Monthly State Let Maintenance Report For Beaumont District As Of May 15, 2013 Page 2 Of 2

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCHAMBERS
Highway FM1410
From FM1410,FM1663(CHAMBERS CO.)
To FM736 (ORANGE CO)
CSJ 6249-54-001
Proj ID RMC - 624954001
Work Type DISTRICTWIDE SEAL COAT
 
11.976 337890.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-30-13
Work Began 05-06-13
Work Completed  
Time Computed 05-06-13
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6249-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134032
Totals 337890.85 0.00 0.00 0.0

CountyCHAMBERS
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6250-86-001
Proj ID RMC - 625086001
Work Type PAVEMENT MARKINGS
 
0.001 694020.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6250-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02134014
Totals 694020.20 0.00 0.00 0.0

CountyORANGE
Highway FM1006
From ADAMS BAYOU
To DIVISION AVENUE
CSJ 6251-86-001
Proj ID RMC - 625186001
Work Type MILL AND OVERLAY ROADWAY
 
2.281 732186.15 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-28-13
Work Began 00-00-00
Work Completed  
Time Computed 06-03-13
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134026
Totals 732186.15 0.00 0.00 0.0

CountyJEFFERSON
Highway US0090
From JEFFERSON, ORANGE, AND HARDIN COUNTIES
To JEFFERSON, ORANGE, AND HARDIN COUNTIES
CSJ 6252-45-001
Proj ID RMC - 625245001
Work Type MILL AND OVERALY VARIOUS LOCATIONS
 
0.001 1347159.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-28-13
Work Began 00-00-00
Work Completed  
Time Computed 05-20-13
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134012
Totals 1347159.26 0.00 0.00 0.0

CountyJEFFERSON
Highway IH0010
From VARIOUS HIGHWAYS IN DISTRICT 20
To VARIOUS HIGHWAYS IN DISTRICT 20
CSJ 6253-63-001
Proj ID RMC - 625363001
Work Type CALLOUT DEBRIS REMOVAL AFTER A HURRICANE
 
0.001 1600000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6253-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04134017
Totals 1600000.00 0.00 0.00 0.0

CountyLIBERTY
Highway US0090
From VARIOUS
To VAROUS
CSJ 6254-93-001
Proj ID RMC - 625493001
Work Type MOWING OF RIGHT OF WAY
 
10.000 449516.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6254-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134013
Totals 449516.00 0.00 0.00 0.0

CountyCHAMBERS
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6254-95-001
Proj ID RMC - 625495001
Work Type MOWING OF RIGHT OF WAY
 
10.000 395599.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 155
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6254-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134014
Totals 395599.00 0.00 0.00 0.0

CountyJASPER
Highway US0096
From VARIOUS
To VARIOUS
CSJ 6255-00-001
Proj ID RMC - 625500001
Work Type MOWING OF RIGHT OF WAY
 
256.000 437316.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6255-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134027
Totals 437316.80 0.00 0.00 0.0

page 1 | page 2