Monthly Local Let Maintenance Report For Brownwood District As Of Apr 11, 2014 Page 3 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOLEMAN
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6259-65-001
Proj ID SUP - 625965001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 82500.00 2475.00 17775.00 21.5
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132330
Totals 82500.00 2475.00 17775.00 21.5

CountyMCCULLOCH
Highway US0377
From VARIOUS
To VARIOUS
CSJ 6259-66-001
Proj ID SUP - 625966001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 91100.00 3060.00 23150.00 25.4
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132331
Totals 91100.00 3060.00 23150.00 25.4

CountyBROWN
Highway US0183
From N/A
To N/A
CSJ 6259-67-001
Proj ID SUP - 625967001
Work Type STATE USE JANITORIAL BWD AREA OFC
 
0.001 14258.72 488.68 2989.08 20.9
Work Order 10-01-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132332
Totals 14258.72 488.68 2989.08 20.9

CountyBROWN
Highway US0183
From VARIOUS
To VARIOUS
CSJ 6259-68-001
Proj ID SUP - 625968001
Work Type STATE USE JANITORIAL BROWN CO MAINT OFC
 
0.001 13816.80 841.70 3055.20 22.1
Work Order 10-01-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132333
Totals 13816.80 841.70 3055.20 22.1

CountyMILLS
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6259-69-001
Proj ID SUP - 625969001
Work Type STATE USE JANITORIAL MILLS CO MAINT OFC
 
0.001 10957.73 415.60 2493.60 22.7
Work Order 10-01-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132334
Totals 10957.73 415.60 2493.60 22.7

CountyEASTLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6265-77-001
Proj ID RMC - 626577001
Work Type ROADSIDE MOWING
 
367.820 259802.50 0.00 110696.25 42.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-03-13
Work Began 00-00-00
Work Completed  
Time Computed 12-10-13
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 20
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6265-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10132301
Totals 259802.50 0.00 110696.25 42.6

CountySAN SABA
Highway US0190
From N/A
To N/A
CSJ 6267-26-001
Proj ID SUP - 626726001
Work Type STATE USE JANITORIAL - SAN SABA
 
0.001 21886.00 479.00 2517.00 11.5
Work Order 01-01-14
Work Began 00-00-00
Work Completed  
Time Computed 01-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6267-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11132330
Totals 21886.00 479.00 2517.00 11.5

CountyBROWN
Highway US0183
From N/A
To N/A
CSJ 6268-63-001
Proj ID SUP - 626863001
Work Type STATE USE JANITORIAL - DIST OFC
 
0.001 60473.00 0.00 3823.25 6.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-14
Work Began 00-00-00
Work Completed  
Time Computed 03-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6268-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12132330
Totals 60473.00 0.00 3823.25 6.3

page 1 | page 2 | page 3