Monthly State Let Construction Report For Bryan District As Of Jul 11, 2014 Page 2 Of 3

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBURLESON
Highway FM 50
From THE BNSF RAILROAD
To THE WASHINGTON COUNTY LINE
CSJ 0457-01-056
Proj ID STP 2014(340)
Work Type REHABILITATE EXISTING ROAD
 
1.361 1532334.42 0.00 0.00 0.0
Work Order 03-03-14
Work Began 07-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0457-01-056
J & M CONTRACTING, COMPANY (3.86%)
CEN TEX HYDROSEED, INC.(1.82%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.05%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(0.52%)
Contract # 01143207
Totals 1532334.42 0.00 0.00 0.0

CountyBRAZOS
Highway FM 60
From SH 6
To FM 158
CSJ 0506-01-082
Proj ID STP 2004(74)
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
1.747 7633962.49 180615.13 6232232.36 81.6
Work Order 07-23-12
Work Began 08-04-12
Work Completed  
Time Computed 08-04-12
Contract Working Days 296
Addl Days Granted 26
Working Days Charged 286
Percent Time Used 88
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0506-01-082
JEFFERY BAILEY TRUCKING, INC.(1.17%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(3.69%)
FLASHER EQUIPMENT COMPANY(0.73%)
KELLYSTONE, INC(1.12%)
TEX OP CONSTRUCTION, LP(0.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%)
HEMPHILL PILE DRIVING CO., A CORP. (0.96%)
ROADWAY SPECIALTIES, INC.(0.38%)
CEN TEX HYDROSEED, INC.(0.95%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.97%)
MESA ROD BUSTERS, INC. (0.73%)
RIOS TRUCKING CO.(0.00%)
PRIMATE CONSTRUCTION, INC. (0.31%)
Contract # 05123205
Totals 7633962.49 180615.13 6232232.36 81.6

CountyLEON
Highway FM 3
From 4.0 MILES SOUTH OF CR 470
To FM 39
CSJ 0552-01-031
Proj ID STP 2013(814)
Work Type RESTORE EXISTING ROAD
 
7.231 2758787.87 48447.00 2570891.63 93.1
Work Order 09-05-13
Work Began 10-10-13
Work Completed  
Time Computed 10-10-13
Contract Working Days 128
Addl Days Granted 2
Working Days Charged 128
Percent Time Used 98
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0552-01-031
CEN TEX HYDROSEED, INC.(0.68%)
INTERSTATE BARRICADES & MARKINGS, INC. (3.34%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.17%)
ODUM SERVICES, L.P.(2.45%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.14%)
Contract # 06133225
Totals 2758787.87 48447.00 2570891.63 93.1

CountyMILAM
Highway FM 486
From AT SAN GABRIEL RIVER
To .
CSJ 0590-05-027
Proj ID BR 2012(706)
Work Type GR, STRS, BASE AND SURFACE
 
0.176 1943618.46 28418.26 1951132.83 99.9
Work Order 09-24-12
Work Began 10-31-12
Work Completed  
Time Computed 10-10-12
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 260
Percent Time Used 98
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0590-05-027
N-LINE TRAFFIC MAINTENANCE, L.P. (0.34%)
RICE ENVIRONMENTAL SERVICES(0.49%)
D. I. J. CONSTRUCTION, INC.(0.75%)
PRIMATE CONSTRUCTION, INC. (0.34%)
S & S BRIDGE PAINTING, INC.(0.17%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.07%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.98%)
GK CONSTRUCTION, LLC (1.08%)
BEAIRD DRILLING(3.67%)
JOY LATTIMER, LLC. (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.87%)
K.L. DURHAM CONSTRUCTION, LLC(0.30%)
Contract # 08123227
Totals 1943618.46 28418.26 1951132.83 99.9

CountyBURLESON
Highway FM 60
From 1.2 MILES WEST OF FM 2039
To 0.62 MILE EAST OF OLD RIVER
CSJ 0648-03-050
Proj ID C 648-3-50
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
3.984 10487720.87 147729.33 928607.92 8.8
Work Order 02-19-14
Work Began 04-07-14
Work Completed  
Time Computed 04-07-14
Contract Working Days 227
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 12
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0648-03-050
BLUE STAR BARRICADES, INC. (0.26%)
COWBELL TRAFFIC SERVICES, INC. (0.07%)
D. I. J. CONSTRUCTION, INC.(0.65%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.52%)
MURRAY CONSTRUCTION(0.38%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.16%)
TEXAS ALTERNATIVE GRASSER, INC.(0.30%)
PRIME ECO GROUP, INC.(0.00%)
PIPE WHOLESALERS OF TEXAS, INC.(0.00%)
Contract # 12133003
Totals 10487720.87 147729.33 928607.92 8.8

CountyFREESTONE
Highway IH 45
From THE LEON COUNTY LINE
To US 84
CSJ 0675-02-070
Proj ID IM 0452(139)
Work Type HMA OVERLAY
 
