| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | ROBERTSON |
| Highway |
SH 6 |
| From |
WILLIS ST IN CALVERT |
| To |
SH 14 |
| CSJ |
0049-06-061 |
| Proj ID |
NH 2004(788) |
| Work Type |
WIDEN, GR, STRS, BASE AND SURF |
| |
|
13.872 |
28961593.75 |
963191.25 |
27985004.85 |
96.8 |
| Work Order |
12-27-04 |
| Work Began |
05-02-05 |
| Work Completed |
|
| Time Computed |
05-02-05 |
| Contract Working Days |
714 |
| Addl Days Granted |
79 |
| Working Days Charged |
830 |
| Percent Time Used |
104 |
| Contractor(s) |
| A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-061 UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.79%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.49%) AMERICAN REMEDIATION OPTIONS, INC. (0.27%) WILLOW CITY SIGN & RAIL, INC.(0.55%) COX PAVING COMPANY, L.P. (1.10%) PNEU-ROCK TRANSPORTATION, INC. (4.78%) WEST TEXAS RUMBLE STRIP(0.06%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.52%) CEN TEX HYDROSEED, INC.(0.02%) J & M CONTRACTING, COMPANY (0.51%)
|
| Contract # |
11043001 |
|
Totals |
28961593.75 |
963191.25 |
27985004.85 |
96.8 |
|
| County | ROBERTSON |
| Highway |
SH 6 |
| From |
FM 1644 IN CALVERT |
| To |
1.2 MILES NORTH OF MUD CREEK |
| CSJ |
0049-06-073 |
| Proj ID |
NH 2008(659) |
| Work Type |
PREPARATION OF RIGHT OF WAY |
| |
|
6.064 |
710014.50 |
255056.78 |
255574.28 |
35.9 |
| Work Order |
07-10-08 |
| Work Began |
09-30-08 |
| Work Completed |
|
| Time Computed |
09-29-08 |
| Contract Working Days |
34 |
| Addl Days Granted |
0 |
| Working Days Charged |
23 |
| Percent Time Used |
67 |
| Contractor(s) |
| PACE SERVICES, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-073 HILTON SERVICES, LP( 34.60%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.40%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.( 12.03%) TEXAS ALTERNATIVE GRASSER, INC.(2.40%)
|
| Contract # |
06083221 |
|
Totals |
710014.50 |
255056.78 |
255574.28 |
35.9 |
|
| County | ROBERTSON |
| Highway |
SH 6 |
| From |
AT CAMPBELLS CREEK |
| To |
STRUCTURE NOS. 66 (NB) AND 157 (SB) |
| CSJ |
0049-08-053 |
| Proj ID |
BR 2009(014) |
| Work Type |
REHABILITATE AND WIDEN EXISTING BRI |
| |
|
0.378 |
2540044.45 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-28-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-13-08 |
| Contract Working Days |
229 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-053 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09083203 |
|
Totals |
2540044.45 |
0.00 |
0.00 |
0.0 |
|
| County | ROBERTSON |
| Highway |
US 190 |
| From |
ANDERSON STREET IN HEARNE |
| To |
1.5 MILE NORTH OF OSR |
| CSJ |
0049-08-058 |
| Proj ID |
NH 2007(867) |
| Work Type |
PAVEMENT REPAIRS AND HMA INLAY |
| |
|
9.977 |
5754588.86 |
852296.97 |
5190094.45 |
90.1 |
| Work Order |
09-11-07 |
| Work Began |
05-20-08 |
| Work Completed |
|
| Time Computed |
09-27-07 |
| Contract Working Days |
113 |
| Addl Days Granted |
0 |
| Working Days Charged |
64 |
| Percent Time Used |
