Monthly State Let Construction Report For Bryan District As Of Feb 11, 2015 Page 2 Of 3

Last Update: Wednesday, February 11, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGRIMES
Highway SH 90
From 1.4 MILES NORTH OF CR 150
To SOUTH CITY LIMITS OF BEDIAS
CSJ 0315-02-049
Proj ID STP 1402(098)
Work Type REHABILITATE EXISTING ROAD
 
2.617 3129292.87 0.00 0.00 0.0
Work Order 10-30-14
Work Began 01-28-15
Work Completed  
Time Computed 01-28-15
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 1
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0315-02-049
CPAVE, INC.(0.73%)
CEN TEX HYDROSEED, INC.(1.19%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.50%)
WILLOW CITY SIGN & RAIL, INC.(4.65%)
Contract # 08143024
Totals 3129292.87 0.00 0.00 0.0

CountyBRAZOS
Highway SH 105
From AT THE BRAZOS RIVER
To .
CSJ 0315-05-026
Proj ID BR 2014(643)
Work Type GRADING, STRUCTURES, BASE AND SURF
 
3.289 23601410.92 341137.24 5230628.09 22.1
Work Order 07-02-14
Work Began 09-30-14
Work Completed  
Time Computed 09-30-14
Contract Working Days 443
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 10
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0315-05-026
CHOCTAW ERECTORS, INC. (7.06%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.19%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.15%)
ATS DRILLING, INC. (7.09%)
HOUSTON SAWING & DRILLING(0.06%)
BIG CREEK CONSTRUCTION, LTD. (6.72%)
MINE SERVICE, INC. (5.33%)
GEOSOURCE, INC.(0.94%)
RICE ENVIRONMENTAL SERVICES(1.93%)
PERFORMANCE EQUIPMENT(0.25%)
MESA ROD BUSTERS, INC. (0.53%)
EPCS ENVIRONMENTAL LLC (1.52%)
MCL CONTRACTING, LLC (0.25%)
Contract # 05143202
Totals 23601410.92 341137.24 5230628.09 22.1

CountyLEON
Highway SH 7
From CR 348
To FM 39
CSJ 0335-03-046
Proj ID STP 2015(607)
Work Type REHABILITATE EXISTING ROAD
 
1.562 1443902.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0335-03-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153204
Totals 1443902.82 0.00 0.00 0.0

CountyWALKER
Highway SH 150
From SH 75
To THE SAN JACINTO COUNTY LINE
CSJ 0395-01-029
Proj ID STP 2015(159)
Work Type GRADING, STRUCTURES, BASE AND SURF
 
8.012 5846147.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-03-14
Work Began 02-02-15
Work Completed  
Time Computed 02-02-15
Contract Working Days 148
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0395-01-029
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(0.81%)
CEN TEX HYDROSEED, INC.(0.14%)
J & M CONTRACTING, COMPANY (3.72%)
WATERS CONSTRUCTION CO., INC.(9.52%)
WILLOW CITY SIGN & RAIL, INC.(1.07%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.40%)
MURRAY CONSTRUCTION(0.59%)
Contract # 09143207
Totals 5846147.45 0.00 0.00 0.0

CountyLEON
Highway FM 542
From US 79
To 1.8 MILES SOUTHEAST OF CR 242
CSJ 0426-03-039
Proj ID STP 2014(644)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
6.408 1887337.85 396607.88 1564853.24 82.9
Work Order 07-22-14
Work Began 09-08-14
Work Completed  
Time Computed 08-07-14
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 78
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0426-03-039
FORTSON CONTRACTING, INC.(3.72%)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.61%)
SAN-ANN-CO., INC.(1.25%)
STRIPING TECHNOLOGY, L.P.(2.17%)
TEXAS ALTERNATIVE GRASSER, INC.(0.37%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 05143225
Totals 1887337.85 396607.88 1564853.24 82.9

CountyFREESTONE
Highway FM 27
From AT TEHUACANA CREEK
To AND RELIEF STRUCTURE
CSJ 0456-01-044
Proj ID BR 2013(526)
Work Type GRADING, STRUCTURE, BASE AND SURF
 
