Monthly Local Let Maintenance Report For Fort Worth District As Of Sep 21, 2017 Page 1 Of 6

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOOD
HighwayUS0377
FromVARIOUS ROADWAYS WITHIN
ToHOOD, SOMERVELL & ERATH COUNTIES
CSJ6242-33-001
Proj IDRMC - 624233001
Work TypeCALL-OUT REFLECTORIZED PAV MRKGS & MRKS
 
0.010187963.75462394.2899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-19-13
Work Began08-19-13
Work Completed
Time Computed08-26-13
Contract Working Days75
Addl Days Granted75
Working Days Charged57
Percent Time Used38
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6242-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08120201
Totals187963.750.00462394.2899.9

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToPARKER & PALO PINTO COUNTY
CSJ6254-49-001
Proj IDRMC - 625449001
Work TypeGUARDRAIL INSTALLATION & REPAIR
 
0.010132486.00340741.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-03-13
Work Began07-03-13
Work Completed
Time Computed07-09-13
Contract Working Days365
Addl Days Granted446
Working Days Charged810
Percent Time Used99
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6254-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03130201
Totals132486.000.00340741.0099.9

CountyTARRANT
HighwayFM0156
FromJANITORIAL MAINTENANCE AT
ToSAGINAW MAINTENANCE OFFICE
CSJ6257-39-001
Proj IDSUP - 625739001
Work TypeJANITIORIAL MAINTENANCE
 
0.01010868.0410868.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-13
Work Began07-02-13
Work Completed
Time Computed07-08-13
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6257-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06130231
Totals10868.040.0010868.0499.9

CountyTARRANT
HighwayIH0030
FromIH 30 EASTBOUND AT N. COLLINS
ToIN TARRANT COUNTY
CSJ6258-88-001
Proj IDRMC - 625888001
Work TypeREPAIR RETAINING WALL WITH SOIL NAILS
 
0.018252175.00269714.5799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-27-15
Work Began05-04-15
Work Completed
Time Computed05-03-15
Contract Working Days42
Addl Days Granted0
Working Days Charged36
Percent Time Used85
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6258-88-001
TEXAS ENVIRONMENTAL MANAGEMENT, INC (21.18)
CRAIG OLDEN, INC. (17.04)
DALLAS LITE AND BARRICADE INC. (1.06)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED (4.68)
Contract #11140207
Totals252175.000.00269714.5799.9

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToFORT WORTH DISTRICT
CSJ6259-56-001
Proj IDRMC - 625956001
Work TypeLOOP DETECTOR REPAIR AND/OR REPLACE
 
0.010256748.0010391.604.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-12-13
Work Began12-20-13
Work Completed
Time Computed12-19-13
Contract Working Days365
Addl Days Granted0
Working Days Charged133
Percent Time Used36
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07130203
Totals256748.000.0010391.604.0

CountyTARRANT
HighwaySH0360
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT & JOHNSON COUNTIES
CSJ6261-69-001
Proj IDRMC - 626169001
Work TypeFULL-DEPTH REPAIR OF EXIST. CONC. PAV.
 
0.010289381.09133873.0046.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-14-14
Work Began04-14-14
Work Completed
Time Computed04-21-14
Contract Working Days37
Addl Days Granted0
Working Days Charged33
Percent Time Used89
Contractor(s)
OMEGA CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6261-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09130201
Totals289381.090.00133873.0046.2

CountyWISE
HighwayUS0380
FromVARIOUS ROADWAYS WITHIN
ToWISE & JACK COUNTY
CSJ6263-14-001
Proj IDRMC - 626314001
Work TypeGUARDRAIL INSTALLATION/REPAIR
 
0.01076570.00229914.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-13
Work Began11-11-13
Work Completed
Time Computed11-14-13
Contract Working Days365
Addl Days Granted0
Working Days Charged352
Percent Time Used96
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10130201
Totals76570.000.00229914.5099.9

CountyTARRANT
HighwayUS0287
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6263-50-001
Proj IDRMC - 626350001
Work TypeROADSIDE MOWING
 
0.010214872.00114919.2055.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-19-14
Work Began05-21-14
Work Completed
Time Computed05-26-14
Contract Working Days56
Addl Days Granted0
Working Days Charged38
Percent Time Used67
Contractor(s)
SIGNATURE CONTRACTING SERVICES, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6263-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12130201
Totals214872.000.00114919.2055.1

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT
CSJ6265-95-001
Proj IDSUP - 626595001
Work TypeROADSIDE MOWING
 
0.010101970.42101970.4299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-05-14
Work Began05-12-14
Work Completed
Time Computed05-12-14
Contract Working Days90
Addl Days Granted0
Working Days Charged46
Percent Time Used51
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6265-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04140233
Totals101970.420.00101970.4299.9

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToPARKER, PALO PINTO AND ERATH COUNTY
CSJ6267-65-001
Proj IDRMC - 626765001
Work TypeDEBRIS REMOVAL
 
0.010143325.00211712.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-02-14
Work Began00-00-00
Work Completed
Time Computed06-09-14
Contract Working Days164
Addl Days Granted0
Working Days Charged161
Percent Time Used98
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6267-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04140204
Totals143325.000.00211712.5099.9

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS WITHIN
ToNORTH TARRANT COUNTY
CSJ6269-80-001
Proj IDRMC - 626980001
Work TypeFULL-DEPTH REPAIR OF EXIST. CONC. PAV.
 
