Monthly Local Let Maintenance Report For Houston District As Of Jan 11, 2017 Page 3 Of 8

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6283-16-001
Proj IDRMC - 628316001
Work TypePUMP STA & DRAINAGE SYS CLN
 
0.001268420.00271870.75100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-30-15
Work Began07-01-15
Work Completed07-01-16
Time Computed07-01-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
CLEAN SERVE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6283-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04151203
Totals268420.000.00271870.75100.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6283-17-001
Proj IDRMC - 628317001
Work TypeREFL PAV MRK (GRAPHICS)
 
0.001301088.00169154.10100.0
Work Order00-00-00
Work Began08-03-15
Work Completed08-15-16
Time Computed08-03-15
Contract Working Days365
Addl Days Granted6
Working Days Charged371
Percent Time Used100
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04151204
Totals301088.0029817.08169154.10100.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6283-62-001
Proj IDRMC - 628362001
Work TypeDITCH CLEANING AND RESHAPING
 
0.001248850.00265659.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-15-15
Work Began07-15-15
Work Completed12-28-15
Time Computed07-16-15
Contract Working Days366
Addl Days Granted0
Working Days Charged166
Percent Time Used45
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151204
Totals248850.000.00265659.50100.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS IN S BRAZORIA COUNTY
ToVARIOUS HWYS IN S BRAZORIA COUNTY
CSJ6283-96-001
Proj IDRMC - 628396001
Work TypeMOWING HIGHWAY ROW (S STATE)
 
0.001311443.49562227.2599.9
Work Order00-00-00
Work Began08-12-15
Work Completed
Time Computed08-12-15
Contract Working Days111
Addl Days Granted167
Working Days Charged177
Percent Time Used63
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151205
Totals311443.49140699.29562227.2599.9

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS IN N BRAZORIA COUNTY
ToVARIOUS HWYS IN N BRAZORIA COUNTY
CSJ6284-01-001
Proj IDRMC - 628401001
Work TypeMOWING HIGHWAY ROW (NORTH)
 
0.001344159.74317964.7592.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-30-15
Work Began07-06-15
Work Completed
Time Computed07-06-15
Contract Working Days145
Addl Days Granted18
Working Days Charged119
Percent Time Used73
Contractor(s)
RELIANT SAND AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04151205
Totals344159.740.00317964.7592.7

CountyBRAZORIA
HighwayFM0521
FromVARIOUS FM ROADS IN BRAZORIA COUNTY
ToVARIOUS FM ROADS IN BRAZORIA COUNTY
CSJ6284-02-001
Proj IDRMC - 628402001
Work TypeMOWING HIGHWAY ROW (S FMS)
 
0.001216224.930.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed09-28-15
Contract Working Days71
Addl Days Granted0
Working Days Charged1
Percent Time Used1
Contractor(s)
OSI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6284-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151201
Totals216224.930.000.000.0

CountyGALVESTON
HighwaySH0087
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6284-37-001
Proj IDRMC - 628437001
Work TypeMOWING HWY RIGHT-OF-WAY
 
0.001249459.60483905.8499.9
Work Order05-28-15
Work Began06-01-15
Work Completed
Time Computed06-01-15
Contract Working Days80
Addl Days Granted80
Working Days Charged139
Percent Time Used86
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04151206
Totals249459.600.00483905.8499.9

CountyBRAZORIA
HighwaySH288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6284-87-001
Proj IDRMC - 628487001
Work TypeREFL PAV MRKS (LONG LINE)
 
0.001319717.80371494.54100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-03-15
Work Completed08-09-16
Time Computed08-03-15
Contract Working Days365
Addl Days Granted30
Working Days Charged371
Percent Time Used93
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6284-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04151209
Totals319717.800.00371494.54100.0

CountyMONTGOMERY
HighwayIH0069
FromVARIOUS ROADWAYS IN MONTGOMERY COUNTY
ToVARIOUS ROADWAYS IN MONTGOMERY COUNTY
CSJ6285-50-001
Proj IDRMC - 628550001
Work TypeTREE TRIMMING, UNDERBRUSH, AND
 
0.001213800.00181950.0085.1
Work Order03-29-16
Work Began03-29-16
Work Completed
Time Computed03-29-16
Contract Working Days366
Addl Days Granted0
Working Days Charged274
Percent Time Used74
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6285-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161201
Totals213800.000.00181950.0085.1

CountyMONTGOMERY
HighwayFM3083
From901 N. FM 3083
To.
CSJ6285-55-001
Proj IDSUP - 628555001
Work TypeJANITORIAL MAINTENANCE
 
