Monthly State Let Maintenance Report For Beaumont District As Of Aug 10, 2015 Page 1 Of 3

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyORANGE
Highway FM1130
From FM 1130 AT ADAMS BAYOU
To FM 1130 AT ADAMS BAYOU
CSJ 6137-97-001
Proj ID BPM - 613797001
Work Type BRIDGE REPAIR
 
0.704 344188.12 0.00 354836.35 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-14
Work Began 03-24-14
Work Completed 09-25-14
Time Computed 03-25-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 93
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6137-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134020
Totals 344188.12 0.00 354836.35 100.0

CountyJEFFERSON
Highway IH0010
From ORANGE COUNTY LINE
To HARRIS COUNTY LINE
CSJ 6164-51-001
Proj ID RMC - 616451001
Work Type SWEEPING MAIN ROUTE HIGHWAYS
 
0.100 1801022.09 0.00 1859518.64 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-27-08
Work Began 06-03-08
Work Completed  
Time Computed 06-03-08
Contract Working Days 480
Addl Days Granted 60
Working Days Charged 535
Percent Time Used 99
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6164-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03084014
Totals 1801022.09 0.00 1859518.64 99.9

CountyJEFFERSON
Highway IH0010
From VARIOUS ROADS IN COASTAL DISTRICT
To VARIOUS ROADS IN COASTAL DISTRICT
CSJ 6193-72-001
Proj ID RMC - 619372001
Work Type CALL OUT DEBRIS REMOVAL AND DISPOSAL
 
0.100 1857950.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6193-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06094001
Totals 1857950.00 0.00 0.00 0.0

CountyJEFFERSON
Highway IH0010
From BRAKES BAYOU
To BRIDGE
CSJ 6221-53-001
Proj ID ABT - 622153001
Work Type HAZ - MAT
 
0.066 69000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 10
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05124021
Totals 69000.00 0.00 0.00 0.0

CountyTYLER
Highway FM0256
From FROM 2 MILES NORTH OF US 190 INTERSECT.
To NORTH 1.778 MILES
CSJ 6230-34-001
Proj ID RMC - 623034001
Work Type PAVEMENT WIDENING
 
1.778 491333.01 0.00 495007.02 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-22-14
Work Completed 01-02-15
Time Computed 00-00-00
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 76
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6230-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144013
Totals 491333.01 0.00 495007.02 100.0

CountyJEFFERSON
Highway IH0010
From CHAMBERS/ HARRIS COUNTY LINE
To TEXAS/ LOUISIANA STATE LINE
CSJ 6247-47-001
Proj ID RMC - 624747001
Work Type ROUTINE SWEEPING OF ROADWAYS
 
0.100 1893193.18 0.00 1640834.32 100.0
Work Order 03-08-13
Work Began 03-13-13
Work Completed 07-14-15
Time Computed 03-13-13
Contract Working Days 720
Addl Days Granted 0
Working Days Charged 523
Percent Time Used 72
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6247-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134016
Totals 1893193.18 0.00 1640834.32 100.0

CountyNEWTON
Highway FM2460
From 2.5 MI. EAST OF SH 87, EAST
To FM 1416
CSJ 6248-20-001
Proj ID RMC - 624820001
Work Type FM 2460 PAVEMENT WIDENING
 
3.660 1187970.52 833948.85 1628165.38 99.9
Work Order 12-19-14
Work Began 01-16-15
Work Completed  
Time Computed 01-16-15
Contract Working Days 60
Addl Days Granted 5
Working Days Charged 74
Percent Time Used 113
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6248-20-001
AMERICAN REMEDIATION OPTIONS, INC. (1.60%)
CRABTREE BARRICADE SYSTEMS, INC. (2.46%)
NORMAN HIGHWAY CONSTRUCTORS, INC.(6.48%)
Contract # 10144009
Totals 1187970.52 833948.85 1628165.38 99.9

CountyJEFFERSON
Highway IH0010
From VARIOUS HIGHWAYS IN DISTRICT 20
To VARIOUS HIGHWAYS IN DISTRICT 20
CSJ 6253-63-001
Proj ID RMC - 625363001
Work Type CALLOUT DEBRIS REMOVAL AFTER A HURRICANE
 
0.001 1600000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04134017
Totals 1600000.00 0.00 0.00 0.0

CountyCHAMBERS
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6254-95-001
Proj ID RMC - 625495001
Work Type MOWING OF RIGHT OF WAY
 
10.000 395599.00 0.00 400570.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-16-13
Work Began 05-23-13
Work Completed 02-11-15
Time Computed 05-23-13
Contract Working Days 155
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 60
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6254-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134014
Totals 395599.00 0.00 400570.00 100.0

CountyJASPER
Highway US0096
From VARIOUS
To VARIOUS
CSJ 6255-00-001
Proj ID RMC - 625500001
Work Type MOWING OF RIGHT OF WAY
 
256.000 437316.80 0.00 437216.80 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-13
Work Began 05-13-13
Work Completed 01-01-15
Time Computed 05-13-13
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 37
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6255-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134027
Totals 437316.80 0.00 437216.80 100.0

CountyJEFFERSON
Highway IH0010
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6255-67-001
Proj ID RMC - 625567001
Work Type CABLE BARRIER REPAIRS
 
0.001 272209.00 0.00 395060.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-13
Work Began 09-01-13
Work Completed 11-24-14
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6255-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07134013
Totals 272209.00 0.00 395060.00 100.0

