Monthly Local Let Maintenance Report For Brownwood District As Of Nov 22, 2017 Page 2 Of 3

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLAMPASAS
HighwayUS0183
FromVARIOUS
To***
CSJ6297-50-001
Proj IDSUP - 629750001
Work TypeSTATE USE/LITTER/BOOTSTRAPS
 
0.00191193.2469827.6476.5
Work Order12-01-15
Work Began12-01-15
Work Completed
Time Computed12-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged701
Percent Time Used96
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6297-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11152331
Totals91193.240.0069827.6476.5

CountyEASTLAND
HighwaySH0112
FromEASTLAND AREA/MNT OFFICE
To***
CSJ6298-23-001
Proj IDSUP - 629823001
Work TypeSTATE USE JANITOR-JCI/CFLR
 
0.00155091.9241025.4874.4
Work Order02-01-16
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged669
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6298-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11152332
Totals55091.921988.0641025.4874.4

CountyEASTLAND
HighwaySH0006
FromVARIOUS
To***
CSJ6301-28-001
Proj IDRMC - 630128001
Work TypeTREE TRIMMING, ETC.
 
0.001278780.00446690.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-30-17
Work Began12-01-16
Work Completed
Time Computed06-06-17
Contract Working Days100
Addl Days Granted100
Working Days Charged63
Percent Time Used31
Contractor(s)
DEKALB TREE SPECIALIST
SUBCONTRACTOR(S) FOR CCSJ: 6301-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162301
Totals278780.000.00446690.0099.9

CountyBROWN
HighwaySH0279
FromVARIOUS
To***
CSJ6301-29-001
Proj IDRMC - 630129001
Work TypeTREE TRIMMING, ETC.
 
0.001278780.00345308.0099.9
Work Order10-06-16
Work Began09-07-16
Work Completed
Time Computed09-13-16
Contract Working Days100
Addl Days Granted0
Working Days Charged55
Percent Time Used55
Contractor(s)
DEKALB TREE SPECIALIST
SUBCONTRACTOR(S) FOR CCSJ: 6301-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162302
Totals278780.000.00345308.0099.9

CountyCOMANCHE
HighwayUS0067
FromVARIOUS
To***
CSJ6301-76-001
Proj IDRMC - 630176001
Work TypeROADSIDE MOWING (WILL-CALL) (AS NEEDED)
 
0.001354857.95371912.5799.9
Work Order06-21-16
Work Began06-23-16
Work Completed
Time Computed06-28-16
Contract Working Days85
Addl Days Granted0
Working Days Charged62
Percent Time Used72
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162301
Totals354857.9568701.32371912.5799.9

CountyEASTLAND
HighwayIH0020
FromVARIOUS
To***
CSJ6301-77-001
Proj IDRMC - 630177001
Work TypeROADSIDE MOWING (WILL-CALL)(AS NEEDED)
 
0.001331712.00401596.0099.9
Work Order07-05-16
Work Began07-12-16
Work Completed
Time Computed07-12-16
Contract Working Days90
Addl Days Granted0
Working Days Charged81
Percent Time Used90
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6301-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162302
Totals331712.000.00401596.0099.9

CountyMILLS
HighwayUS0084
FromVARIOUS
To***
CSJ6301-78-001
Proj IDRMC - 630178001
Work TypeROADSIDE MOWING (WILL-CALL)(AS NEEDED)
 
0.001314621.06187017.8659.4
Work Order07-12-16
Work Began07-13-16
Work Completed
Time Computed07-19-16
Contract Working Days76
Addl Days Granted0
Working Days Charged23
Percent Time Used30
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6301-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162303
Totals314621.060.00187017.8659.4

CountyBROWN
HighwayUS0377
FromVARIOUS
To***
CSJ6304-51-001
Proj IDSUP - 630451001
Work TypeALDERSGATE/STATE USE/LITTER REMOVAL
 
0.001157255.90108926.6269.2
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged539
Percent Time Used73
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162330
Totals157255.904009.59108926.6269.2

CountyEASTLAND
HighwaySH0006
FromSH0006 AT LAKE CISCO
To***
CSJ6305-90-001
Proj IDEMC - 630590001
Work TypeBUILD 3 SPAN BRIDGE
 
0.0033343810.503425818.8199.9
Work Order08-08-16
Work Began08-08-16
Work Completed
Time Computed08-08-16
Contract Working Days185
Addl Days Granted0
Working Days Charged308
Percent Time Used166
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-90-001
BEAIRD DRILLING (7.68)
GRANBURY EXCAVATING, INC. (19.60)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.49)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.82)
HJC FARMS, INC. (2.03)
LONE STAR PAVING COMPANY (5.45)
Contract #07162302
Totals3343810.500.003425818.8199.9

