Monthly State Let Construction Report For Bryan District As Of Aug 10, 2015 Page 3 Of 4

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGRIMES
Highway FM 244
From CR 170
To CR 171
CSJ 0643-04-028
Proj ID STP 1402(102)
Work Type MISCELLANEOUS WORK
 
5.175 2156938.65 234744.52 1896320.71 88.0
Work Order 09-22-14
Work Began 01-21-15
Work Completed  
Time Computed 12-21-14
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 105
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0643-04-028
J & M CONTRACTING, COMPANY ( 12.18%)
CEN TEX HYDROSEED, INC.(2.05%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.96%)
PLANTERSVILLE WATER SERVICES, INC. (0.91%)
Contract # 08143013
Totals 2156938.65 234744.52 1896320.71 88.0

CountyGRIMES
Highway FM 244
From SH 30
To FM 3090
CSJ 0643-05-046
Proj ID STP 1502(012)HES
Work Type INCREASE SUPERELEVATION
 
2.396 1787891.25 149638.22 149638.22 8.3
Work Order 06-30-15
Work Began 08-03-15
Work Completed  
Time Computed 09-29-15
Contract Working Days 60
Addl Days Granted 13
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0643-05-046
CEN TEX HYDROSEED, INC.(0.37%)
WILLOW CITY SIGN & RAIL, INC.(3.57%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.55%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.32%)
Contract # 04153015
Totals 1787891.25 149638.22 149638.22 8.3

CountyBURLESON
Highway FM 60
From 1.2 MILES WEST OF FM 2039
To 0.62 MILE EAST OF OLD RIVER
CSJ 0648-03-050
Proj ID C 648-3-50
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
3.984 10487720.87 595268.28 7110412.71 67.7
Work Order 02-19-14
Work Began 04-07-14
Work Completed  
Time Computed 04-07-14
Contract Working Days 227
Addl Days Granted 0
Working Days Charged 186
Percent Time Used 81
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0648-03-050
BLUE STAR BARRICADES, INC. (0.26%)
COWBELL TRAFFIC SERVICES, INC. (0.07%)
D. I. J. CONSTRUCTION, INC.(0.65%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.52%)
MURRAY CONSTRUCTION(0.38%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.16%)
TEXAS ALTERNATIVE GRASSER, INC.(0.30%)
PRIME ECO GROUP, INC.(0.00%)
PIPE WHOLESALERS OF TEXAS, INC.(0.00%)
COMEN ENTERPRISE (0.36%)
Contract # 12133003
Totals 10487720.87 595268.28 7110412.71 67.7

CountyFREESTONE
Highway IH 45
From THE LEON COUNTY LINE
To US 84
CSJ 0675-02-077
Proj ID IM 0452(143)
Work Type HMA OVERLAY (REHABILITATION)
 
34.574 4687021.87 0.00 4819312.30 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-13
Work Began 05-22-14
Work Completed 01-28-15
Time Computed 03-04-14
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 130
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-02-077
COWBELL TRAFFIC SERVICES, INC. (0.68%)
MPB, INC.(0.55%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.13%)
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
FORTSON CONTRACTING, INC.(1.08%)
STRIPING TECHNOLOGY, L.P.(2.78%)
Contract # 09133015
Totals 4687021.87 0.00 4819312.30 100.0

CountyMADISON
Highway IH 45
From SPUR 104
To SH 21
CSJ 0675-05-082
Proj ID NH 1502(428)
Work Type CONVERT FRT RD TO ONE - WAY OPERATION
 
2.078 3642170.67 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0675-05-082
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153048
Totals 3642170.67 0.00 0.00 0.0

CountyWALKER
Highway IH 45
From SH 75
To THE MADISON COUNTY LINE
CSJ 0675-06-099
Proj ID IM 0452(141)
Work Type HMA OVERLAY
 
14.952 5387237.10 129512.55 4974510.48 92.4
Work Order 01-17-14
Work Began 02-09-15
Work Completed  
Time Computed 04-17-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 107
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-06-099
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
COWBELL TRAFFIC SERVICES, INC. (0.43%)
ODUM SERVICES, L.P.(1.55%)
STRIPING TECHNOLOGY, L.P.(2.99%)
Contract # 10133221
Totals 5387237.10 129512.55 4974510.48 92.4

CountyWALKER
Highway IH 45
From AT THE INTERSECTION WITH FM 1375
To .
CSJ 0675-07-089
Proj ID STP 2014(483)HES
Work Type REALIGN INTERSECTION
 
0.600 3355020.53 177839.20 2490874.18 74.2
Work Order 05-09-14
Work Began 08-14-14
Work Completed  
Time Computed 08-07-14
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 139
Percent Time Used 78
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0675-07-089
ALLSTATE SIGNAL & CONSTRUCTION, LLC(3.17%)
CEN TEX HYDROSEED, INC.(0.14%)
A & A CONSTRUCTION (2.86%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.48%)
MURRAY CONSTRUCTION(1.14%)
DUSTIN ALLEN, INC. (2.08%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.47%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.56%)
Contract # 03143228
Totals 3355020.53 177839.20 2490874.18 74.2