0.459 2127943.49 0.00 2120709.27 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-24-13
Work Began 07-15-13
Work Completed 09-23-14
Time Computed 07-15-13
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 135
Percent Time Used 100
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0456-01-044
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.26%)
NORTH TEXAS REBAR, LLC (0.74%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.79%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.18%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.62%)
RAYFORD"S TRUCK & TRACTOR( 12.94%)
FORTSON CONTRACTING, INC.(1.58%)
HOUSTON SAWING & DRILLING(0.20%)
APAC-TEXAS, INC. (5.79%)
SOTO"S STEEL (0.13%)
SOTO"S STEEL (0.24%)
Contract # 04133215
Totals 2127943.49 0.00 2120709.27 100.0

CountyBURLESON
Highway FM 50
From THE BNSF RAILROAD
To THE WASHINGTON COUNTY LINE
CSJ 0457-01-056
Proj ID STP 2014(340)
Work Type REHABILITATE EXISTING ROAD
 
1.361 1532334.42 101366.88 867667.13 56.6
Work Order 03-03-14
Work Began 07-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 69
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0457-01-056
J & M CONTRACTING, COMPANY (3.86%)
CEN TEX HYDROSEED, INC.(1.82%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.05%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(0.52%)
Contract # 01143207
Totals 1532334.42 101366.88 867667.13 56.6

CountyBRAZOS
Highway FM 60
From SH 6
To FM 158
CSJ 0506-01-082
Proj ID STP 2004(74)
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
1.747 7633962.49 19041.70 7574250.49 99.4
Work Order 07-23-12
Work Began 08-04-12
Work Completed  
Time Computed 08-04-12
Contract Working Days 296
Addl Days Granted 26
Working Days Charged 338
Percent Time Used 104
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0506-01-082
JEFFERY BAILEY TRUCKING, INC.(1.17%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(3.69%)
FLASHER EQUIPMENT COMPANY(0.73%)
KELLYSTONE, INC(1.12%)
TEX OP CONSTRUCTION, LP(0.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%)
HEMPHILL PILE DRIVING CO., A CORP. (0.96%)
ROADWAY SPECIALTIES, INC.(0.38%)
CEN TEX HYDROSEED, INC.(0.95%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.97%)
MESA ROD BUSTERS, INC. (0.73%)
RIOS TRUCKING CO.(0.00%)
PRIMATE CONSTRUCTION, INC. (0.31%)
Contract # 05123205
Totals 7633962.49 19041.70 7574250.49 99.4

CountyMILAM
Highway FM 486
From AT SAN GABRIEL RIVER
To .
CSJ 0590-05-027
Proj ID BR 2012(706)
Work Type GR, STRS, BASE AND SURFACE
 
0.176 1943618.46 0.00 2071051.63 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-24-12
Work Began 10-31-12
Work Completed 11-14-14
Time Computed 10-10-12
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 270
Percent Time Used 102
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0590-05-027
N-LINE TRAFFIC MAINTENANCE, L.P. (0.34%)
RICE ENVIRONMENTAL SERVICES(0.49%)
D. I. J. CONSTRUCTION, INC.(0.75%)
PRIMATE CONSTRUCTION, INC. (0.34%)
S & S BRIDGE PAINTING, INC.(0.17%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.07%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.98%)
GK CONSTRUCTION, LLC (1.08%)
BEAIRD DRILLING(3.67%)
JOY LATTIMER, LLC. (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.87%)
K.L. DURHAM CONSTRUCTION, LLC(0.30%)
BIG CREEK CONSTRUCTION, LTD. (2.76%)
Contract # 08123227
Totals 1943618.46 0.00 2071051.63 100.0

CountyGRIMES
Highway FM 244
From CR 170
To CR 171
CSJ 0643-04-028
Proj ID STP 1402(102)
Work Type MISCELLANEOUS WORK
 
5.175 2156938.65 150467.40 150467.40 6.9
Work Order 09-22-14
Work Began 01-21-15
Work Completed  
Time Computed 12-21-14
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 9
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0643-04-028
J & M CONTRACTING, COMPANY ( 12.18%)
CEN TEX HYDROSEED, INC.(2.05%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.96%)
Contract # 08143013
Totals 2156938.65 150467.40 150467.40 6.9

