Monthly Local Let Maintenance Report For Fort Worth District As Of Apr 10, 2017 Page 3 Of 5

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyERATH
HighwayUS0377
FromVARIOUS ROADWAYS IN ERATH, HOOD,
To& SOMERVELL COUNTIES
CSJ6294-01-001
Proj IDRMC - 629401001
Work TypeTREE & BRUSH TRIMMING/REMOVAL
 
0.010299500.0044310.0014.7
Work Order02-21-17
Work Began00-00-00
Work Completed
Time Computed02-28-17
Contract Working Days100
Addl Days Granted0
Working Days Charged11
Percent Time Used11
Contractor(s)
DIAMOND JK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160207
Totals299500.0044310.0044310.0014.7

CountyERATH
HighwayUS0377
FromVARIOUS ROADWAYS IN
ToERATH COUNTY
CSJ6294-98-001
Proj IDRMC - 629498001
Work TypeROADSIDE MOWING
 
0.010290282.52145037.7649.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-23-16
Work Began05-23-16
Work Completed
Time Computed05-30-16
Contract Working Days74
Addl Days Granted0
Working Days Charged23
Percent Time Used31
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150206
Totals290282.520.00145037.7649.9

CountyHOOD
HighwayUS0377
FromVARIOUS ROADWAYS IN HOOD AND
ToSOMERVELL COUNTIES
CSJ6294-99-001
Proj IDRMC - 629499001
Work TypeROADSIDE MOWING
 
0.010242961.36115920.2447.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-16
Work Began05-16-16
Work Completed
Time Computed05-23-16
Contract Working Days64
Addl Days Granted0
Working Days Charged60
Percent Time Used93
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150204
Totals242961.360.00115920.2447.7

CountyTARRANT
HighwayIH0030
FromIH 30 IN
ToSOUTH TARRANT COUNTY
CSJ6295-00-001
Proj IDRMC - 629500001
Work TypeBRIDGE PAINTING
 
0.010103589.1056351.1554.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-06-17
Work Began00-00-00
Work Completed
Time Computed03-13-17
Contract Working Days90
Addl Days Granted0
Working Days Charged10
Percent Time Used11
Contractor(s)
M & S CONCRETE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6295-00-001
DALLAS LITE AND BARRICADE, INC. (7.24)
Contract #12150201
Totals103589.100.0056351.1554.3

CountyWISE
HighwayUS0081
FromWISE & JACK COUNTY
ToMAINTENANCE OFFICES AND YARDS
CSJ6295-54-001
Proj IDSUP - 629554001
Work TypeGROUNDS MAINTENANCE
 
0.01022860.0033210.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-16
Work Began03-20-16
Work Completed
Time Computed03-22-16
Contract Working Days365
Addl Days Granted0
Working Days Charged222
Percent Time Used60
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6295-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150233
Totals22860.000.0033210.0099.9

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATION WITHIN PARKER &
ToPALO PINTO COUNTIES
CSJ6295-61-001
Proj IDSUP - 629561001
Work TypePICNIC_AREA MAINTENANCE
 
0.01071135.6268252.6095.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-01-16
Work Began01-01-16
Work Completed
Time Computed01-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6295-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150232
Totals71135.620.0068252.6095.9

CountyTARRANT
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6296-05-001
Proj IDRMC - 629605001
Work TypeFULL-WIDTH MOWING
 
0.010325410.30154247.7547.5
Work Order05-17-16
Work Began05-17-16
Work Completed
Time Computed05-24-16
Contract Working Days56
Addl Days Granted0
Working Days Charged26
Percent Time Used46
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150205
Totals325410.300.00154247.7547.5

CountyTARRANT
HighwayIH0035W
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6296-37-001
Proj IDRMC - 629637001
Work TypeCALL-OUT THERMO
 
0.010275156.50147732.6056.2
Work Order09-26-16
Work Began10-05-16
Work Completed
Time Computed10-03-16
Contract Working Days106
Addl Days Granted0
Working Days Charged46
Percent Time Used43
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160205
Totals275156.5022544.53147732.6056.2

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS IN PARKER, PALO PINTO,
ToAND ERATH COUNTIES
CSJ6296-63-001
Proj IDRMC - 629663001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010309572.40328834.9099.9
Work Order03-25-16
Work Began04-01-16
Work Completed
Time Computed04-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged222
Percent Time Used60
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150206
Totals309572.4023567.70328834.9099.9

CountyJACK
HighwayUS0380
FromVARIOUS ROADWAYS IN
ToJACK COUNTY
CSJ6297-09-001
Proj IDRMC - 629709001
Work TypeROADSIDE MOWING
 
