Monthly Local Let Maintenance Report For Corpus Christi District As Of Feb 09, 2018 Page 4 Of 4

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyARANSAS
HighwayFM1069
FromSL 70
ToEND OF STATE MAINTENANCE
CSJ6325-55-001
Proj IDEMC - 632555001
Work TypeSMALL SIGN REPLACEMENT
 
21.090248688.00119489.7048.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged52
Percent Time Used69
Contractor(s)
TRIPLE R CONTRACTING, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6325-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171644
Totals248688.00119489.70119489.7048.0

CountyNUECES
HighwayIH0037
FromVARIOUS
To.
CSJ6325-56-001
Proj IDSUP - 632556001
Work TypeLITTER PICKUP
 
0.999120751.1016050.5613.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged62
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
NC MHMR INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6325-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171639
Totals120751.108630.5116050.5613.2

CountyARANSAS
HighwaySH0035
From100FT N. OF CACTUS ST.
To100FT S. OF MAPLE ST.
CSJ6325-83-001
Proj IDEMC - 632583001
Work TypeTRAFFIC SIGNAL ITEM REPLACEMENT
 
2.500579805.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-12-18
Work Began00-00-00
Work Completed
Time Computed01-22-18
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171640
Totals579805.250.000.000.0

CountyARANSAS
HighwayFM0136
FromSH 35 TO FM 2678 &
ToFM 2678 FROM FM 136 TO FM 774
CSJ6326-12-001
Proj IDEMC - 632612001
Work TypeSMALL SIGN REPLACEMENT
 
29.500329836.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-24-18
Work Began00-00-00
Work Completed
Time Computed03-01-18
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6326-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171641
Totals329836.000.000.000.0

CountySAN PATRICIO
HighwaySH0188
FromBUS 35
ToFM 136
CSJ6326-13-001
Proj IDEMC - 632613001
Work TypeSMALL SIGN REPLACEMENT
 
14.240188130.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6326-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01181640
Totals188130.000.000.000.0

CountyREFUGIO
HighwayUS0077
FromVARIOUS ROADWAYS
To.
CSJ6326-14-001
Proj IDEMC - 632614001
Work TypeSMALL SIGN REPLACEMENT
 
40.420498520.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRIPLE R CONTRACTING, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6326-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01181641
Totals498520.000.000.000.0

CountySAN PATRICIO
HighwayUS0181
FromUS181, SH35, AND US77
To.
CSJ6326-15-001
Proj IDEMC - 632615001
Work TypeLARGE SIGN REPLACEMENT
 
0.999714159.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6326-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01181642
Totals714159.400.000.000.0

CountyBEE
HighwayUS0181
FromVARIOUS
To.
CSJ6326-54-001
Proj IDSUP - 632654001
Work TypePICNIC AREA MAINTENANCE
 
0.99960724.723992.456.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged62
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6326-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171630
Totals60724.722113.653992.456.5

CountyARANSAS
HighwaySH0035
FromSH 35
To12TH ST
CSJ6327-21-001
Proj IDEMC - 632721001
Work TypeDEBRIS SITE MANAGEMENT
 
0.100747502.00169973.2022.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged26
Percent Time Used86
Contractor(s)
FAULKNER LAND CLEARING AND SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6327-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171642
Totals747502.00169973.20169973.2022.7

CountyARANSAS
HighwaySH0035
FromVARIOUS
To.
CSJ6328-25-001
Proj IDSUP - 632825001
Work TypePICNIC AREA MAINTENANCE
 
0.99959043.042502.094.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged31
Percent Time Used4
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6328-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171639
Totals59043.042502.092502.094.2