56 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-058 TEXAS OPERATIONS (4.83%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%) D. I. J. CONSTRUCTION, INC.(2.34%) BRENDA PRICE TRUCKING(0.13%)
|
| Contract # |
08073046 |
|
Totals |
5754588.86 |
852296.97 |
5190094.45 |
90.1 |
|
| County | BRAZOS |
| Highway |
SH 6 |
| From |
0.4 MILE NORTH OF FM 2818 |
| To |
0.3 MILE SOUTH OF ROCK PRAIRIE ROAD |
| CSJ |
0049-12-069 |
| Proj ID |
NH 2008(092) |
| Work Type |
GRADING, STRUCTURES, BASE AND SURFA |
| |
|
3.768 |
8150789.76 |
560412.08 |
3549825.07 |
43.5 |
| Work Order |
01-03-08 |
| Work Began |
02-26-08 |
| Work Completed |
|
| Time Computed |
02-26-08 |
| Contract Working Days |
297 |
| Addl Days Granted |
5 |
| Working Days Charged |
141 |
| Percent Time Used |
46 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-069 SCOTT DERR PAINTING CO (0.15%) BREDA COMPANY, INC.(2.35%) N-LINE TRAFFIC MAINTENANCE, L.P. (1.04%) W. W. FOUNDATION DRILLING, LTD.(1.28%) S & S BRIDGE PAINTING, INC.(2.35%) CRAWFORD YANT(1.46%) HIGHWAY TECHNOLOGIES, L.P. (0.73%) WEST TEXAS RUMBLE STRIP(0.04%) WILLOW CITY SIGN & RAIL, INC.(0.41%) WILEY CONSTRUCTION COMPANY, INC. (5.08%) GUAJARDO STEEL (0.07%) CAPROCK SPECIALITY CONTRACTORS (0.05%)
|
| Contract # |
10073204 |
|
Totals |
8150789.76 |
560412.08 |
3549825.07 |
43.5 |
|
| County | BRAZOS |
| Highway |
SH 6 |
| From |
AT OLD RELIANCE ROAD / MLK DRIVE |
| To |
AND THE SH 6 FRONTAGE ROADS |
| CSJ |
0049-12-074 |
| Proj ID |
HP 2008(483) |
| Work Type |
PAVEMENT WIDENING AND SIGNAL WORK |
| |
|
0.165 |
621421.31 |
82292.70 |
526934.78 |
87.0 |
| Work Order |
05-12-08 |
| Work Began |
05-29-08 |
| Work Completed |
|
| Time Computed |
05-28-08 |
| Contract Working Days |
63 |
| Addl Days Granted |
0 |
| Working Days Charged |
91 |
| Percent Time Used |
144 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-074 CEN TEX HYDROSEED, INC.(1.29%) HIGHWAY TECHNOLOGIES (1.23%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.80%) THIRD COAST SERVICES, LLC( 30.05%)
|
| Contract # |
04083228 |
|
Totals |
621421.31 |
82292.70 |
526934.78 |
87.0 |
|
| County | BRAZOS |
| Highway |
SH 6 |
| From |
SH 21 |
| To |
FM 158 |
| CSJ |
0049-12-077 |
| Proj ID |
HP 2009(015) |
| Work Type |
RECONSTRUCT ENTRANCE AND EXIT RAMPS |
| |
|
2.097 |
1934634.09 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-30-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
108 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-077 BATTSON CONTRACTING CO., INC.( 11.45%) DUSTROL, INC. (ROANOKE)(3.10%) JONA CONTRACTING, INC. (2.40%) N-LINE TRAFFIC MAINTENANCE, L.P. (1.39%) UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.69%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.61%)
|
| Contract # |
09083204 |
|
Totals |
1934634.09 |
0.00 |
0.00 |
0.0 |
|
| County | ROBERTSON |
| Highway |
SH 14 ETC |
| From |
SH 6 |
| To |
FM 1373 |
| CSJ |
0049-15-011 |
| Proj ID |
STP 2009(063) |
| Work Type |
SEAL COAT |
| |
|
285.183 |
13510472.72 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