0.010275530.80411803.13100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-29-14
Work Began06-29-14
Work Completed09-10-14
Time Computed07-06-14
Contract Working Days37
Addl Days Granted16
Working Days Charged34
Percent Time Used64
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6269-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04140202
Totals275530.800.00411803.13100.0

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS WITHIN
ToNORTH TARRANT COUNTY
CSJ6270-72-001
Proj IDRMC - 627072001
Work TypeCALL-OUT REFLEC. PAV. MRKINGS & MRKS
 
0.010196175.00272457.2799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-20-14
Work Began10-20-14
Work Completed
Time Computed10-23-14
Contract Working Days70
Addl Days Granted0
Working Days Charged44
Percent Time Used62
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05140201
Totals196175.000.00272457.2799.9

CountyERATH
HighwayUS0067
FromVARIOUS ROADWAYS WITHIN
ToERATH, HOOD & SOMERVELL COUNTY
CSJ6272-00-001
Proj IDRMC - 627200001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.010231973.72282544.7899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-21-15
Work Began00-00-00
Work Completed
Time Computed04-28-15
Contract Working Days20
Addl Days Granted0
Working Days Charged17
Percent Time Used85
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06140202
Totals231973.720.00282544.7899.9

CountyTARRANT
HighwayIH0035W
FromSPECIAL MAINTENANCE OFFICE
ToAT WAGGONMON STREET
CSJ6272-01-001
Proj IDSUP - 627201001
Work TypeJANITORIAL MAINTENANCE
 
0.0107822.927822.92100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-01-14
Work Began05-01-14
Work Completed04-30-15
Time Computed05-08-14
Contract Working Days365
Addl Days Granted0
Working Days Charged300
Percent Time Used82
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6272-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04140231
Totals7822.920.007822.92100.0

CountyWISE
HighwayUS0380
FromVARIOUS ROADWAYS WITHIN
ToWISE & JACK COUNTY
CSJ6272-03-001
Proj IDRMC - 627203001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.010154121.26134654.5787.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-25-14
Work Began08-06-14
Work Completed
Time Computed08-01-14
Contract Working Days11
Addl Days Granted0
Working Days Charged12
Percent Time Used109
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06140203
Totals154121.260.00134654.5787.7

CountyTARRANT
HighwayIH0820
FromJANITORIAL MAINTENANCE @
ToDISTRICT COMPLEX
CSJ6272-37-001
Proj IDSUP - 627237001
Work TypeJANITORIAL MAINTENANCE
 
0.010156163.46216306.2199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-02-14
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted184
Working Days Charged489
Percent Time Used89
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6272-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04140232
Totals156163.460.00216306.2199.9

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS WITHIN
ToNORTH TARRANT COUNTY
CSJ6272-40-001
Proj IDRMC - 627240001
Work TypeREFLECTORIZED PAV.MARKINGS & MARKERS
 
0.010351001.50350490.1799.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-13-15
Work Completed
Time Computed00-00-00
Contract Working Days17
Addl Days Granted0
Working Days Charged17
Percent Time Used100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06150211
Totals351001.500.00350490.1799.8

CountyTARRANT
HighwayIH0030
FromVARIOUS ROADWAYS IN SOUTH TARRANT,
ToPARKER, & JOHNSON COUNTIES
CSJ6273-53-001
Proj IDRMC - 627353001
Work TypeCLEANING & SEALING JOINTS & CRACKS
 
0.010195507.70240868.5199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-05-15
Work Began00-00-00
Work Completed
Time Computed01-12-15
Contract Working Days37
Addl Days Granted0
Working Days Charged25
Percent Time Used67
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11140206
Totals195507.700.00240868.5199.9

CountyTARRANT
HighwayIH0020
FromFORT WORTH
ToDISTRICT COMPLEX
CSJ6277-91-001
Proj IDSUP - 627791001
Work TypeGROUNDS MAINTENANCE
 
0.01050990.3439344.9477.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged304
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6277-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09140231
Totals50990.340.0039344.9477.1

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPARKER/PALO PINTO COUNTIES
CSJ6277-96-001
Proj IDSUP - 627796001
Work TypePICNIC AREA MAINTENANCE
 
0.01071135.6263635.5689.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-01-15
Work Began00-00-00
Work Completed
Time Computed01-08-15
Contract Working Days365
Addl Days Granted0
Working Days Charged396
Percent Time Used108
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6277-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01150232
Totals71135.620.0063635.5689.4