Monthly State Let Construction Report For Bryan District As Of Dec 9, 2016 Page 3 Of 3

Last Update: Friday, December 9, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMILAM
Highway FM 487
From COUNTY ROAD 402
To 0.7 MILE NORTH OF COUNTY ROAD 235
CSJ 0858-01-033
Proj ID STP 1502(528)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
15.409 5587641.64 206780.55 4882189.90 87.7
Work Order 10-30-15
Work Began 02-15-16
Work Completed  
Time Computed 01-28-16
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 169
Percent Time Used 112
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0858-01-033
R K STEPHENS CONSTRUCTION, LLC (7.02%)
ROADWAY SPECIALTIES, INC.(1.91%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45%)
CEN TEX HYDROSEED, INC.(1.57%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.78%)
NIXON ENGINEERING(0.00%)
Contract # 08153237
Totals 5587641.64 206780.55 4882189.90 87.7

CountyBRAZOS
Highway VA
From AT VARIOUS LOCATIONS
To IN THE BRYAN DISTRICT
CSJ 0917-00-040
Proj ID NH 2014(949)
Work Type CONSTRUCT SIDEWALK CURB RAMPS
 
1.000 3503761.00 0.00 3173409.40 90.5
Work Order 08-27-14
Work Began 10-06-14
Work Completed  
Time Computed 09-12-14
Contract Working Days 418
Addl Days Granted 0
Working Days Charged 363
Percent Time Used 86
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-040
CLASSIC TEJAS CONSTRUCTION, INC. (6.88%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(0.09%)
STEEL EFFECTS(0.00%)
FLASHER EQUIPMENT COMPANY(2.56%)
Contract # 07143242
Totals 3503761.00 0.00 3173409.40 90.5

CountyBRAZOS
Highway VA
From VAR. LOCATIONS IN BRAZOS, WALKER,
To MADISON, LEON & FREESTONE COUNTIES
CSJ 0917-00-042
Proj ID ITS 2001(537)
Work Type FY16 ITS DEVELOPMENT PROGRAM
 
0.001 549299.80 8950.44 347619.47 63.2
Work Order 05-12-16
Work Began 07-26-16
Work Completed  
Time Computed 06-11-16
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 47
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-042
BUYER BARRICADES (2.30%)
SPECIALTY DRILLING, LTD. (4.73%)
Contract # 04163239
Totals 549299.80 8950.44 347619.47 63.2

CountyLEON
Highway CR
From ON CR 110 - LOCAL CR 348
To AT BRUSHY CREEK RELIEF
CSJ 0917-16-034
Proj ID BR 1502(027)
Work Type REPLACE EXISTING BRIDGE
 
0.078 357813.60 59300.00 108206.00 30.2
Work Order 04-19-16
Work Began 10-11-16
Work Completed  
Time Computed 07-18-16
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 23
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-16-034
LONESTAR TRAFFIC SAFETY, LLC (0.95%)
SPECIALTY DRILLING, LTD. (5.14%)
FUQUAY, INC. (1.11%)
Contract # 02163040
Totals 357813.60 59300.00 108206.00 30.2

CountyGRIMES
Highway CR
From ON CR 297 - LOCAL CR 162
To AT THE NAVASOTA RIVER RELIEF
CSJ 0917-17-058
Proj ID BR 1502(026)
Work Type GRADING, STRUCTURES, BASE AND SURF
 
0.097 417154.55 0.00 42182.00 10.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-15-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163025
Totals 417154.55 0.00 42182.00 10.1

CountyGRIMES
Highway CR
From ON CR 182 (MILL CREEK RUN)
To AT YORKE CREEK
CSJ 0917-17-062
Proj ID BR 2012(270)
Work Type REPLACE EXISTING BRIDGE
 
0.049 553516.53 72273.45 297961.85 53.8
Work Order 06-01-16
Work Began 09-26-16
Work Completed  
Time Computed 08-30-16
Contract Working Days 111
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 37
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-062
ODUM SERVICES, L.P.(4.51%)
HEMPHILL PILE DRIVING CO., A CORP. (9.03%)
FRANK & SON DOZERWORKS, LLC(1.35%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64%)
AFFORDABLE EROSION (1.22%)
Contract # 03163226
Totals 553516.53 72273.45 297961.85 53.8

CountyFREESTONE
Highway CR
From ON CR 183 - LOCAL CR 930
To AT SMALL CREEK
CSJ 0917-20-038
Proj ID BR 1502(214)
Work Type REPLACE EXISTING BRIDGE
 
0.080 490735.18 33323.25 458970.21 93.5
Work Order 03-28-16
Work Began 06-28-16
Work Completed  
Time Computed 06-26-16
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 97
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-038
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 10.06%)
JUST GROOVING, LTD.(0.29%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.59%)
FORTSON CONTRACTING, INC.(2.39%)
CEN TEX HYDROSEED, INC.(1.90%)
MESA ROD BUSTERS, INC. (0.32%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.46%)
Contract # 01163236
Totals 490735.18 33323.25 458970.21 93.5

CountyWALKER
Highway VA
From IN HUNTSVILLE
To ON SH 75, FM 1374, AND LAKE RD
CSJ 0917-27-045
Proj ID STP 1602(419)TAPS
Work Type ADA SIDEWALKS, CURB RAMPS, DW APRONS
 
2.746 1833580.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10163030
Totals 1833580.00 0.00 0.00 0.0

CountyMADISON
Highway CR
From ON CR 229 - LOCAL LONE STAR ROAD
To AT TURKEY CREEK
CSJ 0917-31-022
Proj ID BR 2012(336)
Work Type GRADING, STRUCTURE, BASE AND SURF
 
0.190 1204839.77 145345.44 724005.56 60.0
Work Order 04-19-16
Work Began 07-28-16
Work Completed  
Time Computed 07-18-16
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 30
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-31-022
CEN TEX HYDROSEED, INC.(1.73%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.80%)
JUST GROOVING, LTD.(0.19%)
W. W. FOUNDATION DRILLING, LTD.(8.50%)
MESA ROD BUSTERS, INC. (0.24%)
Contract # 01163233
Totals 1204839.77 145345.44 724005.56 60.0

CountyWALKER
Highway FM 1791
From 3.5 MILES SOUTH OF SH 30
To THE MONTGOMERY COUNTY LINE
CSJ 1706-01-025
Proj ID STP 2014(933)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.092 3187515.87 0.00 2854831.80 89.5
Work Order 09-24-14
Work Began 02-13-15
Work Completed  
Time Computed 12-23-14
Contract Working Days 328
Addl Days Granted 0
Working Days Charged 216
Percent Time Used 65
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1706-01-025
COLD CREEK CONSTRUCTION, LTD (4.71%)
CEN TEX HYDROSEED, INC.(5.07%)
HIGHWAY 19 CONSTRUCTION, LLC (8.11%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45%)
TEXAS ALTERNATIVE GRASSER, INC.(0.70%)
WILLOW CITY SIGN & RAIL, INC.(2.09%)
A. L. HELMCAMP, INC. (0.00%)
Contract # 07143239
Totals 3187515.87 0.00 2854831.80 89.5

page 1 | page 2 | page 3