Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLIBERTY
Highway US0059
From FM2025
To SH105
CSJ 6177-59-001
Proj ID SUP - 617759001
Work Type PICNIC AREA MAINTENANCE - CLEVELAND
 
1.000 20795.28 0.00 13863.52 66.6
Work Order 03-07-08
Work Began 03-07-08
Work Completed  
Time Computed 03-07-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 186
Percent Time Used 50
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6177-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082007
Totals 20795.28 0.00 13863.52 66.6

CountyJEFFERSON
Highway SH0347
From PORT ARTHUR OFFICE
To PORT ARTHUR OFFICE
CSJ 6177-60-001
Proj ID SUP - 617760001
Work Type GROUNDS MAINTENANCE - PORT ARTHUR
 
1.000 10740.98 562.06 8992.96 83.7
Work Order 03-07-08
Work Began 03-07-08
Work Completed  
Time Computed 03-07-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 188
Percent Time Used 51
Contractor(s)
TIBH INDUSTRIES, INC.
BEAUMONT PRODUCTS AND SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6177-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082008
Totals 10740.98 562.06 8992.96 83.7

CountyJEFFERSON
Highway SH0347
From PORT ARTHUR OFFICE
To PORT ARTHUR OFFICE
CSJ 6177-61-001
Proj ID SUP - 617761001
Work Type JANITORIAL MAINTENANCE - PORT ARTHUR
 
1.000 4637.19 258.58 2133.29 46.0
Work Order 03-01-08
Work Began 03-01-08
Work Completed  
Time Computed 03-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 192
Percent Time Used 52
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES INDUSTRIAL CONTRACTS AND TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6177-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082009
Totals 4637.19 258.58 2133.29 46.0

CountyJEFFERSON
Highway US0069
From VARIOUS
To VARIOUS
CSJ 6177-62-001
Proj ID SUP - 617762001
Work Type LANDSCAPE MAINTENANCE - PORT ARTHUR
 
1.000 84027.48 6701.04 62192.90 74.0
Work Order 03-07-08
Work Began 03-07-08
Work Completed  
Time Computed 03-07-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 188
Percent Time Used 51
Contractor(s)
TIBH INDUSTRIES, INC.
BEAUMONT PRODUCTS AND SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6177-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082010
Totals 84027.48 6701.04 62192.90 74.0

CountyNEWTON
Highway US0190
From NEWTON OFFICE
To NEWTON OFFICE
CSJ 6177-63-001
Proj ID SUP - 617763001
Work Type GROUNDS MAINTENANCE - NEWTON
 
1.000 5786.83 0.00 2141.88 37.0
Work Order 03-21-08
Work Began 03-21-08
Work Completed  
Time Computed 03-21-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 172
Percent Time Used 47
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6177-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082015
Totals 5786.83 0.00 2141.88 37.0

CountyNEWTON
Highway US0190
From NEWTON OFFICE
To NEWTON OFFICE
CSJ 6177-64-001
Proj ID SUP - 617764001
Work Type JANITORIAL MAINTENANCE - NEWTON
 
1.000 4187.40 297.66 2996.76 71.5
Work Order 04-01-08
Work Began 04-01-08
Work Completed  
Time Computed 04-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 165
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6177-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082016
Totals 4187.40 297.66 2996.76 71.5

CountyNEWTON
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6177-65-001
Proj ID SUP - 617765001
Work Type PICNIC AREA MAINTENANCE - NEWTON
 
1.000 6709.24 414.28 4637.34 69.1
Work Order 03-21-08
Work Began 03-21-08
Work Completed  
Time Computed 03-21-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 172
Percent Time Used 47
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6177-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082017
Totals 6709.24 414.28 4637.34 69.1

CountyJASPER
Highway US0190
From JASPER OFFICE
To JASPER OFFICE
CSJ 6177-66-001
Proj ID SUP - 617766001
Work Type GROUNDS MAINTENANCE - JASPER
 
1.000 4838.78 148.50 1821.40 37.6
Work Order 03-07-08
Work Began 03-07-08
Work Completed  
Time Computed 03-07-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 50
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6177-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082011
Totals 4838.78 148.50 1821.40 37.6

CountyJASPER
Highway US0190
From JASPER OFFICE
To JASPER OFFICE
CSJ 6177-67-001
Proj ID SUP - 617767001
Work Type JANITORIAL MAINTENANCE - JASPER
 
1.000 9983.56 511.13 4089.04 40.9
Work Order 04-01-08
Work Began 04-01-08
Work Completed  
Time Computed 04-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 167
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6177-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082012
Totals 9983.56 511.13 4089.04 40.9

CountyJASPER
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6177-68-001
Proj ID SUP - 617768001
Work Type PICNIC AREA MAINTENANCE - JASPER
 
1.000 5991.86 421.04 4291.58 71.6
Work Order 03-07-08
Work Began 03-07-08
Work Completed  
Time Computed 03-07-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 50
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6177-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082013
Totals 5991.86 421.04 4291.58 71.6

CountyLIBERTY
Highway US0090
From LIBERTY OFFICE
To LIBERTY OFFICE
CSJ 6177-82-001
Proj ID SUP - 617782001
Work Type GROUNDS MAINTENANCE - LIBERTY
 
