|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | LEON |
| Highway |
IH 45 |
| From |
SH 7 |
| To |
THE FREESTONE COUNTY LINE |
| CSJ |
0675-03-064 |
| Proj ID |
STP 2008(573)HES |
| Work Type |
INSTALL MEDIAN BARRIER |
| |
|
28.573 |
3056822.40 |
253687.16 |
1519949.91 |
49.7 |
| Work Order |
06-13-08 |
| Work Began |
10-06-08 |
| Work Completed |
|
| Time Computed |
10-06-08 |
| Contract Working Days |
273 |
| Addl Days Granted |
0 |
| Working Days Charged |
25 |
| Percent Time Used |
9 |
| Contractor(s) |
| A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0675-03-064 CANOGA CONSTRUCTION CO.( 20.17%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.55%)
|
| Contract # |
05083207 |
|
Totals |
3056822.40 |
253687.16 |
1519949.91 |
49.7 |
|
| County | LEON |
| Highway |
IH 45 |
| From |
SH 7 |
| To |
KEECHI CREEK |
| CSJ |
0675-03-066 |
| Proj ID |
IM 0452(126) |
| Work Type |
PLANING AND HMA OVERLAY |
| |
|
15.508 |
2803358.41 |
51223.34 |
2449071.95 |
87.3 |
| Work Order |
05-12-08 |
| Work Began |
08-25-08 |
| Work Completed |
|
| Time Computed |
08-25-08 |
| Contract Working Days |
62 |
| Addl Days Granted |
0 |
| Working Days Charged |
38 |
| Percent Time Used |
61 |
| Contractor(s) |
| BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0675-03-066 BATTERSON, L.L.P.(5.61%) INTERSTATE BARRICADES & MARKINGS, INC. (0.23%)
|
| Contract # |
04083210 |
|
Totals |
2803358.41 |
51223.34 |
2449071.95 |
87.3 |
|
| County | LEON |
| Highway |
IH 45 |
| From |
THE MADISON COUNTY LINE |
| To |
0.3 MILE NORTH OF FM 977 |
| CSJ |
0675-04-057 |
| Proj ID |
IM 0452(125) |
| Work Type |
PLN, CONC PAV REPR, SEAL, HMA & PFC |
| |
|
56.004 |
2297268.70 |
6092.70 |
2166552.90 |
94.3 |
| Work Order |
05-12-08 |
| Work Began |
07-14-08 |
| Work Completed |
|
| Time Computed |
07-14-08 |
| Contract Working Days |
72 |
| Addl Days Granted |
0 |
| Working Days Charged |
55 |
| Percent Time Used |
76 |
| Contractor(s) |
| BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0675-04-057 BATTERSON, L.L.P.(2.60%) INTERSTATE BARRICADES & MARKINGS, INC. (0.36%) WEST TEXAS RUMBLE STRIP(4.16%)
|
| Contract # |
04083230 |
|
Totals |
2297268.70 |
6092.70 |
2166552.90 |
94.3 |
|
| County | WALKER |
| Highway |
IH 45 |
| From |
SAFETY REST AREAS NORTH OF HUNTSVIL |
| To |
. |
| CSJ |
0675-06-080 |
| Proj ID |
STP 2000(326)TE |
| Work Type |
RECONSTRUCT EXISTING SAFETY REST AR |
| |
|
0.001 |
17852484.65 |
0.00 |
19349990.97 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-13-06 |
| Work Began |
02-06-06 |
| Work Completed |
|
| Time Computed |
01-29-06 |
| Contract Working Days |
420 |
| Addl Days Granted |
248 |
| Working Days Charged |
668 |
| Percent Time Used |
100 |
| Contractor(s) |
| SPAWGLASS CIVIL CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0675-06-080 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11053403 |
|
Totals |
17852484.65 |
0.00 |
19349990.97 |
99.9 |
|
| County | WALKER |
| Highway |
IH 45 |
| From |
0.4 MILE NORTH OF AVENUE S |
| To |
SH 19 |
| CSJ |
0675-07-065 |
| Proj ID |
IM 0452(127) |
| Work Type |
CONVERT FRT RD TO ONE - WAY OPERATION |
| |
|
3.067 |
10102410.28 |
619480.61 |
2382321.16 |
23.5 |
| Work Order |
08-04-08 |
| Work Began |
09-22-08 |
| Work Completed |
|
| Time Computed |
09-22-08 |
| Contract Working Days |
486 |
| Addl Days Granted |
0 |
| Working Days Charged |
43 |
| Percent Time Used |
8 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0675-07-065 J & M CONTRACTING, COMPANY ( 21.96%) HIGHWAY TECHNOLOGIES, L.P. (1.03%) BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(2.55%) WILLOW CITY SIGN & RAIL, INC.(1.94%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.74%)
|
| Contract # |
06083202 |
|
Totals |
10102410.28 |
619480.61 |
2382321.16 |
23.5 |
|
| County | WALKER |
| Highway |
IH 45 |
| From |
SH 30 |
| To |
