Monthly Local Let Maintenance Report For Brownwood District As Of May 15, 2013 Page 3 Of 4

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEASTLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6221-86-001
Proj ID SUP - 622186001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 95234.00 0.00 89530.00 94.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-01-11
Work Began 02-01-11
Work Completed  
Time Computed 02-01-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 759
Percent Time Used 103
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02112330
Totals 95234.00 0.00 89530.00 94.0

CountyBROWN
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6224-08-001
Proj ID SUP - 622408001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.100 99405.00 0.00 82317.40 82.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-11
Work Began 03-01-11
Work Completed  
Time Computed 03-01-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 731
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6224-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03112330
Totals 99405.00 0.00 82317.40 82.8

CountyBROWN
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6224-84-001
Proj ID RMC - 622484001
Work Type ROADSIDE MOWING
 
326.700 168699.24 0.00 226485.72 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-11
Work Began 07-15-11
Work Completed  
Time Computed 07-18-11
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 47
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6224-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04112301
Totals 168699.24 0.00 226485.72 99.9

CountyCOLEMAN
Highway US0283
From VARIOUS
To VARIOUS
CSJ 6224-85-001
Proj ID RMC - 622485001
Work Type ROADSIDE MOWING
 
328.700 190058.49 0.00 232941.33 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-28-11
Work Began 07-28-11
Work Completed  
Time Computed 08-04-11
Contract Working Days 65
Addl Days Granted 65
Working Days Charged 29
Percent Time Used 22
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6224-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04112302
Totals 190058.49 0.00 232941.33 99.9

CountyLAMPASAS
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6224-86-001
Proj ID RMC - 622486001
Work Type ROADSIDE MOWING
 
220.940 170503.33 0.00 110065.42 64.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-01-11
Work Began 12-06-11
Work Completed  
Time Computed 12-08-11
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 9
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6224-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04112303
Totals 170503.33 0.00 110065.42 64.5

CountySTEPHENS
Highway US0183
From VARIOUS
To VARIOUS
CSJ 6224-87-001
Proj ID RMC - 622487001
Work Type ROADSIDE MOWING
 
261.110 178895.71 0.00 179593.57 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-25-11
Work Began 07-25-11
Work Completed  
Time Computed 08-01-11
Contract Working Days 55
Addl Days Granted 55
Working Days Charged 22
Percent Time Used 20
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6224-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04112304
Totals 178895.71 0.00 179593.57 99.9

CountyEASTLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6225-04-001
Proj ID RMC - 622504001
Work Type ROADSIDE MOWING
 
367.820 207427.00 0.00 372780.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-11
Work Began 07-22-11
Work Completed  
Time Computed 07-29-11
Contract Working Days 65
Addl Days Granted 65
Working Days Charged 51
Percent Time Used 39
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6225-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04112305
Totals 207427.00 0.00 372780.00 99.9

CountyMCCULLOCH
Highway US0087
From VARIOUS
To VARIOUS
CSJ 6226-12-001
Proj ID SUP - 622612001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 78130.00 2955.00 74410.00 95.2
Work Order 05-01-11
Work Began 05-01-11
Work Completed  
Time Computed 05-01-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 731
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6226-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05112331
Totals 78130.00 2955.00 74410.00 95.2

CountyCOLEMAN
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6226-13-001
Proj ID SUP - 622613001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 76300.00 2730.00 65080.00 85.2
Work Order 05-01-11
Work Began 05-01-11
Work Completed  
Time Computed 05-01-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 731
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6226-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05112330
Totals 76300.00 2730.00 65080.00 85.2

CountyCOMANCHE
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6228-82-001
Proj ID RMC - 622882001
Work Type ROADSIDE MOWING
 
345.560 206743.47 0.00 200629.18 97.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-07-11
Work Began 11-07-11
Work Completed  
Time Computed 11-14-11
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 40
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6228-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06112301
Totals 206743.47 0.00 200629.18 97.0

CountyMCCULLOCH
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6228-83-001
Proj ID RMC - 622883001
Work Type ROADSIDE MOWING
 
286.300 156557.76 0.00 145796.64 93.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-26-11
Work Began 08-04-11
Work Completed  
Time Computed 08-02-11
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 67
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6228-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06112302
Totals 156557.76 0.00 145796.64 93.1

