Monthly State Let Maintenance Report For Beaumont District As Of Nov 9, 2016 Page 2 Of 2

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyORANGE
Highway IH0010
From VARIOUS LOCATIONS IN ORANGE COUNTY
To VARIOUS LOCATIONS IN ORANGE COUNTY
CSJ 6291-36-001
Proj ID BPM - 629136001
Work Type RIPRAP AND SCOUR REPAIRS
 
0.001 570205.00 0.00 550771.87 97.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-05-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 115
Contractor(s)
DEZTEX INDUSTRIAL SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12154010
Totals 570205.00 0.00 550771.87 97.5

CountyCHAMBERS
Highway IH0010
From IH 0010 IN CHAMBERS COUNTY
To .
CSJ 6291-55-001
Proj ID RMC - 629155001
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIR
 
28.840 397769.95 0.00 721259.25 99.9
CountyLIBERTY
Highway US0059
From VARIOUS LOCATIONS IN LIBERTY COUNTY
To .
CSJ 6291-55-002
Proj ID RMC - 629155002
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIR
 
8.845 438673.05 0.00 725519.60 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 02-17-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 67
Working Days Charged 118
Percent Time Used 99
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-55-001
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(2.04%)
STRIPES & STOPS COMPANY, INC.(0.27%)
Contract # 10154010
Totals 836443.00 0.00 1446778.85 99.9

CountyCHAMBERS
Highway IH0010
From CHAMBERS COUNTY
To LIBERTY COUNTY
CSJ 6291-88-001
Proj ID RMC - 629188001
Work Type CLEAN EXIST CULVERTS / DITCH CLEAN / RESHAPE
 
32.597 358461.10 0.00 32418.05 9.0
CountyLIBERTY
Highway SH0105
From VARIOUS LOCATIONS IN LIBERTY COUNTY
To .
CSJ 6291-88-002
Proj ID RMC - 629188002
Work Type CLEAN EXIST CULVERTS, DITCH CLEAN & RESH
 
25.505 524674.65 0.00 312500.20 59.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 40
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04164014
Totals 883135.75 0.00 344918.25 39.0

CountyHARDIN
Highway US0069
From US 69, FM 1009, FM 562,
To FM 834, FM 2991
CSJ 6292-38-001
Proj ID RMC - 629238001
Work Type DISTRICTWIDE SEAL COAT
 
32.206 1094740.80 0.00 1130936.01 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 05-15-16
Work Completed 10-28-16
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 2
Working Days Charged 26
Percent Time Used 81
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-38-001
INTERSTATE BARRICADES & MARKINGS, INC. ( 12.47%)
Contract # 11154206
Totals 1094740.80 0.00 1130936.01 100.0

CountyLIBERTY
Highway FM0563
From VARIOUS
To VARIOUS
CSJ 6293-66-001
Proj ID RMC - 629366001
Work Type EROSION REPAIR
 
1.000 386888.00 0.00 938704.78 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-13-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 10
Working Days Charged 49
Percent Time Used 70
Contractor(s)
SHIRLEY & SONS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-66-001
EROSION PREVENTION PRODUCTS(0.00%)
Contract # 04164214
Totals 386888.00 0.00 938704.78 99.9

CountyJEFFERSON
Highway US0090
From JEFFERSON AND HARDIN COUNTIES
To JEFFERSON AND HARDIN COUNTIES
CSJ 6294-59-001
Proj ID RMC - 629459001
Work Type MILL AND OVERLAY VARIOUS ROADWAYS
 
0.001 1285827.15 0.00 1804416.38 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 05-02-16
Work Completed 08-08-16
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 90
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02164015
Totals 1285827.15 0.00 1804416.38 100.0

CountyORANGE
Highway SH0012
From AT FM1136
To AT FM1136
CSJ 6297-93-001
Proj ID RMC - 629793001
Work Type EMULSION TREAT ROADWAY AND OVERLAY
 
0.545 441682.15 0.00 479806.75 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 27
Addl Days Granted 6
Working Days Charged 55
Percent Time Used 166
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-93-001
CRABTREE BARRICADE SYSTEMS, INC. (2.22%)
Contract # 04164215
Totals 441682.15 0.00 479806.75 99.9

CountyJEFFERSON
Highway US0069
From DISTRICT WIDE
To DISTRICT WIDE
CSJ 6298-01-001
Proj ID RMC - 629801001
Work Type TRAFFIC CONTROL SERVICES
 
0.001 4726673.25 0.00 548510.49 11.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 04-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 50
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6298-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02164016
Totals 4726673.25 0.00 548510.49 11.6

CountyORANGE
Highway FM1078
From ORANGE COUNTY
To ORANGE COUNTY
CSJ 6299-88-001
Proj ID RMC - 629988001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIRS
 
0.001 591413.00 0.00 419901.65 70.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 10-05-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 45
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6299-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06164206
Totals 591413.00 0.00 419901.65 70.9

CountyORANGE
Highway IH0010
From ORANGE AND JEFFERSON COUNTIES
To ORANGE AND JEFFERSON COUNTIES
CSJ 6300-48-001
Proj ID RMC - 630048001
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIRS
 
0.001 337500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEZTEX INDUSTRIAL SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09164216
Totals 337500.00 0.00 0.00 0.0

CountyJEFFERSON
Highway US0069
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6300-92-001
Proj ID RMC - 630092001
Work Type SIGNAL / ILLUMINATION INSTALL / MAINTENANCE
 
0.001 1306822.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10164216
Totals 1306822.00 0.00 0.00 0.0

CountyCHAMBERS
Highway IH0010
From CHAMBERS, LIBERTY, JEFFERSON COUNTIES
To CHAMBERS, LIBERTY, JEFFERSON COUNTIES
CSJ 6301-19-001
Proj ID RMC - 630119001
Work Type MBGF REPAIRS
 
0.001 444156.00 0.00 111953.70 25.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 16
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07164211
Totals 444156.00 0.00 111953.70 25.2

CountyCHAMBERS
Highway IH0010
From VARIOUS LOCATIONS IN CHAMBERS COUNTY
To VARIOUS LOCATIONS IN CHAMBERS COUNTY
CSJ 6302-43-001
Proj ID RMC - 630243001
Work Type PLANE AND OVERLAY
 
1.000 0.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11164210
Totals 0.00 0.00 0.00 0.0

CountyJEFFERSON
Highway US0069
From JEFFERSON, HARDIN, AND ORANGE COUNTIES
To JEFFERSON, HARDIN, AND ORANGE COUNTIES
CSJ 6304-63-001
Proj ID RMC - 630463001
Work Type RUBBER ASPHALT CRACKSEALING
 
0.001 353063.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 16
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6304-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10164015
Totals 353063.00 0.00 0.00 0.0

CountyJASPER
Highway FM0254
From JASPER,NEWTON,TYLER,LIBERTY
To AND CHAMBERS COUNTIES
CSJ 6308-26-001
Proj ID RMC - 630826001
Work Type SEAL COAT
 
39.236 1177089.58 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11164018
Totals 1177089.58 0.00 0.00 0.0

page 1 | page 2