Monthly State Let Construction Report For Bryan District As Of May 11, 2017 Page 3 Of 3

Last Update: Wednesday, May 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMILAM
HighwayFM 487
FromCOUNTY ROAD 402
To0.7 MILE NORTH OF COUNTY ROAD 235
CSJ0858-01-033
Proj IDSTP 1502(528)HES
Work TypePROVIDE ADDITIONAL PAVEMENT WIDTH
 
15.4095587641.645136399.6093.7
Work Order10-30-15
Work Began02-15-16
Work Completed
Time Computed01-28-16
Contract Working Days150
Addl Days Granted0
Working Days Charged241
Percent Time Used160
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0858-01-033
R K STEPHENS CONSTRUCTION, LLC (7.02)
ROADWAY SPECIALTIES, INC. (1.91)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45)
CEN TEX HYDROSEED, INC. (1.57)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.78)
NIXON ENGINEERING (0.00)
Contract #08153237
Totals5587641.6452927.055136399.6093.7

CountyBRAZOS
HighwayVA
FromAT VARIOUS LOCATIONS
ToIN THE BRYAN DISTRICT
CSJ0917-00-040
Proj IDNH 2014(949)
Work TypeCONSTRUCT SIDEWALK CURB RAMPS
 
1.0003503761.003187120.4490.9
Work Order08-27-14
Work Began10-06-14
Work Completed
Time Computed09-12-14
Contract Working Days418
Addl Days Granted0
Working Days Charged363
Percent Time Used86
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-040
CLASSIC TEJAS CONSTRUCTION, INC. (6.88)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.09)
STEEL EFFECTS (0.00)
FLASHER EQUIPMENT COMPANY (2.56)
JACKRABBIT MANUFACTURING, LLC (0.30)
Contract #07143242
Totals3503761.000.003187120.4490.9

CountyBRAZOS
HighwayVA
FromVAR. LOCATIONS IN BRAZOS, WALKER,
ToMADISON, LEON & FREESTONE COUNTIES
CSJ0917-00-042
Proj IDITS 2001(537)
Work TypeFY16 ITS DEVELOPMENT PROGRAM
 
0.001549299.80546514.0599.4
Work Order05-12-16
Work Began07-26-16
Work Completed
Time Computed06-11-16
Contract Working Days85
Addl Days Granted0
Working Days Charged74
Percent Time Used87
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-042
BUYER BARRICADES (2.30)
SPECIALTY DRILLING, LTD. (4.73)
Contract #04163239
Totals549299.800.00546514.0599.4

CountyLEON
HighwayCR
FromON CR 110 - LOCAL CR 348
ToAT BRUSHY CREEK RELIEF
CSJ0917-16-034
Proj IDBR 1502(027)
Work TypeREPLACE EXISTING BRIDGE
 
0.078357813.60340190.6795.0
Work Order04-19-16
Work Began10-11-16
Work Completed
Time Computed07-18-16
Contract Working Days78
Addl Days Granted0
Working Days Charged74
Percent Time Used94
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-16-034
LONESTAR TRAFFIC SAFETY, LLC (0.95)
SPECIALTY DRILLING, LTD. (5.14)
FUQUAY, INC. (1.11)
Contract #02163040
Totals357813.600.00340190.6795.0

CountyGRIMES
HighwayCR
FromON CR 297 - LOCAL CR 162
ToAT THE NAVASOTA RIVER RELIEF
CSJ0917-17-058
Proj IDBR 1502(026)
Work TypeGRADING, STRUCTURES, BASE AND SURF
 
0.097417154.55326218.7878.2
Work Order09-15-16
Work Began01-10-17
Work Completed
Time Computed12-14-16
Contract Working Days80
Addl Days Granted0
Working Days Charged61
Percent Time Used76
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-058
N-LINE TRAFFIC MAINTENANCE, L.P. (2.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.43)
FRANK & SON DOZERWORKS, LLC (2.39)
ODUM SERVICES, L.P. (5.81)
CEN TEX HYDROSEED, INC. (1.09)
Contract #08163025
Totals417154.5559894.10326218.7878.2

CountyGRIMES
HighwayCR
FromON CR 182 (MILL CREEK RUN)
ToAT YORKE CREEK
CSJ0917-17-062
Proj IDBR 2012(270)
Work TypeREPLACE EXISTING BRIDGE
 
0.049553516.53550166.8299.3
Work Order06-01-16
Work Began09-26-16
Work Completed
Time Computed08-30-16
Contract Working Days111
Addl Days Granted0
Working Days Charged109
Percent Time Used98
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-062
ODUM SERVICES, L.P. (4.51)
HEMPHILL PILE DRIVING CO., A CORP. (9.03)
FRANK & SON DOZERWORKS, LLC (1.35)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
AFFORDABLE EROSION (1.22)
LONESTAR LAWNS (0.93)
Contract #03163226
Totals553516.534069.34550166.8299.3

