Monthly State Let Construction Report For Bryan District As Of Apr 10, 2017 Page 2 Of 3

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZOS
HighwayFM 158
FromSH 6 NORTHBOUND FRONTAGE ROAD
ToSH 30
CSJ0212-03-057
Proj IDSTP 1602(409)TAPS
Work TypePEDESTRIAN SAFETY LIGHTING
 
3.9661380692.25370180.8026.8
Work Order09-15-16
Work Began01-10-17
Work Completed
Time Computed12-14-16
Contract Working Days177
Addl Days Granted0
Working Days Charged50
Percent Time Used28
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0212-03-057
N-LINE TRAFFIC MAINTENANCE, L.P. (0.54)
BRITTEN HYDROSEEDING (4.92)
SHAW DRILLING, LLC (3.24)
Contract #08163014
Totals1380692.25125921.90370180.8026.8

CountyGRIMES
HighwaySH 30
FromAT THE INTERSECTION OF SH 30
ToAND FM 244
CSJ0212-04-033
Proj IDSTP 1402(194)
Work TypeCONSTRUCT GRADE SEPARATION
 
0.8335718784.142673036.5746.7
Work Order09-30-14
Work Began11-12-15
Work Completed
Time Computed10-16-14
Contract Working Days251
Addl Days Granted19
Working Days Charged125
Percent Time Used46
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0212-04-033
TEXOP CONSTRUCTION (1.66)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.94)
PENHALL COMPANY (0.18)
MESA ROD BUSTERS, INC. (0.38)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.70)
WILLOW CITY SIGN & RAIL, INC. (2.17)
SCOTT DERR PAINTING CO (0.22)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.95)
CEN TEX HYDROSEED, INC. (2.61)
BRICK PAVING PLUS, INC. (0.51)
MCL CONTRACTING, LLC (0.14)
D. I. J. CONSTRUCTION, INC. (0.03)
Contract #07143023
Totals5718784.14310528.122673036.5746.7

CountyGRIMES
HighwaySH 90
FromMADISON COUNTY LINE
ToTHE SOUTH CITY LIMITS OF BEDIAS
CSJ0315-02-047
Proj IDSTP 1502(235)
Work TypeREHABILITATE EXISTING ROAD
 
6.8717051873.093648655.7351.7
Work Order08-10-15
Work Began09-14-15
Work Completed
Time Computed09-14-15
Contract Working Days168
Addl Days Granted5
Working Days Charged147
Percent Time Used84
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0315-02-047
CEN TEX HYDROSEED, INC. (1.13)
COLD CREEK CONSTRUCTION, LTD (0.90)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.99)
WILLOW CITY SIGN & RAIL, INC. (1.61)
NIXON ENGINEERING (0.00)
A. L. HELMCAMP, INC. (0.00)
RIOS TRUCKING CO. (0.00)
Contract #06153227
Totals7051873.0995511.943648655.7351.7

CountyBRAZOS
HighwaySH 105
FromAT THE BRAZOS RIVER
To.
CSJ0315-05-026
Proj IDBR 2014(643)
Work TypeGRADING, STRUCTURES, BASE AND SURF
 
3.28923601410.9217668593.6974.8
Work Order07-02-14
Work Began09-30-14
Work Completed
Time Computed09-30-14
Contract Working Days443
Addl Days Granted0
Working Days Charged388
Percent Time Used87
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0315-05-026
CHOCTAW ERECTORS, INC. (7.06)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.19)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.15)
ATS DRILLING, INC. (7.09)
HOUSTON SAWING & DRILLING (0.06)
BIG CREEK CONSTRUCTION, LTD. (6.72)
MINE SERVICE, INC. (5.33)
GEOSOURCE, INC. (0.94)
RICE ENVIRONMENTAL SERVICES (1.93)
PERFORMANCE EQUIPMENT (0.25)
MESA ROD BUSTERS, INC. (0.53)
EPCS ENVIRONMENTAL LLC (1.52)
MCL CONTRACTING, LLC (0.25)
S & K TRUCKING (0.00)
TOM-MAC, INC. (1.03)
TNT CRANE & RIGGING, INC. (0.07)
CEN TEX HYDROSEED, INC. (0.41)
WILLOW CITY SIGN & RAIL, INC. (0.39)
Contract #05143202
Totals23601410.92124897.9617668593.6974.8

