Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyERATH
Highway US0377
From ROADWSIDE MOWING WITHIN
To ERATH COUNTY
CSJ 6228-94-001
Proj ID RMC - 622894001
Work Type ROADSIDE MOWING
 
0.010 254104.00 0.00 242483.00 95.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-11-12
Work Began 06-18-12
Work Completed  
Time Computed 06-18-12
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 83
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6228-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11110206
Totals 254104.00 0.00 242483.00 95.4

CountyHOOD
Highway US0377
From VARIOUS ROADWAYS WITHIN
To HOOD AND SOMERVELL COUNTY
CSJ 6228-95-001
Proj ID RMC - 622895001
Work Type ROADSIDE MOWING
 
0.010 215372.00 0.00 201365.00 93.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-30-12
Work Began 05-30-12
Work Completed  
Time Computed 06-06-12
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 48
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6228-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11110205
Totals 215372.00 0.00 201365.00 93.4

CountyHOOD
Highway US0377
From VARIOUS ROADWAYS WITHIN
To HOOD, SOMERVELL AND ERATH COUNTIES
CSJ 6237-30-001
Proj ID RMC - 623730001
Work Type REFLECTORIZED PAVEMENT MARKINGS
 
0.010 97998.56 0.00 51019.56 52.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-08-13
Work Began 04-08-13
Work Completed  
Time Computed 04-15-13
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 24
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6237-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09120203
Totals 97998.56 0.00 51019.56 52.0

CountyTARRANT
Highway IH0820
From JANITORIAL MAINTENANCE @
To FORT WORTH DISTRICT COMPLEX
CSJ 6240-97-001
Proj ID SUP - 624097001
Work Type JANITORIAL MAINTENANCE
 
0.010 156163.46 17938.98 293764.39 99.9
Work Order 05-01-12
Work Began 05-02-12
Work Completed  
Time Computed 05-08-12
Contract Working Days 365
Addl Days Granted 184
Working Days Charged 693
Percent Time Used 126
Contractor(s)
TIBH INDUSTRIES, INC.
WILLIAMS & STROBLE YOUTH FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6240-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04120232
Totals 156163.46 17938.98 293764.39 99.9

CountyERATH
Highway US0067
From VARIOUS ROADWAYS WITH
To ERATH, HOOD & SOMERVELL COUNTIES
CSJ 6241-64-001
Proj ID RMC - 624164001
Work Type REFLECTORIZED PAVEMENT MARKINGS
 
0.010 276099.62 0.00 247050.60 89.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-13
Work Began 05-23-13
Work Completed  
Time Computed 05-31-13
Contract Working Days 15
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 13
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6241-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07120201
Totals 276099.62 0.00 247050.60 89.4

CountyHOOD
Highway US0377
From VARIOUS ROADWAYS WITHIN
To HOOD, SOMERVELL & ERATH COUNTIES
CSJ 6242-33-001
Proj ID RMC - 624233001
Work Type CALL - OUT REFLECTORIZED PAV MRKGS & MRKS
 
0.010 187963.75 15243.72 135256.66 71.9
Work Order 08-19-13
Work Began 08-19-13
Work Completed  
Time Computed 08-26-13
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 14
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6242-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120201
Totals 187963.75 15243.72 135256.66 71.9

CountyPARKER
Highway IH0020
From VARIOUS ROADWAYS
To WITHIN PARKER, PALO PINTO & ERATH CO.
CSJ 6249-99-001
Proj ID RMC - 624999001
Work Type DEBRIS REMOVAL
 
0.010 162618.00 12509.00 165761.50 99.9
Work Order 03-04-13
Work Began 03-04-13
Work Completed  
Time Computed 03-11-13
Contract Working Days 164
Addl Days Granted 24
Working Days Charged 159
Percent Time Used 84
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6249-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12120201
Totals 162618.00 12509.00 165761.50 99.9

CountyPARKER
Highway IH0020
From VARIOUS ROADWAYS WITHIN
To PARKER & PALO PINTO COUNTY
CSJ 6254-49-001
Proj ID RMC - 625449001
Work Type GUARDRAIL INSTALLATION & REPAIR
 
0.010 132486.00 10312.50 92357.50 69.7
Work Order 07-03-13
Work Began 07-03-13
Work Completed  
Time Computed 07-09-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 266
Percent Time Used 72
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6254-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03130201
Totals 132486.00 10312.50 92357.50 69.7

CountyWISE
Highway US0380
From VARIOUS ROADWAYS WITHIN
To WISE & JACK COUNTY
CSJ 6255-49-001
Proj ID RMC - 625549001
Work Type CALL - OUT REFLEC.PAV. MRKINGS & MRKERS
 
0.010 189537.25 0.00 118245.70 62.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-24-13
Work Began 06-25-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 24
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6255-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03130202
Totals 189537.25 0.00 118245.70 62.3

CountyTARRANT
Highway IH0035W
From SPEICIAL MAINTENANCE OFFICE
To AT WAGGONMAN STREET
CSJ 6255-68-001
Proj ID SUP - 625568001
Work Type JANITORIAL MAINTENANCE
 
