Monthly State Let Construction Report For Bryan District As Of Jan 11, 2017 Page 3 Of 3

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLEON
HighwayCR
FromON CR 110 - LOCAL CR 348
ToAT BRUSHY CREEK RELIEF
CSJ0917-16-034
Proj IDBR 1502(027)
Work TypeREPLACE EXISTING BRIDGE
 
0.078357813.60258061.6072.1
Work Order04-19-16
Work Began10-11-16
Work Completed
Time Computed07-18-16
Contract Working Days78
Addl Days Granted0
Working Days Charged37
Percent Time Used47
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-16-034
LONESTAR TRAFFIC SAFETY, LLC (0.95)
SPECIALTY DRILLING, LTD. (5.14)
FUQUAY, INC. (1.11)
Contract #02163040
Totals357813.60149855.60258061.6072.1

CountyGRIMES
HighwayCR
FromON CR 297 - LOCAL CR 162
ToAT THE NAVASOTA RIVER RELIEF
CSJ0917-17-058
Proj IDBR 1502(026)
Work TypeGRADING, STRUCTURES, BASE AND SURF
 
0.097417154.5542182.0010.1
Work Order09-15-16
Work Began01-10-17
Work Completed
Time Computed12-14-16
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-058
N-LINE TRAFFIC MAINTENANCE, L.P. (2.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.43)
FRANK & SON DOZERWORKS, LLC (2.39)
Contract #08163025
Totals417154.550.0042182.0010.1

CountyGRIMES
HighwayCR
FromON CR 182 (MILL CREEK RUN)
ToAT YORKE CREEK
CSJ0917-17-062
Proj IDBR 2012(270)
Work TypeREPLACE EXISTING BRIDGE
 
0.049553516.53422425.8576.3
Work Order06-01-16
Work Began09-26-16
Work Completed
Time Computed08-30-16
Contract Working Days111
Addl Days Granted0
Working Days Charged60
Percent Time Used54
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-062
ODUM SERVICES, L.P. (4.51)
HEMPHILL PILE DRIVING CO., A CORP. (9.03)
FRANK & SON DOZERWORKS, LLC (1.35)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
AFFORDABLE EROSION (1.22)
LONESTAR LAWNS (0.93)
Contract #03163226
Totals553516.53124464.00422425.8576.3

CountyFREESTONE
HighwayCR
FromON CR 183 - LOCAL CR 930
ToAT SMALL CREEK
CSJ0917-20-038
Proj IDBR 1502(214)
Work TypeREPLACE EXISTING BRIDGE
 
0.080490735.18474693.0096.7
Work Order03-28-16
Work Began06-28-16
Work Completed
Time Computed06-26-16
Contract Working Days70
Addl Days Granted0
Working Days Charged69
Percent Time Used98
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-038
M & D FOUNDATION DRILLING INDUSTRIES, INC. (10.06)
JUST GROOVING, LTD. (0.29)
TOTAL HIGHWAY MAINTENANCE, LLC (0.59)
FORTSON CONTRACTING, INC. (2.39)
CEN TEX HYDROSEED, INC. (1.90)
MESA ROD BUSTERS, INC. (0.32)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.46)
Contract #01163236
Totals490735.1815722.79474693.0096.7

CountyWALKER
HighwayVA
FromIN HUNTSVILLE
ToON SH 75, FM 1374, AND LAKE RD
CSJ0917-27-045
Proj IDSTP 1602(419)TAPS
Work TypeADA SIDEWALKS,CURB RAMPS,DW APRONS
 
2.7461833580.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-15-16
Work Began01-06-17
Work Completed
Time Computed01-04-17
Contract Working Days205
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-045
W.A. ROBBINS CONSTRUCTION CO., INC. (5.32)
Contract #10163030
Totals1833580.000.000.000.0

CountyMADISON
HighwayCR
FromON CR 229 - LOCAL LONE STAR ROAD
ToAT TURKEY CREEK
CSJ0917-31-022
Proj IDBR 2012(336)
Work TypeGRADING, STRUCTURE, BASE AND SURF
 
0.1901204839.77948155.1278.6
Work Order04-19-16
Work Began07-28-16
Work Completed
Time Computed07-18-16
Contract Working Days205
Addl Days Granted0
Working Days Charged80
Percent Time Used39
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-31-022
CEN TEX HYDROSEED, INC. (1.73)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.80)
JUST GROOVING, LTD. (0.19)
W. W. FOUNDATION DRILLING, LTD. (8.50)
MESA ROD BUSTERS, INC. (0.24)
CD TRUCKING, INC (0.00)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
Contract #01163233
Totals1204839.77224149.56948155.1278.6

CountyGRIMES
HighwayFM 1696
FromFM 39
ToSH 90
CSJ1562-03-018
Proj IDSTP 2017(349)
Work TypeREHABILITATE EXISTING ROADWAY
 
9.1145527215.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days215
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1562-03-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173017
Totals5527215.430.000.000.0

CountyWALKER
HighwayFM 1791
From3.5 MILES SOUTH OF SH 30
ToTHE MONTGOMERY COUNTY LINE
CSJ1706-01-025
Proj IDSTP 2014(933)HES
Work TypePROVIDE ADDITIONAL PAVEMENT WIDTH
 
9.0923187515.872854831.8089.5
Work Order09-24-14
Work Began02-13-15
Work Completed
Time Computed12-23-14
Contract Working Days328
Addl Days Granted0
Working Days Charged223
Percent Time Used67
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1706-01-025
COLD CREEK CONSTRUCTION, LTD (4.71)
CEN TEX HYDROSEED, INC. (5.07)
HIGHWAY 19 CONSTRUCTION, LLC (8.11)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45)
TEXAS ALTERNATIVE GRASSER, INC. (0.70)
WILLOW CITY SIGN & RAIL, INC. (2.09)
A. L. HELMCAMP, INC. (0.00)
Contract #07143239
Totals3187515.870.002854831.8089.5

CountyBRAZOS
HighwayFM 2818
FromAT LONGMIRE DR
To.
CSJ2399-01-076
Proj IDSTP 2017(509)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.400641000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2399-01-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173235
Totals641000.000.000.000.0

page 1 | page 2 | page 3