Monthly State Let Construction Report For Bryan District As Of Jan 13, 2015 Page 3 Of 3

Last Update: Tuesday, January 13, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBRAZOS
Highway FM 1179
From KENT STREET
To FM 2818
CSJ 1316-01-059
Proj ID STP 2015(635)
Work Type HMA OVERLAY
 
2.726 2436656.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1316-01-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153227
Totals 2436656.96 0.00 0.00 0.0

CountyWALKER
Highway FM 1375
From SH 150
To GOURD CREEK ROAD
CSJ 1402-01-032
Proj ID STP 2014(746)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
5.643 2371297.26 186525.71 1605339.37 67.6
Work Order 08-13-14
Work Began 08-25-14
Work Completed  
Time Computed 08-25-14
Contract Working Days 105
Addl Days Granted 9
Working Days Charged 68
Percent Time Used 59
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1402-01-032
CEN TEX HYDROSEED, INC.(1.53%)
J & M CONTRACTING, COMPANY (8.57%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.61%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.29%)
WATERS CONSTRUCTION CO., INC.( 13.72%)
WILLOW CITY SIGN & RAIL, INC.(1.91%)
Contract # 06143042
Totals 2371297.26 186525.71 1605339.37 67.6

CountyWALKER
Highway FM 1791
From 3.5 MILES SOUTH OF SH 30
To THE MONTGOMERY COUNTY LINE
CSJ 1706-01-025
Proj ID STP 2014(933)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.092 3187515.87 0.00 0.00 0.0
Work Order 09-24-14
Work Began 00-00-00
Work Completed  
Time Computed 12-23-14
Contract Working Days 328
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1706-01-025
COLD CREEK CONSTRUCTION, LTD (4.71%)
CEN TEX HYDROSEED, INC.(5.07%)
HIGHWAY 19 CONSTRUCTION, LLC (8.11%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45%)
TEXAS ALTERNATIVE GRASSER, INC.(0.70%)
WILLOW CITY SIGN & RAIL, INC.(2.09%)
Contract # 07143239
Totals 3187515.87 0.00 0.00 0.0

CountyWALKER
Highway FM 1696
From THE GRIMES COUNTY LINE
To SH 75
CSJ 1809-02-024
Proj ID STP 2014(214)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
13.806 4305079.51 112700.34 3045744.48 70.7
Work Order 01-09-14
Work Began 04-21-14
Work Completed  
Time Computed 04-09-14
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 70
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1809-02-024
ROADSAFE TRAFFIC SYSTEMS, INC. (2.54%)
CEN TEX HYDROSEED, INC.(3.83%)
J & M CONTRACTING, COMPANY (0.30%)
Contract # 11133017
Totals 4305079.51 112700.34 3045744.48 70.7

CountyMILAM
Highway FM 2269
From FM 485
To 0.3 MILE NORTH OF US 190
CSJ 2133-03-019
Proj ID STP 2014(057)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.762 3309494.89 0.00 2710316.35 81.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-09-14
Work Began 03-17-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 173
Percent Time Used 87
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2133-03-019
J & M CONTRACTING, COMPANY ( 12.78%)
CEN TEX HYDROSEED, INC.(3.32%)
ROADSAFE TRAFFIC SYSTEMS, INC. (4.05%)
ROADWAY SPECIALTIES, INC.(5.08%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.54%)
Contract # 10133017
Totals 3309494.89 0.00 2710316.35 81.8

CountyBRAZOS
Highway FM 2818
From AT THE INTERSECTION OF FM 2818
To AND FM 1179
CSJ 2399-01-060
Proj ID STP 1102(237)SB
Work Type CONSTRUCT GRADE SEPARATION
 
1.293 14139148.97 80414.22 13623100.45 97.3
Work Order 10-21-11
Work Began 02-20-12
Work Completed  
Time Computed 02-20-12
Contract Working Days 316
Addl Days Granted 14
Working Days Charged 433
Percent Time Used 131
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2399-01-060
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(1.74%)
FLASHER EQUIPMENT COMPANY(0.43%)
FORTSON CONTRACTING, INC.(0.22%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.03%)
HIGHWAY TECHNOLOGIES, INC. (1.22%)
KELLYSTONE, INC(0.42%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.34%)
MAGNUM TUNNELING, LLC(0.11%)
SOUTH TEXAS PAINTING COMPANY (0.89%)
TEX OP CONSTRUCTION, LP(0.63%)
WEBBER BARRIER SERVICES, INC.(0.45%)
WILLOW CITY SIGN & RAIL, INC.(0.39%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.61%)
INDUS CONSTRUCTION, L.P. (0.52%)
MESA ROD BUSTERS, INC. (0.02%)
AUSTIN LAND SERVICE(0.09%)
D. I. J. CONSTRUCTION, INC.(0.90%)
A BRUSH ABOVE SERVICES, LLC(0.09%)
BEDO CONSTRUCTION PRODUCTS, INC. (0.00%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.00%)
Contract # 08113004
Totals 14139148.97 80414.22 13623100.45 97.3

page 1 | page 2 | page 3