AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - CORPUS CHRISTI DISTRICT
Last Update: Friday, May 3, 2013
| ITEMS 730 2002 TO 760 2003 |
| Item No |
Description |
Units |
April 30, 2013 |
Twelve Month Moving |
Usage |
| Quantity |
Avg Bid |
Quantity |
Avg Bid |
| 730 2002 |
FULL - WIDTH MOWING |
AC |
|
|
507.000 |
59.46746 |
2 |
| 740 2005 |
ANTI - GRAFFITI COATING (PERMANENT) |
SF |
|
|
6,124.000 |
.33000 |
1 |
| 752 2020 |
TREE TRIMMING / BRUSH REMOVAL |
MI |
|
|
6.300 |
6,000.00000 |
1 |
| 752 2022 |
TREE REMOVAL (4" - 12" DIA) |
EA |
|
|
1.000 |
543.00000 |
1 |
| 752 2023 |
TREE REMOVAL (12" - 18" DIA) |
EA |
|
|
7.000 |
858.00000 |
1 |
| 752 2024 |
TREE REMOVAL (18" - 24" DIA) |
EA |
|
|
5.000 |
1,593.00000 |
1 |
| 760 2001 |
DITCH CLEANING AND RESHAPING (FOOT) |
LF |
|
|
66,306.000 |
1.82000 |
2 |
| 760 2003 |
DITCH CLEAN / RESHAPING (CU YD IN VEHICLE |
CY |
|
|
370.000 |
14.75000 |
1 |