CountyWASHINGTON
HighwayFM 389
From0.06 MILES WEST OF FM 332
ToUS 290
CSJ0315-08-037
Proj IDSTP 1602(156)
Work TypeREHABILITATE EXISTING ROADWAY
 
0.7454243520.680.000.0
Work Order09-20-16
Work Began00-00-00
Work Completed
Time Computed10-20-16
Contract Working Days209
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0315-08-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06163011
Totals4243520.680.000.000.0

CountyLEON
HighwaySH 7
FromRUSK ST.
To3.8 MI EAST OF FM 1511
CSJ0335-01-031
Proj IDSTP 1602(317)
Work TypeREHABILITATE EXISTING ROAD
 
55.83825152378.873633663.2114.4
Work Order09-20-16
Work Began10-31-16
Work Completed
Time Computed10-20-16
Contract Working Days522
Addl Days Granted40
Working Days Charged92
Percent Time Used16
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0335-01-031
COWBELL TRAFFIC SERVICES, INC. (0.33)
CHEROKEE SERVICES (0.07)
CEN TEX HYDROSEED, INC. (1.11)
FORTSON CONTRACTING, INC. (1.53)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.84)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.19)
W.S. CONSTRUCTION COMPANY (10.64)
COLD CREEK CONSTRUCTION, LTD (1.89)
Contract #07163204
Totals25152378.87104622.323633663.2114.4

CountyBRAZOS
HighwayFM 60
FromAT THE INTERCHANGE OF FM 60 WITH
ToFM 2818
CSJ0506-01-105
Proj IDNH 1602(416)
Work TypeIMPROVE INTERCHANGE
 
0.48513863443.802243930.5116.1
Work Order12-12-16
Work Began03-06-17
Work Completed
Time Computed01-11-17
Contract Working Days396
Addl Days Granted7
Working Days Charged18
Percent Time Used4
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0506-01-105
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.66)
FLASHER EQUIPMENT COMPANY (1.25)
SCOTT DERR PAINTING CO, LLC (0.22)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.74)
BRICK PAVING PLUS, INC. (3.07)
BOENIGK MASONRY (0.28)
FORTSON CONTRACTING, INC. (0.18)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (6.90)
SCR CIVIL CONSTRUCTION, LLC (0.47)
AREA WIDE PROTECTIVE, INC. (0.53)
Contract #10163002
Totals13863443.802125318.012243930.5116.1

CountyBURLESON
HighwayFM 2155
FromAT BETHEL DRAW
To.
CSJ0506-04-022
Proj IDBR 2016(579)
Work TypeREPLACE EXISTING BRIDGE
 
0.2981647283.551233663.9474.8
Work Order03-29-16
Work Began06-16-16
Work Completed
Time Computed06-16-16
Contract Working Days212
Addl Days Granted3
Working Days Charged156
Percent Time Used72
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0506-04-022
CEN TEX HYDROSEED, INC. (2.37)
DUSTIN ALLEN, INC. (3.44)
FLASHER EQUIPMENT COMPANY (0.87)
JUST GROOVING, LTD. (0.27)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.09)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27)
MESA ROD BUSTERS, INC. (0.42)
BROCK CONSTRUCTION, LLC (0.87)
Contract #01163213
Totals1647283.55101242.751233663.9474.8

CountyBRAZOS
HighwayFM 2154
FromON FM 2154
ToAT GREENS PRAIRIE TRAIL
CSJ0540-04-072
Proj IDSTP 2016(837)
Work TypeINTERSECTION IMPROVEMENTS
 
0.4812056099.02428380.4920.8
Work Order09-23-16
Work Began10-24-16
Work Completed
Time Computed10-23-16
Contract Working Days97
Addl Days Granted0
Working Days Charged14
Percent Time Used14
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0540-04-072
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (9.51)
BRICK PAVING PLUS, INC. (0.07)
CEN TEX HYDROSEED, INC. (0.82)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.65)
PEDRO CARLOS CONSTRUCTION CO. (1.23)
TEXAS ALTERNATIVE GRASSER, INC. (0.72)
FLASHER EQUIPMENT COMPANY (1.99)
Contract #05163209
Totals2056099.0295370.00428380.4920.8

