Monthly State Let Construction Report For Bryan District As Of Apr 11, 2014 Page 2 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGRIMES
Highway SH 105
From THE NAVASOTA CITY LIMITS
To 0.355 MILE W. OF THE MONTGOMERY CL
CSJ 0338-01-054
Proj ID STP 2013(058)SB
Work Type REHABILITATION OF EXISTING ROAD
 
16.487 6821958.57 871384.66 6641569.33 97.3
Work Order 12-14-12
Work Began 04-22-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 141
Addl Days Granted 2
Working Days Charged 137
Percent Time Used 95
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0338-01-054
N-LINE TRAFFIC MAINTENANCE, L.P. (0.10%)
CEN TEX HYDROSEED, INC.(0.49%)
PEDRO CARLOS CONSTRUCTION CO.(1.51%)
ROADWAY SPECIALTIES, INC.(1.66%)
JEFFERY BAILEY TRUCKING, INC.(0.00%)
D. I. J. CONSTRUCTION, INC.(1.94%)
SCR CONSTRUCTION CO., INC. (0.50%)
WEST TEXAS RUMBLE STRIP(0.52%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.19%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 09123215
Totals 6821958.57 871384.66 6641569.33 97.3

CountyFREESTONE
Highway FM 27
From AT TEHUACANA CREEK
To AND RELIEF STRUCTURE
CSJ 0456-01-044
Proj ID BR 2013(526)
Work Type GRADING, STRUCTURE, BASE AND SURF
 
0.459 2127943.49 103346.38 1672417.81 78.5
Work Order 06-24-13
Work Began 07-15-13
Work Completed  
Time Computed 07-15-13
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 95
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0456-01-044
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.26%)
NORTH TEXAS REBAR, LLC (0.74%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.79%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.18%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.62%)
RAYFORD"S TRUCK & TRACTOR( 12.94%)
FORTSON CONTRACTING, INC.(1.58%)
HOUSTON SAWING & DRILLING(0.20%)
APAC-TEXAS, INC. (5.79%)
SOTO"S STEEL (0.13%)
SOTO"S STEEL (0.24%)
Contract # 04133215
Totals 2127943.49 103346.38 1672417.81 78.5

CountyBURLESON
Highway FM 50
From THE BNSF RAILROAD
To THE WASHINGTON COUNTY LINE
CSJ 0457-01-056
Proj ID STP 2014(340)
Work Type REHABILITATE EXISTING ROAD
 
1.361 1532334.42 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-03-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0457-01-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143207
Totals 1532334.42 0.00 0.00 0.0

CountyBRAZOS
Highway FM 60
From SH 6
To FM 158
CSJ 0506-01-082
Proj ID STP 2004(74)
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
1.747 7633962.49 189915.02 5144216.05 67.3
Work Order 07-23-12
Work Began 08-04-12
Work Completed  
Time Computed 08-04-12
Contract Working Days 296
Addl Days Granted 6
Working Days Charged 290
Percent Time Used 96
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0506-01-082
JEFFERY BAILEY TRUCKING, INC.(1.17%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(3.69%)
FLASHER EQUIPMENT COMPANY(0.73%)
KELLYSTONE, INC(1.12%)
TEX OP CONSTRUCTION, LP(0.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%)
HEMPHILL PILE DRIVING CO., A CORP. (0.96%)
ROADWAY SPECIALTIES, INC.(0.38%)
CEN TEX HYDROSEED, INC.(0.95%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.97%)
MESA ROD BUSTERS, INC. (0.73%)
RIOS TRUCKING CO.(0.00%)
Contract # 05123205
Totals 7633962.49 189915.02 5144216.05 67.3

CountyROBERTSON
Highway FM 46
From COLORADO STREET
To FM 979 (EAST)
CSJ 0540-01-044
Proj ID STP 2013(059)HRR
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
12.537 3105423.29 55332.69 3169579.31 99.9
Work Order 11-01-12
Work Began 11-12-12
Work Completed  
Time Computed 11-17-12
Contract Working Days 169
Addl Days Granted 13
Working Days Charged 176
Percent Time Used 96
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0540-01-044
CEN TEX HYDROSEED, INC.(1.75%)
ROADSAFE TRAFFIC SYSTEMS, INC. (4.41%)
J & M CONTRACTING, COMPANY (8.51%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.00%)
PLANTERSVILLE WATER SERVICES, INC. (1.33%)
Contract # 09123222
Totals 3105423.29 55332.69 3169579.31 99.9

CountyLEON
Highway FM 3
From 4.0 MILES SOUTH OF CR 470
To FM 39
CSJ 0552-01-031
Proj ID STP 2013(814)
Work Type RESTORE EXISTING ROAD
 
