Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway IH0045
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6177-39-001
Proj ID RMC - 617739001
Work Type SPALL REPAIR
 
0.001 110820.00 0.00 58113.78 52.4
Work Order 06-09-08
Work Began 06-09-08
Work Completed  
Time Computed 06-09-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 175
Percent Time Used 47
Contractor(s)
CLEANSERVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6177-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05081205
Totals 110820.00 0.00 58113.78 52.4

CountyWALLER
Highway US0290
From VARIOUS HIGHWAYS IN WALLER COUNTY
To VARIOUS HIGHWAYS IN WALLER COUNTY
CSJ 6177-56-001
Proj ID RMC - 617756001
Work Type PUMP STATION CLEANING
 
0.100 77550.00 0.00 2686.00 3.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-08
Work Began 07-01-08
Work Completed  
Time Computed 07-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 41
Contractor(s)
CLEANSERVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6177-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05081206
Totals 77550.00 0.00 2686.00 3.4

CountyHARRIS
Highway FM0529
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6177-69-001
Proj ID RMC - 617769001
Work Type CRACK SEAL
 
0.001 179000.00 0.00 34547.36 19.3
Work Order 08-26-08
Work Began 10-01-08
Work Completed  
Time Computed 09-01-08
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
AUSTIMPACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6177-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05081207
Totals 179000.00 0.00 34547.36 19.3

CountyMONTGOMERY
Highway IH0045
From VARIOUS HWYS IN MONTGOMERY COUNTY
To VARIOUS HWYS IN MONTGOMERY COUNTY
CSJ 6177-75-001
Proj ID SUP - 617775001
Work Type LITTER REMOVAL
 
0.001 536828.61 44899.22 188862.00 35.1
Work Order 08-01-08
Work Began 08-01-08
Work Completed  
Time Computed 08-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6177-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081231
Totals 536828.61 44899.22 188862.00 35.1

CountyWALLER
Highway US0290
From VARIOUS HWYS IN WALLER COUNTY
To VARIOUS HWYS IN WALLER COUNTY
CSJ 6178-05-001
Proj ID RMC - 617805001
Work Type ASPHALT PAVMENT REPAIR
 
0.001 330850.00 0.00 60239.52 20.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-08
Work Began 10-27-08
Work Completed  
Time Computed 07-23-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 131
Percent Time Used 35
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6178-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05081208
Totals 330850.00 0.00 60239.52 20.5

CountyWALLER
Highway FM1488
From WALLER MAINTENANCE OFFICE
To WALLER MAINTENANCE OFFICE
CSJ 6178-08-001
Proj ID SUP - 617808001
Work Type LANDSCAPE MAINTENANCE
 
0.001 35382.06 0.00 3666.97 13.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-08
Work Began 07-23-08
Work Completed  
Time Computed 07-01-08
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 20
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6178-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06081230
Totals 35382.06 0.00 3666.97 13.3

CountyWALLER
Highway IH0010
From VARIOUS ROADWAYS IN WALLER COUNTY
To VARIOUS ROADWAYS IN WALLER COUNTY
CSJ 6178-09-001
Proj ID SUP - 617809001
Work Type LITTER PICKUP & DISPOSAL
 
0.001 126571.04 0.00 44208.08 45.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-30-08
Work Began 06-09-08
Work Completed  
Time Computed 06-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 50
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6178-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04081230
Totals 126571.04 0.00 44208.08 45.8

CountyWALLER
Highway US0290
From VARIOUS HIGHWAYS IN WALLER COUNTY
To VARIOUS HIGHWAYS IN WALLER COUNTY
CSJ 6178-14-001
Proj ID RMC - 617814001
Work Type REFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.001 128038.60 0.00 3684.83 2.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-08
Work Began 08-25-08
Work Completed  
Time Computed 08-25-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 26
Contractor(s)
BATTERSON, L.L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6178-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081205
Totals 128038.60 0.00 3684.83 2.8

CountyWALLER
Highway IH0010
From VARIOUS HIGHWAYS IN WALLER COUNTY
To VARIOUS HIGHWAYS IN WALLER COUNTY
CSJ 6178-15-001
Proj ID RMC - 617815001
Work Type CLEANING & SWEEPING HIGHWAYS
 
0.001 239880.00 0.00 14090.00 8.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-26-08
Work Began 09-23-08
Work Completed  
Time Computed 09-09-08
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 11
Contractor(s)
AUSTIMPACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6178-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081206
Totals 239880.00 0.00 14090.00 8.6

CountyFORT BEND
Highway SH0036
From AT FORT BEND AREA OFFICE
To AT FORT BEND AREA OFFICE
CSJ 6178-16-001
Proj ID RMC - 617816001
Work Type JANITORIAL MAINTENANCE
 
0.001 67400.00 2175.00 5950.00 8.8
Work Order 10-01-08
Work Began 10-01-08
Work Completed  
Time Computed 10-01-08
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 8
Contractor(s)
THE ORGANIZED MAINTENANCE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6178-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08081202
Totals 67400.00 2175.00 5950.00 8.8

