Monthly Local Let Maintenance Report For Houston District As Of Dec 10, 2014 Page 1 Of 6

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBRAZORIA
Highway SH0288
From VARIOUS HWYS IN BRAZORIA COUNTY
To VARIOUS HWYS IN BRAZORIA COUNTY
CSJ 6225-76-001
Proj ID RMC - 622576001
Work Type CLEANING & SWEEPING HIGHWAYS
 
0.001 236986.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ADENVIRON LLC
SUBCONTRACTOR(S) FOR CCSJ: 6225-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07111202
Totals 236986.98 0.00 0.00 0.0

CountyHARRIS
Highway SH0225
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6243-92-001
Proj ID RMC - 624392001
Work Type CLEANING AND SEALING JOINTS AND CRACKS
 
0.001 711300.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6243-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131201
Totals 711300.00 0.00 0.00 0.0

CountyWALLER
Highway US0290
From VARIOUS HIGHWAYS IN WALLER COUNTY
To VARIOUS HIGHWAYS IN WALLER COUNTY
CSJ 6244-26-001
Proj ID RMC - 624426001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 198000.00 24200.00 219700.00 100.0
Work Order 10-30-12
Work Began 11-02-12
Work Completed 10-31-14
Time Computed 11-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 729
Percent Time Used 99
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6244-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08121205
Totals 198000.00 24200.00 219700.00 100.0

CountyHARRIS
Highway SH0288
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6249-75-001
Proj ID RMC - 624975001
Work Type ROADSIDE MOWING
 
0.001 226417.63 28525.42 195101.66 86.1
Work Order 04-08-13
Work Began 05-20-13
Work Completed  
Time Computed 05-20-13
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 81
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12121203
Totals 226417.63 28525.42 195101.66 86.1

CountyWALLER
Highway FM1488
From VARIOUS ROADWAYS IN WALLER COUNTY
To VARIOUS ROADWAYS IN WALLER COUNTY
CSJ 6250-11-001
Proj ID RMC - 625011001
Work Type DELINEATOR, OBJ MRKR & MAILBOXES
 
0.001 201145.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
QUALLS SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6250-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01131204
Totals 201145.00 0.00 0.00 0.0

CountyGALVESTON
Highway SH0146
From 0.804 MI NORTH OF LP 197
To 0.274 MI NORTH OF LP 197
CSJ 6251-09-001
Proj ID RMC - 625109001
Work Type DRAINAGE CONSTRUCTION
 
0.804 118994.81 0.00 110014.81 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-09-14
Work Began 08-01-14
Work Completed 09-09-14
Time Computed 07-21-14
Contract Working Days 19
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 42
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-09-001
BATTERSON,LLP(8.20%)
Contract # 03141201
Totals 118994.81 0.00 110014.81 100.0

CountyBRAZORIA
Highway SH0288
From VARIOUS HWYS IN N BRAZORIA COUNTY
To VARIOUS HWYS IN N BRAZORIA COUNTY
CSJ 6252-89-001
Proj ID RMC - 625289001
Work Type MOWING HIGHWAY ROW (NORTH)
 
0.001 255382.57 41644.95 247522.57 96.9
Work Order 07-01-13
Work Began 07-15-13
Work Completed  
Time Computed 07-15-13
Contract Working Days 131
Addl Days Granted 3
Working Days Charged 102
Percent Time Used 76
Contractor(s)
CIRCLE H MOWING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131202
Totals 255382.57 41644.95 247522.57 96.9

CountyBRAZORIA
Highway FM2004
From VARIOUS FM ROADS IN BRAZORIA COUNTY
To VARIOUS FM ROADS IN BRAZORIA COUNTY
CSJ 6252-90-001
Proj ID RMC - 625290001
Work Type MOWING HIGHWAY ROW (S FMS)
 
0.001 276552.90 0.00 129401.59 49.1
Work Order 07-01-13
Work Began 07-01-13
Work Completed  
Time Computed 07-15-13
Contract Working Days 142
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 52
Contractor(s)
CIRCLE H MOWING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131203
Totals 276552.90 0.00 129401.59 49.1

CountyHARRIS
Highway US0059
From VARIOUS HWYS IN NORTH HARRIS AREA
To VARIOUS HWYS IN NORTH HARRIS AREA
CSJ 6253-43-001
Proj ID RMC - 625343001
Work Type ROADSIDE MOWING
 
0.001 126716.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PARRA INVESTMENTS
SUBCONTRACTOR(S) FOR CCSJ: 6253-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03131204
Totals 126716.64 0.00 0.00 0.0

CountyHARRIS
Highway SH0225
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6253-77-001
Proj ID RMC - 625377001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 270857.08 41165.28 127108.31 46.9
Work Order 03-28-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 158
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 31
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131203
Totals 270857.08 41165.28 127108.31 46.9

CountyWALLER
Highway US0290
From VARIOUS ROADWAYS IN WALLER COUNTY
To VARIOUS ROADWAYS IN WALLER COUNTY
CSJ 6253-88-001
Proj ID RMC - 625388001
Work Type MOWING RIGHT OF WAY
 
