| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | WISE |
| Highway |
US0081 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
WISE COUNTY |
| CSJ |
6220-28-001 |
| Proj ID |
RMC - 622028001 |
| Work Type |
DEBRIS REMOVAL |
| |
|
0.010 |
85703.11 |
4653.41 |
81600.41 |
99.9 |
| Work Order |
06-29-11 |
| Work Began |
07-06-11 |
| Work Completed |
|
| Time Computed |
07-06-11 |
| Contract Working Days |
84 |
| Addl Days Granted |
17 |
| Working Days Charged |
95 |
| Percent Time Used |
94 |
| Contractor(s) |
| TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6220-28-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04110201 |
|
Totals |
85703.11 |
4653.41 |
81600.41 |
99.9 |
|
| County | WISE |
| Highway |
US0380 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
WISE AND JACK COUNTY |
| CSJ |
6222-35-001 |
| Proj ID |
RMC - 622235001 |
| Work Type |
GUARDRAIL INSTALLATION / REPAIR |
| |
|
0.010 |
98092.90 |
625.00 |
61411.79 |
62.6 |
| Work Order |
09-08-11 |
| Work Began |
09-16-11 |
| Work Completed |
|
| Time Computed |
09-15-11 |
| Contract Working Days |
730 |
| Addl Days Granted |
0 |
| Working Days Charged |
594 |
| Percent Time Used |
81 |
| Contractor(s) |
| CKORP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6222-35-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
06110201 |
|
Totals |
98092.90 |
625.00 |
61411.79 |
62.6 |
|
| County | HOOD |
| Highway |
US0377 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
HOOD, SOMERVELL AND ERATH COUNTY |
| CSJ |
6222-59-001 |
| Proj ID |
RMC - 622259001 |
| Work Type |
GUARDRAIL INSTALLATION / REPAIR |
| |
|
0.010 |
102056.00 |
3290.00 |
73994.00 |
72.5 |
| Work Order |
01-03-12 |
| Work Began |
01-06-12 |
| Work Completed |
|
| Time Computed |
01-05-12 |
| Contract Working Days |
730 |
| Addl Days Granted |
0 |
| Working Days Charged |
482 |
| Percent Time Used |
66 |
| Contractor(s) |
| CKORP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6222-59-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09110202 |
|
Totals |
102056.00 |
3290.00 |
73994.00 |
72.5 |
|
| County | PARKER |
| Highway |
IH0020 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
PARKER & PALO PINTO COUNTY |
| CSJ |
6222-72-001 |
| Proj ID |
RMC - 622272001 |
| Work Type |
GUARDRAIL INSTALLATION / REPAIR |
| |
|
0.010 |
124798.00 |
11361.00 |
134778.70 |
99.9 |
| Work Order |
07-11-11 |
| Work Began |
08-01-11 |
| Work Completed |
|
| Time Computed |
07-18-11 |
| Contract Working Days |
730 |
| Addl Days Granted |
0 |
| Working Days Charged |
653 |
| Percent Time Used |
89 |
| Contractor(s) |
| T & L CLEANING SERVICES |
SUBCONTRACTOR(S) FOR CCSJ: 6222-72-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05110201 |
|
Totals |
124798.00 |
11361.00 |
134778.70 |
99.9 |
|
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
FORT WORTH DISTRICT |
| CSJ |
6224-34-001 |
| Proj ID |
RMC - 622434001 |
| Work Type |
LOOP DETECTOR REPAIR OR REPLACEMENT |
| |
|
0.010 |
240600.00 |
0.00 |
117753.95 |
48.9 |
| Work Order |
08-22-11 |
| Work Began |
08-22-11 |
| Work Completed |
|
| Time Computed |
08-29-11 |
| Contract Working Days |
730 |
| Addl Days Granted |
0 |
| Working Days Charged |
611 |
| Percent Time Used |
83 |
| Contractor(s) |
| SIG-OP SYSTEMS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6224-34-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
06110204 |
|
Totals |
240600.00 |
0.00 |
117753.95 |
48.9 |
|
| County | JOHNSON |
| Highway |
SH0174 |
| From |
VARIOUS ROADWAYS |
| To |
WITHIN JOHNSON COUNTY |
| CSJ |
6228-89-001 |
| Proj ID |
RMC - 622889001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
301816.14 |
0.00 |
143067.72 |
47.4 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-15-12 |
| Work Began |
05-19-12 |
| Work Completed |
|
| Time Computed |
05-22-12 |
| Contract Working Days |
84 |
| Addl Days Granted |
0 |
| Working Days Charged |
34 |
| Percent Time Used |
40 |
| Contractor(s) |
| TEXAS MOWING SERVICE |
SUBCONTRACTOR(S) FOR CCSJ: 6228-89-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11110203 |
|
Totals |
301816.14 |
0.00 |
143067.72 |
47.4 |
|
| County | WISE |
| Highway |
US0081 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
WISE COUNTY |
| CSJ |
6228-90-001 |
| Proj ID |
RMC - 622890001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
400940.80 |
0.00 |
187394.96 |
46.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
07-09-12 |
| Work Began |
07-09-12 |
| Work Completed |
|
| Time Computed |
07-16-12 |