CountyFREESTONE
HighwayPW
FromWITHIN FAIRFIELD STATE PARK IN THE
ToSPRINGFIELD AND POST OAK AREAS
CSJ0917-20-036
Proj IDC 917-20-36
Work TypeRECONSTRUCT ROADS AND CAMPSITES
 
1.0001862429.040.000.0
Work Order03-15-17
Work Began05-01-17
Work Completed
Time Computed04-14-17
Contract Working Days175
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-036
AREA WIDE PROTECTIVE, INC. (0.17)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (3.22)
COLD CREEK CONSTRUCTION, LTD (0.66)
STRIPING TECHNOLOGY, L.P. (0.39)
MOORE PLUMBING REPAIR, LLC (0.89)
Contract #02173215
Totals1862429.040.000.000.0

CountyWALKER
HighwayVA
FromIN HUNTSVILLE
ToON SH 75, FM 1374, AND LAKE RD
CSJ0917-27-045
Proj IDSTP 1602(419)TAPS
Work TypeADA SIDEWALKS,CURB RAMPS,DW APRONS
 
2.7461833580.002169204.5899.9
Work Order12-15-16
Work Began01-06-17
Work Completed
Time Computed01-04-17
Contract Working Days205
Addl Days Granted0
Working Days Charged41
Percent Time Used20
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-045
W.A. ROBBINS CONSTRUCTION CO., INC. (5.32)
HUNTSVILLE STEEL & FABRICATION, INC. (5.06)
Contract #10163030
Totals1833580.001000.002169204.5899.9

CountyMADISON
HighwayCR
FromON CR 229 - LOCAL LONE STAR ROAD
ToAT TURKEY CREEK
CSJ0917-31-022
Proj IDBR 2012(336)
Work TypeGRADING, STRUCTURE, BASE AND SURF
 
0.1901204839.771204488.6099.9
Work Order04-19-16
Work Began07-28-16
Work Completed
Time Computed07-18-16
Contract Working Days205
Addl Days Granted0
Working Days Charged135
Percent Time Used65
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-31-022
CEN TEX HYDROSEED, INC. (1.73)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.80)
JUST GROOVING, LTD. (0.19)
W. W. FOUNDATION DRILLING, LTD. (8.50)
MESA ROD BUSTERS, INC. (0.24)
CD TRUCKING, INC (0.00)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
HOUSTON SAWING & DRILLING (0.28)
HEMPHILL WBE PILE DRIVING CO. (1.07)
Contract #01163233
Totals1204839.7723925.791204488.6099.9

CountyGRIMES
HighwayFM 1696
FromFM 39
ToSH 90
CSJ1562-03-018
Proj IDSTP 2017(349)
Work TypeREHABILITATE EXISTING ROADWAY
 
9.1145527215.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days215
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1562-03-018
ROADSAFE TRAFFIC SYSTEMS, INC. (1.38)
CEN TEX HYDROSEED, INC. (0.56)
COLD CREEK CONSTRUCTION, LTD (1.99)
ODUM SERVICES, L.P. (1.06)
J & M CONTRACTING, COMPANY (4.44)
AWP, INC. (1.38)
Contract #01173017
Totals5527215.430.000.000.0

CountyBRAZOS
HighwayFM 2818
FromAT LONGMIRE DR
To.
CSJ2399-01-076
Proj IDSTP 2017(509)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.400641000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-02-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2399-01-076
NORTH TEXAS CONTRACTING, INC. (5.82)
ROAD MASTER STRIPING LLC (1.93)
DYNAMIC VISION CO., INC. (0.00)
Contract #01173235
Totals641000.000.000.000.0

CountyBRAZOS
HighwaySH 30
FromBS 6-R
ToSH 6 EFR
CSJ2446-01-026
Proj IDSTP 2017(759)
Work TypeOVERLAY
 
1.8411679419.00326178.8119.4
Work Order03-16-17
Work Began04-19-17
Work Completed
Time Computed04-15-17
Contract Working Days50
Addl Days Granted0
Working Days Charged3
Percent Time Used6
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2446-01-026
BATTEN DRILLING, INC. (0.23)
CEN TEX HYDROSEED, INC. (0.27)
FLASHER EQUIPMENT COMPANY (3.72)
Contract #02173216
Totals1679419.00326178.81326178.8119.4

CountyBRAZOS
HighwaySH 47
FromON SH 47
ToCURVE WEST(NORTH) OF FM 60
CSJ3138-02-011
Proj IDSTP 2017(760)HES
Work TypeHIGH FRICTION SURFACE TREATMENT
 
0.23065138.9066522.2099.9
Work Order03-10-17
Work Began04-24-17
Work Completed
Time Computed04-10-17
Contract Working Days12
Addl Days Granted7
Working Days Charged3
Percent Time Used15
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3138-02-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173013
Totals65138.9066522.2066522.2099.9

page 1 | page 2 | page 3