Monthly State Let Maintenance Report For Beaumont District As Of Jul 14, 2017 Page 1 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJEFFERSON
HighwayIH0010
FromORANGE COUNTY LINE
ToHARRIS COUNTY LINE
CSJ6164-51-001
Proj IDRMC - 616451001
Work TypeSWEEPING MAIN ROUTE HIGHWAYS
 
0.1001801022.091859518.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-27-08
Work Began06-03-08
Work Completed
Time Computed06-03-08
Contract Working Days480
Addl Days Granted60
Working Days Charged535
Percent Time Used99
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6164-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03084014
Totals1801022.090.001859518.6499.9

CountyJEFFERSON
HighwayIH0010
FromVARIOUS ROADS IN COASTAL DISTRICT
ToVARIOUS ROADS IN COASTAL DISTRICT
CSJ6193-72-001
Proj IDRMC - 619372001
Work TypeCALL OUT DEBRIS REMOVAL AND DISPOSAL
 
0.1001857950.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6193-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06094001
Totals1857950.000.000.000.0

CountyJEFFERSON
HighwayIH0010
FromBRAKES BAYOU
ToBRIDGE
CSJ6221-53-001
Proj IDABT - 622153001
Work TypeHAZ-MAT
 
0.06669000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05124021
Totals69000.000.000.000.0

CountyJEFFERSON
HighwayIH0010
FromVARIOUS HIGHWAYS IN DISTRICT 20
ToVARIOUS HIGHWAYS IN DISTRICT 20
CSJ6253-63-001
Proj IDRMC - 625363001
Work TypeCALLOUT DEBRIS REMOVAL AFTER A HURRICANE
 
0.0011600000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04134017
Totals1600000.000.000.000.0

CountyCHAMBERS
HighwayFM2936
FromFM 2936, FM 2939, FM 1738, FM 1007,
ToFM 1408, FM 2800, FM 686
CSJ6274-34-001
Proj IDRMC - 627434001
Work TypeDISTRICTWIDE SEAL COAT
 
31.317951388.94995575.03100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-18-15
Work Completed07-28-15
Time Computed05-18-15
Contract Working Days29
Addl Days Granted0
Working Days Charged29
Percent Time Used100
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-34-001
INTERSTATE BARRICADES & MARKINGS, INC. (12.61)
Contract #01154015
Totals951388.940.00995575.03100.0

CountyJEFFERSON
HighwayIH0010
FromCHAMBERS/ HARRIS COUNTY LINE
ToTEXAS/ LOUISIANA STATE LINE
CSJ6276-67-001
Proj IDRMC - 627667001
Work TypeHIGH VOLUME SWEEPING
 
0.1002340019.202258675.93100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-15
Work Completed06-28-17
Time Computed00-00-00
Contract Working Days720
Addl Days Granted0
Working Days Charged720
Percent Time Used100
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6276-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154217
Totals2340019.200.002258675.93100.0

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6281-39-001
Proj IDRMC - 628139001
Work TypeROW MOWING IN LIBERTY MAINTENANCE SECTIO
 
355.000581577.00573514.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-20-15
Work Completed05-04-17
Time Computed00-00-00
Contract Working Days186
Addl Days Granted0
Working Days Charged100
Percent Time Used53
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6281-39-001
P-VILLE, INCORPORATED (100.00)
Contract #03154214
Totals581577.000.00573514.00100.0

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6285-35-001
Proj IDRMC - 628535001
Work TypePAVEMENT MARKINGS
 
0.001872950.002006232.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted365
Working Days Charged471
Percent Time Used83
Contractor(s)
CRABTREE BARRICADE SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154206
Totals872950.0050572.252006232.1099.9

CountyORANGE
HighwayIH0010
FromVARIOUS LOCATIONS IN ORANGE COUNTY
ToVARIOUS LOCATIONS IN ORANGE COUNTY
CSJ6291-36-001
Proj IDBPM - 629136001
Work TypeRIPRAP AND SCOUR REPAIRS
 
0.001570205.00645871.03100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-05-16
Work Completed06-02-17
Time Computed00-00-00
Contract Working Days58
Addl Days Granted40
Working Days Charged104
Percent Time Used106
Contractor(s)
DEZTEX INDUSTRIAL SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154010
Totals570205.000.00645871.03100.0

CountyCHAMBERS
HighwayIH0010
FromIH 0010 IN CHAMBERS COUNTY
To.
CSJ6291-55-001
Proj IDRMC - 629155001
Work TypeFULL DEPTH CONCRETE PAVEMENT REPAIR
 
28.840397769.95721259.25100.0
CountyLIBERTY
HighwayUS0059
FromVARIOUS LOCATIONS IN LIBERTY COUNTY
To.
CSJ6291-55-002
Proj IDRMC - 629155002
Work TypeFULL DEPTH CONCRETE PAVEMENT REPAIR
 
8.845438673.05725519.60100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-17-16
Work Completed03-15-17
Time Computed00-00-00
Contract Working Days52
Addl Days Granted67
Working Days Charged118
Percent Time Used99
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-55-001
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (2.04)
STRIPES & STOPS COMPANY, INC. (0.27)
Contract #10154010
Totals836443.000.001446778.85100.0