VETERANS MEMORIAL PARKWAY |
| CSJ |
0675-07-082 |
| Proj ID |
IM 0452(124) |
| Work Type |
CONVERT FRT RD TO ONE - WAY OPERATION |
| |
|
4.124 |
13777980.01 |
286073.13 |
3103817.19 |
22.5 |
| Work Order |
04-02-08 |
| Work Began |
08-04-08 |
| Work Completed |
|
| Time Computed |
08-04-08 |
| Contract Working Days |
822 |
| Addl Days Granted |
0 |
| Working Days Charged |
56 |
| Percent Time Used |
6 |
| Contractor(s) |
| A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0675-07-082 N-LINE TRAFFIC MAINTENANCE, L.P. (1.78%) FORTSON CONTRACTING, INC.(1.29%) INTERSTATE BARRICADES & MARKINGS, INC. (1.08%) J & M CONTRACTING, COMPANY ( 16.56%) WATERS CONSTRUCTION CO., INC.(0.32%) CANOGA CONSTRUCTION CO.(0.63%)
|
| Contract # |
02083202 |
|
Totals |
13777980.01 |
286073.13 |
3103817.19 |
22.5 |
|
| County | ROBERTSON |
| Highway |
VA |
| From |
HEARNE STATION DEPOT, PHASE II |
| To |
. |
| CSJ |
0917-18-039 |
| Proj ID |
STP 2000(545)TE |
| Work Type |
REHABLILITATION OF HISTORIC STRUCTU |
| |
|
0.002 |
894600.00 |
41151.60 |
754147.80 |
84.3 |
| Work Order |
03-18-08 |
| Work Began |
04-21-08 |
| Work Completed |
|
| Time Computed |
04-21-08 |
| Contract Working Days |
165 |
| Addl Days Granted |
0 |
| Working Days Charged |
132 |
| Percent Time Used |
80 |
| Contractor(s) |
| TEXAS TREE & LANDSCAPE, LTD |
SUBCONTRACTOR(S) FOR CCSJ: 0917-18-039 C.W. RHODES ELECTRIC, INC. (3.35%) A-1 TERMITES COMPANY (0.20%) AIR CONTROL(5.79%)
|
| Contract # |
02083013 |
|
Totals |
894600.00 |
41151.60 |
754147.80 |
84.3 |
|
| County | FREESTONE |
| Highway |
VA |
| From |
AT THE RICHLAND CREEK WILDLIFE |
| To |
MANAGEMENT AREA IN FREESTONE COUNTY |
| CSJ |
0917-20-027 |
| Proj ID |
C 917-20-27 |
| Work Type |
GRADING, STRUCTURES AND BASE |
| |
|
1.501 |
1441878.12 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
118 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SIMON TRAYLOR & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-027 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12083208 |
|
Totals |
1441878.12 |
0.00 |
0.00 |
0.0 |
|
| County | WALKER |
| Highway |
CR |
| From |
ON CR 288 (O'BANNON ROAD) |
| To |
AT CANEY CREEK |
| CSJ |
0917-27-029 |
| Proj ID |
BR 2002(816) |
| Work Type |
GRADING, STRUCTURES, BASE AND SURFA |
| |
|
0.073 |
682628.42 |
11580.00 |
50157.15 |
7.3 |
| Work Order |
03-18-08 |
| Work Began |
12-03-08 |
| Work Completed |
|
| Time Computed |
12-03-08 |
| Contract Working Days |
65 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TRIPLE B SERVICES, L.L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-029 ROADSAFE TRAFFIC SYSTEMS, INC. (0.45%)
|
| Contract # |
02083015 |
|
Totals |
682628.42 |
11580.00 |
50157.15 |
7.3 |
|
| County | WALKER |
| Highway |
VA |
| From |
AT VARIOUS LOCATIONS IN THE CITY OF |
| To |
HUNTSVILLE |
| CSJ |
0917-27-035 |
| Proj ID |
STP 2008(574) |
| Work Type |
CONSTRUCT CURB RAMPS AND LANDINGS |
| |
|
0.002 |
1705010.00 |
118291.84 |
471750.56 |
27.6 |
| Work Order |
07-10-08 |
| Work Began |
08-15-08 |
| Work Completed |
|
| Time Computed |
08-18-08 |
| Contract Working Days |
252 |
| Addl Days Granted |
0 |
| Working Days Charged |
52 |
| Percent Time Used |
20 |
| Contractor(s) |
| CLASSIC CITY UTILITY, INC |
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-035 N-LINE TRAFFIC MAINTENANCE, L.P. (3.99%) ENVIRONMENTAL ALLIES, L.P. (0.34%) LONE STAR HIGHWAY PRODUCTS, INC. (3.46%) EASTER CONSTRUCTION, INC.( 16.55%) ROADWAY ENGINEERING AND CONSTRUCTION, INC. ( 11.08%)
|
| Contract # |
05083006 |
|
Totals |
1705010.00 |
118291.84 |
471750.56 |
27.6 |
|
| County | WASHINGTON |
| Highway |
FM 2447 |
| From |
AT NEW YEARS CREEK |
| To |
. |
| CSJ |
1299-01-021 |
| Proj ID |
BR 2007(604) |
| Work Type |
GR, STRS, BASE AND SURFACE |
| |
|
7.807 |
4248853.52 |
99702.21 |
3690489.56 |
86.8 |
| Work Order |
08-09-07 |