7.231 2758787.87 505632.23 1533125.82 55.5
Work Order 09-05-13
Work Began 10-10-13
Work Completed  
Time Computed 10-10-13
Contract Working Days 128
Addl Days Granted 2
Working Days Charged 94
Percent Time Used 72
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0552-01-031
CEN TEX HYDROSEED, INC.(0.68%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.34%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.17%)
ODUM SERVICES, L.P.(2.45%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.14%)
Contract # 06133225
Totals 2758787.87 505632.23 1533125.82 55.5

CountyMILAM
Highway FM 486
From AT SAN GABRIEL RIVER
To .
CSJ 0590-05-027
Proj ID BR 2012(706)
Work Type GR, STRS, BASE AND SURFACE
 
0.176 1943618.46 137803.99 1708233.98 87.8
Work Order 09-24-12
Work Began 10-31-12
Work Completed  
Time Computed 10-10-12
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 207
Percent Time Used 78
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0590-05-027
N-LINE TRAFFIC MAINTENANCE, L.P. (0.34%)
RICE ENVIRONMENTAL SERVICES(0.49%)
D. I. J. CONSTRUCTION, INC.(0.75%)
PRIMATE CONSTRUCTION, INC. (0.34%)
S & S BRIDGE PAINTING, INC.(0.17%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.07%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.98%)
GK CONSTRUCTION, LLC (1.08%)
BEAIRD DRILLING(3.67%)
JOY LATTIMER, LLC. (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.87%)
Contract # 08123227
Totals 1943618.46 137803.99 1708233.98 87.8

CountyBURLESON
Highway FM 60
From 1.2 MILES WEST OF FM 2039
To 0.62 MILE EAST OF OLD RIVER
CSJ 0648-03-050
Proj ID C 648-3-50
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
3.984 10487720.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-19-14
Work Began 04-07-14
Work Completed  
Time Computed 04-07-14
Contract Working Days 227
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0648-03-050
BLUE STAR BARRICADES, INC. (0.26%)
COWBELL TRAFFIC SERVICES, INC. (0.07%)
D. I. J. CONSTRUCTION, INC.(0.65%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.52%)
MURRAY CONSTRUCTION(0.38%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.16%)
TEXAS ALTERNATIVE GRASSER, INC.(0.30%)
PRIME ECO GROUP, INC.(0.00%)
PIPE WHOLESALERS OF TEXAS, INC.(0.00%)
Contract # 12133003
Totals 10487720.87 0.00 0.00 0.0

CountyFREESTONE
Highway IH 45
From THE LEON COUNTY LINE
To US 84
CSJ 0675-02-070
Proj ID IM 0452(139)
Work Type HMA OVERLAY
 
17.316 2217971.87 0.00 2007189.97 90.4
CountyFREESTONE
Highway IH 45
From THE LEON COUNTY LINE
To US 84
CSJ 0675-02-074
Proj ID IM 0452(139)
Work Type OVERLAY (REHABILITATION)
 
17.316 3011426.00 0.00 2719044.48 90.2
Work Order 03-19-13
Work Began 04-05-13
Work Completed  
Time Computed 04-05-13
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 75
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-02-070
COWBELL TRAFFIC SERVICES, INC. (0.61%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
PRIMATE CONSTRUCTION, INC. (0.80%)
STRIPING TECHNOLOGY, L.P.(2.41%)
FORTSON CONTRACTING, INC.(0.98%)
POTTER TRUCKING(0.00%)
Contract # 01133011
Totals 5229397.87 0.00 4726234.45 90.3

CountyFREESTONE
Highway IH 45
From THE LEON COUNTY LINE
To US 84
CSJ 0675-02-077
Proj ID IM 0452(143)
Work Type HMA OVERLAY (REHABILITATION)
 
34.574 4687021.87 0.00 0.00 0.0
Work Order 12-04-13
Work Began 00-00-00
Work Completed  
Time Computed 03-04-14
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-02-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09133015
Totals 4687021.87 0.00 0.00 0.0

CountyMADISON
Highway IH 45
From ON IH 45 NBML FROM THE WALKER C/L
To SH 21
CSJ 0675-05-076
Proj ID IM 0452(144)
Work Type HMA OVERLAY
 
8.679 908902.09 0.00 0.00 0.0
CountyMADISON
Highway IH 45
From ON IH 45 NBML FROM THE WALKER C/L
To SH 21
CSJ 0675-05-078
Proj ID IM 0452(144)
Work Type HMA OVERLAY
 
8.679 1478620.81 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-05-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133214
Totals 2387522.90 0.00 0.00 0.0

CountyWALKER
Highway IH 45
From SH 75
To THE MADISON COUNTY LINE
CSJ 0675-06-099
Proj ID IM 0452(141)
Work Type HMA OVERLAY
 
14.952 5387237.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-06-099
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10133221
Totals 5387237.10 0.00 0.00 0.0

CountyWALKER
Highway IH 45
From AT THE INTERSECTION WITH FM 1375
To .
CSJ 0675-07-089
Proj ID STP 2014(483)HES
Work Type REALIGN INTERSECTION
 
