Monthly Local Let Maintenance Report For Corpus Christi District As Of Feb 10, 2017 Page 3 Of 4

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKARNES
HighwayFM1353
FromVARIOUS
To.
CSJ6303-47-001
Proj IDBPM - 630347001
Work TypeCONCRETE STRUCTURE REPAIR
 
0.99931861.0038580.0099.9
Work Order12-05-16
Work Began00-00-00
Work Completed
Time Computed12-12-16
Contract Working Days34
Addl Days Granted0
Working Days Charged9
Percent Time Used26
Contractor(s)
TCB CONSTRUCTION, INC
SUBCONTRACTOR(S) FOR CCSJ: 6303-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161605
Totals31861.0038580.0038580.0099.9

CountyKLEBERG
HighwayUS0077
FromUS 77 @ ARANA CREEK
To.
CSJ6303-48-001
Proj IDBPM - 630348001
Work TypeCONCRETE STRUCTURE REPAIR
 
0.99924948.0038404.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-16
Work Began00-00-00
Work Completed
Time Computed09-26-16
Contract Working Days17
Addl Days Granted0
Working Days Charged7
Percent Time Used41
Contractor(s)
TEXCAVATION COMPANY LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161604
Totals24948.000.0038404.0099.9

CountyREFUGIO
HighwaySH0035
FromVARIOUS
To.
CSJ6303-50-001
Proj IDBPM - 630350001
Work TypeCONCRETE STRUCTURE REPAIR
 
0.999165244.00164494.0099.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-28-16
Work Began00-00-00
Work Completed
Time Computed11-29-16
Contract Working Days34
Addl Days Granted0
Working Days Charged16
Percent Time Used47
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161603
Totals165244.000.00164494.0099.5

CountySAN PATRICIO
HighwayIH0037
FromNORTHBOUND N. OF IH 37 & US 77
ToSOUTHBOUND N. OF IH 37 & US 77
CSJ6303-53-001
Proj IDSUP - 630353001
Work TypePICNIC AREA MAINTENANCE
 
0.02560489.6410857.9817.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161630
Totals60489.640.0010857.9817.9

CountyNUECES
HighwayUS0077
FromWEST NUECES MAINTENANCE YARD
To.
CSJ6303-54-001
Proj IDSUP - 630354001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.99926678.604991.7518.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161631
Totals26678.600.004991.7518.7

CountyREFUGIO
HighwayUS0077
FromREFUGIO COUNTY MAINTENANCE OFFICE
To.
CSJ6303-55-001
Proj IDSUP - 630355001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.99927558.565859.2021.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161632
Totals27558.560.005859.2021.2

CountyJIM WELLS
HighwayUS0281
FromJIM WELLS COUNTY MAINTENANE/AREA OFFICES
To.
CSJ6303-56-001
Proj IDSUP - 630356001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.99946685.446665.1614.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged123
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161639
Totals46685.440.006665.1614.2

CountyARANSAS
HighwayFM3036
FromARANSAS COUNTY MAINTENANCE OFFICE
To.
CSJ6303-57-001
Proj IDSUP - 630357001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.99931770.926060.0019.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
G & H EQUITAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161635
Totals31770.920.006060.0019.0

CountySAN PATRICIO
HighwayUS0181
FromSAN PATRICIO COUNTY MAINT./AREA OFFICES
To.
CSJ6303-58-001
Proj IDSUP - 630358001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.99930856.965018.0716.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
G & H EQUITAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161637
Totals30856.960.005018.0716.2

CountyLIVE OAK
HighwayUS0281
FromLIVE OAK COUNTY MAINTENANCE OFFICE
To.
CSJ6303-59-001
Proj IDSUP - 630359001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.99944756.169709.1221.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
G & H EQUITAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161636
Totals44756.160.009709.1221.6

CountyGOLIAD
HighwayUS0059
FromGOLIAD COUNTY MAINTENANCE OFFICE
To.
CSJ6303-60-001
Proj IDSUP - 630360001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.99922785.123967.5117.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161634
Totals22785.120.003967.5117.4

CountyBEE
HighwayFM0799
FromVARIOUS
To.
CSJ6307-79-001
Proj IDRMC - 630779001
Work TypeCRACK SEAL
 
156.400100098.5061423.9070.2
Work Order11-15-16
Work Began00-00-00
Work Completed
Time Computed11-28-16
Contract Working Days19
Addl Days Granted0
Working Days Charged34
Percent Time Used178
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161601
Totals100098.5061423.9061423.9070.2

CountyREFUGIO
HighwayFM0774
FromVARIOUS
To.
CSJ6307-80-001
Proj IDRMC - 630780001
Work TypeCRACK SEAL
 
193.200122608.6029672.0024.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-16
Work Began00-00-00
Work Completed
Time Computed01-02-17
Contract Working Days22
Addl Days Granted0
Working Days Charged19
Percent Time Used86
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161602
Totals122608.600.0029672.0024.2

CountyKARNES
HighwayUS0181
FromKARNES COUNTY MAINT./AREA OFFICES
To.
CSJ6308-50-001
Proj IDSUP - 630850001
Work TypeJANITORIAL & GROUNDS
 
0.99929967.443901.8713.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161633
Totals29967.440.003901.8713.0

CountyNUECES
HighwaySH0358
FromE. NUECES COUNTY MAINTENANCE OFFICE
To.
CSJ6308-51-001
Proj IDSUP - 630851001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.99912606.081654.6813.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged123
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
CORPUS CHRISTI STATE SCHOOL/PRO PAC
SUBCONTRACTOR(S) FOR CCSJ: 6308-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161630
Totals12606.080.001654.6813.1

CountyKLEBERG
HighwayBU0077V
FromKLEBERG COUNTY MAINTENANCE OFFICE
To.
CSJ6308-52-001
Proj IDSUP - 630852001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.99914974.562389.7715.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
CORPUS CHRISTI STATE SCHOOL/PRO PAC
SUBCONTRACTOR(S) FOR CCSJ: 6308-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161638
Totals14974.560.002389.7715.9

CountyNUECES
HighwaySH0361
FromPORT ARANSAS FERRY OFFICE
To.
CSJ6310-05-001
Proj IDSUP - 631005001
Work TypeJANITORIAL MAINTENANCE
 
0.999228620.5226712.3911.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged92
Percent Time Used12
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161631
Totals228620.520.0026712.3911.6

CountyNUECES
HighwaySH0358
FromCORPUS CHRISTI DISTRICT HEADQUARTERS
To.
CSJ6310-06-001
Proj IDSUP - 631006001
Work TypeDISTRICT JANITORIAL
 
0.999268530.7210001.283.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged31
Percent Time Used4
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161630
Totals268530.720.0010001.283.7

CountyNUECES
HighwayIH0037
From.26 MI S. OF NUECES RIVER BRIDGE
To.59 MI N. OF SHARPSBURG ROAD
CSJ6310-23-001
Proj IDEMC - 631023001
Work TypeEMERGENCY OHSB REPAIR
 
0.999209505.00214615.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days17
Addl Days Granted0
Working Days Charged17
Percent Time Used100
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161641
Totals209505.000.00214615.0099.9

CountyNUECES
HighwaySH0358
FromDISTRICT COMPLEX
To.
CSJ6310-31-001
Proj IDSUP - 631031001
Work TypeGROUNDS MAINTENANCE
 
0.99990558.7215093.1216.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged123
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
NC MHMR INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6310-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161632
Totals90558.720.0015093.1216.6