Monthly Local Let Maintenance Report For Corpus Christi District As Of Jan 11, 2017 Page 3 Of 5

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEE
HighwayUS0181
FromVARIOUS
To.
CSJ6297-96-001
Proj IDSUP - 629796001
Work TypePICNIC AREA MAINTENANCE
 
0.99960724.7232233.7853.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-15
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged397
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6297-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11151635
Totals60724.720.0032233.7853.0

CountySAN PATRICIO
HighwayBU0077T
From1000' SOUTH OF HELM RD.
To4TH STREET
CSJ6298-03-001
Proj IDRMC - 629803001
Work TypeWIDENING OF EXISTING ROADWAY
 
0.590144662.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days17
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161605
Totals144662.360.000.000.0

CountyARANSAS
HighwaySH0035
FromVARIOUS
To.
CSJ6298-41-001
Proj IDRMC - 629841001
Work TypeMOWING
 
155.246135245.5076207.0056.3
Work Order06-09-16
Work Began00-00-00
Work Completed
Time Computed06-08-16
Contract Working Days365
Addl Days Granted0
Working Days Charged192
Percent Time Used52
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161601
Totals135245.504342.0076207.0056.3

CountyBEE
HighwayUS0181
FromVARIOUS
To.
CSJ6298-42-001
Proj IDRMC - 629842001
Work TypeMOWING
 
260.357197967.0065213.5032.9
Work Order05-31-16
Work Began06-08-16
Work Completed
Time Computed06-08-16
Contract Working Days365
Addl Days Granted0
Working Days Charged207
Percent Time Used56
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161603
Totals197967.000.0065213.5032.9

CountyGOLIAD
HighwayUS0059
FromVARIOUS
To.
CSJ6298-43-001
Proj IDRMC - 629843001
Work TypeMOWING
 
270.237159779.5090203.0056.4
Work Order06-01-16
Work Began00-00-00
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged207
Percent Time Used56
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161604
Totals159779.507998.0090203.0056.4

CountyJIM WELLS
HighwayUS0281
FromVARIOUS
To.
CSJ6298-44-001
Proj IDRMC - 629844001
Work TypeMOWING
 
217.730227726.00114511.0050.2
Work Order06-27-16
Work Began00-00-00
Work Completed
Time Computed07-11-16
Contract Working Days365
Addl Days Granted0
Working Days Charged174
Percent Time Used47
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161603
Totals227726.0020857.00114511.0050.2

CountyKARNES
HighwayUS0181
FromVARIOUS
To.
CSJ6298-45-001
Proj IDRMC - 629845001
Work TypeMOWING
 
275.064211526.5085813.5040.5
Work Order05-31-16
Work Began06-08-16
Work Completed
Time Computed06-08-16
Contract Working Days365
Addl Days Granted0
Working Days Charged207
Percent Time Used56
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161605
Totals211526.5016088.0085813.5040.5

CountyKLEBERG
HighwayUS0077
FromVARIOUS
To.
CSJ6298-46-001
Proj IDRMC - 629846001
Work TypeMOWING
 
222.835178885.0058069.5032.4
Work Order05-25-16
Work Began00-00-00
Work Completed
Time Computed06-08-16
Contract Working Days365
Addl Days Granted0
Working Days Charged207
Percent Time Used56
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161602
Totals178885.000.0058069.5032.4

CountyNUECES
HighwayUS0077
FromVARIOUS
To.
CSJ6298-48-001
Proj IDRMC - 629848001
Work TypeMOWING
 
207.053156113.50102556.0065.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-16
Work Began00-00-00
Work Completed
Time Computed10-03-16
Contract Working Days365
Addl Days Granted0
Working Days Charged207
Percent Time Used56
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161606
Totals156113.500.00102556.0065.6

CountyREFUGIO
HighwayUS0077
FromVARIOUS
To.
CSJ6298-49-001
Proj IDRMC - 629849001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
190.445149480.0086827.5058.0
Work Order06-27-16
Work Began00-00-00
Work Completed
Time Computed07-11-16
Contract Working Days365
Addl Days Granted0
Working Days Charged174
Percent Time Used47
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161601
Totals149480.000.0086827.5058.0