0.010241384.05107280.5044.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-29-16
Work Began00-00-00
Work Completed
Time Computed07-07-16
Contract Working Days64
Addl Days Granted0
Working Days Charged44
Percent Time Used68
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150203
Totals241384.050.00107280.5044.4

CountyERATH
HighwayBU0377J
FromVARIOUS ROADWAYS IN ERATH, HOOD,
ToSOMERVELL, & PARKER COUNTIES
CSJ6297-14-001
Proj IDRMC - 629714001
Work TypeCALLOUT REFLECTORIZED PVMNT MRKS & MRKR
 
0.010184315.00118279.4064.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-13-16
Work Began09-13-16
Work Completed
Time Computed09-20-16
Contract Working Days53
Addl Days Granted0
Working Days Charged4
Percent Time Used7
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160206
Totals184315.000.00118279.4064.1

CountyJOHNSON
HighwaySH0174
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6297-54-001
Proj IDRMC - 629754001
Work TypeCALL OUT REFLEC PAV MRKGS & MRKRS
 
0.010264215.00132656.1550.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-28-16
Work Began09-27-16
Work Completed
Time Computed11-05-16
Contract Working Days86
Addl Days Granted0
Working Days Charged17
Percent Time Used19
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160203
Totals264215.000.00132656.1550.2

CountyPARKER
HighwayIH0020
FromWEATHERFORD/MINERAL WELLS OFFICES &
ToGORDON LOCATION
CSJ6298-59-001
Proj IDSUP - 629859001
Work TypeJANITORIAL & GROUNDS WORK MAINTENANCE
 
0.01063455.1255225.1287.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-25-16
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged360
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6298-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160231
Totals63455.120.0055225.1287.0

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6298-99-001
Proj IDSUP - 629899001
Work TypeLANDSCAPE MAINTENANCE
 
0.010105030.00105030.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-16
Work Began04-05-16
Work Completed
Time Computed04-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged53
Percent Time Used14
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6298-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160231
Totals105030.000.00105030.0099.9

CountyERATH
HighwayBU0377J
FromVARIOUS ROADWAYS IN ERATH, HOOD,
ToAND SOMERVELL COUNTIES
CSJ6299-81-001
Proj IDRMC - 629981001
Work TypeRUMBLE STRIP
 
0.010196000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09160201
Totals196000.000.000.000.0

CountyWISE
HighwayUS0380
FromVARIOUS LOCATIONS IN WISE AND JACK
ToCOUNTIES
CSJ6299-90-001
Proj IDRMC - 629990001
Work TypeGUARDRAIL INSTALLATION AND REPAIR
 
0.100347400.00104821.0030.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-31-16
Work Began00-00-00
Work Completed
Time Computed11-10-16
Contract Working Days365
Addl Days Granted0
Working Days Charged60
Percent Time Used16
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160201
Totals347400.000.00104821.0030.1

CountyWISE
HighwayUS0081
FromVARIOUS LOCATIONS IN
ToWISE COUNTY
CSJ6299-91-001
Proj IDRMC - 629991001
Work TypeDEBRIS REMOVAL
 
0.010194817.0055350.1028.4
Work Order07-19-16
Work Began07-26-16
Work Completed
Time Computed07-27-16
Contract Working Days180
Addl Days Granted0
Working Days Charged45
Percent Time Used25
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6299-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160202
Totals194817.003019.4555350.1028.4

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS IN
ToJOHNSON COUNTY
CSJ6300-67-001
Proj IDRMC - 630067001
Work TypeCLEANING & SHAPING DITCHES KEENE FY17
 
0.010243000.00193415.6579.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged34
Percent Time Used9
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160201
Totals243000.000.00193415.6579.5

CountyWISE
HighwayUS0380
FromVARIOUS LOCATIONS IN
ToWISE AND JACK COUNTIES
CSJ6300-87-001
Proj IDRMC - 630087001
Work TypeCRACKSEAL
 
0.100222933.28183512.4882.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-07-17
Work Began00-00-00
Work Completed
Time Computed02-14-17
Contract Working Days35
Addl Days Granted0
Working Days Charged16
Percent Time Used45
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160202
Totals222933.280.00183512.4882.3

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN PARKER
ToAND PALO PINTO COUNTIES
CSJ6301-31-001
Proj IDRMC - 630131001
Work TypeCALL OUT REFLEC PAV MRKGS PARKER
 
0.010255737.50134474.8052.5
Work Order07-11-16
Work Began07-17-16
Work Completed
Time Computed07-14-16
Contract Working Days89
Addl Days Granted0
Working Days Charged31
Percent Time Used34
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160206
Totals255737.5017466.95134474.8052.5