Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | JEFFERSON |
Highway | IH0010 |
From | VARIOUS LOCATIONS IN |
To | JEFFERSON , HARDIN, AND TYLER COUNTIES |
CSJ | 6435-38-001 |
Proj ID | RMC - 643538001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 706468.40 | | 451009.94 | 63.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 182 |
Percent Time Used | 49 |
Contractor(s) |
ROSS SA ENTERPRISE LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6435-38-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234003 |
| Totals | 706468.40 | 18932.42 | 451009.94 | 63.8 |
|
County | JASPER |
Highway | US0190 |
From | US 190 |
To | VARIOUS ROADS IN JASPER, NEWTON, ORANGE |
CSJ | 6436-19-001 |
Proj ID | RMC - 643619001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 992676.03 | | 129327.00 | 13.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-15-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 77 |
Percent Time Used | 21 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6436-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10234005 |
| Totals | 992676.03 | 36673.00 | 129327.00 | 13.0 |
|
County | JASPER |
Highway | US0190 |
From | DISTRICTWIDE |
To | DISTRICTWIDE |
CSJ | 6436-47-001 |
Proj ID | MMC - 643647001 |
Work Type | AGGREGATE |
|
| 0.010 | 477540.00 | | 1158557.96 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-24-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 254 |
Percent Time Used | 69 |
Contractor(s) |
ARCOSA LWS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6436-47-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04234002 |
| Totals | 477540.00 | 0.00 | 1158557.96 | 99.9 |
|
County | JEFFERSON |
Highway | IH0010 |
From | VARIOUS LOCATIONS IN |
To | JEFFERSON , HARDIN, AND TYLER COUNTIES |
CSJ | 6441-35-001 |
Proj ID | RMC - 644135001 |
Work Type | FULL DEPTH CONCRETE REPAIR |
|
| 0.010 | 886093.00 | | 910798.44 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-18-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 44 |
Addl Days Granted | 0 |
Working Days Charged | 33 |
Percent Time Used | 75 |
Contractor(s) |
ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6441-35-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234210 |
| Totals | 886093.00 | 0.00 | 910798.44 | 99.9 |
|
County | LIBERTY |
Highway | SH0105 |
From | MONTGOMERY CO. LINE |
To | SH 105 BYPASS |
CSJ | 6442-45-001 |
Proj ID | RMC - 644245001 |
Work Type | ACP OVERLAY |
|
| 0.010 | 1435988.05 | | 420142.81 | 29.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-15-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 45 |
Addl Days Granted | 0 |
Working Days Charged | 6 |
Percent Time Used | 13 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6442-45-001 NORTEX CONCRETE LIFT & STABILIZATION, INC. (2.76)
|
Contract # | 11234205 |
| Totals | 1435988.05 | 291339.03 | 420142.81 | 29.2 |
|
County | JEFFERSON |
Highway | IH0010 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6443-40-001 |
Proj ID | RMC - 644340001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 1250570.24 | | 127897.12 | 10.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 11-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 726 |
Addl Days Granted | 0 |
Working Days Charged | 121 |
Percent Time Used | 16 |
Contractor(s) |
WAYNE YANCEY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6443-40-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234012 |
| Totals | 1250570.24 | 17164.00 | 127897.12 | 10.2 |
|
County | JEFFERSON |
Highway | IH0010 |
From | VARIOUS LOCATIONS IN |
To | JEFFERSON AND HARDIN COUNTIES |
CSJ | 6445-82-001 |
Proj ID | BPM - 644582001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 759064.50 | | 206800.00 | 27.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-08-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 65 |
Addl Days Granted | 15 |
Working Days Charged | 17 |
Percent Time Used | 21 |
Contractor(s) |
AAD CONTRACTING INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6445-82-001 SJ&J CONSTRUCTION, LLC (38.78) THE TRUESDELL CORPORATION (20.44) L & M MOWING CONTRACTORS, LLC (2.89)
|
Contract # | 10234205 |
| Totals | 759064.50 | 202250.00 | 206800.00 | 27.2 |
|
County | TYLER |
Highway | FM0256 |
From | DISTRICTWIDE |
To | DISTRICTWIDE |
CSJ | 6448-69-001 |
Proj ID | MMC - 644869001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 511077.00 | | 614621.97 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-19-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 130 |
Percent Time Used | 35 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6448-69-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234013 |
| Totals | 511077.00 | 99851.76 | 614621.97 | 99.9 |
|
County | CHAMBERS |
Highway | IH0010 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6449-59-001 |
Proj ID | BPM - 644959001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 381541.00 | | 550102.55 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-16-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 38 |
Addl Days Granted | 0 |
Working Days Charged | 33 |
Percent Time Used | 86 |
Contractor(s) |
STRUCTURAL INTEGRITY GROUP LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6449-59-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234206 |
| Totals | 381541.00 | 221477.75 | 550102.55 | 99.9 |
|
County | JEFFERSON |
Highway | US0069 |
From | DISTRICTWIDE |
To | DISTRICTWIDE |
CSJ | 6450-75-001 |
Proj ID | MMC - 645075001 |
Work Type | HOT MIX |
|
