| AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - CORPUS CHRISTI DISTRICT | ||||
| Last Update: Thursday, October 29, 2009 |
| ITEMS 100 2002 TO 192 2077 |
| Items | Items | Bid Code Range |
|---|---|---|
| 0100 - 0192 0216 - 0275 0310 - 0354 0400 - 0497 0500 - 0560 0610 - 0690 0712 - 0730 |
3185 - 3185 4444 - 4448 5049 - 5696 6006 - 6834 8251 - 8397 |
100 2002 - 192 2077 |
| Item No | Description | Units | October 31, 2009 | Twelve Month Moving | Usage | ||
|---|---|---|---|---|---|---|---|
| Quantity | Avg Bid | Quantity | Avg Bid | ||||
| 100 2002 | PREPARING ROW | STA | 1,609.440 | 1,165.49262 | 10 | ||
| 104 2009 | REMOVING CONC (RIPRAP) | SY | 234.000 | 4.41462 | 2 | ||
| 104 2010 | REMOVING CONC (RIPRAP) | CY | 124.000 | 395.16000 | 124.000 | 395.16000 | 1 |
| 104 2021 | REMOVING CONC (CURB) | LF | 535.000 | 3.33000 | 1 | ||
| 104 2022 | REMOVING CONC (CURB AND GUTTER) | LF | 5,709.000 | 4.38762 | 3 | ||
| 104 2026 | REMOVE CONC (GUTTER) | LF | 305.000 | 3.33000 | 1 | ||
| 104 2040 | REMOVING CONC (PAVERS) | SY | 381.000 | 2.13000 | 1 | ||
| 106 2001 | OBLITERATING ABANDONED ROAD | STA | 48.000 | 79.00000 | 1 | ||
| 110 2001 | EXCAVATION (ROADWAY) | CY | 159,342.000 | 3.06628 | 8 | ||
| 110 2002 | EXCAVATION (CHANNEL) | CY | 14,247.000 | 5.19372 | 5 | ||
| 110 2003 | EXCAVATION (SPECIAL) | CY | 1,426.000 | 38.50000 | 1 | ||
| 112 2002 | SUBGRADE WIDENING (DENS CONT) | STA | 299.200 | 84.00000 | 1 | ||
| 132 2001 | EMBANKMENT (FINAL) (ORD COMP) (TY A) | CY | 42.000 | 142.97000 | 2 | ||
| 132 2004 | EMBANKMENT (FINAL) (DENS CONT) (TY B) | CY | 14,406.000 | 2.34381 | 2 | ||
| 132 2005 | EMBANKMENT (FINAL) (ORD COMP) (TY C) | CY | 283.000 | 7.94000 | 1 | ||
| 132 2006 | EMBANKMENT (FINAL) (DENS CONT) (TY C) | CY | 374,443.000 | 6.07785 | 4 | ||
| 132 2008 | EMBANKMENT (FINAL) (DENS CONT) (TY D) | CY | 3,313.000 | 3.17199 | 2 | ||
| 132 2021 | EMBANKMENT (VEHICLE) (ORD COMP) (TY C) | CY | 2,083.000 | 5.00000 | 1 | ||
| 134 2001 | BACKFILL (TY A) | STA | 4,721.220 | 61.69558 | 9 | ||
| 134 2002 | BACKFILL (TY B) | STA | 299.200 | 35.00000 | 1 | ||
| 134 2004 | BACKFILL (TY A OR B) | STA | 564.300 | 52.48527 | 4 | ||
| 150 2001 | BLADING | STA | 2,492.000 | 3.30000 | 1 | ||
| 161 2002 | COMPOST MANUF TOPSOIL (BOS) (4") | SY | 3,225.000 | 2.00000 | 1 | ||
| 161 2026 | COMPOST MANUF TOPSOIL (BOS OR PB) (6") | SY | 4,206.000 | 4.39000 | 2 | ||
| 161 2028 | EROSION CONTROL COMPOST (3") | SY | 619.000 | 2.50000 | 1 | ||
| 162 2002 | BLOCK SODDING | SY | 24,396.000 | 2.84636 | 4 | ||
| 164 2003 | BROADCAST SEED (PERM) (RURAL) (CLAY) | SY | 2,890.000 | .60000 | 1 | ||
| 164 2015 | STRAW / HAY MLCH SEED (PERM) (RURAL) (CLAY) | SY | 149,102.000 | .22000 | 1 | ||
| 164 2021 | CELL FBR MLCH SEED (PERM) (RURAL) (SANDY) | SY | 9,027.000 | .23000 | 1 | ||
| 164 2023 | CELL FBR MLCH SEED (PERM) (RURAL) (CLAY) | SY | 16,212.000 | .29061 | 2 | ||
| 164 2031 | CELL FBR MLCH SEED (TEMP) (COOL) | SY | 2,890.000 | .60000 | 1 | ||
| 164 2035 | DRILL SEEDING (PERM) (RURAL) (CLAY) | SY | 646,309.000 | .07350 | 4 | ||
| 166 2002 | FERTILIZER | TON | 26.300 | 440.64106 | 4 | ||
| 168 2001 | VEGETATIVE WATERING | MG | 13,694.130 | 8.19197 | 8 | ||
| 170 2001 | IRRIGATION SYSTEM | LS | 1.000 | 13,500.00000 | 1 | ||
| 192 2015 | LANDSCAPE EDGE | LF | 588.000 | 1.20000 | 1 | ||
| 192 2016 | PLANT BED PREPARATION | SY | 620.000 | 10.00000 | 1 | ||
| 192 2023 | PLANT MATERIAL (15 GAL) (TREE) | EA | 29.000 | 100.00000 | 1 | ||
| 192 2024 | PLANT MATERIAL (30 GAL) (TREE) | EA | 48.000 | 100.00000 | 1 | ||
| 192 2031 | PLANT MATERIAL (5 GAL) (SHRUB) | EA | 861.000 | 15.95000 | 1 | ||
| 192 2052 | PLANT MATERIAL (MIN 10' TRNK HT) (PALM | EA | 46.000 | 700.00000 | 1 | ||
| 192 2077 | PLANT MATERIAL (MIN 3' HT) (PALM) | EA | 64.000 | 400.00000 | 1 | ||
| | ||||
|