17.316 2217971.87 0.00 2144031.36 96.6
CountyFREESTONE
Highway IH 45
From THE LEON COUNTY LINE
To US 84
CSJ 0675-02-074
Proj ID IM 0452(139)
Work Type OVERLAY (REHABILITATION)
 
17.316 3011426.00 0.00 2719044.48 90.2
Work Order 03-19-13
Work Began 04-05-13
Work Completed  
Time Computed 04-05-13
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 82
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-02-070
COWBELL TRAFFIC SERVICES, INC. (0.61%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
PRIMATE CONSTRUCTION, INC. (0.80%)
STRIPING TECHNOLOGY, L.P.(2.41%)
FORTSON CONTRACTING, INC.(0.98%)
POTTER TRUCKING(0.00%)
PAVETEX ENGINEERING & TESTING, INC.(0.34%)
Contract # 01133011
Totals 5229397.87 0.00 4863075.84 92.9

CountyFREESTONE
Highway IH 45
From THE LEON COUNTY LINE
To US 84
CSJ 0675-02-077
Proj ID IM 0452(143)
Work Type HMA OVERLAY (REHABILITATION)
 
34.574 4687021.87 1646162.16 1649412.16 35.1
Work Order 12-04-13
Work Began 05-22-14
Work Completed  
Time Computed 03-04-14
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 25
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-02-077
COWBELL TRAFFIC SERVICES, INC. (0.68%)
MPB, INC.(0.55%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.13%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
FORTSON CONTRACTING, INC.(1.08%)
STRIPING TECHNOLOGY, L.P.(2.78%)
Contract # 09133015
Totals 4687021.87 1646162.16 1649412.16 35.1

CountyMADISON
Highway IH 45
From ON IH 45 NBML FROM THE WALKER C/L
To SH 21
CSJ 0675-05-076
Proj ID IM 0452(144)
Work Type HMA OVERLAY
 
8.679 908902.09 87216.85 802762.04 88.3
CountyMADISON
Highway IH 45
From ON IH 45 NBML FROM THE WALKER C/L
To SH 21
CSJ 0675-05-078
Proj ID IM 0452(144)
Work Type HMA OVERLAY
 
8.679 1478620.81 19578.55 22909.55 1.5
Work Order 03-06-14
Work Began 05-02-14
Work Completed  
Time Computed 05-02-14
Contract Working Days 50
Addl Days Granted 6
Working Days Charged 9
Percent Time Used 16
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-05-076
N-LINE TRAFFIC MAINTENANCE, L.P. (0.30%)
COWBELL TRAFFIC SERVICES, INC. (0.48%)
R K STEPHENS CONSTRUCTION, LLC (1.53%)
TEXAS ALTERNATIVE GRASSER, INC.(0.15%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.97%)
WILLOW CITY SIGN & RAIL, INC.(0.00%)
Contract # 11133214
Totals 2387522.90 106795.40 825671.59 34.5

CountyWALKER
Highway IH 45
From SH 75
To THE MADISON COUNTY LINE
CSJ 0675-06-099
Proj ID IM 0452(141)
Work Type HMA OVERLAY
 
14.952 5387237.10 0.00 0.00 0.0
Work Order 01-17-14
Work Began 00-00-00
Work Completed  
Time Computed 04-17-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-06-099
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
COWBELL TRAFFIC SERVICES, INC. (0.43%)
ODUM SERVICES, L.P.(1.55%)
STRIPING TECHNOLOGY, L.P.(2.99%)
Contract # 10133221
Totals 5387237.10 0.00 0.00 0.0

CountyWALKER
Highway IH 45
From AT THE INTERSECTION WITH FM 1375
To .
CSJ 0675-07-089
Proj ID STP 2014(483)HES
Work Type REALIGN INTERSECTION
 
0.600 3355020.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-07-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143228
Totals 3355020.53 0.00 0.00 0.0

CountyWALKER
Highway FM 980
From 0.067 MILE NORTH OF LEIGH ANNE
To SH 19
CSJ 0756-02-027
Proj ID STP 2013(060)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
13.328 4394843.38 0.00 4264933.57 97.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-18-12
Work Began 10-26-12
Work Completed  
Time Computed 10-26-12
Contract Working Days 264
Addl Days Granted 26
Working Days Charged 256
Percent Time Used 88
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0756-02-027
ROADSAFE TRAFFIC SYSTEMS, INC. (2.72%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.27%)
BWF FREIGHT(4.69%)
W.D.F. HAULING (2.34%)
CEN TEX HYDROSEED, INC.(1.57%)
J & M CONTRACTING, COMPANY (5.67%)
PLANTERSVILLE WATER SERVICES, INC. (1.95%)
Contract # 09123046
Totals 4394843.38 0.00 4264933.57 97.0

CountyBRAZOS
Highway VA
From AT VARIOUS LOCATIONS
To IN THE BRYAN DISTRICT
CSJ 0917-00-040
Proj ID NH 2014(949)
Work Type CONSTRUCT SIDEWALK CURB RAMPS
 
