Monthly State Let Construction Report For Bryan District As Of Feb 10, 2017 Page 3 Of 3

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGRIMES
HighwayCR
FromON CR 297 - LOCAL CR 162
ToAT THE NAVASOTA RIVER RELIEF
CSJ0917-17-058
Proj IDBR 1502(026)
Work TypeGRADING, STRUCTURES, BASE AND SURF
 
0.097417154.55131417.7431.5
Work Order09-15-16
Work Began01-10-17
Work Completed
Time Computed12-14-16
Contract Working Days80
Addl Days Granted0
Working Days Charged10
Percent Time Used12
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-058
N-LINE TRAFFIC MAINTENANCE, L.P. (2.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.43)
FRANK & SON DOZERWORKS, LLC (2.39)
Contract #08163025
Totals417154.5589235.74131417.7431.5

CountyGRIMES
HighwayCR
FromON CR 182 (MILL CREEK RUN)
ToAT YORKE CREEK
CSJ0917-17-062
Proj IDBR 2012(270)
Work TypeREPLACE EXISTING BRIDGE
 
0.049553516.53470365.8584.9
Work Order06-01-16
Work Began09-26-16
Work Completed
Time Computed08-30-16
Contract Working Days111
Addl Days Granted0
Working Days Charged73
Percent Time Used65
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-062
ODUM SERVICES, L.P. (4.51)
HEMPHILL PILE DRIVING CO., A CORP. (9.03)
FRANK & SON DOZERWORKS, LLC (1.35)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
AFFORDABLE EROSION (1.22)
LONESTAR LAWNS (0.93)
Contract #03163226
Totals553516.5347940.00470365.8584.9

CountyFREESTONE
HighwayPW
FromWITHIN FAIRFIELD STATE PARK IN THE
ToSPRINGFIELD AND POST OAK AREAS
CSJ0917-20-036
Proj IDC 917-20-36
Work TypeRECONSTRUCT ROADS AND CAMPSITES
 
1.0001862429.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173215
Totals1862429.040.000.000.0

CountyFREESTONE
HighwayCR
FromON CR 183 - LOCAL CR 930
ToAT SMALL CREEK
CSJ0917-20-038
Proj IDBR 1502(214)
Work TypeREPLACE EXISTING BRIDGE
 
0.080490735.18477216.5097.2
Work Order03-28-16
Work Began06-28-16
Work Completed
Time Computed06-26-16
Contract Working Days70
Addl Days Granted0
Working Days Charged69
Percent Time Used98
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-038
M & D FOUNDATION DRILLING INDUSTRIES, INC. (10.06)
JUST GROOVING, LTD. (0.29)
TOTAL HIGHWAY MAINTENANCE, LLC (0.59)
FORTSON CONTRACTING, INC. (2.39)
CEN TEX HYDROSEED, INC. (1.90)
MESA ROD BUSTERS, INC. (0.32)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.46)
Contract #01163236
Totals490735.182523.50477216.5097.2

CountyWALKER
HighwayVA
FromIN HUNTSVILLE
ToON SH 75, FM 1374, AND LAKE RD
CSJ0917-27-045
Proj IDSTP 1602(419)TAPS
Work TypeADA SIDEWALKS,CURB RAMPS,DW APRONS
 
2.7461833580.00871452.5347.5
Work Order12-15-16
Work Began01-06-17
Work Completed
Time Computed01-04-17
Contract Working Days205
Addl Days Granted0
Working Days Charged17
Percent Time Used8
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-045
W.A. ROBBINS CONSTRUCTION CO., INC. (5.32)
Contract #10163030
Totals1833580.00871452.53871452.5347.5

CountyMADISON
HighwayCR
FromON CR 229 - LOCAL LONE STAR ROAD
ToAT TURKEY CREEK
CSJ0917-31-022
Proj IDBR 2012(336)
Work TypeGRADING, STRUCTURE, BASE AND SURF
 
0.1901204839.771074312.5289.1
Work Order04-19-16
Work Began07-28-16
Work Completed
Time Computed07-18-16
Contract Working Days205
Addl Days Granted0
Working Days Charged100
Percent Time Used48
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-31-022
CEN TEX HYDROSEED, INC. (1.73)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.80)
JUST GROOVING, LTD. (0.19)
W. W. FOUNDATION DRILLING, LTD. (8.50)
MESA ROD BUSTERS, INC. (0.24)
CD TRUCKING, INC (0.00)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
Contract #01163233
Totals1204839.77126157.401074312.5289.1

CountyGRIMES
HighwayFM 1696
FromFM 39
ToSH 90
CSJ1562-03-018
Proj IDSTP 2017(349)
Work TypeREHABILITATE EXISTING ROADWAY
 
9.1145527215.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days215
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1562-03-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173017
Totals5527215.430.000.000.0

CountyWALKER
HighwayFM 1791
From3.5 MILES SOUTH OF SH 30
ToTHE MONTGOMERY COUNTY LINE
CSJ1706-01-025
Proj IDSTP 2014(933)HES
Work TypePROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.0923187515.872854831.8089.5
Work Order09-24-14
Work Began02-13-15
Work Completed
Time Computed12-23-14
Contract Working Days328
Addl Days Granted0
Working Days Charged223
Percent Time Used67
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1706-01-025
COLD CREEK CONSTRUCTION, LTD (4.71)
CEN TEX HYDROSEED, INC. (5.07)
HIGHWAY 19 CONSTRUCTION, LLC (8.11)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45)
TEXAS ALTERNATIVE GRASSER, INC. (0.70)
WILLOW CITY SIGN & RAIL, INC. (2.09)
A. L. HELMCAMP, INC. (0.00)
Contract #07143239
Totals3187515.870.002854831.8089.5

CountyBRAZOS
HighwayFM 2818
FromAT LONGMIRE DR
To.
CSJ2399-01-076
Proj IDSTP 2017(509)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.400641000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2399-01-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173235
Totals641000.000.000.000.0

CountyBRAZOS
HighwaySH 30
FromBS 6-R
ToSH 6 EFR
CSJ2446-01-026
Proj IDSTP 2017(759)
Work TypeOVERLAY
 
1.8411679419.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2446-01-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173216
Totals1679419.000.000.000.0

CountyBRAZOS
HighwaySH 47
FromON SH 47
ToCURVE WEST(NORTH) OF FM 60
CSJ3138-02-011
Proj IDSTP 2017(760)HES
Work TypeHIGH FRICTION SURFACE TREATMENT
 
0.23065138.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days12
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3138-02-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173013
Totals65138.900.000.000.0

page 1 | page 2 | page 3