86 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| F. N. PLOCH CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-15-011 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10083202 |
|
Totals |
13510472.72 |
0.00 |
0.00 |
0.0 |
|
| County | BRAZOS |
| Highway |
BS 6-R |
| From |
FM 2347 (GEORGE BUSH DRIVE) |
| To |
FM 2818 |
| CSJ |
0050-01-060 |
| Proj ID |
STP 2004(390) |
| Work Type |
GRADING, STRUCTURES, AND CONC. PAVE |
| |
|
1.835 |
14885998.41 |
37437.36 |
15279446.21 |
99.9 |
| County | BRAZOS |
| Highway |
BS 6-R |
| From |
FM 2347 (GEORGE BUSH DRIVE) |
| To |
FM 2818 |
| CSJ |
0050-01-072 |
| Proj ID |
RW 50-1-72 |
| Work Type |
UTILITY ADJUSTMENT |
| |
|
0.001 |
2213797.30 |
0.00 |
2207503.69 |
99.9 |
| Work Order |
10-21-04 |
| Work Began |
03-21-05 |
| Work Completed |
|
| Time Computed |
03-21-05 |
| Contract Working Days |
814 |
| Addl Days Granted |
111 |
| Working Days Charged |
836 |
| Percent Time Used |
90 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-060 BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(8.79%) KELLYSTONE, INC(1.35%) N-LINE TRAFFIC MAINTENANCE, L.P. (2.26%) J & M CONTRACTING, COMPANY (1.68%) AMERICAN REMEDIATION OPTIONS, INC. (0.65%) UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.85%) BULL'S EYE BORING, INC.(1.36%) JDF SERVICE CORP.(0.23%) LANEY, INC.(0.42%) TROY CONSTRUCTION(0.52%) FLASHER EQUIPMENT COMPANY(0.08%) DUSTROL, INC. (ROANOKE)(1.15%) F & L CONCRETE SERVICES, INC.(0.28%) MAGNUM TUNNELING, LLC(0.58%) MMM CONSTRUCTION PRODUCTS, INC.(0.00%) PNEU-ROCK TRANSPORTATION, INC. (0.01%) O & D TRUCKING (0.01%) JEFFERY BAILEY TRUCKING, INC.(0.01%) WELLBORN EQUIPMENT (0.01%) BRENDA PRICE TRUCKING(0.00%) BATTEN DRILLING(0.01%) O & D TRUCKING (0.00%) HARDING BORING (0.01%)
|
| Contract # |
08043005 |
|
Totals |
17099795.71 |
37437.36 |
17486949.90 |
99.9 |
|
| County | BRAZOS |
| Highway |
SH 6 |
| From |
NORTH OF PEACH CREEK AT FRONTAGE RO |
| To |
0.5 MILES NORTH OF FM 2154 |
| CSJ |
0050-02-055 |
| Proj ID |
NH 2005(182) |
| Work Type |
GRADING, STRUCTURES, BASE AND SURFA |
| |
|
8.952 |
88434322.19 |
855169.31 |
60071327.52 |
70.6 |
| County | BRAZOS |
| Highway |
SH 6 |
| From |
THE TEXAS WORLD SPEEDWAY |
| To |
NO. OF PEACH CR. AT FRONTAGE ROADS |
| CSJ |
0050-02-093 |
| Proj ID |
NH 2006(110) |
| Work Type |
GRADING, STRUCTURES, BASE AND SURF |
| |
|
1.884 |
11878948.61 |
28.93 |
10864655.49 |
95.2 |
| Work Order |
02-10-06 |
| Work Began |
03-06-06 |
| Work Completed |
|
| Time Computed |
02-26-06 |
| Contract Working Days |
1,036 |
| Addl Days Granted |
0 |
| Working Days Charged |
651 |
| Percent Time Used |
62 |
| Contractor(s) |
