AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - CORPUS CHRISTI DISTRICT

Last Update: Thursday, November 20, 2014
ITEMS 100 2002 TO 193 2001
Items Items Bid Code Range
0100 - 0193
0216 - 0275
0310 - 0354
0400 - 0496
0500 - 0560
0610 - 0690
0760 - 0760
1122 - 1122
2214 - 2214
3142 - 3268
4174 - 4174
5367 - 5367
6007 - 6834
8020 - 8942
100 2002 - 193 2001
Item No Description Units November 30, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 2002 PREPARING ROW STA     1,594.520 412.12655 12
100 2004 PREPARING ROW (TREE) (12" TO 24" DIA) EA     5.000 1,303.08000 1
100 2005 PREP ROW (TREE) (24" - 30"DIA) EA     5.000 1,303.08000 1
100 2010 PREPARING ROW (TREE) (10" TO 48" DIA) EA     15.000 1,100.00000 1
104 2009 REMOVING CONC (RIPRAP) SY     382.000 28.27199 5
104 2015 REMOVING CONC (SIDEWALKS) SY     31.000 65.00000 1
104 2017 REMOVING CONC (DRIVEWAYS) SY     708.000 11.81921 2
104 2022 REMOVING CONC (CURB AND GUTTER) LF     493.000 9.00000 1
104 2024 REMOVING CONC (RETAINING WALLS) SY     343.000 72.54000 1
104 2028 REMOVING CONC (MISC) SY     16.000 78.68000 1
104 2036 REMOVING CONC (SIDEWALK OR RAMP) SY     8.000 22.00000 1
105 2018 REMOVING STAB BASE AND ASPH PAV (7") SY     5,058.000 4.78000 1
106 2002 OBLITERATING ABANDONED ROAD SY     6,813.000 4.15446 3
110 2001 EXCAVATION (ROADWAY) CY     33,865.000 8.45955 7
110 2002 EXCAVATION (CHANNEL) CY     877.000 15.93501 3
112 2001 SUBGRADE WIDENING (ORD COMP) STA     865.000 405.25676 3
112 2002 SUBGRADE WIDENING (DENS CONT) STA     132.000 954.54545 2
132 2003 EMBANKMENT (FINAL) (ORD COMP) (TY B) CY     5,726.000 15.45992 2
132 2006 EMBANKMENT (FINAL) (DENS CONT) (TY C) CY     26,423.000 10.14165 6
132 2007 EMBANKMENT (FINAL) (ORD COMP) (TY D) CY     425.000 30.00000 1
134 2001 BACKFILL (TY A) STA     1,238.000 213.51430 2
134 2002 BACKFILL (TY B) STA     325.000 242.15077 2
134 2004 BACKFILL (TY A OR B) STA     1,667.000 95.55000 1
150 2002 BLADING HR     50.000 228.70000 1
160 2003 FURNISHING AND PLACING TOPSOIL (4") SY     18,599.000 2.73621 2
160 2005 FURNISHING AND PLACING TOPSOIL CY     2,088.000 2.05000 1
161 2005 COMPOST MANUF TOPSOIL (PB) (4") SY     1,350.000 7.00000 1
161 2022 GENERAL USE COMPOST (4") SY     275.000 5.00000 1
161 2026 COMPOST MANUF TOPSOIL (BOS OR PB) (6") SY     16.000 85.88000 1
161 2028 EROSION CONTROL COMPOST (3") SY     275.000 5.00000 1
162 2002 BLOCK SODDING SY     7,552.000 4.14964 3
164 2001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY     2,250.000 .45000 1
164 2011 BROADCAST SEED (TEMP) (COOL) SY     431.000 2.25000 1
164 2021 CELL FBR MLCH SEED (PERM) (RURAL) (SANDY) SY     175,339.000 .27740 2
164 2023 CELL FBR MLCH SEED (PERM) (RURAL) (CLAY) SY     53,228.000 .40288 3
164 2029 CELL FBR MLCH SEED (TEMP) (WARM) SY     2,719.000 .64000 1
164 2031 CELL FBR MLCH SEED (TEMP) (COOL) SY     50,755.000 .12893 2
164 2035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY     231,964.000 .23781 4
166 2002 FERTILIZER TON     11.580 1,123.77375 5
168 2001 VEGETATIVE WATERING MG     13,021.660 26.25292 11
169 2002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY     2,681.000 1.45000 1
170 2001 IRRIGATION SYSTEM LS     2.000 28,305.00000 2
180 2001 WILDFLOWER SEEDING AC     16.000 1,500.00000 1
192 2001 PLANT MATERIAL (4" CNTR) EA     50.000 2.00000 1
192 2002 PLANT MATERIAL (1 - GAL) EA     1,166.000 11.00000 1
192 2004 PLANT MATERIAL (5 - GAL) EA     257.000 30.00000 1
192 2012 MULCH CY     157.000 69.00000 1
192 2015 LANDSCAPE EDGE LF     460.000 20.00000 1
192 2016 PLANT BED PREPARATION SY     2,149.000 14.15635 2
192 2017 VEGETATION BARRIER SY     1,874.000 2.75000 1
192 2024 PLANT MATERIAL (30 GAL) (TREE) EA     66.000 280.00000 1
192 2049 PLANT MATERIAL (MIN 4' TRNK HT) (PALM) EA     23.000 500.00000 1
193 2001 PLANT MAINTENANCE MO     12.000 1,000.00000 1