1.000 3503761.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 418
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143242
Totals 3503761.00 0.00 0.00 0.0

CountyMILAM
Highway CR
From ON CR 355 (LOCAL CR 428)
To AT SAN GABRIEL RIVER
CSJ 0917-12-069
Proj ID BR 1102(536)
Work Type REHABILITATE HISTORIC BRIDGE
 
0.152 1272327.40 0.00 1253478.30 98.5
Work Order 07-08-13
Work Began 10-25-13
Work Completed  
Time Computed 10-28-13
Contract Working Days 115
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 72
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0917-12-069
SAN-ANN-CO., INC.(0.34%)
APAC-TEXAS, INC. (1.76%)
FORTSON CONTRACTING, INC.(0.28%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.40%)
S & S BRIDGE PAINTING, INC.( 15.97%)
SOTO"S STEEL (0.09%)
Contract # 05133026
Totals 1272327.40 0.00 1253478.30 98.5

CountyGRIMES
Highway CR
From ON CR 202 (PINEBROOK DRIVE)
To AT KICKAPOO CREEK
CSJ 0917-17-043
Proj ID BR 2012(269)
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
0.164 662557.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-01-14
Work Began 06-30-14
Work Completed  
Time Computed 06-30-14
Contract Working Days 121
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-043
ODUM SERVICES, L.P.(3.63%)
W. W. FOUNDATION DRILLING, LTD.(2.90%)
HEMPHILL PILE DRIVING CO., A CORP. (4.89%)
JUST GROOVING, LTD.(0.27%)
CEN TEX HYDROSEED, INC.(1.94%)
Contract # 03143014
Totals 662557.78 0.00 0.00 0.0

CountyFREESTONE
Highway CR
From ON COUNTY ROAD 352 (LOCAL CR 1041)
To AT TEHUACANA CREEK
CSJ 0917-20-011
Proj ID BR 96(480)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.104 448406.84 48325.00 450550.87 99.9
Work Order 01-17-14
Work Began 00-00-00
Work Completed  
Time Computed 02-02-14
Contract Working Days 83
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 87
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-011
CEN TEX HYDROSEED, INC.(1.02%)
FORTSON CONTRACTING, INC.(2.71%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.94%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.64%)
JUST GROOVING, LTD.(0.39%)
REDROD STEEL AND CABLE, LLC(0.40%)
Contract # 10133010
Totals 448406.84 48325.00 450550.87 99.9

CountyFREESTONE
Highway PW
From AT THE FAIRFIELD LAKE STATE PARK
To .
CSJ 0917-20-034
Proj ID C 917-20-34
Work Type RECONSTRUCT ROADWAYS AND CAMPSITES
 
7.000 1574868.18 4632.89 1145858.12 72.7
Work Order 09-10-13
Work Began 09-17-13
Work Completed  
Time Computed 09-17-13
Contract Working Days 118
Addl Days Granted 5
Working Days Charged 122
Percent Time Used 99
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-034
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20%)
SPEEDY PAVING(8.14%)
STRIPING TECHNOLOGY, L.P.(0.30%)
Contract # 06133011
Totals 1574868.18 4632.89 1145858.12 72.7

CountyWALKER
Highway PW
From AT THE HUNTSVILLE STATE PARK
To .
CSJ 0917-27-043
Proj ID C 917-27-43
Work Type RECONSTRUCT EXISTING RV PULLOUTS
 
1.000 262456.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143019
Totals 262456.50 0.00 0.00 0.0

CountyFREESTONE
Highway FM 416
From THE NAVARRO COUNTY LINE
To FM 488
CSJ 0998-05-009
Proj ID STP 2014(645)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
5.990 1235167.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0998-05-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143009
Totals 1235167.98 0.00 0.00 0.0

CountyLEON
Highway FM 977
From AT TWO MILE CREEK
To .
CSJ 1147-03-014
Proj ID BR 1302(021)
Work Type REPLACE EXISTING BRIDGE FACILITY
 
0.117 691407.39 1603.07 688549.94 99.5
Work Order 10-10-13
Work Began 10-28-13
Work Completed  
Time Computed 10-28-13
Contract Working Days 101
Addl Days Granted 3
Working Days Charged 100
Percent Time Used 96
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1147-03-014
ACTION SERVICES(0.44%)
FORTSON CONTRACTING, INC.(2.32%)
HOUSTON SAWING & DRILLING(0.27%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.72%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.78%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.10%)
MESA ROD BUSTERS, INC. (0.33%)
WATERS CONSTRUCTION CO., INC.(1.08%)
Contract # 07133249
Totals 691407.39 1603.07 688549.94 99.5

CountyWALKER
Highway FM 1375
From SH 150
To GOURD CREEK ROAD
CSJ 1402-01-032
Proj ID STP 2014(746)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
5.643 2371297.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1402-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143042
Totals 2371297.26 0.00 0.00 0.0