CountyBRAZOS
HighwayFM 159
FromSH 6
ToSH 105
CSJ0540-05-046
Proj IDSTP 1602(417)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
34.1772209014.25476684.7221.5
Work Order12-20-16
Work Began01-17-17
Work Completed
Time Computed01-17-17
Contract Working Days203
Addl Days Granted0
Working Days Charged27
Percent Time Used13
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0540-05-046
COMEN ENTERPRISE LLC (2.18)
Contract #08163213
Totals2209014.25188133.51476684.7221.5

CountyMADISON
HighwayFM 247
FromSH 21
ToWALKER COUNTY LINE
CSJ0578-01-029
Proj IDSTP 1602(157)
Work TypeREHABILITATE EXISTING ROAD
 
9.7294354851.443681441.8984.5
Work Order07-29-16
Work Began08-29-16
Work Completed
Time Computed08-28-16
Contract Working Days154
Addl Days Granted0
Working Days Charged135
Percent Time Used87
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0578-01-029
CEN TEX HYDROSEED, INC. (4.36)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.80)
J & M CONTRACTING, COMPANY (14.85)
BROCK CONSTRUCTION, LLC (2.10)
AREA WIDE PROTECTIVE, INC. (1.76)
Contract #06163220
Totals4354851.44279930.623681441.8984.5

CountyGRIMES
HighwayFM 3090
From0.08 MILES SOUTH OF HOLLAND CREEK
To0.23 MILES S OF SPRING/HOLLAND RELF
CSJ0643-05-027
Proj IDBR 2016(971)
Work TypeREPLACE EXISTING BRIDGE
 
0.6392353004.361221186.8151.8
Work Order10-06-16
Work Began01-03-17
Work Completed
Time Computed01-04-17
Contract Working Days185
Addl Days Granted0
Working Days Charged48
Percent Time Used25
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0643-05-027
STRIPE-A-ZONE, INC. (0.33)
ROADWAY SPECIALTIES, INC. (4.10)
LONESTAR TRAFFIC SAFETY, LLC (0.26)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25)
W. W. FOUNDATION DRILLING, LTD. (12.95)
MESA ROD BUSTERS, INC. (1.24)
Contract #08163012
Totals2353004.36312866.351221186.8151.8

CountyBURLESON
HighwayFM 60
From1.2 MILES WEST OF FM 2039
To0.62 MILE EAST OF OLD RIVER
CSJ0648-03-050
Proj IDC 648-3-50
Work TypeGRADING, STRUCTURES, BASE AND SURFA
 
3.98410487720.8710738376.4299.9
Work Order02-19-14
Work Began04-07-14
Work Completed
Time Computed04-07-14
Contract Working Days227
Addl Days Granted28
Working Days Charged305
Percent Time Used119
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0648-03-050
BLUE STAR BARRICADES, INC. (0.26)
COWBELL TRAFFIC SERVICES, INC. (0.07)
D. I. J. CONSTRUCTION, INC. (0.65)
LONE STAR HIGHWAY PRODUCTS, INC. (0.52)
MURRAY CONSTRUCTION (0.38)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.16)
TEXAS ALTERNATIVE GRASSER, INC. (0.30)
PRIME ECO GROUP, INC. (0.00)
PIPE WHOLESALERS OF TEXAS, INC. (0.00)
COMEN ENTERPRISE (0.36)
Contract #12133003
Totals10487720.870.0010738376.4299.9

CountyFREESTONE
HighwayIH 45
FromON IH 45 EFR & WFR FROM US 84
ToFM 27
CSJ0675-01-066
Proj IDNH 2017(348)
Work TypeREHABILITATE EXISTING ROAD
 
0.8712450487.60482052.3919.6
Work Order01-25-17
Work Began03-13-17
Work Completed
Time Computed02-24-17
Contract Working Days110
Addl Days Granted0
Working Days Charged14
Percent Time Used12
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-01-066
COMEN ENTERPRISE LLC (0.93)
R K STEPHENS CONSTRUCTION, LLC (5.06)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.84)
TEXAS ALTERNATIVE GRASSER, INC. (0.23)
AREA WIDE PROTECTIVE, INC. (0.51)
NIXON ENGINEERING (0.00)
Contract #12163027
Totals2450487.60482052.39482052.3919.6

CountyBURLESON
HighwayFM 60
FromSH 21 W
ToFM 111
CSJ0713-01-032
Proj IDSTP 1602(321)
Work TypeREHABILITATE EXISTING ROAD
 
