Monthly State Let Construction Report For Bryan District As Of Aug 11, 2017 Page 3 Of 3

Last Update: Friday, August 11, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLEON
HighwayIH 45
From1.5 MILES SOUTH OF US 79
To1.0 MILES NORTH OF US 79
CSJ0675-03-081
Proj IDNH 1702(563)
Work TypeRAMP RELOCATION
 
2.5008878806.510.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-03-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173231
Totals8878806.510.000.000.0

CountyBURLESON
HighwayFM 60
FromSH 21 W
ToFM 111
CSJ0713-01-032
Proj IDSTP 1602(321)
Work TypeREHABILITATE EXISTING ROAD
 
2.4982429597.65701555.3528.8
Work Order10-14-16
Work Began12-08-16
Work Completed
Time Computed11-13-16
Contract Working Days100
Addl Days Granted0
Working Days Charged68
Percent Time Used68
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0713-01-032
J & M CONTRACTING, COMPANY (30.56)
CEN TEX HYDROSEED, INC. (2.05)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.86)
BROCK CONSTRUCTION, LLC (1.44)
Contract #07163228
Totals2429597.6550851.80701555.3528.8

CountyMILAM
HighwayFM 487
FromCOUNTY ROAD 402
To0.7 MILE NORTH OF COUNTY ROAD 235
CSJ0858-01-033
Proj IDSTP 1502(528)HES
Work TypePROVIDE ADDITIONAL PAVEMENT WIDTH
 
15.4095587641.645205787.0695.0
Work Order10-30-15
Work Began02-15-16
Work Completed
Time Computed01-28-16
Contract Working Days150
Addl Days Granted0
Working Days Charged242
Percent Time Used161
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0858-01-033
R K STEPHENS CONSTRUCTION, LLC (7.02)
ROADWAY SPECIALTIES, INC. (1.91)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45)
CEN TEX HYDROSEED, INC. (1.57)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.78)
NIXON ENGINEERING (0.00)
Contract #08153237
Totals5587641.647828.265205787.0695.0

CountyBRAZOS
HighwayVA
FromAT VARIOUS LOCATIONS
ToIN THE BRYAN DISTRICT
CSJ0917-00-040
Proj IDNH 2014(949)
Work TypeCONSTRUCT SIDEWALK CURB RAMPS
 
1.0003503761.003194647.4491.1
Work Order08-27-14
Work Began10-06-14
Work Completed
Time Computed09-12-14
Contract Working Days418
Addl Days Granted7
Working Days Charged423
Percent Time Used99
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-040
CLASSIC TEJAS CONSTRUCTION, INC. (6.88)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.09)
STEEL EFFECTS (0.00)
FLASHER EQUIPMENT COMPANY (2.56)
JACKRABBIT MANUFACTURING, LLC (0.30)
Contract #07143242
Totals3503761.007527.003194647.4491.1

CountyBRAZOS
HighwayVA
FromVAR. LOCATIONS IN BRAZOS, WALKER,
ToMADISON, LEON & FREESTONE COUNTIES
CSJ0917-00-042
Proj IDITS 2001(537)
Work TypeFY16 ITS DEVELOPMENT PROGRAM
 
0.001549299.80552918.0399.9
Work Order05-12-16
Work Began07-26-16
Work Completed
Time Computed06-11-16
Contract Working Days85
Addl Days Granted5
Working Days Charged74
Percent Time Used82
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-042
BUYER BARRICADES (2.30)
SPECIALTY DRILLING, LTD. (4.73)
Contract #04163239
Totals549299.800.00552918.0399.9

CountyMILAM
HighwayCR
FromON CR 398 - LOCAL CR 440
ToAT BRUSHY CREEK RELIEF
CSJ0917-12-080
Proj IDBR 2012(334)
Work TypeREPLACE AN EXISTING BRIDGE FACILITY
 
0.132447590.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0917-12-080
VOGES DRILLING CO. (10.37)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.11)
SAN-ANN-CO., INC. (0.67)
Contract #06173019
Totals447590.000.000.000.0

CountyGRIMES
HighwayCR
FromON CR 251 - LOCAL CR 190
ToAT GIBBONS CREEK
CSJ0917-17-065
Proj IDBR 2012(273)
Work TypeREPLACE EXISTING BRIDGE
 
0.192905681.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days196
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173223
Totals905681.320.000.000.0

CountyFREESTONE
HighwayPW
FromWITHIN FAIRFIELD STATE PARK IN THE
ToSPRINGFIELD AND POST OAK AREAS
CSJ0917-20-036
Proj IDC 917-20-36
Work TypeRECONSTRUCT ROADS AND CAMPSITES
 
1.0001862429.04464688.9624.9
Work Order03-15-17
Work Began05-01-17
Work Completed
Time Computed04-14-17
Contract Working Days175
Addl Days Granted0
Working Days Charged58
Percent Time Used33
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-036
AREA WIDE PROTECTIVE, INC. (0.17)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (3.22)
COLD CREEK CONSTRUCTION, LTD (0.66)
STRIPING TECHNOLOGY, L.P. (0.39)
MOORE PLUMBING REPAIR, LLC (0.89)
Contract #02173215
Totals1862429.04214926.74464688.9624.9

