Monthly Local Let Maintenance Report For Corpus Christi District As Of Dec 9, 2016 Page 2 Of 4

Last Update: Friday, December 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyKARNES
Highway FM2985
From FM2985 (1.20 MI SOUTH OF SH72)
To FM1344 (0.23 MI NW OF FM0791)
CSJ 6279-83-001
Proj ID RMC - 627983001
Work Type REPLACING EXISTING PIPE STRUCTURE
 
0.014 194496.00 0.00 326259.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-15
Work Began 00-00-00
Work Completed  
Time Computed 04-09-15
Contract Working Days 32
Addl Days Granted 18
Working Days Charged 15
Percent Time Used 30
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6279-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151601
Totals 194496.00 0.00 326259.00 99.9

CountyBEE
Highway US0181
From BEE COUNTY MAINTENANCE OFFICE
To .
CSJ 6282-83-001
Proj ID SUP - 628283001
Work Type JANITORIAL & GROUNDS
 
0.999 29133.16 0.00 28346.70 97.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 12-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 730
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
G & H EQUITAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141630
Totals 29133.16 0.00 28346.70 97.3

CountyNUECES
Highway IH0037
From DISTRICTWIDE
To .
CSJ 6282-84-001
Proj ID RMC - 628284001
Work Type LARGE SIGN MAINTENANCE
 
0.999 248985.00 0.00 242049.64 97.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-04-15
Work Began 00-00-00
Work Completed  
Time Computed 03-11-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 519
Percent Time Used 71
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6282-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151605
Totals 248985.00 0.00 242049.64 97.2

CountyNUECES
Highway SH0358
From VARIOUS
To .
CSJ 6282-85-001
Proj ID SUP - 628285001
Work Type LANDSCAPING
 
0.999 169795.40 0.00 123451.72 72.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 669
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151634
Totals 169795.40 0.00 123451.72 72.7

CountySAN PATRICIO
Highway US0077
From VARIOUS ROADWAYS IN SAN PATRICIO,
To REFUGIO, & ARANSAS COUNTIES
CSJ 6283-02-001
Proj ID SUP - 628302001
Work Type GUARDRAIL REPAIR
 
0.999 438400.00 0.00 207181.00 47.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-01-15
Work Began 00-00-00
Work Completed  
Time Computed 10-01-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 333
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151633
Totals 438400.00 0.00 207181.00 47.2

CountyLIVE OAK
Highway IH0037
From VARIOUS
To .
CSJ 6283-29-001
Proj ID SUP - 628329001
Work Type GUARDRAIL REPAIR
 
999.000 382775.00 0.00 169331.00 44.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-15
Work Began 00-00-00
Work Completed  
Time Computed 03-18-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 333
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151632
Totals 382775.00 0.00 169331.00 44.2

CountyNUECES
Highway SH0358
From VARIOUS LOCATIONS
To .
CSJ 6284-60-001
Proj ID SUP - 628460001
Work Type TREE TRIMMING
 
0.999 137500.00 0.00 137700.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 575
Percent Time Used 157
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04151630
Totals 137500.00 0.00 137700.00 99.9

CountyKARNES
Highway FM0099
From VARIOUS
To .
CSJ 6284-98-001
Proj ID RMC - 628498001
Work Type FLEXIBLE PAVEMENT REPAIR
 
5.925 313645.82 0.00 593097.59 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 90
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6284-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03151604
Totals 313645.82 0.00 593097.59 99.9

CountyNUECES
Highway PR0022
From PR0022FR
To AT HUMBLE CHANNEL
CSJ 6287-06-001
Proj ID BPM - 628706001
Work Type CONCRETE STRUCTURE REPAIR
 
0.999 29800.00 0.00 51450.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 32
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6287-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03161607
Totals 29800.00 0.00 51450.00 99.9

CountyKARNES
Highway US0181
From VARIOUS
To .
CSJ 6287-07-001
Proj ID BPM - 628707001
Work Type BACKFILL & RIPRAP REPAIR
 
