Monthly State Let Maintenance Report For Beaumont District As Of Apr 11, 2014 Page 2 Of 2

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyNEWTON
Highway FM2829
From 240 FT EAST OF SH87, EAST
To END OF MAINTENANCE
CSJ 6259-14-001
Proj ID RMC - 625914001
Work Type FM 2829 REHABILITATION & WIDENING
 
2.000 604899.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6259-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144040
Totals 604899.70 0.00 0.00 0.0

CountyJASPER
Highway FM1007
From FM 1007, EAST OF US 96
To END OF MAINTENANCE
CSJ 6260-17-001
Proj ID RMC - 626017001
Work Type ADDING OR WIDENING PAVEMENT
 
1.766 484850.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 00-00-00
Work Completed  
Time Computed 04-21-14
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6260-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144014
Totals 484850.56 0.00 0.00 0.0

CountyJASPER
Highway FM0252
From FM 252, FROM 375 FT SOUTH OF US 190
To FOR 3.1 MILES
CSJ 6260-34-001
Proj ID RMC - 626034001
Work Type HMA OVERLAY
 
3.100 661886.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 27
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144028
Totals 661886.78 0.00 0.00 0.0

CountyHARDIN
Highway US0096
From JEFFERSON, ORANGE, AND HARDIN COUNTIES
To JEFFERSON, ORANGE, AND HARDIN COUNTIES
CSJ 6261-40-001
Proj ID RMC - 626140001
Work Type US 69 ETC. MILL AND OVERLAY
 
0.001 797816.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144032
Totals 797816.05 0.00 0.00 0.0

CountyCHAMBERS
Highway IH0010
From VARIOUS LOCATIONS IN CHAMBERS COUNTY
To .
CSJ 6262-47-001
Proj ID RMC - 626247001
Work Type CONCRETE PAVEMENT REPAIR
 
1.000 423986.00 58932.75 58932.75 13.8
Work Order 02-14-14
Work Began 03-17-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 15
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134019
Totals 423986.00 58932.75 58932.75 13.8

CountyJEFFERSON
Highway IH0010
From JEFFERSON AND ORANGE COUNTIES
To JEFFERSON AND ORANGE COUNTIES
CSJ 6265-16-001
Proj ID RMC - 626516001
Work Type BRIDGE HEADER JOINT REPAIR
 
0.001 205736.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 04-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS ROAD MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6265-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144015
Totals 205736.00 0.00 0.00 0.0

CountyCHAMBERS
Highway FM1663
From FM 1663, FM 1410,FM2626, FM1013,FM1415,
To FM1943,FM1007 AND FM 3063
CSJ 6265-36-001
Proj ID RMC - 626536001
Work Type DISTRICTWIDE SEAL COAT
 
38.410 919522.21 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6265-36-001
STRIPE-A-ZONE, INC.( 13.61%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.03%)
Contract # 01144032
Totals 919522.21 0.00 0.00 0.0

page 1 | page 2