Monthly Local Let Maintenance Report For Brownwood District As Of Jul 14, 2017 Page 4 Of 5

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMILLS
HighwayUS0084
FromMILLS COUNTY MAINTENANCE OFFICE
To***
CSJ6294-66-001
Proj IDSUP - 629466001
Work TypeSTATE USE JANITORIAL-CFLR/JCI
 
0.00115201.689870.8567.5
Work Order10-01-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged639
Percent Time Used87
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6294-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152332
Totals15201.68590.389870.8567.5

CountySTEPHENS
HighwayUS0180
FromVARIOUS
To***
CSJ6297-08-001
Proj IDSUP - 629708001
Work TypeSTATE USE LITTER-BOOTSTRAPS
 
0.00163764.8122900.6335.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-15
Work Began11-01-15
Work Completed
Time Computed11-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged458
Percent Time Used125
Contractor(s)
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6297-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10152330
Totals63764.810.0022900.6335.9

CountySAN SABA
HighwayUS0190
FromVARIOUS
To***
CSJ6297-49-001
Proj IDSUP - 629749001
Work TypeSTATE USE PICNIC/ALDERSGATE
 
0.001101800.0068714.0067.4
Work Order12-01-15
Work Began12-01-15
Work Completed
Time Computed12-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged578
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11152330
Totals101800.004078.0068714.0067.4

CountyLAMPASAS
HighwayUS0183
FromVARIOUS
To***
CSJ6297-50-001
Proj IDSUP - 629750001
Work TypeSTATE USE/LITTER/BOOTSTRAPS
 
0.00191193.2454852.2360.1
Work Order12-01-15
Work Began12-01-15
Work Completed
Time Computed12-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged578
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6297-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11152331
Totals91193.240.0054852.2360.1

CountyEASTLAND
HighwaySH0112
FromEASTLAND AREA/MNT OFFICE
To***
CSJ6298-23-001
Proj IDSUP - 629823001
Work TypeSTATE USE JANITOR-JCI/CFLR
 
0.00155091.9232689.9859.3
Work Order02-01-16
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6298-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11152332
Totals55091.922136.5432689.9859.3

CountyEASTLAND
HighwaySH0006
FromVARIOUS
To***
CSJ6301-28-001
Proj IDRMC - 630128001
Work TypeTREE TRIMMING, ETC.
 
0.001278780.00420140.0099.9
Work Order05-30-17
Work Began00-00-00
Work Completed
Time Computed06-06-17
Contract Working Days100
Addl Days Granted100
Working Days Charged57
Percent Time Used28
Contractor(s)
DEKALB TREE SPECIALIST
SUBCONTRACTOR(S) FOR CCSJ: 6301-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162301
Totals278780.00204525.00420140.0099.9

CountyBROWN
HighwaySH0279
FromVARIOUS
To***
CSJ6301-29-001
Proj IDRMC - 630129001
Work TypeTREE TRIMMING, ETC.
 
0.001278780.00345308.0099.9
Work Order10-06-16
Work Began09-07-16
Work Completed
Time Computed09-13-16
Contract Working Days100
Addl Days Granted0
Working Days Charged55
Percent Time Used55
Contractor(s)
DEKALB TREE SPECIALIST
SUBCONTRACTOR(S) FOR CCSJ: 6301-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162302
Totals278780.000.00345308.0099.9

CountyLAMPASAS
HighwayUS0281
FromVARIOUS
To***
CSJ6301-30-001
Proj IDRMC - 630130001
Work TypeTREE TRIMMING, ETC.
 
0.001286970.0092977.0032.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-16
Work Began09-19-16
Work Completed
Time Computed09-26-16
Contract Working Days100
Addl Days Granted0
Working Days Charged43
Percent Time Used43
Contractor(s)
BOEN LANDSCAPING & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162303
Totals286970.000.0092977.0032.3

CountyCOMANCHE
HighwayUS0067
FromVARIOUS
To***
CSJ6301-76-001
Proj IDRMC - 630176001
Work TypeROADSIDE MOWING (WILL-CALL) (AS NEEDED)
 
0.001354857.95303211.2585.4
Work Order06-21-16
Work Began06-23-16
Work Completed
Time Computed06-28-16
Contract Working Days85
Addl Days Granted0
Working Days Charged43
Percent Time Used50
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162301
Totals354857.95101075.36303211.2585.4

CountyEASTLAND
HighwayIH0020
FromVARIOUS
To***
CSJ6301-77-001
Proj IDRMC - 630177001
Work TypeROADSIDE MOWING (WILL-CALL)(AS NEEDED)
 
