Monthly Local Let Maintenance Report For Brownwood District As Of Feb 10, 2017 Page 2 Of 5

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBROWN
HighwayUS0183
FromN/A
ToN/A
CSJ6259-67-001
Proj IDSUP - 625967001
Work TypeSTATE USE JANITORIAL BWD AREA OFC
 
0.00114258.7213050.5291.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-13
Work Began10-01-13
Work Completed
Time Computed10-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08132332
Totals14258.720.0013050.5291.5

CountyBROWN
HighwayUS0183
FromVARIOUS
ToVARIOUS
CSJ6259-68-001
Proj IDSUP - 625968001
Work TypeSTATE USE JANITORIAL BROWN CO MAINT
 
0.00113816.8011821.8085.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-13
Work Began10-01-13
Work Completed
Time Computed10-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08132333
Totals13816.800.0011821.8085.5

CountyMILLS
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6259-69-001
Proj IDSUP - 625969001
Work TypeSTATE USE JANITORIAL MILLS CO MAINT
 
0.00110957.7310828.6598.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-13
Work Began10-01-13
Work Completed
Time Computed10-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged673
Percent Time Used92
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08132334
Totals10957.730.0010828.6598.8

CountyEASTLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6265-77-001
Proj IDRMC - 626577001
Work TypeROADSIDE MOWING
 
367.820259802.50529394.8899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-03-13
Work Began12-10-13
Work Completed
Time Computed12-10-13
Contract Working Days85
Addl Days Granted85
Working Days Charged102
Percent Time Used60
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6265-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10132301
Totals259802.500.00529394.8899.9

CountySAN SABA
HighwayUS0190
FromN/A
ToN/A
CSJ6267-26-001
Proj IDSUP - 626726001
Work TypeSTATE USE JANITORIAL - SAN SABA
 
0.00121886.0019964.0091.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-01-14
Work Began00-00-00
Work Completed
Time Computed01-01-14
Contract Working Days730
Addl Days Granted790
Working Days Charged593
Percent Time Used39
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6267-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11132330
Totals21886.000.0019964.0091.2

CountyBROWN
HighwayUS0183
FromN/A
ToN/A
CSJ6268-63-001
Proj IDSUP - 626863001
Work TypeSTATE USE JANITORIAL - DIST OFC
 
0.00160473.0082886.2599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-14
Work Began00-00-00
Work Completed
Time Computed03-01-14
Contract Working Days730
Addl Days Granted730
Working Days Charged802
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6268-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12132330
Totals60473.000.0082886.2599.9

CountyBROWN
HighwayUS0067
FromBROWN COUNTY
ToBROWN COUNTY
CSJ6270-71-001
Proj IDRMC - 627071001
Work TypeROADSIDE MOWING
 
326.700288805.20453862.1299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-03-16
Work Began00-00-00
Work Completed
Time Computed10-10-16
Contract Working Days95
Addl Days Granted95
Working Days Charged78
Percent Time Used41
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6270-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04142301
Totals288805.200.00453862.1299.9

CountyMCCULLOCH
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6270-97-001
Proj IDRMC - 627097001
Work TypeREMOVAL/DISPOSAL OF
 
0.001245768.20541408.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-16-14
Work Began06-16-14
Work Completed
Time Computed06-23-14
Contract Working Days45
Addl Days Granted75
Working Days Charged84
Percent Time Used70
Contractor(s)
DEKALB TREE SPECIALIST
SUBCONTRACTOR(S) FOR CCSJ: 6270-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05142301
Totals245768.200.00541408.5099.9

CountyBROWN
HighwayUS0377
FromVARIOUS
ToVARIOUS
CSJ6272-68-001
Proj IDSUP - 627268001
Work TypeSTATE-USE LITTER PICKUP AND
 
0.00196521.5291521.5294.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-14
Work Began06-01-14
Work Completed
Time Computed06-01-14
Contract Working Days730
Addl Days Granted0
Working Days Charged739
Percent Time Used101
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04142330
Totals96521.520.0091521.5294.8

CountyBROWN
HighwayUS0377
FromDISTRICT-WIDE
ToDISTRICT-WIDE
CSJ6273-26-001
Proj IDRMC - 627326001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.001379430.00495372.3899.9
Work Order04-19-16
Work Began11-17-14
Work Completed
Time Computed04-26-16
Contract Working Days100
Addl Days Granted0
Working Days Charged65
Percent Time Used65
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 6273-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06142301
Totals379430.0025620.00495372.3899.9