| T. J. LAMBRECHT CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0050-02-055 N-LINE TRAFFIC MAINTENANCE, L.P. (0.37%) W.W. WEBBER INC. ( 16.56%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.71%) AARON CONCRETE CONTRACTORS, L.P. (1.30%) BOOTHE BROTHERS PAVING COMPANY, INC. (0.05%) C.B. SERVICES, INC.(0.24%) CONCHO CONSTRUCTION COMPANY, INC.(7.85%) DGI-MENARD, INC. (0.02%) W. W. FOUNDATION DRILLING, LTD.(0.84%) PNEU-ROCK TRANSPORTATION, INC. (0.12%) BIG CREEK CONSTRUCTION, LTD. ( 13.77%) HJC FARMS, INC.(0.47%) SAN-ANN-CO., INC.(0.56%) DUSTROL, INC. (ROANOKE)(0.20%) CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(0.00%) STRIPING TECHNOLOGY, L.P.(0.70%) TREVCON, INC.(6.84%) J & M CONTRACTING, COMPANY (4.55%) AFS ENVIRONMENTAL, INC.(0.28%) MELENDREZ BROTHERS TRUCKING, INC.(0.01%) STOMPER DEMOLITION (0.00%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.00%) HOLLY WATERWELL SERVICE(0.00%) INDUS CONSTRUCTION, L.P. (0.39%) HOUSTON SAWING & DRILLING(0.02%) CRAIG OLDEN, INC.(0.36%) K. SAVAGE TRUCKING, INC. (0.55%) AZTEC TRUCKING, INC. (0.02%)
|
| Contract # |
12053001 |
|
Totals |
100313270.80 |
855198.24 |
70935983.01 |
73.5 |
|
| County | BURLESON |
| Highway |
SH 21 |
| From |
0.14 MI WEST OF UPRR OVERPASS |
| To |
0.13 MI EAST OF UPRR OVERPASS |
| CSJ |
0116-03-057 |
| Proj ID |
NH 2008(118) |
| Work Type |
GRADING, STRUCTURES, BASE AND SURFA |
| |
|
0.284 |
976131.15 |
364772.48 |
846725.31 |
86.7 |
| Work Order |
11-12-07 |
| Work Began |
06-19-08 |
| Work Completed |
|
| Time Computed |
11-28-07 |
| Contract Working Days |
76 |
| Addl Days Granted |
0 |
| Working Days Charged |
71 |
| Percent Time Used |
93 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0116-03-057 FARR FOUNDATION, INC.(4.58%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.47%) CEN TEX HYDROSEED, INC.(0.15%) ODUM SERVICES, L.P.(3.13%) RFE CONSTRUCTION, INC. ( 25.72%)
|
| Contract # |
10073223 |
|
Totals |
976131.15 |
364772.48 |
846725.31 |
86.7 |
|
| County | BRAZOS |
| Highway |
SH 21 |
| From |
0.4 MILE WEST OF SH 6 |
| To |
SH 6 |
| CSJ |
0117-01-041 |
| Proj ID |
NH 2008(252) |
| Work Type |
REHABILITATE EXISTING ROAD |
| |
|
0.800 |
1046803.24 |
153137.88 |
948500.92 |
91.2 |
| Work Order |
01-03-08 |
| Work Began |
04-07-08 |
| Work Completed |
|
| Time Computed |
04-07-08 |
| Contract Working Days |
79 |
| Addl Days Granted |
21 |
| Working Days Charged |
109 |
| Percent Time Used |
109 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0117-01-041 CRAWFORD YANT(0.21%) TEX OP CONSTRUCTION, LP(1.24%) AGGREGATE TECHNOLOGIES, INC. (1.21%) HIGHWAY TECHNOLOGIES, L.P. (1.03%) MURRAY CONSTRUCTION(1.36%) D. I. J. CONSTRUCTION, INC.(3.38%) WILEY CONSTRUCTION COMPANY, INC. ( 14.71%) GRACE UTILITY, LLC (0.46%)
|
| Contract # |
12073223 |
|
Totals |
1046803.24 |
153137.88 |
948500.92 |
91.2 |
|
| County | BRAZOS |
| Highway |
SH 21 |
| From |
DEMOCRAT ROAD |
| To |
THE NAVASOTA RIVER |
| CSJ |
0117-02-032 |
| Proj ID |
NH 2008(660) |
| Work Type |
PREPARATION OF RIGHT OF WAY |
| |
|
7.471 |
528301.00 |
39046.00 |
63026.00 |
11.9 |
| Work Order |
07-10-08 |
| Work Began |
09-16-08 |
| Work Completed |
|
| Time Computed |
09-15-08 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
30 |
| Percent Time Used |
50 |
| Contractor(s) |
