Monthly Local Let Maintenance Report For Fort Worth District As Of Jan 11, 2017 Page 2 Of 5

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayIH0035W
FromSPECIAL MAINTENANCE OFFICE
ToWAGGOMAN STREET
CSJ6277-97-001
Proj IDSUP - 627797001
Work TypeJANITORIAL MAINTENANCE
 
0.0108253.488253.4899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-15
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged337
Percent Time Used92
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6277-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04150232
Totals8253.480.008253.4899.9

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPARKER AND PALO PINTO COUNTIES
CSJ6280-89-001
Proj IDRMC - 628089001
Work TypeTREE & BRUSH TRIMMING/REMOVAL
 
0.010291850.00583700.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-23-15
Work Began11-30-15
Work Completed
Time Computed11-30-15
Contract Working Days150
Addl Days Granted31
Working Days Charged174
Percent Time Used96
Contractor(s)
FMWB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12140206
Totals291850.000.00583700.0099.9

CountyPALO PINTO
HighwayUS0180
FromVARIOUS ROADWAYS WITHIN PARKER
ToAND PALO PINTO COUNTIES
CSJ6280-90-001
Proj IDRMC - 628090001
Work TypeTREE REMOVAL
 
0.010263200.00544180.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-29-15
Work Began07-14-14
Work Completed
Time Computed07-06-15
Contract Working Days150
Addl Days Granted89
Working Days Charged199
Percent Time Used83
Contractor(s)
KASPARIAN UNDERGROUND, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6280-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12140205
Totals263200.000.00544180.0099.9

CountyTARRANT
HighwaySH0360
FromVARIOUS LOCATIONS WITHIN
ToNORTH TARRANT COUNTY
CSJ6281-46-001
Proj IDRMC - 628146001
Work TypeTREE & BRUSH TRIMMING/REMOVAL
 
0.100181715.00129677.0071.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-15
Work Began02-17-15
Work Completed
Time Computed02-23-15
Contract Working Days100
Addl Days Granted0
Working Days Charged41
Percent Time Used41
Contractor(s)
SMITH LAWN AND TREE
SUBCONTRACTOR(S) FOR CCSJ: 6281-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12140202
Totals181715.000.00129677.0071.3

CountyTARRANT
HighwayIH0820
FromIH 820/FM 156 AND IH 820 WB FTG RD @
ToSH 199 IN NORTH TARRANT COUNTY
CSJ6283-21-001
Proj IDRMC - 628321001
Work TypeASBESTOS ABATEMENT
 
0.01074331.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06150206
Totals74331.250.000.000.0

CountyTARRANT
HighwayIH0035W
FromVARIOUS ROADS WITHIN_SOUTH TARRANT
ToCOUNTY MAINTENENACE SECTION
CSJ6284-39-001
Proj IDRMC - 628439001
Work TypeCALL-OUT REFL PAV MRKS & MRKRS
 
0.010260825.00321595.3599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-15
Work Began08-05-15
Work Completed
Time Computed08-27-15
Contract Working Days102
Addl Days Granted11
Working Days Charged69
Percent Time Used61
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6284-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06150205
Totals260825.000.00321595.3599.9

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6285-32-001
Proj IDRMC - 628532001
Work TypeMAILBOX ASSEMBLIES
 
0.01038500.0041220.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-15
Work Began01-29-16
Work Completed
Time Computed12-21-15
Contract Working Days12
Addl Days Granted0
Working Days Charged5
Percent Time Used41
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6285-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09150201
Totals38500.000.0041220.0099.9

CountyTARRANT
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6286-28-001
Proj IDRMC - 628628001
Work TypeCLEANING & SEALIN JOINTS & CRACKS
 
0.010201132.006222.813.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-06-16
Work Began01-13-16
Work Completed
Time Computed01-13-16
Contract Working Days38
Addl Days Granted0
Working Days Charged5
Percent Time Used13
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150203
Totals201132.000.006222.813.0

CountyTARRANT
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6286-95-001
Proj IDRMC - 628695001
Work TypeFULL-DEPTH CONCRETE PAVAMENT REPAIR
 
0.010287066.60272153.6099.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-14-16
Work Began03-14-16
Work Completed
Time Computed03-21-16
Contract Working Days22
Addl Days Granted0
Working Days Charged43
Percent Time Used195
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6286-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150201
Totals287066.600.00272153.6099.1

CountyJOHNSON
HighwayFM0157
FromFM 157 IN
ToJOHNSON COUNTY
CSJ6287-59-001
Proj IDRMC - 628759001
Work TypeCULVERT REPLACEMENT
 