CountyHARDIN
Highway US0096
From JEFFERSON, ORANGE, AND HARDIN COUNTIES
To JEFFERSON, ORANGE, AND HARDIN COUNTIES
CSJ 6261-40-001
Proj ID RMC - 626140001
Work Type US 69 ETC. MILL AND OVERLAY
 
0.001 797816.05 0.00 3165230.09 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-28-14
Work Began 06-16-14
Work Completed 10-17-14
Time Computed 06-16-14
Contract Working Days 38
Addl Days Granted 15
Working Days Charged 47
Percent Time Used 88
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-40-001
CPAVE, INC.(0.67%)
CRABTREE BARRICADE SYSTEMS, INC. (4.09%)
DUSTROL, INC.( 18.13%)
Contract # 03144032
Totals 797816.05 0.00 3165230.09 100.0

CountyCHAMBERS
Highway FM1663
From FM 1663, FM 1410,FM2626, FM1013,FM1415,
To FM1943,FM1007 AND FM 3063
CSJ 6265-36-001
Proj ID RMC - 626536001
Work Type DISTRICTWIDE SEAL COAT
 
38.410 919522.21 0.00 939749.77 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 05-19-14
Work Completed 08-08-14
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6265-36-001
STRIPE-A-ZONE, INC.( 13.61%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.03%)
Contract # 01144032
Totals 919522.21 0.00 939749.77 100.0

CountyJEFFERSON
Highway IH0010
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6266-83-001
Proj ID RMC - 626683001
Work Type CABLE BARRIER REPAIRS
 
0.001 292731.68 60479.00 322078.00 99.9
Work Order 07-29-14
Work Began 09-10-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 334
Percent Time Used 91
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6266-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144210
Totals 292731.68 60479.00 322078.00 99.9

CountyJEFFERSON
Highway US0069
From BEAUMONT AREA OFFICE
To BEAUMONT AREA OFFICE
CSJ 6266-84-001
Proj ID RMC - 626684001
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIRS
 
0.001 710330.00 93860.50 815969.00 100.0
Work Order 00-00-00
Work Began 04-02-15
Work Completed 08-04-15
Time Computed 10-20-14
Contract Working Days 49
Addl Days Granted 6
Working Days Charged 55
Percent Time Used 100
Contractor(s)
CPAVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08144008
Totals 710330.00 93860.50 815969.00 100.0

CountyJEFFERSON
Highway FM0366
From NORTH OF 39TH ST
To 32ND ST
CSJ 6266-89-001
Proj ID RMC - 626689001
Work Type FM 366 FULL DEPTH PAVEMENT REPAIRS
 
0.632 538011.70 0.00 643210.16 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-25-14
Work Began 09-23-14
Work Completed 06-05-15
Time Computed 09-01-14
Contract Working Days 40
Addl Days Granted 17
Working Days Charged 57
Percent Time Used 100
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-89-001
AMERICAN REMEDIATION OPTIONS, INC. (0.32%)
CPAVE, INC.(3.13%)
CRABTREE BARRICADE SYSTEMS, INC. (1.25%)
HALL BROTHERS, INC.(8.21%)
WIDGEON CONSTRUCTION, INC. ( 56.19%)
Contract # 07144208
Totals 538011.70 0.00 643210.16 100.0

CountyJEFFERSON
Highway US0069
From JEFFERSON, HARDIN, ORANGE COUNTIES
To JEFFERSON, HARDIN, ORANGE COUNTIES
CSJ 6269-11-001
Proj ID RMC - 626911001
Work Type FLEXIBLE PAVEMENT REPAIRS
 
0.001 878915.00 2000.00 1190383.80 100.0
Work Order 08-25-14
Work Began 10-13-14
Work Completed 06-05-15
Time Computed 09-01-14
Contract Working Days 60
Addl Days Granted 22
Working Days Charged 69
Percent Time Used 84
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6269-11-001
CRABTREE BARRICADE SYSTEMS, INC. (0.39%)
Contract # 07144012
Totals 878915.00 2000.00 1190383.80 100.0

CountyJEFFERSON
Highway US0069
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6269-50-001
Proj ID RMC - 626950001
Work Type PAVEMENT MARKINGS
 
0.001 836940.00 283679.57 1762297.27 99.9
Work Order 00-00-00
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 164
Percent Time Used 82
Contractor(s)
CRABTREE BARRICADE SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144012
Totals 836940.00 283679.57 1762297.27 99.9

CountyJEFFERSON
Highway US0069
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6269-51-001
Proj ID RMC - 626951001
Work Type ILLUMINATION AND ELECTRICAL MAINTENANCE
 
0.001 1013170.50 0.00 1230676.15 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-04-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 60
Working Days Charged 213
Percent Time Used 88
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6269-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144013
Totals 1013170.50 0.00 1230676.15 99.9

CountyORANGE
Highway SH0087
From BEAUMONT AREA OFFICE
To BEAUMONT AREA OFFICE
CSJ 6271-04-001
Proj ID RMC - 627104001
Work Type CLEAN DITCHES AND CULVERTS
 
47.100 349951.23 0.00 342762.46 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 03-04-15
Work Completed 07-14-15
Time Computed 00-00-00
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 33
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154213
Totals 349951.23 0.00 342762.46 100.0

page 1 | page 2 | page 3