1.000 5041.84 265.36 2918.96 57.8
Work Order 03-21-08
Work Began 03-21-08
Work Completed  
Time Computed 03-21-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 177
Percent Time Used 48
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES INDUSTRIAL CONTRACTS AND TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6177-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082025
Totals 5041.84 265.36 2918.96 57.8

CountyLIBERTY
Highway US0090
From LIBERTY OFFICE
To LIBERTY OFFICE
CSJ 6177-83-001
Proj ID SUP - 617783001
Work Type JANITORIAL MAINTENANCE - LIBERTY
 
1.000 5208.86 299.06 2392.48 45.9
Work Order 04-01-08
Work Began 04-01-08
Work Completed  
Time Computed 04-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 170
Percent Time Used 46
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES INDUSTRIAL CONTRACTS AND TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6177-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082024
Totals 5208.86 299.06 2392.48 45.9

CountyLIBERTY
Highway US0090
From VARIOUS
To VARIOUS
CSJ 6177-84-001
Proj ID SUP - 617784001
Work Type PICNIC AREA MAINTENANCE - LIBERTY
 
1.000 19758.04 1625.64 13492.30 68.2
Work Order 03-21-08
Work Began 03-21-08
Work Completed  
Time Computed 03-21-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 178
Percent Time Used 48
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES INDUSTRIAL CONTRACTS AND TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6177-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04082007
Totals 19758.04 1625.64 13492.30 68.2

CountyJEFFERSON
Highway US0069
From DISTRICT OFFICE
To DISTRICT OFFICE
CSJ 6177-85-001
Proj ID SUP - 617785001
Work Type JANITORIAL MAINTENANCE - DISTRICT
 
1.000 47084.20 3924.25 28911.04 61.4
Work Order 04-01-08
Work Began 04-01-08
Work Completed  
Time Computed 04-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 170
Percent Time Used 46
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES INDUSTRIAL CONTRACTS AND TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6177-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082023
Totals 47084.20 3924.25 28911.04 61.4

CountyTYLER
Highway US0287
From WOODVILLE OFFICE
To WOODVILLE OFFICE
CSJ 6177-86-001
Proj ID SUP - 617786001
Work Type GROUNDS MAINTENANCE - WOODVILLE
 
1.000 2710.50 110.00 1430.00 52.7
Work Order 03-21-08
Work Began 03-21-08
Work Completed  
Time Computed 03-21-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 173
Percent Time Used 47
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6177-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082018
Totals 2710.50 110.00 1430.00 52.7

CountyTYLER
Highway US0287
From WOODVILLE OFFICE
To WOODVILLE OFFICE
CSJ 6177-87-001
Proj ID SUP - 617787001
Work Type JANITORIAL MAINTENANCE - WOODVILLE
 
1.000 3660.00 305.00 2440.00 66.6
Work Order 04-01-08
Work Began 04-01-08
Work Completed  
Time Computed 04-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 166
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6177-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082019
Totals 3660.00 305.00 2440.00 66.6

CountyTYLER
Highway US0287
From VARIOUS
To VARIOUS
CSJ 6177-88-001
Proj ID SUP - 617788001
Work Type PICNIC AREA MAINTENANCE - WOODVILLE
 
1.000 11672.80 717.00 6939.00 59.4
Work Order 03-21-08
Work Began 03-21-08
Work Completed  
Time Computed 03-21-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 173
Percent Time Used 47
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6177-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082020
Totals 11672.80 717.00 6939.00 59.4

CountyCHAMBERS
Highway FM0563
From ANAHUAC OFFICE
To ANAHUAC OFFICE
CSJ 6177-89-001
Proj ID SUP - 617789001
Work Type GROUNDS MAINTENANCE - ANAHUAC
 
1.000 7886.45 0.00 4169.09 52.8
Work Order 03-21-08
Work Began 03-21-08
Work Completed  
Time Computed 03-21-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 177
Percent Time Used 48
Contractor(s)
TIBH INDUSTRIES, INC.
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6177-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04082006
Totals 7886.45 0.00 4169.09 52.8

CountyCHAMBERS
Highway FM0563
From ANAHUAC OFFICE
To ANAHUAC OFFICE
CSJ 6177-90-001
Proj ID SUP - 617790001
Work Type JANITORIAL MAINTENANCE - ANAHUAC
 
1.000 4071.30 290.08 2175.60 53.4
Work Order 04-01-08
Work Began 04-01-08
Work Completed  
Time Computed 04-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 170
Percent Time Used 46
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6177-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03082021
Totals 4071.30 290.08 2175.60 53.4

CountyCHAMBERS
Highway FM0563
From VARIOUS
To VARIOUS
CSJ 6177-91-001
Proj ID SUP - 617791001
Work Type PICNIC AREA MAINTENANCE - AHANUAC
 
1.000 31539.52 1936.72 21597.88 68.4
Work Order 03-21-08
Work Began 03-21-08
Work Completed  
Time Computed 03-21-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 180
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6177-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04082005
Totals 31539.52 1936.72 21597.88 68.4