0.010285707.06551482.3399.9
Work Order07-13-15
Work Began07-20-15
Work Completed
Time Computed07-20-15
Contract Working Days43
Addl Days Granted60
Working Days Charged206
Percent Time Used200
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-59-001
DALLAS LITE AND BARRICADE INC. (9.67)
J & G CONCRETE PRODUCTS (5.50)
STRIPING TECHNOLOGY, L.P. (2.00)
THE TURNER CO. (2.10)
OLDCASTLE PRECAST INC. (BROOKS PRODUCTS) (1.93)
RATLIFF READY MIX (0.00)
APAC-TEXAS, INC. (0.00)
GSI HIGHWAY PRODUCTS (0.00)
GSI HIGHWAY PRODUCTS (2.55)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (11.15)
BICK"S CONSTRUCTION, INC. (0.00)
REED HYDROMULCHING, INC. (1.13)
Contract #05150201
Totals285707.060.00551482.3399.9

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6289-54-001
Proj IDRMC - 628954001
Work TypeRAISED PAVEMENT MARKERS
 
81.000265050.25203325.7578.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-15
Work Began12-14-15
Work Completed
Time Computed12-21-15
Contract Working Days38
Addl Days Granted0
Working Days Charged46
Percent Time Used121
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6289-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06150208
Totals265050.250.00203325.7578.4

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6289-88-001
Proj IDRMC - 628988001
Work TypeROADSIDE MOWING & HERBICIDE
 
0.010262978.8860862.2223.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-18-16
Work Began05-05-16
Work Completed
Time Computed10-25-16
Contract Working Days68
Addl Days Granted0
Working Days Charged53
Percent Time Used77
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6289-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150202
Totals262978.880.0060862.2223.1

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6289-89-001
Proj IDRMC - 628989001
Work TypeGUARDRAIL & MEDIAN CABLE REPAIR
 
0.010325690.00562083.5099.9
Work Order12-01-15
Work Began12-02-15
Work Completed
Time Computed12-08-15
Contract Working Days365
Addl Days Granted0
Working Days Charged354
Percent Time Used96
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150202
Totals325690.0041097.00562083.5099.9

CountyTARRANT
HighwayIH0020
FromFORT WORTH
ToDISTRICT COMPLEX
CSJ6291-17-001
Proj IDSUP - 629117001
Work TypeGROUNDS MAINTENANCE
 
0.01063628.1640583.3263.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged299
Percent Time Used81
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6291-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150237
Totals63628.160.0040583.3263.7

CountyWISE
HighwayUS0380
FromVARIOUS ROADWAYS IN WISE
ToAND JACK COUNTIES
CSJ6291-80-001
Proj IDRMC - 629180001
Work TypeCALL-OUT THERMO
 
0.010234520.00114156.0548.6
Work Order08-24-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days83
Addl Days Granted0
Working Days Charged13
Percent Time Used15
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160203
Totals234520.0059955.10114156.0548.6

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6291-83-001
Proj IDSUP - 629183001
Work TypeLITTER REMOVAL
 
0.010476530.57430406.0890.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began09-08-15
Work Completed
Time Computed09-08-15
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6291-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150232
Totals476530.570.00430406.0890.3

CountyHOOD
HighwayUS0377
FromLITTER REMOVAL IN VARIOUS ROADWAYS
ToWITHIN HOOD,SOMERVELL & ERATH COUNTIES
CSJ6291-84-001
Proj IDSUP - 629184001
Work TypeLITTER REMOVAL WITHIN HSE
 
0.010106883.87104604.1697.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged345
Percent Time Used94
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6291-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150231
Totals106883.870.00104604.1697.8

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS WITIN PARKER
ToAND PALO PINTO COUNTY
CSJ6291-85-001
Proj IDSUP - 629185001
Work TypeLITTER REMOVAL WITHIN PARKER/PALO
 
0.010301614.62296084.2198.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-15
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6291-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150235
Totals301614.620.00296084.2198.1

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6291-98-001
Proj IDRMC - 629198001
Work TypeCLEANING/SHAPING DITCHES
 
0.010228500.00661000.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-03-16
Work Began01-20-16
Work Completed
Time Computed02-10-16
Contract Working Days365
Addl Days Granted0
Working Days Charged65
Percent Time Used17
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150204
Totals228500.000.00661000.0099.9

CountyERATH
HighwayUS0377
FromVARIOUS ROADWAYS IN ERATH, HOOD,
To& SOMERVELL COUNTIES
CSJ6294-01-001
Proj IDRMC - 629401001
Work TypeTREE & BRUSH TRIMMING/REMOVAL
 
0.010299500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DIAMOND JK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160207
Totals299500.000.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5