| Contract Working Days |
112 |
| Addl Days Granted |
0 |
| Working Days Charged |
46 |
| Percent Time Used |
41 |
| Contractor(s) |
| TEXAS MOWING SERVICE |
SUBCONTRACTOR(S) FOR CCSJ: 6228-90-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11110201 |
|
Totals |
400940.80 |
0.00 |
187394.96 |
46.9 |
|
| County | JACK |
| Highway |
US0380 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
JACK COUNTY |
| CSJ |
6228-91-001 |
| Proj ID |
RMC - 622891001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
199957.16 |
0.00 |
99878.58 |
49.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
07-09-12 |
| Work Began |
07-11-12 |
| Work Completed |
|
| Time Computed |
07-16-12 |
| Contract Working Days |
64 |
| Addl Days Granted |
0 |
| Working Days Charged |
20 |
| Percent Time Used |
31 |
| Contractor(s) |
| JASCO |
SUBCONTRACTOR(S) FOR CCSJ: 6228-91-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11110202 |
|
Totals |
199957.16 |
0.00 |
99878.58 |
49.9 |
|
| County | TARRANT |
| Highway |
US0287 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
SOUTH TARRANT COUNTY |
| CSJ |
6228-93-001 |
| Proj ID |
RMC - 622893001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
234894.00 |
0.00 |
125829.00 |
53.5 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-15-12 |
| Work Began |
05-21-12 |
| Work Completed |
|
| Time Computed |
05-22-12 |
| Contract Working Days |
56 |
| Addl Days Granted |
0 |
| Working Days Charged |
21 |
| Percent Time Used |
37 |
| Contractor(s) |
| JASCO |
SUBCONTRACTOR(S) FOR CCSJ: 6228-93-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11110204 |
|
Totals |
234894.00 |
0.00 |
125829.00 |
53.5 |
|
| County | ERATH |
| Highway |
US0377 |
| From |
ROADWSIDE MOWING WITHIN |
| To |
ERATH COUNTY |
| CSJ |
6228-94-001 |
| Proj ID |
RMC - 622894001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
254104.00 |
69.00 |
119801.00 |
47.1 |
| Work Order |
06-11-12 |
| Work Began |
06-18-12 |
| Work Completed |
|
| Time Computed |
06-18-12 |
| Contract Working Days |
78 |
| Addl Days Granted |
0 |
| Working Days Charged |
40 |
| Percent Time Used |
51 |
| Contractor(s) |
| CEN-TEX IRRIGATION SYSTEMS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6228-94-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11110206 |
|
Totals |
254104.00 |
69.00 |
119801.00 |
47.1 |
|
| County | HOOD |
| Highway |
US0377 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
HOOD AND SOMERVELL COUNTY |
| CSJ |
6228-95-001 |
| Proj ID |
RMC - 622895001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
215372.00 |
69.00 |
100717.00 |
46.7 |
| Work Order |
05-30-12 |
| Work Began |
05-30-12 |
| Work Completed |
|
| Time Computed |
06-06-12 |
| Contract Working Days |
68 |
| Addl Days Granted |
0 |
| Working Days Charged |
15 |
| Percent Time Used |
22 |
| Contractor(s) |
| CEN-TEX IRRIGATION SYSTEMS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6228-95-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11110205 |
|
Totals |
215372.00 |
69.00 |
100717.00 |
46.7 |
|
| County | PALO PINTO |
| Highway |
US0281 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
PALO PINTO COUNTY |
| CSJ |
6228-96-001 |
| Proj ID |
RMC - 622896001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
311208.72 |
0.00 |
155504.36 |
49.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
07-02-12 |
| Work Began |
07-02-12 |
| Work Completed |
|
| Time Computed |
07-09-12 |
| Contract Working Days |
92 |
| Addl Days Granted |
0 |
| Working Days Charged |
25 |
| Percent Time Used |
27 |
| Contractor(s) |
| LONESTAR HAWK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6228-96-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11110209 |
|
Totals |
311208.72 |
0.00 |
155504.36 |
49.9 |
|
| County | PARKER |
| Highway |
IH0020 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
PARKER COUNTY |
| CSJ |
6228-97-001 |
| Proj ID |
RMC - 622897001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
342200.00 |
0.00 |
156825.00 |
45.8 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
06-05-12 |
| Work Began |
06-05-12 |
| Work Completed |
|
| Time Computed |
06-12-12 |
| Contract Working Days |
92 |
| Addl Days Granted |
0 |
| Working Days Charged |
21 |
| Percent Time Used |
22 |
| Contractor(s) |
| ANTHONY SERVICES |
SUBCONTRACTOR(S) FOR CCSJ: 6228-97-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11110210 |
|
Totals |
342200.00 |
0.00 |
156825.00 |
45.8 |
|
| County | TARRANT |
| Highway |
IH0820 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