CountySAN PATRICIO
HighwayIH0037
FromVARIOUS
To.
CSJ6298-50-001
Proj IDRMC - 629850001
Work TypeMOWING
 
240.863184325.0066646.0036.1
Work Order06-27-16
Work Began00-00-00
Work Completed
Time Computed07-11-16
Contract Working Days365
Addl Days Granted0
Working Days Charged174
Percent Time Used47
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161602
Totals184325.0017035.0066646.0036.1

CountyNUECES
HighwayIH0037
FromVARIOUS
To.
CSJ6298-63-001
Proj IDRMC - 629863001
Work TypeMOWING
 
50.67884227.0049900.2859.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-27-16
Work Began00-00-00
Work Completed
Time Computed11-04-16
Contract Working Days365
Addl Days Granted3
Working Days Charged214
Percent Time Used58
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161608
Totals84227.000.0049900.2859.2

CountyARANSAS
HighwaySH0035
FromVARIOUS
To.
CSJ6298-84-001
Proj IDSUP - 629884001
Work TypePICNIC AREA MAINTENANCE
 
0.99957243.0428621.5250.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged366
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151631
Totals57243.040.0028621.5250.0

CountyNUECES
HighwaySH0361
FromFERRY BUILDING
ToFERRY BUILDING
CSJ6300-46-001
Proj IDEMC - 630046001
Work TypeFERRY BUILDING COMPLETION
 
0.00985400.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BALDWIN ROOFING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6300-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02161655
Totals85400.000.000.000.0

CountyNUECES
HighwaySH0358
FromVARIOUS
To.
CSJ6300-59-001
Proj IDSUP - 630059001
Work TypeLITTER PICKUP
 
25.200344887.50226335.8965.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged245
Percent Time Used67
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161632
Totals344887.500.00226335.8965.6

CountyNUECES
HighwaySH0286
FromDISTRICT HEADQUARTERS
To.
CSJ6302-76-001
Proj IDSUP - 630276001
Work TypeSERVICE STATION ATTENDANT
 
0.99922353.2812026.7553.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged245
Percent Time Used67
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161630
Totals22353.280.0012026.7553.8

CountyLIVE OAK
HighwayFM0534
FromVARIOUS
To.
CSJ6303-46-001
Proj IDBPM - 630346001
Work TypeCONCRETE STRUCTURE REPAIR
 
0.99954940.0054940.0099.9
Work Order10-04-16
Work Began00-00-00
Work Completed
Time Computed10-17-16
Contract Working Days34
Addl Days Granted0
Working Days Charged28
Percent Time Used82
Contractor(s)
OPPORTUNITY EXCAVATION/CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161601
Totals54940.0044240.0054940.0099.9

CountyKARNES
HighwayFM1353
FromVARIOUS
To.
CSJ6303-47-001
Proj IDBPM - 630347001
Work TypeCONCRETE STRUCTURE REPAIR
 
0.99931861.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-05-16
Work Began00-00-00
Work Completed
Time Computed12-12-16
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TCB CONSTRUCTION, INC
SUBCONTRACTOR(S) FOR CCSJ: 6303-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161605
Totals31861.000.000.000.0

CountyKLEBERG
HighwayUS0077
FromUS 77 @ ARANA CREEK
To.
CSJ6303-48-001
Proj IDBPM - 630348001
Work TypeCONCRETE STRUCTURE REPAIR
 
0.99924948.0038404.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-16
Work Began00-00-00
Work Completed
Time Computed09-26-16
Contract Working Days17
Addl Days Granted0
Working Days Charged7
Percent Time Used41
Contractor(s)
TEXCAVATION COMPANY LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161604
Totals24948.000.0038404.0099.9

CountyNUECES
HighwayIH0037
FromVARIOUS
To.
CSJ6303-49-001
Proj IDBPM - 630349001
Work TypeCONCRETE STRUCTURE REPAIR
 
0.99933480.0033150.0099.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days17
Addl Days Granted0
Working Days Charged13
Percent Time Used76
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161602
Totals33480.000.0033150.0099.0

page 1 | page 2 | page 3 | page 4 | page 5