Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyJEFFERSON
Highway US0069
From AT SPUR 93 INTERSECTION
To EAST 0.200 MILES
CSJ 6258-31-001
Proj ID EMC - 625831001
Work Type US 69 SLOPE REPAIR AND STABILIZATION
 
1.000 1933830.12 0.00 1924565.69 99.8
Work Order 12-05-13
Work Began 12-14-13
Work Completed  
Time Computed 12-09-13
Contract Working Days 32
Addl Days Granted 75
Working Days Charged 115
Percent Time Used 107
Contractor(s)
HAYWARD BAKER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-31-001
AMERICAN REMEDIATION OPTIONS, INC. (0.82%)
APAC-TEXAS, INC. (8.06%)
IOWA BRIDGE & CULVERT, LC(2.79%)
CRABTREE BARRICADE SYSTEMS, INC. (1.94%)
L.H. CHANEY TRUCKING (3.99%)
LIBERTY TEXAS TIRE RECYCLING, LLC(1.58%)
GREAT WESTERN ERECTORS ( 22.70%)
AARON CONCRETE CONTRACTORS, L.P. (2.61%)
Contract # 12132009
Totals 1933830.12 0.00 1924565.69 99.8

CountyHARDIN
Highway SH0326
From SH326 AT LITTLE PINE ISLAND BAYOU
To AND SH105 NEAR FM770
CSJ 6261-42-001
Proj ID RMC - 626142001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 213552.79 0.00 223205.30 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-29-14
Work Began 05-14-14
Work Completed 08-08-14
Time Computed 05-06-14
Contract Working Days 14
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 85
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02142002
Totals 213552.79 0.00 223205.30 100.0

CountyCHAMBERS
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6262-60-001
Proj ID SUP - 626260001
Work Type ANAHUAC ~ LITTER
 
1.000 141739.95 0.00 103082.39 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-13
Work Began 09-01-13
Work Completed 08-31-14
Time Computed 09-01-13
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 350
Percent Time Used 97
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132002
Totals 141739.95 0.00 103082.39 100.0

CountyJEFFERSON
Highway US0069
From VARIOUS
To VARIOUS
CSJ 6262-61-001
Proj ID SUP - 626261001
Work Type BEAUMONT ~ LITTER
 
1.000 144937.24 0.00 112220.54 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-13
Work Began 09-01-13
Work Completed 08-31-14
Time Computed 09-05-13
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 369
Percent Time Used 102
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6262-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132003
Totals 144937.24 0.00 112220.54 100.0

CountyJASPER
Highway US0096
From VARIOUS
To VARIOUS
CSJ 6262-62-001
Proj ID SUP - 626262001
Work Type JASPER ~ LITTER
 
1.000 105492.61 0.00 100600.37 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-30-13
Work Began 09-01-13
Work Completed 08-31-14
Time Computed 09-01-13
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 359
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6262-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132004
Totals 105492.61 0.00 100600.37 100.0

CountyLIBERTY
Highway US0090
From VARIOUS
To VARIOUS
CSJ 6262-63-001
Proj ID SUP - 626263001
Work Type LIBERTY ~ LITTER
 
1.000 244597.89 0.00 240061.89 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-13
Work Began 09-01-13
Work Completed 08-31-14
Time Computed 09-01-13
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 354
Percent Time Used 98
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132005
Totals 244597.89 0.00 240061.89 100.0

CountyNEWTON
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6262-64-001
Proj ID SUP - 626264001
Work Type NEWTON ~ LITTER
 
1.000 51512.64 0.00 45912.85 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-30-13
Work Began 09-01-13
Work Completed 08-31-14
Time Computed 09-01-13
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 356
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6262-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132006
Totals 51512.64 0.00 45912.85 100.0

CountyORANGE
Highway SH0062
From VARIOUS
To VARIOUS
CSJ 6262-65-001
Proj ID SUP - 626265001
Work Type ORANGE ~ LITTER
 
1.000 54421.94 0.00 53221.94 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-13
Work Began 09-01-13
Work Completed 08-31-14
Time Computed 09-01-13
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 347
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132007
Totals 54421.94 0.00 53221.94 100.0

CountyJEFFERSON
Highway SH0073
From VARIOUS
To VARIOUS
CSJ 6262-66-001
Proj ID SUP - 626266001
Work Type PT ARTHUR ~ LITTER
 
1.000 80541.90 0.00 68269.15 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-30-13
Work Began 09-01-13
Work Completed 08-31-14
Time Computed 09-01-13
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 360
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6262-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132008
Totals 80541.90 0.00 68269.15 100.0

CountyHARDIN
Highway US0069
From VARIOUS
To VARIOUS
CSJ 6262-67-001
Proj ID SUP - 626267001
Work Type KOUNTZE ~ LITTER
 
