Monthly Local Let Maintenance Report For Corpus Christi District As Of Jul 11, 2014 Page 3 Of 3

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySAN PATRICIO
Highway FM0796
From CHILTIPIN CREEK
To .
CSJ 6268-86-001
Proj ID BPM - 626886001
Work Type CONCRETE STRUCTURE REPAIR
 
0.999 19450.00 6300.00 6300.00 32.3
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 05-01-14
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 60
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141605
Totals 19450.00 6300.00 6300.00 32.3

CountyREFUGIO
Highway US0077
From ON US 77 NORTH OF REFUGIO
To .
CSJ 6269-05-001
Proj ID RMC - 626905001
Work Type OVERHEIGHT DETECTION SYSTEM
 
0.999 203453.19 109476.63 120989.58 59.4
Work Order 04-28-14
Work Began 05-07-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 31
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 38
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6269-05-001
HIGHWAY BARRICADES AND SERVICES, LLC (0.95%)
Contract # 02141602
Totals 203453.19 109476.63 120989.58 59.4

CountyLIVE OAK
Highway US0281
From VARIOUS SECTIONS IN JIM WELLS, KLEBERG
To & LIVE OAK COUNTIES
CSJ 6270-18-001
Proj ID SUP - 627018001
Work Type GUARDRAIL REPAIR
 
0.999 314085.00 9080.00 28976.00 9.2
Work Order 04-01-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141634
Totals 314085.00 9080.00 28976.00 9.2

CountyKARNES
Highway US0181
From VARIOUS
To .
CSJ 6270-19-001
Proj ID SUP - 627019001
Work Type GUARDRAIL REPAIR
 
999.000 206460.00 5973.00 32673.00 15.8
Work Order 04-01-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141632
Totals 206460.00 5973.00 32673.00 15.8

CountySAN PATRICIO
Highway US0077
From VARIOUS ROADWAYS IN SAN PATRICIO,
To REFUGIO, & ARANSAS COUNTIES
CSJ 6270-20-001
Proj ID SUP - 627020001
Work Type GUARDRAIL REPAIR
 
0.999 387455.00 2500.00 33478.40 8.6
Work Order 04-01-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141635
Totals 387455.00 2500.00 33478.40 8.6

CountyNUECES
Highway SH0358
From VARIOUS
To .
CSJ 6271-16-001
Proj ID SUP - 627116001
Work Type LITTER PICKUP
 
25.200 315530.64 25874.22 103496.88 32.8
Work Order 03-01-14
Work Began 03-01-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141630
Totals 315530.64 25874.22 103496.88 32.8