Monthly Local Let Maintenance Report For Brownwood District As Of Jul 13, 2015 Page 4 Of 4

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMILLS
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6286-81-001
Proj ID RMC - 628681001
Work Type ROADSIDE MOWING
 
0.001 258264.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04152305
Totals 258264.69 0.00 0.00 0.0

CountySTEPHENS
Highway US0180
From VARIOUS
To VARIOUS
CSJ 6287-02-001
Proj ID SUP - 628702001
Work Type SU - ALDERSGATE - LITTER REMOVAL
 
0.001 63764.81 0.00 0.00 0.0
Work Order 05-01-15
Work Began 05-01-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03152330
Totals 63764.81 0.00 0.00 0.0

CountyMILLS
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6287-03-001
Proj ID SUP - 628703001
Work Type SU - ALDERSGATE - LITTER REMOVAL
 
0.001 26347.66 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-01-15
Work Began 05-01-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03152331
Totals 26347.66 0.00 0.00 0.0

CountySAN SABA
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6287-04-001
Proj ID SUP - 628704001
Work Type SU - ALDERSGATE - LITTER REMOVAL
 
0.001 31575.16 7143.79 7143.79 22.6
Work Order 06-15-15
Work Began 05-01-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03152332
Totals 31575.16 7143.79 7143.79 22.6

CountyEASTLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6287-05-001
Proj ID SUP - 628705001
Work Type SU - ALDERSGATE - PICNIC
 
0.001 176400.00 5410.00 11395.00 6.4
Work Order 05-01-15
Work Began 05-01-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03152335
Totals 176400.00 5410.00 11395.00 6.4

CountySTEPHENS
Highway US0180
From VARIOUS
To VARIOUS
CSJ 6287-11-001
Proj ID SUP - 628711001
Work Type SU - ALDERSGATE - PICNIC
 
0.001 77225.00 2005.00 4245.00 5.4
Work Order 05-01-15
Work Began 05-01-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03152336
Totals 77225.00 2005.00 4245.00 5.4

CountyMILLS
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6287-12-001
Proj ID SUP - 628712001
Work Type SU - ALDERSGATE - PICNIC
 
0.001 42500.00 1290.00 2580.00 6.0
Work Order 05-01-15
Work Began 05-01-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03152337
Totals 42500.00 1290.00 2580.00 6.0

CountyCOLEMAN
Highway SH0206
From COLEMAN CO MAINT OFFICE
To ***
CSJ 6287-13-001
Proj ID SUP - 628713001
Work Type STATE USE - JANITORIAL - JCI / CFLR
 
0.001 25425.08 770.19 1540.38 6.0
Work Order 05-01-15
Work Began 05-01-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6287-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03152338
Totals 25425.08 770.19 1540.38 6.0

CountyMCCULLOCH
Highway US0377
From MCCULLOCH CO MAINT OFFICE
To ***
CSJ 6287-14-001
Proj ID SUP - 628714001
Work Type STATE USE - JANITORIAL - JCI / CFLR
 
0.001 14862.72 1181.92 1474.08 9.9
Work Order 05-01-15
Work Began 05-01-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6287-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03152339
Totals 14862.72 1181.92 1474.08 9.9

CountyBROWN
Highway US0183
From BWD DIST OFFICE COMPLEX
To ***
CSJ 6287-35-001
Proj ID SUP - 628735001
Work Type STATE USE - MOWING - JCI / CFLR
 
0.001 34000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-01-15
Work Began 05-01-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6287-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03152340
Totals 34000.00 0.00 0.00 0.0