Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBEE
Highway US0181
From VARIOUS
To .
CSJ 6266-95-001
Proj ID SUP - 626695001
Work Type PICNIC AREA MAINTENANCE
 
0.025 52455.36 2104.17 7096.07 13.5
Work Order 00-00-00
Work Began 12-01-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6266-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131630
Totals 52455.36 2104.17 7096.07 13.5

CountyKARNES
Highway SH0123
From SH 0080
To SOUTH END OF CIBOLO CREEK
CSJ 6267-18-001
Proj ID RMC - 626718001
Work Type STRUCTURE REPAIR
 
8.638 331183.27 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141601
Totals 331183.27 0.00 0.00 0.0

CountySAN PATRICIO
Highway SH0359
From SIX MILE CREEK
To .
CSJ 6267-28-001
Proj ID RMC - 626728001
Work Type SAFETY TREAT EXISTING STRUCTURE
 
0.999 66300.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141601
Totals 66300.00 0.00 0.00 0.0

CountyGOLIAD
Highway FM1351
From ON FM 1351 @ DRAW AND
To FM 3410 @ SARCO CREEK
CSJ 6268-56-001
Proj ID BPM - 626856001
Work Type CONCRETE STRUCTURE REPAIR
 
0.999 33710.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
Z & L CONCRETE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141604
Totals 33710.00 0.00 0.00 0.0

CountySAN PATRICIO
Highway FM0796
From CHILTIPIN CREEK
To .
CSJ 6268-86-001
Proj ID BPM - 626886001
Work Type CONCRETE STRUCTURE REPAIR
 
0.999 19450.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141605
Totals 19450.00 0.00 0.00 0.0

CountyREFUGIO
Highway US0077
From ON US 77 NORTH OF REFUGIO
To .
CSJ 6269-05-001
Proj ID RMC - 626905001
Work Type OVERHEIGHT DETECTION SYSTEM
 
0.999 203453.19 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 31
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6269-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141602
Totals 203453.19 0.00 0.00 0.0

CountyKARNES
Highway US0181
From VARIOUS
To .
CSJ 6270-19-001
Proj ID SUP - 627019001
Work Type GUARDRAIL REPAIR
 
999.000 206460.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141632
Totals 206460.00 0.00 0.00 0.0

CountyNUECES
Highway SH0358
From VARIOUS
To .
CSJ 6271-16-001
Proj ID SUP - 627116001
Work Type LITTER PICKUP
 
25.200 315530.64 25874.22 25874.22 8.2
Work Order 03-01-14
Work Began 03-01-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141630
Totals 315530.64 25874.22 25874.22 8.2

CountyKARNES
Highway SH0239
From SH 72
To US 59
CSJ 6271-57-001
Proj ID EMC - 627157001
Work Type SPOT BASE REPAIR
 
17.970 1382571.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6271-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141615
Totals 1382571.48 0.00 0.00 0.0