0.999 58225.00 0.00 68440.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-19-15
Work Began 00-00-00
Work Completed 03-11-16
Time Computed 10-26-15
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 92
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6287-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09151601
Totals 58225.00 0.00 68440.00 100.0

CountyNUECES
Highway IH0037
From VARIOUS
To .
CSJ 6287-10-001
Proj ID BPM - 628710001
Work Type BACKFILL / RIPRAP REPAIR
 
0.999 250025.00 0.00 250071.60 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-19-15
Work Began 00-00-00
Work Completed 04-27-16
Time Computed 01-04-16
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 49
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6287-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151602
Totals 250025.00 0.00 250071.60 100.0

CountyNUECES
Highway SH0358
From CORPUS CHRISTI DISTRICT HEADQUARTERS
To .
CSJ 6288-10-001
Proj ID SUP - 628810001
Work Type DISTRICT JANITORIAL
 
0.999 167208.96 0.00 128411.76 76.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 580
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04151631
Totals 167208.96 0.00 128411.76 76.7

CountyNUECES
Highway IH0037
From VARIOUS
To .
CSJ 6294-29-001
Proj ID SUP - 629429001
Work Type LITTER PICKUP
 
999.000 121497.86 0.00 102274.43 84.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 11-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10151632
Totals 121497.86 0.00 102274.43 84.1

CountyNUECES
Highway SH0358
From VARIOUS
To .
CSJ 6294-46-001
Proj ID RMC - 629446001
Work Type ILLUMINATION MAINTENANCE
 
0.999 179150.00 0.00 175546.25 97.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 75
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10151601
Totals 179150.00 0.00 175546.25 97.9

CountyJIM WELLS
Highway SH0359
From VARIOUS
To .
CSJ 6294-48-001
Proj ID RMC - 629448001
Work Type CRACK SEAL
 
170.000 108866.50 17537.50 17537.50 16.1
Work Order 11-15-16
Work Began 00-00-00
Work Completed  
Time Computed 11-28-16
Contract Working Days 19
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 15
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09161604
Totals 108866.50 17537.50 17537.50 16.1

CountyNUECES
Highway SH0358
From VARIOUS
To .
CSJ 6294-49-001
Proj ID RMC - 629449001
Work Type CRACK SEAL
 
114.000 72962.00 72961.90 72961.90 99.9
Work Order 11-15-16
Work Began 00-00-00
Work Completed  
Time Computed 11-27-16
Contract Working Days 13
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 53
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09161603
Totals 72962.00 72961.90 72961.90 99.9

CountyNUECES
Highway SH0361
From PORT ARANSAS FERRY OFFICE
To .
CSJ 6296-89-001
Proj ID SUP - 629689001
Work Type JANITORIAL MAINTENANCE
 
0.999 119730.26 0.00 107869.91 90.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10151630
Totals 119730.26 0.00 107869.91 90.0

CountyNUECES
Highway IH0037
From VARIOUS
To .
CSJ 6297-58-001
Proj ID SUP - 629758001
Work Type GUARDRAIL REPAIR
 
0.999 538420.20 0.00 353411.28 65.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-16
Work Began 00-00-00
Work Completed  
Time Computed 11-21-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12151632
Totals 538420.20 0.00 353411.28 65.6

CountySAN PATRICIO
Highway US0077
From VARIOUS ROADWAYS IN SAN PATRICIO,
To REFUGIO, & ARANSAS COUNTIES
CSJ 6297-59-001
Proj ID SUP - 629759001
Work Type GUARDRAIL REPAIR
 
0.999 313230.00 0.00 236477.00 75.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-06-16
Work Began 00-00-00
Work Completed  
Time Computed 12-09-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12151633
Totals 313230.00 0.00 236477.00 75.4

CountyJIM WELLS
Highway US0281
From VARIOUS
To .
CSJ 6297-60-001
Proj ID SUP - 629760001
Work Type GUARDRAIL REPAIR
 
999.000 273191.20 21885.00 227648.25 83.3
Work Order 01-20-16
Work Began 00-00-00
Work Completed  
Time Computed 01-21-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12151635
Totals 273191.20 21885.00 227648.25 83.3

page 1 | page 2 | page 3 | page 4