CountyWALLER
Highway US0290
From VARIOUS HIGHWAYS IN WALLER COUNTY
To VARIOUS HIGHWAYS IN WALLER COUNTY
CSJ 6178-19-001
Proj ID RMC - 617819001
Work Type GUARDRAIL REPAIR
 
0.001 256748.50 0.00 0.00 1.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-20-08
Work Began 11-20-08
Work Completed  
Time Computed 11-20-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 3
Contractor(s)
JMHP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6178-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10081211
Totals 256748.50 0.00 0.00 1.8

CountyBRAZORIA
Highway SH0288
From VARIOUS HWYS IN BRAZORIA COUNTY
To VARIOUS HWYS IN BRAZORIA COUNTY
CSJ 6178-85-001
Proj ID RMC - 617885001
Work Type CLEANING AND SEALING JOINTS AND CRACKS
 
0.001 239999.06 0.00 58572.80 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-27-08
Work Began 10-27-08
Work Completed  
Time Computed 10-27-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 9
Contractor(s)
KUNTZ CONTRACTING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6178-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10081212
Totals 239999.06 0.00 58572.80 99.9

CountyBRAZORIA
Highway SH0035
From VARIOUS HWYS IN BRAZORIA COUNTY
To VARIOUS HWYS IN BRAZORIA COUNTY
CSJ 6178-86-001
Proj ID RMC - 617886001
Work Type PUMP STATION & DRAINAGE SYS CLN
 
0.001 157050.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLEANSERVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6178-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10081213
Totals 157050.00 0.00 0.00 0.0

CountyHARRIS
Highway IH0610
From CENTRAL HOUSTON MAINTENANCE OFFICE
To .
CSJ 6178-87-001
Proj ID SUP - 617887001
Work Type BLDG. JANITORIAL & LANDSCAPE MAINT. SVCS
 
1.000 12962.29 1692.66 9644.60 74.4
Work Order 07-01-08
Work Began 07-01-08
Work Completed  
Time Computed 07-01-08
Contract Working Days 184
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
ON OUR OWN SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6178-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05081230
Totals 12962.29 1692.66 9644.60 74.4

CountyGALVESTON
Highway IH0045
From VARIOUS HWYS IN GALVESTON COUNTY
To VARIOUS HWYS IN GALVESTON COUNTY
CSJ 6179-12-001
Proj ID RMC - 617912001
Work Type FULL DEPTH REPAIR
 
0.001 227550.00 0.00 51674.34 22.7
Work Order 09-03-08
Work Began 10-01-08
Work Completed  
Time Computed 09-03-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 24
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6179-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081207
Totals 227550.00 0.00 51674.34 22.7

CountyGALVESTON
Highway IH0045
From VARIOUS HWYS IN GALVESTON COUNTY
To VARIOUS HYWS IN GALVESTON COUNTY
CSJ 6179-16-001
Proj ID RMC - 617916001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 269270.00 25117.60 45580.00 16.9
Work Order 08-25-08
Work Began 09-09-08
Work Completed  
Time Computed 09-07-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 85
Percent Time Used 23
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6179-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081208
Totals 269270.00 25117.60 45580.00 16.9

CountyFORT BEND
Highway US0059
From VARIOUS HWYS IN FORT BEND COUNTY
To VARIOUS HWYS IN FORT BEND COUNTY
CSJ 6179-67-001
Proj ID RMC - 617967001
Work Type REFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.001 187915.00 6394.00 6394.00 3.4
Work Order 09-08-08
Work Began 09-08-08
Work Completed  
Time Computed 09-08-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 23
Contractor(s)
HIGHWAY TECHNOLOGIES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6179-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081209
Totals 187915.00 6394.00 6394.00 3.4

CountyMONTGOMERY
Highway IH0045
From VARIOUS HWYS IN MONTGOMERY COUNTY
To VARIOUS HWYS IN MONTGOMERY COUNTY
CSJ 6179-72-001
Proj ID RMC - 617972001
Work Type PUMP STATION & DRAINAGE SYSTEM CLEANING
 
0.001 76200.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-18-08
Work Began 00-00-00
Work Completed  
Time Computed 12-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLEANSERVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6179-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10081214
Totals 76200.00 0.00 0.00 0.0

CountyHARRIS
Highway IH0045
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6180-20-001
Proj ID RMC - 618020001
Work Type GUARDRAIL / ATTENUATOR REPAIR
 
0.001 166507.00 0.00 36027.00 26.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-26-08
Work Began 09-02-08
Work Completed  
Time Computed 09-02-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 24
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6180-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081210
Totals 166507.00 0.00 36027.00 26.1

CountyHARRIS
Highway IH0045
From IH 45 N. FROM WEST RD TO RANKIN RD
To BW 8 N. FROM VET. MEM. TO HARDY RD
CSJ 6180-22-001
Proj ID RMC - 618022001
Work Type LITTER REMOVAL AND MOWING
 
0.001 55254.00 0.00 8470.00 24.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-18-08
Work Began 08-25-08
Work Completed  
Time Computed 08-25-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 26
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6180-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081211
Totals 55254.00 0.00 8470.00 24.8