Monthly State Let Construction Report For Bryan District As Of Aug 12, 2014 Page 3 Of 3

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWALKER
Highway PW
From AT THE HUNTSVILLE STATE PARK
To .
CSJ 0917-27-043
Proj ID C 917-27-43
Work Type RECONSTRUCT EXISTING RV PULLOUTS
 
1.000 262456.50 62930.15 62930.15 23.9
Work Order 05-13-14
Work Began 07-10-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 41
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-043
CEN TEX HYDROSEED, INC.(4.80%)
Contract # 04143019
Totals 262456.50 62930.15 62930.15 23.9

CountyFREESTONE
Highway FM 416
From THE NAVARRO COUNTY LINE
To FM 488
CSJ 0998-05-009
Proj ID STP 2014(645)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
5.990 1235167.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0998-05-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143009
Totals 1235167.98 0.00 0.00 0.0

CountyLEON
Highway FM 977
From AT TWO MILE CREEK
To .
CSJ 1147-03-014
Proj ID BR 1302(021)
Work Type REPLACE EXISTING BRIDGE FACILITY
 
0.117 691407.39 4979.50 693529.44 99.9
Work Order 10-10-13
Work Began 10-28-13
Work Completed  
Time Computed 10-28-13
Contract Working Days 101
Addl Days Granted 3
Working Days Charged 100
Percent Time Used 96
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1147-03-014
ACTION SERVICES(0.44%)
FORTSON CONTRACTING, INC.(2.32%)
HOUSTON SAWING & DRILLING(0.27%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.72%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.78%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.10%)
MESA ROD BUSTERS, INC. (0.33%)
WATERS CONSTRUCTION CO., INC.(1.08%)
Contract # 07133249
Totals 691407.39 4979.50 693529.44 99.9

CountyWALKER
Highway FM 1375
From SH 150
To GOURD CREEK ROAD
CSJ 1402-01-032
Proj ID STP 2014(746)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
5.643 2371297.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1402-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143042
Totals 2371297.26 0.00 0.00 0.0

CountyWALKER
Highway FM 1791
From 3.5 MILES SOUTH OF SH 30
To THE MONTGOMERY COUNTY LINE
CSJ 1706-01-025
Proj ID STP 2014(933)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.092 3187515.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 328
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1706-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143239
Totals 3187515.87 0.00 0.00 0.0

CountyWALKER
Highway FM 1696
From THE GRIMES COUNTY LINE
To SH 75
CSJ 1809-02-024
Proj ID STP 2014(214)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
13.806 4305079.51 742809.86 1924800.37 44.7
Work Order 01-09-14
Work Began 04-21-14
Work Completed  
Time Computed 04-09-14
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 29
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1809-02-024
ROADSAFE TRAFFIC SYSTEMS, INC. (2.54%)
CEN TEX HYDROSEED, INC.(3.83%)
J & M CONTRACTING, COMPANY (0.30%)
Contract # 11133017
Totals 4305079.51 742809.86 1924800.37 44.7

CountyMILAM
Highway FM 2269
From FM 485
To 0.3 MILE NORTH OF US 190
CSJ 2133-03-019
Proj ID STP 2014(057)HES
Work Type PROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.762 3309494.89 0.00 1146358.36 34.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-09-14
Work Began 03-17-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 44
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2133-03-019
J & M CONTRACTING, COMPANY ( 12.78%)
CEN TEX HYDROSEED, INC.(3.32%)
ROADSAFE TRAFFIC SYSTEMS, INC. (4.05%)
ROADWAY SPECIALTIES, INC.(5.08%)
Contract # 10133017
Totals 3309494.89 0.00 1146358.36 34.6

CountyBRAZOS
Highway FM 2818
From AT THE INTERSECTION OF FM 2818
To AND FM 1179
CSJ 2399-01-060
Proj ID STP 1102(237)SB
Work Type CONSTRUCT GRADE SEPARATION
 
1.293 14139148.97 378911.08 12517255.63 89.0
Work Order 10-21-11
Work Began 02-20-12
Work Completed  
Time Computed 02-20-12
Contract Working Days 316
Addl Days Granted 14
Working Days Charged 380
Percent Time Used 115
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2399-01-060
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(1.74%)
FLASHER EQUIPMENT COMPANY(0.43%)
FORTSON CONTRACTING, INC.(0.22%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.03%)
HIGHWAY TECHNOLOGIES, INC. (1.22%)
KELLYSTONE, INC(0.42%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.34%)
MAGNUM TUNNELING, LLC(0.11%)
SOUTH TEXAS PAINTING COMPANY (0.89%)
TEX OP CONSTRUCTION, LP(0.63%)
WEBBER BARRIER SERVICES, INC.(0.45%)
WILLOW CITY SIGN & RAIL, INC.(0.39%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.61%)
INDUS CONSTRUCTION, L.P. (0.52%)
MESA ROD BUSTERS, INC. (0.02%)
AUSTIN LAND SERVICE(0.09%)
D. I. J. CONSTRUCTION, INC.(0.90%)
A BRUSH ABOVE SERVICES, LLC(0.09%)
Contract # 08113004
Totals 14139148.97 378911.08 12517255.63 89.0

CountyBRAZOS
Highway SH 47
From AT HSC PARKWAY
To .
CSJ 3138-02-010
Proj ID STP 1102(590)
Work Type CONSTRUCT NEW INTERCHANGE
 
1.630 9732289.59 37329.62 9804450.56 100.0
Work Order 01-24-12
Work Began 02-09-12
Work Completed 08-07-14
Time Computed 02-09-12
Contract Working Days 223
Addl Days Granted 93
Working Days Charged 310
Percent Time Used 98
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 3138-02-010
A BROTHERS (0.21%)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.(1.26%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.05%)
KELLYSTONE, INC(0.54%)
FLASHER EQUIPMENT COMPANY(0.14%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.03%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.90%)
MESA ROD BUSTERS, INC. (0.31%)
ROADWAY SPECIALTIES, INC.(1.19%)
SOUTH TEXAS PAINTING COMPANY (1.41%)
THOMAS TURF GRASS(0.05%)
D. I. J. CONSTRUCTION, INC.(0.40%)
A BRUSH ABOVE SERVICES, LLC(0.18%)
Contract # 12113204
Totals 9732289.59 37329.62 9804450.56 100.0

page 1 | page 2 | page 3