Monthly Local Let Maintenance Report For Beaumont District As Of Jul 14, 2017 Page 3 Of 4

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyORANGE
HighwaySH0062
FromVARIOUS
ToVARIOUS
CSJ6306-55-001
Proj IDSUP - 630655001
Work TypeORANGE LITTER
 
1.00087470.3464960.5574.2
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162004
Totals87470.346028.8364960.5574.2

CountyJEFFERSON
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6306-56-001
Proj IDSUP - 630656001
Work TypePORT ARTHUR LITTER
 
1.00095339.0866743.0770.0
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6306-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162008
Totals95339.089959.9166743.0770.0

CountyHARDIN
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6306-57-001
Proj IDSUP - 630657001
Work TypeKOUNTZE LITTER
 
1.00079140.5264788.8181.8
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162005
Totals79140.520.0064788.8181.8

CountyTYLER
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6306-58-001
Proj IDSUP - 630658001
Work TypeWOODVILLE LITTER
 
1.00046758.0226878.0057.4
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6306-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162012
Totals46758.020.0026878.0057.4

CountyLIBERTY
HighwayUS0059
FromUS 59 IN LIBERTY COUNTY
ToUS 59 IN LIBERTY COUNTY
CSJ6307-58-001
Proj IDRMC - 630758001
Work TypeOVERLAY OF EXISTING ROADWAYS
 
1.000192805.00386584.88100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-30-17
Work Completed07-10-17
Time Computed00-00-00
Contract Working Days23
Addl Days Granted0
Working Days Charged23
Percent Time Used100
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6307-58-001
REPUBLIC TRAFFIC SAFETY, INC. (3678.34)
Contract #12162001
Totals192805.000.00386584.88100.0

CountyJASPER
HighwayUS0096
FromVARIOUS ROADWAYS IN JASPER, TYLER
ToAND NEWTON CO.
CSJ6307-89-001
Proj IDRMC - 630789001
Work TypeUS 96 ETC., CRACK SEAL
 
90.01658000.7357411.41100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-09-17
Work Completed03-13-17
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged5
Percent Time Used33
Contractor(s)
AW&E CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162001
Totals58000.730.0057411.41100.0

CountyORANGE
HighwayIH0010
FromVARIOUS
To.
CSJ6308-22-001
Proj IDSUP - 630822001
Work TypeJANITORIAL AND GROUNDS
 
0.001403580.50167263.5541.5
Work Order08-26-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged303
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162031
Totals403580.5016585.50167263.5541.5

CountyJEFFERSON
HighwaySH0347
FromSH 347
ToSH 347
CSJ6308-44-001
Proj IDSUP - 630844001
Work TypePORT ARTHUR GROUNDS
 
1.00024000.0013200.0055.0
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162009
Totals24000.002400.0013200.0055.0

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-29-001
Proj IDRMC - 631029001
Work TypeINSTALLATION OF DELINEATORS
 
0.001155900.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-10-17
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6310-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172001
Totals155900.000.000.000.0

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-16-001
Proj IDSUP - 631116001
Work TypeDMV GROUNDS
 
1.0005217.002239.0042.9
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162002
Totals5217.00623.002239.0042.9

CountyORANGE
HighwaySH0062
FromSH 62
ToSH 62
CSJ6311-17-001
Proj IDSUP - 631117001
Work TypeORANGE GROUNDS MAINTENANCE
 
1.0008910.003465.0038.8
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162003
Totals8910.00990.003465.0038.8

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-18-001
Proj IDSUP - 631118001
Work TypeDISTRICT GROUNDS MAINTENANCE
 
1.00040571.0020822.0051.3
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162004
Totals40571.005724.0020822.0051.3

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-19-001
Proj IDSUP - 631119001
Work TypeWOODVILLE PICNIC MAINTENANCE
 
1.00038898.7021839.5056.1
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162005
Totals38898.702437.8621839.5056.1

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6311-20-001
Proj IDSUP - 631120001
Work TypeNEWTON PICNIC MAINTENANCE
 
1.00019211.9610360.7053.9
Work Order11-01-16
Work Began00-00-00
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162006
Totals19211.961341.1410360.7053.9

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6311-21-001
Proj IDSUP - 631121001
Work TypeJASPER PICNIC MAINTENANCE
 
1.00015654.608110.4051.8
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged270
Percent Time Used73
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162007
Totals15654.601030.408110.4051.8

CountyCHAMBERS
HighwaySH0073
FromVARIOUS LOCATIONS IN CHAMBERS
ToAND LIBERTY COUNTIES
CSJ6311-75-001
Proj IDBPM - 631175001
Work TypeJOINT/CONCRETE REP/CLEAN&SEAL/RAIL UPGRA
 
1.000262770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172004
Totals262770.000.000.000.0

CountyNEWTON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6312-26-001
Proj IDRMC - 631226001
Work TypeNEWTON ~ ROW MOWING
 
272.000295109.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-28-17
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172001
Totals295109.200.000.000.0

CountyTYLER
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6312-30-001
Proj IDRMC - 631230001
Work TypeWOODVILLE ~ ROW MOWING
 
253.400317392.0073340.0023.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-19-17
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged8
Percent Time Used8
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172002
Totals317392.0073340.0073340.0023.1

CountyJEFFERSON
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6312-31-001
Proj IDRMC - 631231001
Work TypeBEAUMONT MAINTENANCE ROW MOWING
 
208.000338025.0060075.0017.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-30-17
Work Completed
Time Computed00-00-00
Contract Working Days154
Addl Days Granted0
Working Days Charged13
Percent Time Used8
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172003
Totals338025.0060075.0060075.0017.7

CountyHARDIN
HighwayUS0069
FromUS 69
ToUS 69
CSJ6313-29-001
Proj IDSUP - 631329001
Work TypeKOUNTZE BARRELS
 
1.00011310.003654.0032.3
Work Order01-01-17
Work Began01-01-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6313-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12162003
Totals11310.00696.003654.0032.3

page 1 | page 2 | page 3 | page 4