NORTH TARRANT COUNTY |
| CSJ |
6228-98-001 |
| Proj ID |
RMC - 622898001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
281111.36 |
0.00 |
139332.18 |
49.5 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-09-12 |
| Work Began |
05-09-12 |
| Work Completed |
|
| Time Computed |
05-16-12 |
| Contract Working Days |
78 |
| Addl Days Granted |
0 |
| Working Days Charged |
26 |
| Percent Time Used |
33 |
| Contractor(s) |
| TEXAS MOWING SERVICE |
SUBCONTRACTOR(S) FOR CCSJ: 6228-98-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11110207 |
|
Totals |
281111.36 |
0.00 |
139332.18 |
49.5 |
|
| County | TARRANT |
| Highway |
US0081 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
NORTH TARRANT COUNTY |
| CSJ |
6228-99-001 |
| Proj ID |
RMC - 622899001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
264433.96 |
0.00 |
131005.98 |
49.5 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-09-12 |
| Work Began |
05-09-12 |
| Work Completed |
|
| Time Computed |
05-16-12 |
| Contract Working Days |
78 |
| Addl Days Granted |
0 |
| Working Days Charged |
27 |
| Percent Time Used |
34 |
| Contractor(s) |
| TEXAS MOWING SERVICE |
SUBCONTRACTOR(S) FOR CCSJ: 6228-99-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11110208 |
|
Totals |
264433.96 |
0.00 |
131005.98 |
49.5 |
|
| County | HOOD |
| Highway |
US0377 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
HOOD, SOMERVELL & ERATH COUNTY |
| CSJ |
6235-50-001 |
| Proj ID |
RMC - 623550001 |
| Work Type |
CALL - OUT REFLEC PAV MRKINGS & MRKS |
| |
|
0.010 |
177333.00 |
0.00 |
122063.68 |
68.8 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-02-12 |
| Work Began |
04-02-12 |
| Work Completed |
|
| Time Computed |
04-09-12 |
| Contract Working Days |
70 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| STRIPING TECHNOLOGY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6235-50-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12110202 |
|
Totals |
177333.00 |
0.00 |
122063.68 |
68.8 |
|
| County | HOOD |
| Highway |
US0377 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
HOOD, SOMERVELL AND ERATH COUNTIES |
| CSJ |
6237-30-001 |
| Proj ID |
RMC - 623730001 |
| Work Type |
REFLECTORIZED PAVEMENT MARKINGS |
| |
|
0.010 |
97998.56 |
42854.73 |
42854.73 |
43.7 |
| Work Order |
04-08-13 |
| Work Began |
04-08-13 |
| Work Completed |
|
| Time Computed |
04-15-13 |
| Contract Working Days |
29 |
| Addl Days Granted |
0 |
| Working Days Charged |
7 |
| Percent Time Used |
24 |
| Contractor(s) |
| STRIPE-A-ZONE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6237-30-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09120203 |
|
Totals |
97998.56 |
42854.73 |
42854.73 |
43.7 |
|
| County | TARRANT |
| Highway |
IH0820 |
| From |
JANITORIAL MAINTENANCE @ |
| To |
FORT WORTH DISTRICT COMPLEX |
| CSJ |
6240-97-001 |
| Proj ID |
SUP - 624097001 |
| Work Type |
JANITORIAL MAINTENANCE |
| |
|
0.010 |
156163.46 |
12028.55 |
155363.21 |
99.9 |
| Work Order |
05-01-12 |
| Work Began |
05-02-12 |
| Work Completed |
|
| Time Computed |
05-08-12 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
358 |
| Percent Time Used |
98 |
| Contractor(s) |
TIBH INDUSTRIES, INC. WILLIAMS & STROBLE YOUTH FOUNDATION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6240-97-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04120232 |
|
Totals |
156163.46 |
12028.55 |
155363.21 |
99.9 |
|
| County | ERATH |
| Highway |
US0067 |
| From |
VARIOUS ROADWAYS WITH |
| To |
ERATH, HOOD & SOMERVELL COUNTIES |
| CSJ |
6241-64-001 |
| Proj ID |
RMC - 624164001 |
| Work Type |
REFLECTORIZED PAVEMENT MARKINGS |
| |
|
0.010 |
276099.62 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
15 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| STRIPE-A-ZONE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6241-64-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07120201 |
|
Totals |
276099.62 |
0.00 |
0.00 |
0.0 |
|
| County | HOOD |
| Highway |
US0377 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
HOOD, SOMERVELL & ERATH COUNTIES |
| CSJ |
6242-33-001 |
| Proj ID |
RMC - 624233001 |
| Work Type |
CALL - OUT REFLECTORIZED PAV MRKGS & MRKS |
| |
|
0.010 |
187963.75 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
75 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| STRIPING TECHNOLOGY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6242-33-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08120201 |
|
Totals |
187963.75 |
0.00 |
0.00 |
0.0 |
|