0.00134400.0014000.0040.6
Work Order07-31-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged149
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
ODJ INC. "OUR SPECIALTY HELPING OTHERS IN NEED"
SUBCONTRACTOR(S) FOR CCSJ: 6285-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161232
Totals34400.002700.0014000.0040.6

CountyWALLER
HighwayUS0290
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6285-97-001
Proj IDRMC - 628597001
Work TypeTREE AND BRUSH REMOVAL
 
0.00195350.00102270.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-24-15
Work Began07-28-15
Work Completed
Time Computed07-20-15
Contract Working Days366
Addl Days Granted0
Working Days Charged365
Percent Time Used99
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151208
Totals95350.000.00102270.0099.9

CountyGALVESTON
HighwaySH0087
FromGALVESTON-PORT BOLIVAR FERRY OPERATION
ToGALVESTON-PORT BOLIVAR FERRY OPERATION
CSJ6286-82-001
Proj IDSUP - 628682001
Work TypeJANITORIAL SERVICES
 
0.010142674.00148567.3299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
SOUTHEAST KELLER CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6286-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151231
Totals142674.000.00148567.3299.9

CountyMONTGOMERY
HighwayFM3083
FromMONTGOMERY AREA/MAINTENANCE OFFICE
ToMONTGOMERY AREA/MAINTENANCE OFFICE
CSJ6286-84-001
Proj IDSUP - 628684001
Work TypeLANDSCAPE MAINTENANCE
 
0.00117969.2610021.8355.7
Work Order06-01-16
Work Began05-17-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged210
Percent Time Used57
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161232
Totals17969.261431.6910021.8355.7

CountyMONTGOMERY
HighwayIH0069
FromVARIOUS HWYS IN MONTGOMERY COUNTY
ToVARIOUS HWYS IN MONTGOMERY COUNTY
CSJ6287-25-001
Proj IDSUP - 628725001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.001288263.35304480.08100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-15
Work Began08-01-15
Work Completed07-31-16
Time Computed08-01-15
Contract Working Days366
Addl Days Granted0
Working Days Charged362
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151232
Totals288263.350.00304480.08100.0

CountyGALVESTON
HighwaySH0146
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6288-02-001
Proj IDRMC - 628802001
Work TypeGUARDRAIL REPAIR
 
0.001176409.00211964.1199.9
Work Order09-02-15
Work Began09-03-15
Work Completed
Time Computed09-02-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151205
Totals176409.000.00211964.1199.9

CountyHARRIS
HighwayUS0059
FromNORTH HARRIS AREA OFFICE
ToNORTH HARRIS AREA OFFICE
CSJ6288-48-001
Proj IDSUP - 628848001
Work TypeLANDSCAPE MAINTENANCE
 
0.00122335.0022335.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-31-15
Work Began08-01-15
Work Completed
Time Computed08-01-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
THE TEXAS HOUSE
SUBCONTRACTOR(S) FOR CCSJ: 6288-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151231
Totals22335.000.0022335.0099.9

CountyWALLER
HighwayIH0010
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6289-46-001
Proj IDSUP - 628946001
Work TypeLITTER REMOVAL
 
0.001128365.11114362.5189.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-15
Work Began06-01-15
Work Completed
Time Computed06-01-15
Contract Working Days366
Addl Days Granted0
Working Days Charged358
Percent Time Used97
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6289-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151233
Totals128365.110.00114362.5189.0

CountyFORT BEND
HighwaySH0036
FromFORT BEND AREA OFFICE
ToFORT BEND AREA OFFICE
CSJ6289-58-001
Proj IDSUP - 628958001
Work TypeLANDSCAPE MAINTENANCE
 
0.00118154.2517340.0095.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-08-15
Work Completed
Time Computed09-01-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6289-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151230
Totals18154.250.0017340.0095.5

CountyWALLER
HighwayFM1488
FromVARIOUS ROADWAYS IN WALLER COUNTY
ToVARIOUS ROADWAYS IN WALLER COUNTY
CSJ6289-65-001
Proj IDRMC - 628965001
Work TypeDELINEATOR, OBJ MRKR AND MAILBOXES
 
0.001191052.00167031.0087.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-02-15
Work Began02-10-16
Work Completed
Time Computed11-09-15
Contract Working Days366
Addl Days Granted0
Working Days Charged318
Percent Time Used86
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6289-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151202
Totals191052.000.00167031.0087.4

CountyBRAZORIA
HighwaySH0006
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6290-01-001
Proj IDRMC - 629001001
Work TypeJOINT AND CRACK SEAL
 
0.001185068.76196630.52100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-08-15
Work Began11-09-15
Work Completed01-27-16
Time Computed11-09-15
Contract Working Days66
Addl Days Granted0
Working Days Charged19
Percent Time Used28
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6290-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151204
Totals185068.760.00196630.52100.0