CountyBROWN
HighwayUS0377
FromDISTRICT-WIDE
ToDISTRICT-WIDE
CSJ6273-28-001
Proj IDRMC - 627328001
Work TypeREPAIR MBGF (WILL-CALL) (AS NEEDED)
 
0.001300575.00384574.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-15
Work Began04-14-15
Work Completed
Time Computed04-15-15
Contract Working Days150
Addl Days Granted0
Working Days Charged120
Percent Time Used80
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6273-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01152301
Totals300575.000.00384574.0099.9

CountyBROWN
HighwayUS0377
FromUNKNOWN LOCATIONS
To" "
CSJ6275-46-001
Proj IDRMC - 627546001
Work TypeMILL & INLAY
 
0.758284123.78556274.15100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-04-14
Work Began08-11-14
Work Completed01-21-15
Time Computed08-11-14
Contract Working Days20
Addl Days Granted20
Working Days Charged18
Percent Time Used45
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07142302
Totals284123.780.00556274.15100.0

CountyLAMPASAS
HighwayUS0281
FromVARIOUS
ToVARIOUS
CSJ6277-99-001
Proj IDSUP - 627799001
Work TypeSTATE USE GROUNDS MAINTENANCE
 
0.00112000.002800.0023.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-14
Work Began08-01-14
Work Completed
Time Computed08-01-14
Contract Working Days730
Addl Days Granted0
Working Days Charged534
Percent Time Used73
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08142330
Totals12000.000.002800.0023.3

CountyCOLEMAN
HighwayUS0283
FromVARIOUS
ToVARIOUS
CSJ6279-86-001
Proj IDRMC - 627986001
Work TypeROADSIDE MOWING
 
0.001229853.73296005.8199.9
Work Order12-01-14
Work Began12-08-14
Work Completed
Time Computed12-08-14
Contract Working Days75
Addl Days Granted75
Working Days Charged129
Percent Time Used86
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6279-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10142302
Totals229853.730.00296005.8199.9

CountyCOMANCHE
HighwayUS0067
FromVARIOUS
ToVARIOUS
CSJ6279-87-001
Proj IDRMC - 627987001
Work TypeROADSIDE MOWING
 
0.001236904.46251333.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-08-14
Work Began12-11-14
Work Completed
Time Computed12-15-14
Contract Working Days65
Addl Days Granted0
Working Days Charged35
Percent Time Used53
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10142303
Totals236904.460.00251333.0499.9

CountyMCCULLOCH
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6279-88-001
Proj IDRMC - 627988001
Work TypeROADSIDE MOWING
 
0.001241118.00318260.5099.9
Work Order11-25-14
Work Began11-29-14
Work Completed
Time Computed12-02-14
Contract Working Days55
Addl Days Granted55
Working Days Charged74
Percent Time Used67
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6279-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10142304
Totals241118.000.00318260.5099.9

CountySAN SABA
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6279-89-001
Proj IDRMC - 627989001
Work TypeROADSIDE MOWING
 
0.001206625.65136151.4065.8
Work Order06-02-15
Work Began06-02-15
Work Completed
Time Computed06-09-15
Contract Working Days55
Addl Days Granted0
Working Days Charged25
Percent Time Used45
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6279-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10142305
Totals206625.650.00136151.4065.8

CountyCOLEMAN
HighwayUS0067
FromVARIOUS
ToVARIOUS
CSJ6281-93-001
Proj IDSUP - 628193001
Work TypeSTATE USE LITTER REMOVAL
 
0.00142359.1630644.3772.3
Work Order03-01-15
Work Began03-01-15
Work Completed
Time Computed03-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged703
Percent Time Used96
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02152330
Totals42359.160.0030644.3772.3

CountyMCCULLOCH
HighwayUS0087
FromVARIOUS
ToVARIOUS
CSJ6281-94-001
Proj IDSUP - 628194001
Work TypeSU-ALDERSGATE-LITTER REMOVAL
 
0.00127557.5819968.9972.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-15
Work Began05-01-15
Work Completed
Time Computed11-16-15
Contract Working Days730
Addl Days Granted0
Working Days Charged642
Percent Time Used87
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02152331
Totals27557.580.0019968.9972.4

CountyCOMANCHE
HighwayUS0067
FromVARIOUS
ToVARIOUS
CSJ6281-95-001
Proj IDSUP - 628195001
Work TypeSU-LITTER-ALDERSGATE
 
0.00183298.1676524.3891.8
Work Order03-01-15
Work Began03-01-15
Work Completed
Time Computed03-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged703
Percent Time Used96
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02152332
Totals83298.167154.1676524.3891.8

page 1 | page 2 | page 3 | page 4 | page 5