CountyBURLESON
Highway FM 60
From 1.2 MILES WEST OF FM 2039
To 0.62 MILE EAST OF OLD RIVER
CSJ 0648-03-050
Proj ID C 648-3-50
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
3.984 10487720.87 221247.07 3733336.06 35.5
Work Order 02-19-14
Work Began 04-07-14
Work Completed  
Time Computed 04-07-14
Contract Working Days 227
Addl Days Granted 0
Working Days Charged 119
Percent Time Used 52
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0648-03-050
BLUE STAR BARRICADES, INC. (0.26%)
COWBELL TRAFFIC SERVICES, INC. (0.07%)
D. I. J. CONSTRUCTION, INC.(0.65%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.52%)
MURRAY CONSTRUCTION(0.38%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.16%)
TEXAS ALTERNATIVE GRASSER, INC.(0.30%)
PRIME ECO GROUP, INC.(0.00%)
PIPE WHOLESALERS OF TEXAS, INC.(0.00%)
Contract # 12133003
Totals 10487720.87 221247.07 3733336.06 35.5

CountyFREESTONE
Highway IH 45
From THE LEON COUNTY LINE
To US 84
CSJ 0675-02-077
Proj ID IM 0452(143)
Work Type HMA OVERLAY (REHABILITATION)
 
34.574 4687021.87 43063.33 4797675.58 100.0
Work Order 12-04-13
Work Began 05-22-14
Work Completed 01-28-15
Time Computed 03-04-14
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 130
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-02-077
COWBELL TRAFFIC SERVICES, INC. (0.68%)
MPB, INC.(0.55%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.13%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
FORTSON CONTRACTING, INC.(1.08%)
STRIPING TECHNOLOGY, L.P.(2.78%)
Contract # 09133015
Totals 4687021.87 43063.33 4797675.58 100.0

CountyMADISON
Highway IH 45
From ON IH 45 NBML FROM THE WALKER C/L
To SH 21
CSJ 0675-05-076
Proj ID IM 0452(144)
Work Type HMA OVERLAY
 
8.679 908902.09 2880.00 819367.92 100.0
CountyMADISON
Highway IH 45
From ON IH 45 NBML FROM THE WALKER C/L
To SH 21
CSJ 0675-05-078
Proj ID IM 0452(144)
Work Type HMA OVERLAY
 
8.679 1478620.81 0.00 1497932.84 100.0
Work Order 03-06-14
Work Began 05-02-14
Work Completed 01-06-15
Time Computed 05-02-14
Contract Working Days 50
Addl Days Granted 6
Working Days Charged 46
Percent Time Used 82
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-05-076
N-LINE TRAFFIC MAINTENANCE, L.P. (0.30%)
COWBELL TRAFFIC SERVICES, INC. (0.48%)
R K STEPHENS CONSTRUCTION, LLC (1.53%)
TEXAS ALTERNATIVE GRASSER, INC.(0.15%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.97%)
WILLOW CITY SIGN & RAIL, INC.(2.34%)
SCR CONSTRUCTION CO., INC. (1.68%)
Contract # 11133214
Totals 2387522.90 2880.00 2317300.76 100.0

CountyWALKER
Highway IH 45
From SH 75
To THE MADISON COUNTY LINE
CSJ 0675-06-099
Proj ID IM 0452(141)
Work Type HMA OVERLAY
 
14.952 5387237.10 0.00 0.00 0.0
Work Order 01-17-14
Work Began 00-00-00
Work Completed  
Time Computed 04-17-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-06-099
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
COWBELL TRAFFIC SERVICES, INC. (0.43%)
ODUM SERVICES, L.P.(1.55%)
STRIPING TECHNOLOGY, L.P.(2.99%)
Contract # 10133221
Totals 5387237.10 0.00 0.00 0.0