| 0.010 | 3421275.00 | | 343684.89 | 10.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 11-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 121 |
Percent Time Used | 33 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6450-75-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09234007 |
| Totals | 3421275.00 | 299505.69 | 343684.89 | 10.0 |
|
County | ORANGE |
Highway | FM0105 |
From | DISTRICTWIDE |
To | DISTRICTWIDE |
CSJ | 6450-81-001 |
Proj ID | MMC - 645081001 |
Work Type | HOT MIX |
|
| 0.010 | 3211500.00 | | 438609.10 | 13.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 11-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 121 |
Percent Time Used | 33 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6450-81-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09234008 |
| Totals | 3211500.00 | 52401.30 | 438609.10 | 13.6 |
|
County | CHAMBERS |
Highway | FM0565 |
From | DISTRICTWIDE |
To | DISTRICTWIDE |
CSJ | 6451-49-001 |
Proj ID | MMC - 645149001 |
Work Type | HOT MIX |
|
| 0.010 | 747500.00 | | 302907.32 | 40.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-30-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 123 |
Percent Time Used | 33 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6451-49-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09234006 |
| Totals | 747500.00 | 0.00 | 302907.32 | 40.5 |
|
County | CHAMBERS |
Highway | IH0010 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6452-75-001 |
Proj ID | RMC - 645275001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 554027.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
HAZMAT INTERNATIONAL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6452-75-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02244011 |
| Totals | 554027.00 | 0.00 | 0.00 | 0.0 |
|
County | NEWTON |
Highway | FM1415 |
From | BEAUMONT AREA DISTRICT |
To | BEAUMONT AREA DISTRICT |
CSJ | 6453-13-001 |
Proj ID | MMC - 645313001 |
Work Type | EMULSION |
|
| 0.010 | 696110.00 | | 92238.94 | 13.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-30-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 123 |
Percent Time Used | 33 |
Contractor(s) |
CLEVELAND ASPHALT PRODUCTS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6453-13-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09234204 |
| Totals | 696110.00 | 11431.83 | 92238.94 | 13.2 |
|
County | JEFFERSON |
Highway | US0069 |
From | DISTRICTWIDE |
To | DISTRICTWIDE |
CSJ | 6455-60-001 |
Proj ID | RMC - 645560001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 557638.75 | | 205061.25 | 36.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-23-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 7 |
Percent Time Used | 1 |
Contractor(s) |
TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6455-60-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234006 |
| Totals | 557638.75 | 205061.25 | 205061.25 | 36.7 |
|
County | JEFFERSON |
Highway | US0069 |
From | JEFFERSON/ORANGE/HARDIN COUNTIES |
To | JEFFERSON/ORANGE/HARDIN COUNTIES |
CSJ | 6456-75-001 |
Proj ID | RMC - 645675001 |
Work Type | TREE TRIMMING AND BRUSH REMOVAL |
|
| 0.010 | 485825.00 | | 59350.00 | 12.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-23-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 38 |
Percent Time Used | 10 |
Contractor(s) |
ACE CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6456-75-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234007 |
| Totals | 485825.00 | 59350.00 | 59350.00 | 12.2 |
|
County | LIBERTY |
Highway | US0090 |
From | LIBERTY COUNTY |
To | CHAMBERS COUNTY |
CSJ | 6456-77-001 |
Proj ID | RMC - 645677001 |
Work Type | TREE TRIMMING AND BRUSH REMOVAL |
|
| 0.010 | 293800.00 | | 39450.00 | 13.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-29-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 32 |
Percent Time Used | 8 |
Contractor(s) |
MARLANE CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6456-77-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234008 |
| Totals | 293800.00 | 39450.00 | 39450.00 | 13.4 |
|
County | JASPER |
Highway | US0096 |
From | JASPER/NEWTON/ORANGE COUNTIES |
To | JASPER/NEWTON/ORANGE COUNTIES |
CSJ | 6456-79-001 |
Proj ID | RMC - 645679001 |
Work Type | TREE TRIMMING AND BRUSH REMOVAL |
|
| 0.010 | 349702.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-24-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 29 |
Percent Time Used | 7 |
Contractor(s) |
ACE CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6456-79-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234009 |
| Totals | 349702.00 | 0.00 | 0.00 | 0.0 |
|
County | JEFFERSON |
Highway | US0069 |
From | DISTRICTWIDE |
To | DISTRICTWIDE |
CSJ | 6458-36-001 |
Proj ID | RMC - 645836001 |
Work Type | ILLUMINATION MAINTENANCE |
|
| 0.010 | 760697.90 | | 7793.00 | 1.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-30-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 31 |
Percent Time Used | 8 |
Contractor(s) |
TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6458-36-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234010 |
| Totals | 760697.90 | 7793.00 | 7793.00 | 1.0 |
|
County | JEFFERSON |
Highway | US0069 |
From | DISTRICTWIDE |
To | DISTRICTWIDE |
CSJ | 6458-93-001 |
Proj ID | RMC - 645893001 |
Work Type | LARGE SIGN REPLACEMENT |
|
| 0.010 | 675755.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
3LW CIVIL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6458-93-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244005 |
| Totals | 675755.00 | 0.00 | 0.00 | 0.0 |
|