| TOTAL HIGHWAY MAINTENANCE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0117-02-032 TEXAS TREE & LANDSCAPE, LTD( 17.01%)
|
| Contract # |
06083222 |
|
Totals |
528301.00 |
39046.00 |
63026.00 |
11.9 |
|
| County | WALKER |
| Highway |
US 190 |
| From |
SH 19 |
| To |
FM 2296 |
| CSJ |
0213-01-037 |
| Proj ID |
STP 2008(162) |
| Work Type |
GRADING, STRUCTURES, BASE & SURFACE |
| |
|
5.129 |
4725502.22 |
378146.39 |
3388345.18 |
71.7 |
| Work Order |
12-31-07 |
| Work Began |
02-28-08 |
| Work Completed |
|
| Time Computed |
02-28-08 |
| Contract Working Days |
235 |
| Addl Days Granted |
0 |
| Working Days Charged |
58 |
| Percent Time Used |
24 |
| Contractor(s) |
| SMITH & COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0213-01-037 WATERS CONSTRUCTION CO., INC.(5.75%) STRIPING TECHNOLOGY, L.P.(3.84%) J & M CONTRACTING, COMPANY ( 18.36%) WILLOW CITY SIGN & RAIL, INC.(0.84%) COASTAL CONCRETE CORPORATION (3.43%) BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(0.74%) BATTERSON, L.L.P.(0.25%) COLD CREEK CONSTRUCTION, LTD (1.93%) CRAWFORD YANT(1.18%) CPAV SPECIALTIES, LP (3.43%)
|
| Contract # |
11073210 |
|
Totals |
4725502.22 |
378146.39 |
3388345.18 |
71.7 |
|
| County | WASHINGTON |
| Highway |
FM 1155 |
| From |
FM 912 |
| To |
0.1 MILE EAST OF PR 12 |
| CSJ |
0315-12-008 |
| Proj ID |
STP 2007(380) |
| Work Type |
GRADING, STRUCTURES, BASE AND SURFA |
| |
|
4.572 |
3497079.80 |
0.00 |
3253535.95 |
93.0 |
| Work Order |
10-03-07 |
| Work Began |
11-30-07 |
| Work Completed |
|
| Time Computed |
11-30-07 |
| Contract Working Days |
116 |
| Addl Days Granted |
51 |
| Working Days Charged |
140 |
| Percent Time Used |
83 |
| Contractor(s) |
| GLENN FUQUA, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0315-12-008 UNITED RENTALS HIGHWAY TECHNOLOGIES, L.P. (HOUSTON)(0.67%) RESONANT MACHINES(0.62%) ANTIGO CONSTRUCTION, INC.(0.73%) N-LINE TRAFFIC MAINTENANCE, L.P. (1.30%) PEDRO CARLOS CONSSTRUCTION (5.56%) CEN TEX HYDROSEED, INC.(0.97%) W.D.F. HAULING (0.70%) PNEU-ROCK TRANSPORTATION, INC. (0.00%) BWF FREIGHT(0.62%)
|
| Contract # |
08073023 |
|
Totals |
3497079.80 |
0.00 |
3253535.95 |
93.0 |
|
| County | LEON |
| Highway |
SH 7 |
| From |
1.4 MILES EAST OF US 79 |
| To |
US 79 |
| CSJ |
0335-03-040 |
| Proj ID |
STP 2008(287) |
| Work Type |
GRADING, STRUCTURES, BASE AND SURF |
| |
|
1.479 |
1216071.57 |
128930.72 |
1075337.60 |
90.3 |
| Work Order |
02-20-08 |
| Work Began |
05-12-08 |
| Work Completed |
|
| Time Computed |
05-12-08 |
| Contract Working Days |
59 |
| Addl Days Granted |
8 |
| Working Days Charged |
96 |
| Percent Time Used |
143 |
| Contractor(s) |
| BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0335-03-040 CRAWFORD YANT(0.50%) FORTSON CONTRACTING, INC.(1.73%) INTERSTATE BARRICADES & MARKINGS, INC. (3.12%) QUALITY TRAFFIC SERVICES, L.L.C. (0.28%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.83%)
|
| Contract # |
01083023 |
|
Totals |
1216071.57 |
128930.72 |
1075337.60 |
90.3 |
|
| County | WALKER |
| Highway |
FM 230 |
| From |
THE HOUSTON COUNTY LINE |
