Monthly State Let Maintenance Report For Beaumont District As Of Feb 11, 2015 Page 2 Of 2

Last Update: Wednesday, February 11, 2015
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyJEFFERSON
Highway US0069
From BEAUMONT AREA OFFICE
To BEAUMONT AREA OFFICE
CSJ 6266-84-001
Proj ID RMC - 626684001
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIRS
 
0.001 710330.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CPAVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08144008
Totals 710330.00 0.00 0.00 0.0

CountyJEFFERSON
Highway FM0366
From NORTH OF 39TH ST
To 32ND ST
CSJ 6266-89-001
Proj ID RMC - 626689001
Work Type FM 366 FULL DEPTH PAVEMENT REPAIRS
 
0.632 538011.70 437336.35 556616.04 99.9
Work Order 08-25-14
Work Began 09-23-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 40
Addl Days Granted 6
Working Days Charged 42
Percent Time Used 91
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-89-001
AMERICAN REMEDIATION OPTIONS, INC. (0.32%)
CPAVE, INC.(3.13%)
CRABTREE BARRICADE SYSTEMS, INC. (1.25%)
HALL BROTHERS, INC.(8.21%)
WIDGEON CONSTRUCTION, INC. ( 56.19%)
Contract # 07144208
Totals 538011.70 437336.35 556616.04 99.9

CountyJEFFERSON
Highway US0069
From JEFFERSON, HARDIN, ORANGE COUNTIES
To JEFFERSON, HARDIN, ORANGE COUNTIES
CSJ 6269-11-001
Proj ID RMC - 626911001
Work Type FLEXIBLE PAVEMENT REPAIRS
 
0.001 878915.00 175467.10 1132930.10 99.9
Work Order 08-25-14
Work Began 10-13-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 81
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6269-11-001
CRABTREE BARRICADE SYSTEMS, INC. (0.39%)
Contract # 07144012
Totals 878915.00 175467.10 1132930.10 99.9

CountyJEFFERSON
Highway US0069
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6269-50-001
Proj ID RMC - 626950001
Work Type PAVEMENT MARKINGS
 
0.001 836940.00 0.00 684466.78 81.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 34
Contractor(s)
CRABTREE BARRICADE SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144012
Totals 836940.00 0.00 684466.78 81.7

CountyJEFFERSON
Highway US0069
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6269-51-001
Proj ID RMC - 626951001
Work Type ILLUMINATION AND ELECTRICAL MAINTENANCE
 
0.001 1013170.50 0.00 330934.65 32.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-04-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 97
Percent Time Used 53
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6269-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144013
Totals 1013170.50 0.00 330934.65 32.6

CountyORANGE
Highway SH0087
From BEAUMONT AREA OFFICE
To BEAUMONT AREA OFFICE
CSJ 6271-04-001
Proj ID RMC - 627104001
Work Type CLEAN DITCHES AND CULVERTS
 
47.100 349951.23 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154213
Totals 349951.23 0.00 0.00 0.0

CountyCHAMBERS
Highway IH0010
From CHAMBERS, LIBERTY AND JEFFERSON COUNTIES
To .
CSJ 6271-25-001
Proj ID RMC - 627125001
Work Type MBGF REPAIRS
 
1.000 367914.00 0.00 91977.75 24.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 41
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144211
Totals 367914.00 0.00 91977.75 24.9

CountyORANGE
Highway IH0010
From JEFFERSON COUNTY LINE
To FM1442
CSJ 6271-39-001
Proj ID RMC - 627139001
Work Type RAISING AND UNDERSEALING CONC SLABS
 
0.001 259811.20 0.00 290752.40 100.0
Work Order 08-25-14
Work Began 09-08-14
Work Completed 01-16-15
Time Computed 09-01-14
Contract Working Days 32
Addl Days Granted 4
Working Days Charged 35
Percent Time Used 97
Contractor(s)
NORTEX CONCRETE LIFT & STABILIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-39-001
CRABTREE BARRICADE SYSTEMS, INC. (0.83%)
Contract # 07144207
Totals 259811.20 0.00 290752.40 100.0

CountyJEFFERSON
Highway US0069
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6272-43-001
Proj ID RMC - 627243001
Work Type DISTRICTWIDE SWEEPING
 
967.390 1089213.03 0.00 157488.71 14.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 11-10-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 720
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 11
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6272-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08144206
Totals 1089213.03 0.00 157488.71 14.4

CountyLIBERTY
Highway SH0146
From VARIOUS LOCATIONS IN LIBERTY COUNTY
To .
CSJ 6273-76-001
Proj ID RMC - 627376001
Work Type SH146 FULL - DEPTH FLEXIBLE PAVEMENT REP
 
1.000 566718.64 0.00 3500.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 17
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6273-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09144206
Totals 566718.64 0.00 3500.00 0.6

CountyCHAMBERS
Highway FM2936
From FM 2936, FM 2939, FM 1738, FM 1007,
To FM 1408, FM 2800, FM 686
CSJ 6274-34-001
Proj ID RMC - 627434001
Work Type DISTRICTWIDE SEAL COAT
 
31.317 951388.94 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154015
Totals 951388.94 0.00 0.00 0.0

CountyJASPER
Highway US0096
From VARIOUS LOCATIONS IN JASPER
To AND NEWTON COUNTIES
CSJ 6274-69-001
Proj ID BPM - 627469001
Work Type RIPRAP / SPALL REPAIR
 
1.000 440182.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154212
Totals 440182.82 0.00 0.00 0.0

page 1 | page 2