56 MILE NORTH OF US 90A
CSJ 6272-84-001
Proj ID RMC - 627284001
Work Type BASE REPAIR, PFC OVERLAY AND PAV MRKS
 
1.477 878488.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 03-02-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6272-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10144203
Totals 878488.96 0.00 0.00 0.0

CountyHARRIS
Highway SH0249
From VARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
To VARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
CSJ 6272-85-001
Proj ID RMC - 627285001
Work Type FULL DEPTH CONCRETE & ASPHALT REPAIR
 
0.001 781855.00 37751.50 163661.11 20.9
Work Order 01-15-15
Work Began 01-21-15
Work Completed  
Time Computed 01-22-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 15
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6272-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10144204
Totals 781855.00 37751.50 163661.11 20.9

CountyFORT BEND
Highway US0059
From VARIOUS HWYS IN FORT BEND COUNTY
To VARIOUS HWYS IN FORT BEND COUNTY
CSJ 6273-27-001
Proj ID RMC - 627327001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 679268.00 56357.20 196357.20 28.9
Work Order 10-23-14
Work Began 11-01-14
Work Completed  
Time Computed 11-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 117
Percent Time Used 32
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6273-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09144202
Totals 679268.00 56357.20 196357.20 28.9

CountyHARRIS
Highway SL0008
From VARIOUS HWYS IN SOUTH HARRIS
To VARIOUS HWYS IN SOUTH HARRIS
CSJ 6273-69-001
Proj ID RMC - 627369001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 889700.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6273-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03154205
Totals 889700.00 0.00 0.00 0.0

CountyHARRIS
Highway SH0146
From SH 146 S/BOUND ENTRANCE & EXIT RAMPS
To AT WHARTON WEEMS
CSJ 6273-74-001
Proj ID RMC - 627374001
Work Type CONCRETE PAVEMENT AND PVMT. MARKINGS
 
0.001 617660.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6273-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04154023
Totals 617660.95 0.00 0.00 0.0

CountyWALLER
Highway US0290
From VARIOUS HWYS IN WALLER COUNTY
To VARIOUS HWYS IN WALLER COUNTY
CSJ 6273-98-001
Proj ID RMC - 627398001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 513125.00 44280.00 294332.24 57.3
Work Order 11-03-14
Work Began 11-03-14
Work Completed  
Time Computed 11-03-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 39
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6273-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09144002
Totals 513125.00 44280.00 294332.24 57.3

CountyFORT BEND
Highway FM1952
From AUSTIN COUNTY LINE
To FM 1489
CSJ 6274-32-001
Proj ID RMC - 627432001
Work Type BASE REPAIR, ACP OVERLAY & PAV MARKINGS
 
5.596 939544.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6274-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154202
Totals 939544.85 0.00 0.00 0.0

CountyWALLER
Highway US0290
From VARIOUS HIGHWAYS IN WALLER COUNTY
To VARIOUS HIGHWAYS IN WALLER COUNTY
CSJ 6274-48-001
Proj ID RMC - 627448001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 484750.00 45250.00 129050.00 26.6
Work Order 11-05-14
Work Began 11-10-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 141
Percent Time Used 38
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6274-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09144203
Totals 484750.00 45250.00 129050.00 26.6