1.000 50080.54 0.00 44944.54 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-13
Work Began 09-01-13
Work Completed 08-31-14
Time Computed 09-01-13
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 358
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6262-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132009
Totals 50080.54 0.00 44944.54 100.0

CountyTYLER
Highway US0069
From VARIOUS
To VARIOUS
CSJ 6262-68-001
Proj ID SUP - 626268001
Work Type WOODVILLE ~ LITTER
 
1.000 59447.28 0.00 56028.16 100.0
Work Order 08-30-13
Work Began 09-01-13
Work Completed 08-31-14
Time Computed 09-01-13
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 348
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6262-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08132010
Totals 59447.28 0.00 56028.16 100.0

CountyJEFFERSON
Highway IH0010
From IH 10
To IH 10
CSJ 6263-63-001
Proj ID SUP - 626363001
Work Type LARGE DEBRIS ~ IH 10
 
1.000 268773.40 29214.50 261280.74 97.2
Work Order 11-01-13
Work Began 10-14-13
Work Completed  
Time Computed 11-04-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 363
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09132003
Totals 268773.40 29214.50 261280.74 97.2

CountyLIBERTY
Highway US0059
From SAN JACINTO COUNTY LINE
To MONTGOMERY COUNTY LINE
CSJ 6263-83-001
Proj ID SUP - 626383001
Work Type LARGE DEBRIS ~ LIBERTY
 
1.000 28183.40 2749.60 30245.60 99.9
Work Order 12-17-13
Work Began 10-01-13
Work Completed  
Time Computed 01-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 277
Percent Time Used 75
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12132011
Totals 28183.40 2749.60 30245.60 99.9

CountyJEFFERSON
Highway US0069
From US69
To US69
CSJ 6264-61-001
Proj ID SUP - 626461001
Work Type DMV GROUNDS
 
1.000 3453.25 0.00 3181.50 92.1
Work Order 10-01-13
Work Began 11-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 275
Percent Time Used 75
Contractor(s)
TIBH INDUSTRIES, INC.
UNITED SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6264-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09132006
Totals 3453.25 0.00 3181.50 92.1

CountyORANGE
Highway SH0062
From US 69
To US 69
CSJ 6265-04-001
Proj ID SUP - 626504001
Work Type ORANGE ~ GROUNDS
 
1.000 6638.50 390.50 6248.00 94.1
Work Order 10-01-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 392
Percent Time Used 107
Contractor(s)
TIBH INDUSTRIES, INC.
UNITED SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6265-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09132004
Totals 6638.50 390.50 6248.00 94.1

CountyJEFFERSON
Highway SH0073
From WESTBOUND BRIDGE
To AT MAIN "A" CANAL
CSJ 6265-47-001
Proj ID RMC - 626547001
Work Type REPLACE DAMAGED BRIDGE RAIL
 
0.135 113589.00 69434.52 110884.92 97.6
Work Order 08-25-14
Work Began 09-08-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 91
Contractor(s)
WIDGEON CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-47-001
CRABTREE BARRICADE SYSTEMS, INC. (3.63%)
Contract # 06142001
Totals 113589.00 69434.52 110884.92 97.6

CountyJEFFERSON
Highway US0069
From US 69
To US 73
CSJ 6265-64-001
Proj ID SUP - 626564001
Work Type LARE DEBRIS ~ US 69 & SH 73
 
1.000 192884.44 18559.80 185116.81 95.9
Work Order 10-11-13
Work Began 10-14-13
Work Completed  
Time Computed 10-14-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 367
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09132005
Totals 192884.44 18559.80 185116.81 95.9

CountyHARDIN
Highway US0069
From US 69
To US 69
CSJ 6265-89-001
Proj ID SUP - 626589001
Work Type KOUNTZE ~ JANITORIAL
 
1.000 5206.80 382.16 3821.60 73.3
Work Order 01-01-13
Work Began 00-00-00
Work Completed  
Time Computed 01-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 305
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6265-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12132003
Totals 5206.80 382.16 3821.60 73.3

CountyHARDIN
Highway US0069
From US 69
To US 69
CSJ 6265-98-001
Proj ID SUP - 626598001
Work Type KOUNTZE ~ BARRELS
 
1.000 10755.55 827.36 9100.89 84.6
Work Order 11-26-13
Work Began 01-01-14
Work Completed  
Time Computed 01-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6265-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12132004
Totals 10755.55 827.36 9100.89 84.6

CountyHARDIN
Highway US0069
From US 69
To US 69
CSJ 6265-99-001
Proj ID SUP - 626599001
Work Type KOUNTZE ~ GROUNDS
 
1.000 7867.30 616.06 4356.64 55.3
Work Order 11-25-13
Work Began 01-01-14
Work Completed  
Time Computed 01-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6265-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12132005
Totals 7867.30 616.06 4356.64 55.3