CountyMILAM
Highway FM 487
From COUNTY ROAD 402
To 0.7 MILE NORTH OF COUNTY ROAD 235
CSJ 0858-01-033
Proj ID STP 1502(528)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
15.409 5587641.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0858-01-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153237
Totals 5587641.64 0.00 0.00 0.0

CountyBRAZOS
Highway VA
From AT VARIOUS LOCATIONS
To IN THE BRYAN DISTRICT
CSJ 0917-00-040
Proj ID NH 2014(949)
Work Type CONSTRUCT SIDEWALK CURB RAMPS
 
1.000 3503761.00 134059.90 1804232.25 51.4
Work Order 08-27-14
Work Began 10-06-14
Work Completed  
Time Computed 09-12-14
Contract Working Days 418
Addl Days Granted 0
Working Days Charged 173
Percent Time Used 41
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-040
CLASSIC TEJAS CONSTRUCTION, INC. (6.88%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(0.09%)
Contract # 07143242
Totals 3503761.00 134059.90 1804232.25 51.4

CountyGRIMES
Highway CR
From ON CR 202 (PINEBROOK DRIVE)
To AT KICKAPOO CREEK
CSJ 0917-17-043
Proj ID BR 2012(269)
Work Type GRADING, STRUCTURES, BASE AND SURFA
 
0.164 662557.78 -4453.66 544101.35 90.4
Work Order 05-01-14
Work Began 06-30-14
Work Completed  
Time Computed 06-30-14
Contract Working Days 121
Addl Days Granted 0
Working Days Charged 251
Percent Time Used 207
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-043
ODUM SERVICES, L.P.(3.63%)
W. W. FOUNDATION DRILLING, LTD.(2.90%)
HEMPHILL PILE DRIVING CO., A CORP. (4.89%)
JUST GROOVING, LTD.(0.27%)
CEN TEX HYDROSEED, INC.(1.94%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.12%)
MESA ROD BUSTERS, INC. (0.17%)
Contract # 03143014
Totals 662557.78 4453.66 544101.35 90.4

CountyGRIMES
Highway PW
From AT THE FANTHORP INN STATE HISTORIC
To PARK IN GRIMES COUNTY
CSJ 0917-17-056
Proj ID C 917-17-56
Work Type GRADING, STRUCTURES AND BASE
 
0.033 198743.80 28608.00 183064.00 92.1
Work Order 05-19-15
Work Began 06-15-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 58
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-056
M & M STRIPING & POWER WASHING, LLC(1.13%)
Contract # 04153219
Totals 198743.80 28608.00 183064.00 92.1

CountyGRIMES
Highway CR
From ON CR 327 (LOCAL CR 102)
To AT THE NAVASOTA RIVER
CSJ 0917-17-063
Proj ID BR 2012(271)
Work Type GRADING, STRUCTURES AND BASE
 
0.091 937686.62 83075.80 83075.80 8.8
Work Order 04-07-15
Work Began 07-06-15
Work Completed  
Time Computed 07-06-15
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 15
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-063
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 10.51%)
ODUM SERVICES, L.P.(1.41%)
JUST GROOVING, LTD.(0.22%)
CEN TEX HYDROSEED, INC.(0.67%)
TEXAS SHAFTS, INC. ( 11.06%)
MCL CONTRACTING, LLC (0.37%)
CD TRUCKING, INC (0.00%)
Contract # 02153036
Totals 937686.62 83075.80 83075.80 8.8

CountyMADISON
Highway CR
From ON CR 253 (ROCKY RIDGE LANE)
To AT POOLES CREEK AND RELIEF
CSJ 0917-31-015
Proj ID BR 2012(335)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.236 653336.52 51198.10 315867.30 48.3
Work Order 01-05-15
Work Began 04-01-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 158
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 34
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-31-015
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.10%)
DUSTIN ALLEN, INC. (5.58%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.86%)
MESA ROD BUSTERS, INC. (0.28%)
Contract # 10143011
Totals 653336.52 51198.10 315867.30 48.3

CountyFREESTONE
Highway FM 416
From THE NAVARRO COUNTY LINE
To FM 488
CSJ 0998-05-009
Proj ID STP 2014(645)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
5.990 1235167.98 0.00 1178440.04 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-14
Work Began 10-14-14
Work Completed 04-23-15
Time Computed 10-06-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 61
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0998-05-009
ROADSAFE TRAFFIC SYSTEMS, INC. (0.71%)
TEXAS ALTERNATIVE GRASSER, INC.(0.36%)
SAN-ANN-CO., INC.(0.45%)
STRIPING TECHNOLOGY, L.P.(3.71%)
Contract # 05143009
Totals 1235167.98 0.00 1178440.04 100.0

CountyBRAZOS
Highway FM 1179
From KENT STREET
To FM 2818
CSJ 1316-01-059
Proj ID STP 2015(635)
Work Type HMA OVERLAY
 