| Work Began |
09-05-07 |
| Work Completed |
|
| Time Computed |
09-13-07 |
| Contract Working Days |
299 |
| Addl Days Granted |
0 |
| Working Days Charged |
231 |
| Percent Time Used |
77 |
| Contractor(s) |
| GLENN FUQUA, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1299-01-021 CEN TEX HYDROSEED, INC.(0.71%) PEDRO CARLOS CONSTRUCTION CO.(6.19%) UNITED RENTALS HIGHWAY TECHNOLOGIES, L.P. (HOUSTON)(1.62%) WEBBER-BALKE FOUNDATION COMPANY, INC.(4.05%) W.D.F. HAULING (2.00%) BWF FREIGHT(1.12%) BREDA COMPANY, INC.(0.13%) PRIMATE CONSTRUCTION, INC. (0.12%)
|
| Contract # |
06073238 |
|
Totals |
4248853.52 |
99702.21 |
3690489.56 |
86.8 |
|
| County | FREESTONE |
| Highway |
FM 1451 |
| From |
THE TEAGUE CITY LIMITS |
| To |
FM 489 |
| CSJ |
1327-02-021 |
| Proj ID |
C 1327-2-21 |
| Work Type |
GRADING, STRUCTURES, BASE AND SURF |
| |
|
5.715 |
1854430.11 |
0.00 |
0.00 |
0.0 |
| Work Order |
11-10-08 |
| Work Began |
12-02-08 |
| Work Completed |
|
| Time Computed |
12-02-08 |
| Contract Working Days |
131 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SMITH & COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1327-02-021 WATERS CONSTRUCTION CO., INC.( 21.16%) MURRAY CONSTRUCTION(1.27%) FORTSON CONTRACTING, INC.(2.05%) INTERSTATE BARRICADES & MARKINGS, INC. (1.76%) SOUTHWEST ENVIRONMENT SERVICES, INC. (3.84%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.48%)
|
| Contract # |
10083208 |
|
Totals |
1854430.11 |
0.00 |
0.00 |
0.0 |
|
| County | FREESTONE |
| Highway |
FM 489 |
| From |
AT KEECHI CREEK |
| To |
. |
| CSJ |
2144-01-011 |
| Proj ID |
BR 2008(034) |
| Work Type |
GRADING, STRUCTURES, BASE AND SURFA |
| |
|
0.293 |
898699.30 |
43187.95 |
897284.48 |
99.9 |
| Work Order |
10-18-07 |
| Work Began |
06-02-08 |
| Work Completed |
|
| Time Computed |
06-02-08 |
| Contract Working Days |
83 |
| Addl Days Granted |
5 |
| Working Days Charged |
98 |
| Percent Time Used |
111 |
| Contractor(s) |
| FUQUA CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2144-01-011 WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.76%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.97%) QUALITY TRAFFIC SERVICES, L.L.C. (2.14%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.97%) DIAMOND E SERVICES ( 28.08%) STOMPER DEMOLITION (0.00%) GUAJARDO STEEL (0.62%) CAPROCK SPECIALITY CONTRACTORS (0.17%) FORTSON CONTRACTING, INC.(1.46%) HIGHWAY TECHNOLOGIES, L.P. (0.41%) WATERS CONSTRUCTION CO., INC.(3.53%)
|
| Contract # |
09073031 |
|
Totals |
898699.30 |
43187.95 |
897284.48 |
99.9 |
|
| County | BRAZOS |
| Highway |
FM 2818 |
| From |
AT UPRR IN COLLEGE STATION |
| To |
DOT NO. 743219D |
| CSJ |
2399-01-022 |
| Proj ID |
STP 2008(683)RGS |
| Work Type |
CONST RAILROAD GRADE SEPARATION STR |
| |
|
3.508 |
20854415.32 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
12-01-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
413 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 2399-01-022 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09083001 |
|
Totals |
20854415.32 |
0.00 |
0.00 |
0.0 |
|
| County | GRIMES |
| Highway |
FM 2562 |
| From |
SH 30 |
| To |
FM 149 |
| CSJ |
3302-01-013 |
| Proj ID |
C 3302-1-13 |
| Work Type |
GRADING, BASE AND SURFACE |
| |
|
3.969 |
1443326.04 |
8383.53 |
1240594.38 |
86.5 |
| Work Order |
03-12-08 |
| Work Began |
06-02-08 |
| Work Completed |
|
| Time Computed |
06-02-08 |
| Contract Working Days |
79 |
| Addl Days Granted |
0 |
| Working Days Charged |
89 |
| Percent Time Used |
112 |
| Contractor(s) |
| GLENN FUQUA, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3302-01-013 BWF FREIGHT(3.32%) D. I. J. CONSTRUCTION, INC.(1.50%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.41%) PNEU-ROCK TRANSPORTATION, INC. (1.40%)
|
| Contract # |
02083010 |
|
Totals |
1443326.04 |
8383.53 |
1240594.38 |
86.5 |
|