0.001331712.00265948.0081.4
Work Order07-05-16
Work Began07-12-16
Work Completed
Time Computed07-12-16
Contract Working Days90
Addl Days Granted0
Working Days Charged59
Percent Time Used65
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6301-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162302
Totals331712.000.00265948.0081.4

CountyMILLS
HighwayUS0084
FromVARIOUS
To***
CSJ6301-78-001
Proj IDRMC - 630178001
Work TypeROADSIDE MOWING (WILL-CALL)(AS NEEDED)
 
0.001314621.06126759.7240.2
Work Order07-12-16
Work Began07-13-16
Work Completed
Time Computed07-19-16
Contract Working Days76
Addl Days Granted0
Working Days Charged16
Percent Time Used21
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6301-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162303
Totals314621.060.00126759.7240.2

CountyBROWN
HighwayUS0377
FromVARIOUS
To***
CSJ6304-51-001
Proj IDSUP - 630451001
Work TypeALDERSGATE/STATE USE/LITTER REMOVAL
 
0.001157255.9083250.3252.9
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged416
Percent Time Used56
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162330
Totals157255.909249.7083250.3252.9

CountyEASTLAND
HighwaySH0006
FromSH0006 AT LAKE CISCO
To***
CSJ6305-90-001
Proj IDEMC - 630590001
Work TypeBUILD 3 SPAN BRIDGE
 
0.0033343810.503423336.5199.9
Work Order08-08-16
Work Began08-08-16
Work Completed
Time Computed08-08-16
Contract Working Days185
Addl Days Granted0
Working Days Charged308
Percent Time Used166
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-90-001
BEAIRD DRILLING (7.68)
GRANBURY EXCAVATING, INC. (19.60)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.49)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.82)
HJC FARMS, INC. (2.03)
LONE STAR PAVING COMPANY (5.45)
Contract #07162302
Totals3343810.5019585.723423336.5199.9

CountySAN SABA
HighwayUS0190
FromSAN SABA MAINTENANCE OFFICE
To***
CSJ6307-67-001
Proj IDSUP - 630767001
Work TypeSTATE USE JANITOR CEN TEX MHMR/CFLR
 
0.00121216.006289.0029.6
Work Order08-01-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged334
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6307-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07162330
Totals21216.00809.006289.0029.6

CountySTEPHENS
HighwayUS0180
FromVARIOUS
To***
CSJ6312-32-001
Proj IDSUP - 631232001
Work TypeSTATE USE LITTER REMOVAL
 
0.001129291.3531178.3824.1
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged150
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01172330
Totals129291.359862.6431178.3824.1

CountySAN SABA
HighwayUS0190
FromVARIOUS
To***
CSJ6315-56-001
Proj IDRMC - 631556001
Work TypeROADSIDE MOWING
 
0.001174960.9429666.0016.9
Work Order06-12-17
Work Began06-13-17
Work Completed
Time Computed06-19-17
Contract Working Days65
Addl Days Granted0
Working Days Charged9
Percent Time Used13
Contractor(s)
BUCKSHOT WELDING & FABRICATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172301
Totals174960.9429666.0029666.0016.9

CountyCOLEMAN
HighwayUS0067
FromVARIOUS
To***
CSJ6315-57-001
Proj IDSUP - 631557001
Work TypeSTATE USE LITTER-ALDERSGATE
 
0.00144712.960.000.0
Work Order05-01-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172330
Totals44712.960.000.000.0

CountyCOMANCHE
HighwayUS0067
FromVARIOUS
To***
CSJ6315-58-001
Proj IDSUP - 631558001
Work TypeSTATE USE LITTER-ALDERSGATE
 
0.00189635.2012331.1413.7
Work Order04-20-17
Work Began04-20-17
Work Completed
Time Computed04-20-17
Contract Working Days735
Addl Days Granted0
Working Days Charged72
Percent Time Used9
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172331
Totals89635.200.0012331.1413.7

CountyEASTLAND
HighwayIH0020
FromVARIOUS
To***
CSJ6315-59-001
Proj IDSUP - 631559001
Work TypeSTATE USE LITTER-ALDERSGATE
 
0.001163320.3636509.4922.3
Work Order03-01-17
Work Began03-01-17
Work Completed
Time Computed03-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172330
Totals163320.3616869.8136509.4922.3

CountyCOMANCHE
HighwaySH0016
FromCOMANCHE MAINTENANCE OFFICE
To***
CSJ6315-71-001
Proj IDSUP - 631571001
Work TypeSTATE USE JANITORIAL-CEN TEX MHMR/JCI
 
0.00132986.244136.0412.5
Work Order03-01-17
Work Began03-01-17
Work Completed
Time Computed03-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6315-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172331
Totals32986.241048.014136.0412.5