CountySAN SABA
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6234-21-001
Proj ID SUP - 623421001
Work Type STATE USE PICNIC AREA MAINTENACE
 
0.001 66080.00 2485.00 45515.00 68.8
Work Order 11-01-11
Work Began 11-01-11
Work Completed  
Time Computed 11-01-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 547
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6234-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11112330
Totals 66080.00 2485.00 45515.00 68.8

CountyEASTLAND
Highway IH0020
From IH0020 & NORTH COUNTIES
To IH0020 & NORTH COUNTIES
CSJ 6234-23-001
Proj ID RMC - 623423001
Work Type MILL & INLAY (WILL - CALL AS NEEDED)
 
0.001 314615.22 0.00 663977.24 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-14-12
Work Began 08-14-12
Work Completed  
Time Computed 08-21-12
Contract Working Days 45
Addl Days Granted 45
Working Days Charged 12
Percent Time Used 13
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6234-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05122301
Totals 314615.22 0.00 663977.24 99.9

CountyCOLEMAN
Highway SH0206
From COLEMAN MAINTENANCE OFFICE
To " " "
CSJ 6239-55-001
Proj ID SUP - 623955001
Work Type STATE USE JANITORIAL
 
0.001 8974.28 0.00 9541.32 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-12
Work Began 01-17-12
Work Completed  
Time Computed 01-17-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 409
Percent Time Used 112
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6239-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01122330
Totals 8974.28 0.00 9541.32 99.9

CountyMCCULLOCH
Highway US0377
From N/A
To N/A
CSJ 6240-67-001
Proj ID SUP - 624067001
Work Type STATE USE JANITORIAL SERVICES
 
0.001 6937.20 0.00 5998.76 86.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-12
Work Began 03-01-12
Work Completed  
Time Computed 03-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6240-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02122330
Totals 6937.20 0.00 5998.76 86.4

CountyBROWN
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6242-63-001
Proj ID SUP - 624263001
Work Type STATE USE LITTER PICKUP AND DISPOSAL
 
0.001 112157.32 915.46 53011.57 47.2
Work Order 06-01-12
Work Began 06-01-12
Work Completed  
Time Computed 06-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6242-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04122330
Totals 112157.32 915.46 53011.57 47.2

CountyBROWN
Highway US0377
From VARIOUS
To VARIOUS
CSJ 6242-78-001
Proj ID RMC - 624278001
Work Type REPAIR MBGF & CABLE BARRIER AS NEEDED
 
0.001 293875.00 23331.00 156461.00 53.2
Work Order 07-19-12
Work Began 07-26-12
Work Completed  
Time Computed 07-26-12
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 29
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6242-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05122303
Totals 293875.00 23331.00 156461.00 53.2

CountyBROWN
Highway US0183
From N/A
To N/A
CSJ 6245-44-001
Proj ID SUP - 624544001
Work Type STATE - USE JANITORIAL
 
0.001 87371.28 593.24 6166.17 7.0
Work Order 06-15-12
Work Began 06-15-12
Work Completed  
Time Computed 06-15-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 320
Percent Time Used 87
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6245-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06122331
Totals 87371.28 593.24 6166.17 7.0

CountyBROWN
Highway US0183
From N/A
To N/A
CSJ 6245-45-001
Proj ID SUP - 624545001
Work Type STATE - USE JANITORIAL SERVICES
 
0.001 7834.00 618.00 6499.40 82.9
Work Order 06-15-12
Work Began 06-15-12
Work Completed  
Time Computed 06-15-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 320
Percent Time Used 87
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6245-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06122332
Totals 7834.00 618.00 6499.40 82.9

CountyMILLS
Highway US0084
From N/A
To N/A
CSJ 6245-46-001
Proj ID SUP - 624546001
Work Type STATE - USE JANITORIAL AT MILLS COUNTY
 
0.001 5760.24 456.70 4975.19 86.3
Work Order 06-15-12
Work Began 06-15-12
Work Completed  
Time Computed 06-15-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 320
Percent Time Used 87
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6245-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06122333
Totals 5760.24 456.70 4975.19 86.3