Monthly Local Let Maintenance Report For Beaumont District As Of Nov 22, 2017 Page 2 Of 5

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJEFFERSON
HighwayIH0010
FromIH 10
ToIH 10
CSJ6303-90-001
Proj IDSUP - 630390001
Work TypeLARGE DEBRIS - IH 10
 
1.000641607.20438020.3068.2
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged518
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162004
Totals641607.2029104.58438020.3068.2

CountyLIBERTY
HighwayUS0059
FromUS 59
ToUS 59
CSJ6303-91-001
Proj IDSUP - 630391001
Work TypeLARGE DEBRIS - LIBERTY
 
1.00075483.2042822.2056.7
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged518
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162005
Totals75483.202903.2042822.2056.7

CountyORANGE
HighwaySH0062
FromSH 62
ToSH 62
CSJ6303-95-001
Proj IDSUP - 630395001
Work TypeORANGE JANITORIAL
 
1.0006889.896078.0088.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
UNITED SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162007
Totals6889.890.006078.0088.2

CountyJASPER
HighwayUS0096
FromVARIOUS LOCATIONS IN JASPER
ToAND NEWTON COUNTIES
CSJ6305-53-001
Proj IDBPM - 630553001
Work TypeRIPRAP/SPALL & JOINT REPAIR
 
1.000200176.00185721.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-13-17
Work Completed08-14-17
Time Computed00-00-00
Contract Working Days22
Addl Days Granted3
Working Days Charged39
Percent Time Used156
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162001
Totals200176.000.00185721.00100.0

CountyHARDIN
HighwayUS0096
FromHARDIN COUNTY
ToHARDIN COUNTY
CSJ6306-44-001
Proj IDBPM - 630644001
Work TypeRIPRAP AND SCOUR REPAIRS
 
0.001244250.00225565.3392.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-03-17
Work Completed
Time Computed00-00-00
Contract Working Days53
Addl Days Granted0
Working Days Charged42
Percent Time Used79
Contractor(s)
NORMAN HIGHWAY CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172001
Totals244250.000.00225565.3392.3

CountyCHAMBERS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6306-50-001
Proj IDSUP - 630650001
Work TypeANAHUAC LITTER
 
1.000186599.18138002.19100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-16
Work Began09-01-16
Work Completed09-01-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162007
Totals186599.180.00138002.19100.0

CountyORANGE
HighwaySH0062
FromVARIOUS
ToVARIOUS
CSJ6306-55-001
Proj IDSUP - 630655001
Work TypeORANGE LITTER
 
1.00087470.3464960.55100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-16
Work Began09-01-16
Work Completed09-01-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162004
Totals87470.340.0064960.55100.0

CountyLIBERTY
HighwayUS0059
FromUS 59 IN LIBERTY COUNTY
ToUS 59 IN LIBERTY COUNTY
CSJ6307-58-001
Proj IDRMC - 630758001
Work TypeOVERLAY OF EXISTING ROADWAYS
 
1.000192805.00386584.88100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-30-17
Work Completed07-10-17
Time Computed00-00-00
Contract Working Days23
Addl Days Granted0
Working Days Charged23
Percent Time Used100
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6307-58-001
REPUBLIC TRAFFIC SAFETY, INC. (3678.34)
Contract #12162001
Totals192805.000.00386584.88100.0

CountyJASPER
HighwayUS0096
FromVARIOUS ROADWAYS IN JASPER, TYLER
ToAND NEWTON CO.
CSJ6307-89-001
Proj IDRMC - 630789001
Work TypeUS 96 ETC., CRACK SEAL
 
90.01658000.7357411.41100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-09-17
Work Completed03-13-17
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged5
Percent Time Used33
Contractor(s)
AW&E CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162001
Totals58000.730.0057411.41100.0

CountyORANGE
HighwayIH0010
FromVARIOUS
To.
CSJ6308-22-001
Proj IDSUP - 630822001
Work TypeJANITORIAL AND GROUNDS
 
0.001403580.50218955.0354.3
Work Order08-26-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged420
Percent Time Used57
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162031
Totals403580.5014374.10218955.0354.3

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-29-001
Proj IDRMC - 631029001
Work TypeINSTALLATION OF DELINEATORS
 
0.001155900.00144396.8092.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-10-17
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged47
Percent Time Used31
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6310-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172001
Totals155900.000.00144396.8092.6

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-16-001
Proj IDSUP - 631116001
Work TypeDMV GROUNDS
 
1.0005217.004662.0089.3
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162002
Totals5217.001109.004662.0089.3

CountyORANGE
HighwaySH0062
FromSH 62
ToSH 62
CSJ6311-17-001
Proj IDSUP - 631117001
Work TypeORANGE GROUNDS MAINTENANCE
 
1.0008910.006930.0077.7
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162003
Totals8910.00990.006930.0077.7

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-18-001
Proj IDSUP - 631118001
Work TypeDISTRICT GROUNDS MAINTENANCE
 
1.00040571.0040026.0098.6
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162004
Totals40571.007507.0040026.0098.6

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-19-001
Proj IDSUP - 631119001
Work TypeWOODVILLE PICNIC MAINTENANCE
 
1.00038898.7037281.76100.0
Work Order11-01-16
Work Began11-01-16
Work Completed11-01-17
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162005
Totals38898.703937.8637281.76100.0

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6311-20-001
Proj IDSUP - 631120001
Work TypeNEWTON PICNIC MAINTENANCE
 
1.00019211.9616863.54100.0
Work Order11-01-16
Work Began00-00-00
Work Completed11-01-17
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162006
Totals19211.961341.1416863.54100.0

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6311-21-001
Proj IDSUP - 631121001
Work TypeJASPER PICNIC MAINTENANCE
 
1.00015654.6013260.8084.7
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162007
Totals15654.601030.4013260.8084.7

CountyCHAMBERS
HighwaySH0073
FromVARIOUS LOCATIONS IN CHAMBERS
ToAND LIBERTY COUNTIES
CSJ6311-75-001
Proj IDBPM - 631175001
Work TypeJOINT/CONCRETE REP/CLEAN&SEAL/RAIL UPGRA
 
1.000262770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172004
Totals262770.000.000.000.0

CountyNEWTON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6312-26-001
Proj IDRMC - 631226001
Work TypeNEWTON ~ ROW MOWING
 
272.000295109.20145924.6049.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-28-17
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged19
Percent Time Used19
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172001
Totals295109.2069206.10145924.6049.9

CountyTYLER
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6312-30-001
Proj IDRMC - 631230001
Work TypeWOODVILLE ~ ROW MOWING
 
253.400317392.0085306.0026.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-19-17
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged12
Percent Time Used12
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172002
Totals317392.000.0085306.0026.8