CountySAN SABA
HighwayUS0190
FromSAN SABA MAINTENANCE OFFICE
To***
CSJ6307-67-001
Proj IDSUP - 630767001
Work TypeSTATE USE JANITOR CEN TEX MHMR/CFLR
 
0.00121216.009195.0043.3
Work Order08-01-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged457
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6307-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07162330
Totals21216.00809.009195.0043.3

CountySTEPHENS
HighwayUS0180
FromVARIOUS
To***
CSJ6312-32-001
Proj IDSUP - 631232001
Work TypeSTATE USE LITTER REMOVAL
 
0.001129291.3544697.7634.5
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged273
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01172330
Totals129291.350.0044697.7634.5

CountySAN SABA
HighwayUS0190
FromVARIOUS
To***
CSJ6315-56-001
Proj IDRMC - 631556001
Work TypeROADSIDE MOWING
 
0.001174960.9429666.0016.9
Work Order06-12-17
Work Began06-13-17
Work Completed
Time Computed06-19-17
Contract Working Days65
Addl Days Granted0
Working Days Charged9
Percent Time Used13
Contractor(s)
BUCKSHOT WELDING & FABRICATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172301
Totals174960.940.0029666.0016.9

CountyCOLEMAN
HighwayUS0067
FromVARIOUS
To***
CSJ6315-57-001
Proj IDSUP - 631557001
Work TypeSTATE USE LITTER-ALDERSGATE
 
0.00144712.9610615.7423.7
Work Order05-01-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged184
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172330
Totals44712.960.0010615.7423.7

CountyCOMANCHE
HighwayUS0067
FromVARIOUS
To***
CSJ6315-58-001
Proj IDSUP - 631558001
Work TypeSTATE USE LITTER-ALDERSGATE
 
0.00189635.2025963.4728.9
Work Order04-20-17
Work Began04-20-17
Work Completed
Time Computed04-20-17
Contract Working Days735
Addl Days Granted0
Working Days Charged195
Percent Time Used26
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172331
Totals89635.203929.6725963.4728.9

CountyEASTLAND
HighwayIH0020
FromVARIOUS
To***
CSJ6315-59-001
Proj IDSUP - 631559001
Work TypeSTATE USE LITTER-ALDERSGATE
 
0.001163320.3657554.3035.2
Work Order03-01-17
Work Began03-01-17
Work Completed
Time Computed03-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged245
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172330
Totals163320.361715.6357554.3035.2

CountyCOMANCHE
HighwaySH0016
FromCOMANCHE MAINTENANCE OFFICE
To***
CSJ6315-71-001
Proj IDSUP - 631571001
Work TypeSTATE USE JANITORIAL-CEN TEX MHMR/JCI
 
0.00132986.249050.2327.4
Work Order03-01-17
Work Began03-01-17
Work Completed
Time Computed03-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged245
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6315-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172331
Totals32986.241258.619050.2327.4

CountyMCCULLOCH
HighwayUS0190
FromVARIOUS
To***
CSJ6318-39-001
Proj IDSUP - 631839001
Work TypeSTATE USE LITTER REMOVAL-ALDERSGATE
 
0.00127129.325639.9620.7
Work Order06-01-17
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05172330
Totals27129.320.005639.9620.7

CountySAN SABA
HighwayUS0190
FromVARIOUS
To***
CSJ6318-40-001
Proj IDSUP - 631840001
Work TypeSTATE USE LITTER REMOVAL-ALDERSGATE
 
0.00131575.160.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-06-17
Work Began06-01-17
Work Completed
Time Computed11-13-17
Contract Working Days735
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05172331
Totals31575.160.000.000.0

CountyCOLEMAN
HighwaySH0206
FromCOLEMAN MAINTENANCE OFFICE
To***
CSJ6319-33-001
Proj IDSUP - 631933001
Work TypeSU JANITORIAL-JCT/CEN TEX MHMR
 
0.00131159.204359.0913.9
Work Order07-01-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged123
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6319-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06172332
Totals31159.201263.304359.0913.9

CountyMCCULLOCH
HighwayUS0377
FromMCCULLOCH COUNTY MAINTENANCE OFFICE
To***
CSJ6319-34-001
Proj IDSUP - 631934001
Work TypeSU JANITORIAL-JCI/CEN TEX MHMR
 
0.00119511.362719.7413.9
Work Order07-01-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged123
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6319-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06172333
Totals19511.36795.472719.7413.9

page 1 | page 2 | page 3