0.010 7595.04 632.92 6962.12 91.6
Work Order 05-01-13
Work Began 05-05-13
Work Completed  
Time Computed 05-08-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 328
Percent Time Used 89
Contractor(s)
TIBH INDUSTRIES, INC.
WILLIAMS & STROBLE YOUTH FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6255-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04130231
Totals 7595.04 632.92 6962.12 91.6

CountyTARRANT
Highway IH0020
From FORT WORTH
To DISTRICT COMPLEX
CSJ 6255-69-001
Proj ID SUP - 625569001
Work Type GROUNDS MAINTENANCE
 
0.010 53193.97 3369.84 24619.23 46.2
Work Order 09-03-13
Work Began 09-05-13
Work Completed  
Time Computed 09-03-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 203
Percent Time Used 55
Contractor(s)
TIBH INDUSTRIES, INC.
WILLIAMS & STROBLE YOUTH FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6255-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130231
Totals 53193.97 3369.84 24619.23 46.2

CountyERATH
Highway US0067
From VARIOUS ROADWAYS WITHIN
To ERATH, HOOD & SOMERVELL COUNTIES
CSJ 6256-70-001
Proj ID RMC - 625670001
Work Type REFLECTORIZED PAVEMENT MARKINGS
 
0.010 164968.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 11
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6256-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05130202
Totals 164968.25 0.00 0.00 0.0

CountyWISE
Highway US0081
From VARIOUS ROADWAYS WITHIN
To WISE COUNTY
CSJ 6257-11-001
Proj ID RMC - 625711001
Work Type DEBRIS REMOVAL
 
0.010 146058.97 0.00 56392.98 38.6
Work Order 07-03-13
Work Began 07-03-13
Work Completed  
Time Computed 07-10-13
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 22
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6257-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05130203
Totals 146058.97 0.00 56392.98 38.6

CountyTARRANT
Highway FM0156
From JANITORIAL MAINTENANCE AT
To SAGINAW MAINTENANCE OFFICE
CSJ 6257-39-001
Proj ID SUP - 625739001
Work Type JANITIORIAL MAINTENANCE
 
0.010 10868.04 905.67 8151.03 75.0
Work Order 07-01-13
Work Began 07-02-13
Work Completed  
Time Computed 07-08-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 267
Percent Time Used 73
Contractor(s)
TIBH INDUSTRIES, INC.
WILLIAMS & STROBLE YOUTH FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06130231
Totals 10868.04 905.67 8151.03 75.0

CountyWISE
Highway SH0114
From VARIOUS ROADWAYS WITHIN
To WISE, JACK AND PARKER COUNTIES
CSJ 6258-34-001
Proj ID RMC - 625834001
Work Type CLEANING AND SEALING JOINTS / CRACKS
 
0.010 117777.00 0.00 99962.34 84.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-13
Work Began 10-22-13
Work Completed  
Time Computed 10-29-13
Contract Working Days 26
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 3
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6258-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130204
Totals 117777.00 0.00 99962.34 84.8

CountyERATH
Highway US0377
From VARIOUS ROADWAYS WITHIN
To ERATH, HOOD & SOMERVELL COUNTIES
CSJ 6258-35-001
Proj ID RMC - 625835001
Work Type CLEANING / SEALING JOINTS & CRACKS
 
0.010 79670.26 0.00 72525.54 91.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-13
Work Began 11-14-13
Work Completed  
Time Computed 11-21-13
Contract Working Days 23
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS ROAD MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6258-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130202
Totals 79670.26 0.00 72525.54 91.0

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS
To WITHIN NORTH TARRANT COUNTY
CSJ 6259-08-001
Proj ID RMC - 625908001
Work Type CALL - OUT REFLE. PAV. MRKINGS & MRKERS
 
0.010 177650.00 2310.28 115041.08 64.7
Work Order 09-03-13
Work Began 09-04-13
Work Completed  
Time Computed 09-06-13
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 16
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6259-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07130201
Totals 177650.00 2310.28 115041.08 64.7

CountyTARRANT
Highway IH0820
From VARIOUS BRIDGES IN TARRANT
To AND JACK COUNTIES
CSJ 6259-38-001
Proj ID BPM - 625938001
Work Type STRUCTURAL BRIDGE REPAIR
 
0.010 202474.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-31-14
Work Began 00-00-00
Work Completed  
Time Computed 04-07-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130208
Totals 202474.00 0.00 0.00 0.0

CountyTARRANT
Highway IH0020
From VARIOUS ROADWAYS WITHIN
To FORT WORTH DISTRICT
CSJ 6259-56-001
Proj ID RMC - 625956001
Work Type LOOP DETECTOR REPAIR AND / OR REPLACE
 
0.010 256748.00 6409.00 10391.60 4.0
Work Order 12-12-13
Work Began 12-20-13
Work Completed  
Time Computed 12-19-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 28
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07130203
Totals 256748.00 6409.00 10391.60 4.0

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS WITHIN
To NORTH TARRANT COUNTY
CSJ 6260-21-001
Proj ID RMC - 626021001
Work Type PREFABRICATED RELFECTORIZED PAV MARKINGS
 
0.010 102544.76 0.00 97155.82 94.7
Work Order 09-24-13
Work Began 10-03-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 100
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130205
Totals 102544.76 0.00 97155.82 94.7