Monthly Local Let Maintenance Report For Beaumont District As Of Nov 22, 2017 Page 4 Of 5

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJEFFERSON
HighwaySH0347
FromSH 347
ToSH 347
CSJ6318-89-001
Proj IDSUP - 631889001
Work TypePORT ARTHUR JANITORIAL
 
1.0007688.682050.04100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-17
Work Began06-01-17
Work Completed10-11-17
Time Computed06-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
UNITED SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6318-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05172002
Totals7688.680.002050.04100.0

CountyHARDIN
HighwayUS0069
FromUS 69
ToUS 69
CSJ6318-90-001
Proj IDSUP - 631890001
Work TypeKOUNTZE LANDSCAPE MAINTENANCE
 
7.00014840.005936.0040.0
Work Order06-01-17
Work Began07-01-17
Work Completed
Time Computed06-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05172003
Totals14840.001484.005936.0040.0

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6320-92-001
Proj IDSUP - 632092001
Work TypeDISTRICT JANITORIAL
 
1.00056737.2316744.0029.5
Work Order07-01-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06172002
Totals56737.234186.0016744.0029.5

CountyJEFFERSON
HighwaySH0087
FromIH-10 AT FM364 AND
ToSH87 AT THE INTRACOASTAL CANAL BRIDGE
CSJ6321-09-001
Proj IDRMC - 632109001
Work TypeHAULING ROADWAY MATERIAL
 
0.001189150.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6321-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172001
Totals189150.000.000.000.0

CountyCHAMBERS
HighwayIH0010
FromIH 10
ToIH 10
CSJ6321-33-001
Proj IDSUP - 632133001
Work TypeORANGE LITTER
 
1.000200212.700.000.0
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172001
Totals200212.700.000.000.0

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6321-34-001
Proj IDSUP - 632134001
Work TypeBEAUMONT LITTER
 
1.000184284.1119355.2910.5
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6321-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172006
Totals184284.1114820.8219355.2910.5

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6321-35-001
Proj IDSUP - 632135001
Work TypeJASPER LITTER
 
1.00086919.8928044.2732.2
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172008
Totals86919.89330.0428044.2732.2

CountyLIBERTY
HighwayUS0090
FromUS 90
ToUS 90
CSJ6321-36-001
Proj IDSUP - 632136001
Work TypeLIBERTY LITTER
 
1.000225188.5036190.6516.0
Work Order08-15-17
Work Began09-01-16
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172002
Totals225188.5017376.6936190.6516.0

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6321-37-001
Proj IDSUP - 632137001
Work TypeNEWTON LITTER
 
1.00064151.8311563.7018.0
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172009
Totals64151.8311563.7011563.7018.0

CountyORANGE
HighwaySH0062
FromSH0062
ToSH0062
CSJ6321-38-001
Proj IDSUP - 632138001
Work TypeORANGE LITTER
 
1.000107759.250.000.0
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172004
Totals107759.250.000.000.0

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6321-39-001
Proj IDSUP - 632139001
Work TypePORT ARTHUR LITTER
 
1.000144654.7123507.3216.2
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6321-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172005
Totals144654.7116917.8023507.3216.2

CountyHARDIN
HighwayUS0069
FromUS 69
ToUS 69
CSJ6321-40-001
Proj IDSUP - 632140001
Work TypeKOUNTZE LITTER
 
1.00092774.8113573.7614.6
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172003
Totals92774.810.0013573.7614.6

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6321-41-001
Proj IDSUP - 632141001
Work TypeWOODVILLE LITTER
 
1.00062304.6412214.9419.6
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172007
Totals62304.640.0012214.9419.6

CountyJEFFERSON
HighwaySH0347
FromSH 347
ToSH 347
CSJ6323-21-001
Proj IDSUP - 632321001
Work TypePORT ARTHUR GROUNDS
 
1.00024000.003600.00100.0
Work Order09-01-17
Work Began00-00-00
Work Completed09-01-17
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172010
Totals24000.001200.003600.00100.0

CountyJEFFERSON
HighwayIH0010
FromJEFFERSON,
ToORANGE, HARDIN COUNTIES
CSJ6323-40-001
Proj IDEMC - 632340001
Work TypeEMERGENCY ROADWAY REPAIRS
 
0.0101924807.20806273.9641.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-11-17
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged21
Percent Time Used70
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-40-001
AMERICAN REMEDIATION OPTIONS, INC. (7.81)
CPAVE, INC. (0.77)
URETEK USA, INC. (1.50)
Contract #10172003
Totals1924807.20806273.96806273.9641.8

CountyJASPER
HighwayUS0096
FromJASPER, NEWTON AND
ToTYLER COUNTIES
CSJ6323-43-001
Proj IDEMC - 632343001
Work TypeEMERGENCY ROADWAY REPAIRS
 
0.010654883.00199536.0030.4
Work Order09-22-17
Work Began09-23-17
Work Completed
Time Computed09-22-17
Contract Working Days30
Addl Days Granted0
Working Days Charged25
Percent Time Used83
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172004
Totals654883.00150928.50199536.0030.4

CountyCHAMBERS
HighwayIH0010
FromCHAMBERS AND
ToLIBERTY COUNTIES
CSJ6323-49-001
Proj IDEMC - 632349001
Work TypeEMERGENCY ROADWAY REPAIRS
 
0.010639123.00780178.8599.9
Work Order09-22-17
Work Began09-21-17
Work Completed
Time Computed09-22-17
Contract Working Days30
Addl Days Granted0
Working Days Charged22
Percent Time Used73
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172005
Totals639123.00203350.05780178.8599.9

CountyJEFFERSON
HighwaySH0087
FromVARIOUS LOCATIONS
ToALONG SH 87
CSJ6323-94-001
Proj IDEMC - 632394001
Work TypeEROSION REPAIR TO ROADWAY AND CANAL
 
3.10619225096.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days205
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10172004
Totals19225096.800.000.000.0

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6324-07-001
Proj IDSUP - 632407001
Work TypeWOODVILLE GROUNDS
 
1.0007650.00500.006.5
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172006
Totals7650.00500.00500.006.5

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6324-08-001
Proj IDSUP - 632408001
Work TypeNEWTON GROUNDS
 
1.00010422.14482.064.6
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172007
Totals10422.14482.06482.064.6