2.726 2436656.96 378058.02 547300.59 22.4
Work Order 03-18-15
Work Began 06-09-15
Work Completed  
Time Computed 06-09-15
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 15
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1316-01-059
A BROTHERS MILLING, LLC(1.21%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(3.23%)
CEN TEX HYDROSEED, INC.(0.57%)
PEDRO CARLOS CONSTRUCTION CO.(5.19%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.19%)
WILLOW CITY SIGN & RAIL, INC.(0.46%)
Contract # 01153227
Totals 2436656.96 378058.02 547300.59 22.4

CountyWALKER
Highway FM 1375
From SH 150
To GOURD CREEK ROAD
CSJ 1402-01-032
Proj ID STP 2014(746)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
5.643 2371297.26 112948.38 2408570.68 99.9
Work Order 08-13-14
Work Began 08-25-14
Work Completed  
Time Computed 08-25-14
Contract Working Days 105
Addl Days Granted 9
Working Days Charged 114
Percent Time Used 100
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1402-01-032
CEN TEX HYDROSEED, INC.(1.53%)
J & M CONTRACTING, COMPANY (8.57%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.61%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.29%)
WATERS CONSTRUCTION CO., INC.( 13.72%)
WILLOW CITY SIGN & RAIL, INC.(1.91%)
Contract # 06143042
Totals 2371297.26 112948.38 2408570.68 99.9

CountyWALKER
Highway FM 1791
From 3.5 MILES SOUTH OF SH 30
To THE MONTGOMERY COUNTY LINE
CSJ 1706-01-025
Proj ID STP 2014(933)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.092 3187515.87 556967.18 1761144.80 55.2
Work Order 09-24-14
Work Began 02-13-15
Work Completed  
Time Computed 12-23-14
Contract Working Days 328
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 33
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1706-01-025
COLD CREEK CONSTRUCTION, LTD (4.71%)
CEN TEX HYDROSEED, INC.(5.07%)
HIGHWAY 19 CONSTRUCTION, LLC (8.11%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45%)
TEXAS ALTERNATIVE GRASSER, INC.(0.70%)
WILLOW CITY SIGN & RAIL, INC.(2.09%)
Contract # 07143239
Totals 3187515.87 556967.18 1761144.80 55.2

CountyWALKER
Highway FM 1696
From THE GRIMES COUNTY LINE
To SH 75
CSJ 1809-02-024
Proj ID STP 2014(214)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
13.806 4305079.51 0.00 4001212.08 92.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-09-14
Work Began 04-21-14
Work Completed  
Time Computed 04-09-14
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 203
Percent Time Used 95
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1809-02-024
ROADSAFE TRAFFIC SYSTEMS, INC. (2.54%)
CEN TEX HYDROSEED, INC.(3.83%)
J & M CONTRACTING, COMPANY (0.30%)
Contract # 11133017
Totals 4305079.51 0.00 4001212.08 92.9

CountyMILAM
Highway FM 2269
From FM 485
To 0.3 MILE NORTH OF US 190
CSJ 2133-03-019
Proj ID STP 2014(057)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.762 3309494.89 0.00 3343796.46 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-09-14
Work Began 03-17-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 14
Working Days Charged 206
Percent Time Used 97
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2133-03-019
J & M CONTRACTING, COMPANY ( 12.78%)
CEN TEX HYDROSEED, INC.(3.32%)
ROADSAFE TRAFFIC SYSTEMS, INC. (4.05%)
ROADWAY SPECIALTIES, INC.(5.08%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.54%)
Contract # 10133017
Totals 3309494.89 0.00 3343796.46 99.9

CountyBRAZOS
Highway FM 2818
From AT THE INTERSECTION OF FM 2818
To AND FM 1179
CSJ 2399-01-060
Proj ID STP 1102(237)SB
Work Type CONSTRUCT GRADE SEPARATION
 
1.293 14139148.97 0.00 13686892.11 97.8
Work Order 10-21-11
Work Began 02-20-12
Work Completed  
Time Computed 02-20-12
Contract Working Days 316
Addl Days Granted 14
Working Days Charged 433
Percent Time Used 131
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2399-01-060
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(1.74%)
FLASHER EQUIPMENT COMPANY(0.43%)
FORTSON CONTRACTING, INC.(0.22%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.03%)
HIGHWAY TECHNOLOGIES, INC. (1.22%)
KELLYSTONE, INC(0.42%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.34%)
MAGNUM TUNNELING, LLC(0.11%)
SOUTH TEXAS PAINTING COMPANY (0.89%)
TEX OP CONSTRUCTION, LP(0.63%)
WEBBER BARRIER SERVICES, INC.(0.45%)
WILLOW CITY SIGN & RAIL, INC.(0.39%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.61%)
INDUS CONSTRUCTION, L.P. (0.52%)
MESA ROD BUSTERS, INC. (0.02%)
AUSTIN LAND SERVICE(0.09%)
D. I. J. CONSTRUCTION, INC.(0.90%)
A BRUSH ABOVE SERVICES, LLC(0.09%)
BEDO CONSTRUCTION PRODUCTS, INC. (0.00%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.00%)
Contract # 08113004
Totals 14139148.97 0.00 13686892.11 97.8

page 1 | page 2 | page 3 | page 4