CountyWALKER
Highway IH 45
From AT THE INTERSECTION WITH FM 1375
To .
CSJ 0675-07-089
Proj ID STP 2014(483)HES
Work Type REALIGN INTERSECTION
 
0.600 3355020.53 77691.25 1442168.41 42.9
Work Order 05-09-14
Work Began 08-14-14
Work Completed  
Time Computed 08-07-14
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 42
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-07-089
ALLSTATE SIGNAL & CONSTRUCTION, LLC(3.17%)
CEN TEX HYDROSEED, INC.(0.14%)
A & A CONSTRUCTION (2.86%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.48%)
MURRAY CONSTRUCTION(1.14%)
DUSTIN ALLEN, INC. (2.08%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.47%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.56%)
Contract # 03143228
Totals 3355020.53 77691.25 1442168.41 42.9

CountyBRAZOS
Highway VA
From AT VARIOUS LOCATIONS
To IN THE BRYAN DISTRICT
CSJ 0917-00-040
Proj ID NH 2014(949)
Work Type CONSTRUCT SIDEWALK CURB RAMPS
 
1.000 3503761.00 122620.90 802244.40 22.8
Work Order 08-27-14
Work Began 10-06-14
Work Completed  
Time Computed 09-12-14
Contract Working Days 418
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 14
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-040
CLASSIC TEJAS CONSTRUCTION, INC. (6.88%)
Contract # 07143242
Totals 3503761.00 122620.90 802244.40 22.8

CountyGRIMES
Highway CR
From ON CR 202 (PINEBROOK DRIVE)
To AT KICKAPOO CREEK
CSJ 0917-17-043
Proj ID BR 2012(269)
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
0.164 662557.78 75950.66 390776.61 61.4
Work Order 05-01-14
Work Began 06-30-14
Work Completed  
Time Computed 06-30-14
Contract Working Days 121
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 115
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-043
ODUM SERVICES, L.P.(3.63%)
W. W. FOUNDATION DRILLING, LTD.(2.90%)
HEMPHILL PILE DRIVING CO., A CORP. (4.89%)
JUST GROOVING, LTD.(0.27%)
CEN TEX HYDROSEED, INC.(1.94%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.12%)
MESA ROD BUSTERS, INC. (0.17%)
Contract # 03143014
Totals 662557.78 75950.66 390776.61 61.4

CountyGRIMES
Highway CR
From ON CR 327 (LOCAL CR 102)
To AT THE NAVASOTA RIVER
CSJ 0917-17-063
Proj ID BR 2012(271)
Work Type GRADING, STRUCTURES AND BASE
 
0.091 937686.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153036
Totals 937686.62 0.00 0.00 0.0

CountyFREESTONE
Highway CR
From ON COUNTY ROAD 352 (LOCAL CR 1041)
To AT TEHUACANA CREEK
CSJ 0917-20-011
Proj ID BR 96(480)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.104 448406.84 1260.00 474051.50 100.0
Work Order 01-17-14
Work Began 03-14-14
Work Completed 09-22-14
Time Computed 02-02-14
Contract Working Days 83
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 97
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-011
CEN TEX HYDROSEED, INC.(1.02%)
FORTSON CONTRACTING, INC.(2.71%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.94%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.64%)
JUST GROOVING, LTD.(0.39%)
REDROD STEEL AND CABLE, LLC(0.40%)
Contract # 10133010
Totals 448406.84 1260.00 474051.50 100.0

CountyFREESTONE
Highway PW
From AT THE FAIRFIELD LAKE STATE PARK
To .
CSJ 0917-20-034
Proj ID C 917-20-34
Work Type RECONSTRUCT ROADWAYS AND CAMPSITES
 
7.000 1574868.18 0.00 1602330.96 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-10-13
Work Began 09-17-13
Work Completed 10-06-14
Time Computed 09-17-13
Contract Working Days 118
Addl Days Granted 37
Working Days Charged 165
Percent Time Used 106
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-034
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20%)
SPEEDY PAVING(8.14%)
STRIPING TECHNOLOGY, L.P.(0.30%)
Contract # 06133011
Totals 1574868.18 0.00 1602330.96 100.0

page 1 | page 2 | page 3