2.4982429597.65526055.7521.6
Work Order10-14-16
Work Began12-08-16
Work Completed
Time Computed11-13-16
Contract Working Days100
Addl Days Granted0
Working Days Charged37
Percent Time Used37
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0713-01-032
J & M CONTRACTING, COMPANY (30.56)
CEN TEX HYDROSEED, INC. (2.05)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.86)
BROCK CONSTRUCTION, LLC (1.44)
Contract #07163228
Totals2429597.6589317.50526055.7521.6

CountyMILAM
HighwayFM 487
FromCOUNTY ROAD 402
To0.7 MILE NORTH OF COUNTY ROAD 235
CSJ0858-01-033
Proj IDSTP 1502(528)HES
Work TypePROVIDE ADDITIONAL PAVEMENT WIDTH
 
15.4095587641.645083472.5592.6
Work Order10-30-15
Work Began02-15-16
Work Completed
Time Computed01-28-16
Contract Working Days150
Addl Days Granted0
Working Days Charged235
Percent Time Used156
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0858-01-033
R K STEPHENS CONSTRUCTION, LLC (7.02)
ROADWAY SPECIALTIES, INC. (1.91)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45)
CEN TEX HYDROSEED, INC. (1.57)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.78)
NIXON ENGINEERING (0.00)
Contract #08153237
Totals5587641.6438444.025083472.5592.6

CountyBRAZOS
HighwayVA
FromAT VARIOUS LOCATIONS
ToIN THE BRYAN DISTRICT
CSJ0917-00-040
Proj IDNH 2014(949)
Work TypeCONSTRUCT SIDEWALK CURB RAMPS
 
1.0003503761.003187120.4490.9
Work Order08-27-14
Work Began10-06-14
Work Completed
Time Computed09-12-14
Contract Working Days418
Addl Days Granted0
Working Days Charged363
Percent Time Used86
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-040
CLASSIC TEJAS CONSTRUCTION, INC. (6.88)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.09)
STEEL EFFECTS (0.00)
FLASHER EQUIPMENT COMPANY (2.56)
JACKRABBIT MANUFACTURING, LLC (0.30)
Contract #07143242
Totals3503761.0013711.043187120.4490.9

CountyBRAZOS
HighwayVA
FromVAR. LOCATIONS IN BRAZOS, WALKER,
ToMADISON, LEON & FREESTONE COUNTIES
CSJ0917-00-042
Proj IDITS 2001(537)
Work TypeFY16 ITS DEVELOPMENT PROGRAM
 
0.001549299.80546514.0599.4
Work Order05-12-16
Work Began07-26-16
Work Completed
Time Computed06-11-16
Contract Working Days85
Addl Days Granted0
Working Days Charged74
Percent Time Used87
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-042
BUYER BARRICADES (2.30)
SPECIALTY DRILLING, LTD. (4.73)
Contract #04163239
Totals549299.800.00546514.0599.4

CountyLEON
HighwayCR
FromON CR 110 - LOCAL CR 348
ToAT BRUSHY CREEK RELIEF
CSJ0917-16-034
Proj IDBR 1502(027)
Work TypeREPLACE EXISTING BRIDGE
 
0.078357813.60340190.6795.0
Work Order04-19-16
Work Began10-11-16
Work Completed
Time Computed07-18-16
Contract Working Days78
Addl Days Granted0
Working Days Charged74
Percent Time Used94
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-16-034
LONESTAR TRAFFIC SAFETY, LLC (0.95)
SPECIALTY DRILLING, LTD. (5.14)
FUQUAY, INC. (1.11)
Contract #02163040
Totals357813.60814.05340190.6795.0

CountyGRIMES
HighwayCR
FromON CR 297 - LOCAL CR 162
ToAT THE NAVASOTA RIVER RELIEF
CSJ0917-17-058
Proj IDBR 1502(026)
Work TypeGRADING, STRUCTURES, BASE AND SURF
 
0.097417154.55266324.6863.8
Work Order09-15-16
Work Began01-10-17
Work Completed
Time Computed12-14-16
Contract Working Days80
Addl Days Granted0
Working Days Charged45
Percent Time Used56
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-058
N-LINE TRAFFIC MAINTENANCE, L.P. (2.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.43)
FRANK & SON DOZERWORKS, LLC (2.39)
Contract #08163025
Totals417154.5531412.92266324.6863.8

page 1 | page 2 | page 3