CountyWALKER
HighwayCR
FromON CR 667 - LOCAL BEAR CREEK ROAD
ToAT WHITES CREEK
CSJ0917-27-044
Proj IDBR 2016(317)
Work TypeGRADING, STRUCTURES AND BASE
 
0.104504029.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days99
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173009
Totals504029.640.000.000.0

CountyWALKER
HighwayVA
FromIN HUNTSVILLE
ToON SH 75, FM 1374, AND LAKE RD
CSJ0917-27-045
Proj IDSTP 1602(419)TAPS
Work TypeADA SIDEWALKS,CURB RAMPS,DW APRONS
 
2.7461833580.002231844.5899.9
Work Order12-15-16
Work Began01-06-17
Work Completed
Time Computed01-04-17
Contract Working Days205
Addl Days Granted0
Working Days Charged57
Percent Time Used27
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-045
W.A. ROBBINS CONSTRUCTION CO., INC. (5.32)
HUNTSVILLE STEEL & FABRICATION, INC. (5.06)
Contract #10163030
Totals1833580.001000.002231844.5899.9

CountyBRAZOS
HighwayVA
FromON SH 308 FROM FM 1179
ToINLOW STREET
CSJ0917-29-129
Proj IDSTP 2017(099)TAPS
Work TypePEDESTRIAN AND BICYCLE IMPROVMENTS
 
1.1641803581.230.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-29-129
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173012
Totals1803581.230.000.000.0

CountyMADISON
HighwayCR
FromON CR 229 - LOCAL LONE STAR ROAD
ToAT TURKEY CREEK
CSJ0917-31-022
Proj IDBR 2012(336)
Work TypeGRADING, STRUCTURE, BASE AND SURF
 
0.1901204839.771242106.4699.9
Work Order04-19-16
Work Began07-28-16
Work Completed
Time Computed07-18-16
Contract Working Days205
Addl Days Granted0
Working Days Charged135
Percent Time Used65
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-31-022
CEN TEX HYDROSEED, INC. (1.73)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.80)
JUST GROOVING, LTD. (0.19)
W. W. FOUNDATION DRILLING, LTD. (8.50)
MESA ROD BUSTERS, INC. (0.24)
CD TRUCKING, INC (0.00)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
HOUSTON SAWING & DRILLING (0.28)
HEMPHILL WBE PILE DRIVING CO. (1.07)
Contract #01163233
Totals1204839.772460.351242106.4699.9

CountyGRIMES
HighwayFM 1696
FromFM 39
ToSH 90
CSJ1562-03-018
Proj IDSTP 2017(349)
Work TypeREHABILITATE EXISTING ROADWAY
 
9.1145527215.431003571.7718.1
Work Order04-04-17
Work Began05-03-17
Work Completed
Time Computed05-03-17
Contract Working Days215
Addl Days Granted0
Working Days Charged57
Percent Time Used26
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1562-03-018
ROADSAFE TRAFFIC SYSTEMS, INC. (1.38)
CEN TEX HYDROSEED, INC. (0.56)
COLD CREEK CONSTRUCTION, LTD (1.99)
ODUM SERVICES, L.P. (1.06)
J & M CONTRACTING, COMPANY (4.44)
AWP, INC. (1.38)
A. L. HELMCAMP, INC. (0.59)
Contract #01173017
Totals5527215.43668828.771003571.7718.1

CountyBRAZOS
HighwayFM 2818
FromAT LONGMIRE DR
To.
CSJ2399-01-076
Proj IDSTP 2017(509)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.400641000.00494876.0077.2
Work Order03-02-17
Work Began06-05-17
Work Completed
Time Computed05-31-17
Contract Working Days59
Addl Days Granted0
Working Days Charged38
Percent Time Used64
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2399-01-076
NORTH TEXAS CONTRACTING, INC. (5.82)
ROAD MASTER STRIPING LLC (1.93)
DYNAMIC VISION CO., INC. (0.00)
ELLIOTT CONSTRUCTION, LLC (1.26)
Contract #01173235
Totals641000.00327056.00494876.0077.2

CountyBRAZOS
HighwaySH 30
FromBS 6-R
ToSH 6 EFR
CSJ2446-01-026
Proj IDSTP 2017(759)
Work TypeOVERLAY
 
1.8411679419.001494117.6088.9
Work Order03-16-17
Work Began04-19-17
Work Completed
Time Computed04-15-17
Contract Working Days50
Addl Days Granted0
Working Days Charged39
Percent Time Used78
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2446-01-026
BATTEN DRILLING, INC. (0.23)
CEN TEX HYDROSEED, INC. (0.27)
FLASHER EQUIPMENT COMPANY (3.72)
Contract #02173216
Totals1679419.0066687.801494117.6088.9

page 1 | page 2 | page 3