0.001 256581.87 27386.19 273588.72 100.0
Work Order 05-22-13
Work Began 06-04-13
Work Completed 11-08-14
Time Computed 05-30-13
Contract Working Days 169
Addl Days Granted 0
Working Days Charged 97
Percent Time Used 57
Contractor(s)
BEN E. SMITH TRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131205
Totals 256581.87 27386.19 273588.72 100.0

CountyGALVESTON
Highway SH0087
From VARIOUS HWYS IN GALVESTON COUNTY
To VARIOUS HWYS IN GALVESTON COUNTY
CSJ 6253-89-001
Proj ID RMC - 625389001
Work Type MOWING HWY RIGHT - OF - WAY
 
0.001 266708.85 0.00 222720.41 83.5
Work Order 05-21-13
Work Began 06-03-13
Work Completed  
Time Computed 06-03-13
Contract Working Days 121
Addl Days Granted 0
Working Days Charged 119
Percent Time Used 98
Contractor(s)
CIRCLE H MOWING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131206
Totals 266708.85 0.00 222720.41 83.5

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6254-12-001
Proj ID RMC - 625412001
Work Type HERBICIDE
 
0.001 74970.00 0.00 53043.51 70.7
Work Order 06-17-13
Work Began 06-24-13
Work Completed  
Time Computed 06-24-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 516
Percent Time Used 70
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6254-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03131205
Totals 74970.00 0.00 53043.51 70.7

CountyHARRIS
Highway US0059
From NORTH HARRIS AREA OFFICE
To NORTH HARRIS AREA OFFICE
CSJ 6255-17-001
Proj ID SUP - 625517001
Work Type LANDSCAPE MAINTENANCE
 
0.001 22335.00 0.00 22335.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-24-13
Work Began 08-01-13
Work Completed  
Time Computed 08-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
THE TEXAS HOUSE
SUBCONTRACTOR(S) FOR CCSJ: 6255-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131231
Totals 22335.00 0.00 22335.00 99.9

CountyFORT BEND
Highway US0059
From VARIOUS HWYS IN FORT BEND COUNTY
To VARIOUS HWYS IN FORT BEND COUNTY
CSJ 6255-32-001
Proj ID RMC - 625532001
Work Type CONCRETE SPALL REPAIR
 
0.001 170050.00 0.00 214612.20 99.9
Work Order 02-01-14
Work Began 02-01-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 295
Percent Time Used 80
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6255-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131201
Totals 170050.00 0.00 214612.20 99.9

CountyMONTGOMERY
Highway US0059
From MONTGOMERY COUNTY AREA ENGINEER AND
To MAINTENANCE OFFICE
CSJ 6255-45-001
Proj ID SUP - 625545001
Work Type JANITORIAL MAINTENANCE
 
0.001 17423.16 0.00 17423.16 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-29-13
Work Began 11-01-13
Work Completed 10-31-14
Time Computed 11-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6255-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131231
Totals 17423.16 0.00 17423.16 100.0

CountyGALVESTON
Highway SH0087
From GALVESTON-PORT BOLIVAR FERRY OPERATION
To GALVESTON-PORT BOLIVAR FERRY OPERATION
CSJ 6256-64-001
Proj ID SUP - 625664001
Work Type JANITORIAL MAINTENANCE
 
0.001 141480.00 0.00 143220.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-13
Work Began 09-01-13
Work Completed 09-02-14
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
SOUTHEAST KELLER CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6256-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131231
Totals 141480.00 0.00 143220.00 100.0

CountyHARRIS
Highway IH0010
From 7600 WASHINGTON AVE
To 6810 OLD KATY ROAD
CSJ 6257-02-001
Proj ID SUP - 625702001
Work Type BLDG & GROUNDS MAINT, OPERATION & REPAIR
 
0.010 1554621.60 0.00 1040557.49 66.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-01-13
Work Began 06-01-13
Work Completed  
Time Computed 06-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 518
Percent Time Used 70
Contractor(s)
TIBH INDUSTRIES, INC.
ON OUR OWN SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131233
Totals 1554621.60 0.00 1040557.49 66.9

CountyHARRIS
Highway US0059
From VARIOUS HWYS IN NORTH HARRIS COUNTY
To VARIOUS HWYS IN NORTH HARRIS COUNTY
CSJ 6258-10-001
Proj ID RMC - 625810001
Work Type ROADSIDE MOWING
 
0.001 182155.17 2599.93 89269.49 49.0
Work Order 10-22-13
Work Began 10-28-13
Work Completed  
Time Computed 10-28-13
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 60
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131202
Totals 182155.17 2599.93 89269.49 49.0

CountyHARRIS
Highway IH0010
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6258-28-001
Proj ID SUP - 625828001
Work Type LITTER REMOVAL
 
0.001 228901.83 14179.34 219076.63 95.7
CountyHARRIS
Highway IH0010
From  
To  
CSJ 6258-28-002
Proj ID SUP - 625828001
Work Type LITTER REMOVAL
 
0.001 0.00 0.00 0.00 0.0
Work Order 12-13-13
Work Began 12-10-13
Work Completed  
Time Computed 12-13-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 347
Percent Time Used 95
Contractor(s)
TIBH INDUSTRIES, INC.
THE TEXAS HOUSE
SUBCONTRACTOR(S) FOR CCSJ: 6258-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131230
Totals 228901.83 14179.34 219076.63 95.7