CountyCHAMBERS
HighwayIH0010
FromCHAMBERS COUNTY
ToLIBERTY COUNTY
CSJ6291-88-001
Proj IDRMC - 629188001
Work TypeCLEAN EXIST CULVERTS/DITCH CLEAN/RESHAPE
 
32.597358461.10287355.8580.1
CountyLIBERTY
HighwaySH0105
FromVARIOUS LOCATIONS IN LIBERTY COUNTY
To.
CSJ6291-88-002
Proj IDRMC - 629188002
Work TypeCLEAN EXIST CULVERTS, DITCH CLEAN & RESH
 
25.505524674.65595125.3599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-16
Work Completed
Time Computed00-00-00
Contract Working Days105
Addl Days Granted70
Working Days Charged129
Percent Time Used73
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164014
Totals883135.7540034.40882481.2099.9

CountyLIBERTY
HighwayFM0563
FromVARIOUS
ToVARIOUS
CSJ6293-66-001
Proj IDRMC - 629366001
Work TypeEROSION REPAIR
 
1.000386888.001002664.78100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-13-16
Work Completed03-15-17
Time Computed00-00-00
Contract Working Days60
Addl Days Granted10
Working Days Charged60
Percent Time Used85
Contractor(s)
SHIRLEY & SONS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-66-001
EROSION PREVENTION PRODUCTS (0.00)
Contract #04164214
Totals386888.004400.001002664.78100.0

CountyJEFFERSON
HighwayUS0069
FromDISTRICT WIDE
ToDISTRICT WIDE
CSJ6298-01-001
Proj IDRMC - 629801001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0014726673.251047709.0022.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted60
Working Days Charged425
Percent Time Used100
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6298-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164016
Totals4726673.250.001047709.0022.1

CountyORANGE
HighwayFM1078
FromORANGE COUNTY
ToORANGE COUNTY
CSJ6299-88-001
Proj IDRMC - 629988001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIRS
 
0.001591413.00880400.25100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-05-16
Work Completed03-13-17
Time Computed00-00-00
Contract Working Days37
Addl Days Granted0
Working Days Charged63
Percent Time Used170
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6299-88-001
CHEROKEE SERVICES (2.34)
Contract #06164206
Totals591413.000.00880400.25100.0

CountyORANGE
HighwayIH0010
FromORANGE AND JEFFERSON COUNTIES
ToORANGE AND JEFFERSON COUNTIES
CSJ6300-48-001
Proj IDRMC - 630048001
Work TypeFULL DEPTH CONCRETE PAVEMENT REPAIRS
 
0.001337500.00331225.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-28-17
Work Completed
Time Computed00-00-00
Contract Working Days24
Addl Days Granted0
Working Days Charged45
Percent Time Used187
Contractor(s)
DEZTEX INDUSTRIAL SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-48-001
HOLES INCORPORATED (13.27)
Contract #09164216
Totals337500.0050710.00331225.0099.9

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6300-76-001
Proj IDRMC - 630076001
Work TypeDISTRICTWIDE SWEEPING
 
967.3901049426.92152540.0614.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-17-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged106
Percent Time Used14
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6300-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174018
Totals1049426.9252693.00152540.0614.5

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6300-92-001
Proj IDRMC - 630092001
Work TypeSIGNAL/ILLUMINATION INSTALL/MAINTENANCE
 
0.0011306822.00392759.4230.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-03-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged179
Percent Time Used49
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164216
Totals1306822.0042217.70392759.4230.0

CountyJEFFERSON
HighwayIH0010
FromCHAMBERS/HARRIS COUNTY LINE
ToTEXAS/LOUISIANA STATE LINE
CSJ6301-04-001
Proj IDRMC - 630104001
Work TypeHIGH VOLUME SWEEPING
 
0.1003437535.36143381.744.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged30
Percent Time Used4
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6301-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174009
Totals3437535.36143381.74143381.744.1

CountyCHAMBERS
HighwayIH0010
FromCHAMBERS, LIBERTY, JEFFERSON COUNTIES
ToCHAMBERS, LIBERTY, JEFFERSON COUNTIES
CSJ6301-19-001
Proj IDRMC - 630119001
Work TypeMBGF REPAIRS
 
0.001444156.00484778.8199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164211
Totals444156.0036756.50484778.8199.9

CountyHARDIN
HighwaySH0105
FromHARDIN,JEFFERSON, AND JASPER COUNTIES
ToHARDIN,JEFFERSON, AND JASPER COUNTIES
CSJ6301-96-001
Proj IDRMC - 630196001
Work TypeFLEXIBLE PAVEMENT REPAIRS
 
0.0011166409.501002376.9285.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-02-17
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged42
Percent Time Used65
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6301-96-001
CHEROKEE SERVICES (4.71)
Contract #01174229
Totals1166409.50411609.421002376.9285.9

page 1 | page 2 | page 3