| To |
THE TRINITY COUNTY LINE |
| CSJ |
0475-07-012 |
| Proj ID |
STP 2007(285)SB |
| Work Type |
PROVIDE ADDITIONAL PAVED SURF WIDTH |
| |
|
9.590 |
2382136.99 |
47423.97 |
2357031.21 |
99.9 |
| Work Order |
05-09-07 |
| Work Began |
07-24-07 |
| Work Completed |
|
| Time Computed |
07-24-07 |
| Contract Working Days |
141 |
| Addl Days Granted |
33 |
| Working Days Charged |
202 |
| Percent Time Used |
116 |
| Contractor(s) |
| A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0475-07-012 N-LINE TRAFFIC MAINTENANCE, L.P. (1.68%) BATTERSON, L.L.P.(2.57%) J & M CONTRACTING, COMPANY (8.21%) WATERS CONSTRUCTION CO., INC.(2.07%)
|
| Contract # |
03073024 |
|
Totals |
2382136.99 |
47423.97 |
2357031.21 |
99.9 |
|
| County | BRAZOS |
| Highway |
FM 2154 |
| From |
0.36 MILE SOUTH OF FM 2818 |
| To |
0.6 MILE SOUTH OF SH 40 |
| CSJ |
0540-04-044 |
| Proj ID |
STP 2006(593) |
| Work Type |
WIDEN NON - FREEWAY FACILITY |
| |
|
2.692 |
13762733.86 |
712582.08 |
1534430.43 |
11.1 |
| County | BRAZOS |
| Highway |
FM 2154 |
| From |
0.36 MILE SOUTH OF FM 2818 |
| To |
0.6 MILE SOUTH OF SH 40 |
| CSJ |
0540-04-056 |
| Proj ID |
STP 2004(304) |
| Work Type |
ACQUISITION, UTILITIES AND RELOCATI |
| |
|
0.001 |
186120.00 |
27036.00 |
56520.00 |
30.3 |
| Work Order |
08-04-08 |
| Work Began |
08-21-08 |
| Work Completed |
|
| Time Computed |
08-21-08 |
| Contract Working Days |
387 |
| Addl Days Granted |
0 |
| Working Days Charged |
36 |
| Percent Time Used |
9 |
| Contractor(s) |
| GLENN FUQUA, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0540-04-044 TREVCON, INC.(6.97%) BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(3.03%) INTERSTATE BARRICADES & MARKINGS, INC. (1.21%) W.D.F. HAULING (0.57%) KNIFE RIVER CORPORATION - SOUTH( 24.02%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.00%) K & B CONSTRUCTION (1.00%)
|
| Contract # |
06083001 |
|
Totals |
13948853.86 |
739618.08 |
1590950.43 |
11.4 |
|
| County | BRAZOS |
| Highway |
FM 2154 |
| From |
FM 2347 |
| To |
0.6 MILE NORTH OF FM 2818 |
| CSJ |
0540-04-061 |
| Proj ID |
STP 2009(016) |
| Work Type |
REHABILITATE EXISTING ROAD |
| |
|
1.175 |
1003268.50 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-16-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
01-02-09 |
| Contract Working Days |
43 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0540-04-061 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09083207 |
|
Totals |
1003268.50 |
0.00 |
0.00 |
0.0 |
|
| County | WALKER |
| Highway |
FM 247 |
| From |
THE MADISON COUNTY LINE |
| To |
5.6 MILES SOUTH |
| CSJ |
0578-02-036 |
| Proj ID |
STP 2009(017) |
| Work Type |
GRADING, STRUCTURES, BASE AND SURF |
| |
|
5.608 |
2814269.81 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-23-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
141 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0578-02-036 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09083009 |
|
Totals |
2814269.81 |
0.00 |
0.00 |
0.0 |
|