0.600 3355020.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-07-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143228
Totals 3355020.53 0.00 0.00 0.0

CountyWALKER
Highway FM 980
From 0.067 MILE NORTH OF LEIGH ANNE
To SH 19
CSJ 0756-02-027
Proj ID STP 2013(060)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
13.328 4394843.38 20172.95 4262557.57 96.9
Work Order 10-18-12
Work Began 10-26-12
Work Completed  
Time Computed 10-26-12
Contract Working Days 264
Addl Days Granted 26
Working Days Charged 256
Percent Time Used 88
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0756-02-027
ROADSAFE TRAFFIC SYSTEMS, INC. (2.72%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.27%)
BWF FREIGHT(4.69%)
W.D.F. HAULING (2.34%)
CEN TEX HYDROSEED, INC.(1.57%)
J & M CONTRACTING, COMPANY (5.67%)
PLANTERSVILLE WATER SERVICES, INC. (1.95%)
Contract # 09123046
Totals 4394843.38 20172.95 4262557.57 96.9

CountyMILAM
Highway CR
From ON CR 355 (LOCAL CR 428)
To AT SAN GABRIEL RIVER
CSJ 0917-12-069
Proj ID BR 1102(536)
Work Type REHABILITATE HISTORIC BRIDGE
 
0.152 1272327.40 117737.80 1099159.14 86.3
Work Order 07-08-13
Work Began 10-25-13
Work Completed  
Time Computed 10-28-13
Contract Working Days 115
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 53
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0917-12-069
SAN-ANN-CO., INC.(0.34%)
APAC-TEXAS, INC. (1.76%)
FORTSON CONTRACTING, INC.(0.28%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.40%)
S & S BRIDGE PAINTING, INC.( 15.97%)
SOTO"S STEEL (0.09%)
Contract # 05133026
Totals 1272327.40 117737.80 1099159.14 86.3

CountyGRIMES
Highway CR
From ON CR 202 (PINEBROOK DRIVE)
To AT KICKAPOO CREEK
CSJ 0917-17-043
Proj ID BR 2012(269)
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
0.164 662557.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 121
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143014
Totals 662557.78 0.00 0.00 0.0

CountyROBERTSON
Highway CR
From ON CR 120 (WILDCAT BRIDGE ROAD)
To AT LITTLE BRAZOS RIVER
CSJ 0917-18-024
Proj ID BR 96(427)
Work Type REHABILITATE HISTORIC BRIDGE
 
0.135 1922884.95 0.00 1984344.48 99.9
Work Order 09-17-12
Work Began 11-27-12
Work Completed  
Time Computed 11-27-12
Contract Working Days 333
Addl Days Granted 110
Working Days Charged 208
Percent Time Used 93
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-18-024
N-LINE TRAFFIC MAINTENANCE, L.P. (0.33%)
S & S BRIDGE PAINTING, INC.( 21.45%)
ASPHALT WORKS COMPANY(0.00%)
Contract # 08123033
Totals 1922884.95 0.00 1984344.48 99.9

CountyFREESTONE
Highway CR
From ON COUNTY ROAD 352 (LOCAL CR 1041)
To AT TEHUACANA CREEK
CSJ 0917-20-011
Proj ID BR 96(480)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.104 448406.84 108637.43 108637.43 24.2
Work Order 01-17-14
Work Began 00-00-00
Work Completed  
Time Computed 02-02-14
Contract Working Days 83
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 10
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-011
CEN TEX HYDROSEED, INC.(1.02%)
FORTSON CONTRACTING, INC.(2.71%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.94%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.64%)
JUST GROOVING, LTD.(0.39%)
REDROD STEEL AND CABLE, LLC(0.40%)
Contract # 10133010
Totals 448406.84 108637.43 108637.43 24.2

CountyFREESTONE
Highway PW
From AT THE FAIRFIELD LAKE STATE PARK
To .
CSJ 0917-20-034
Proj ID C 917-20-34
Work Type RECONSTRUCT ROADWAYS AND CAMPSITES
 
7.000 1574868.18 57640.50 929923.57 59.0
Work Order 09-10-13
Work Began 09-17-13
Work Completed  
Time Computed 09-17-13
Contract Working Days 118
Addl Days Granted 5
Working Days Charged 96
Percent Time Used 78
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-034
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20%)
SPEEDY PAVING(8.14%)
STRIPING TECHNOLOGY, L.P.(0.30%)
Contract # 06133011
Totals 1574868.18 57640.50 929923.57 59.0

CountyWALKER
Highway PW
From AT THE HUNTSVILLE STATE PARK
To .
CSJ 0917-27-043
Proj ID C 917-27-43
Work Type RECONSTRUCT EXISTING RV PULLOUTS
 
1.000 262456.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143019
Totals 262456.50 0.00 0.00 0.0

page 1 | page 2 | page 3