Monthly Local Let Maintenance Report For Beaumont District As Of Aug 11, 2017 Page 3 Of 4

Last Update: Friday, August 11, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyORANGE
HighwayIH0010
FromVARIOUS
To.
CSJ6308-22-001
Proj IDSUP - 630822001
Work TypeJANITORIAL AND GROUNDS
 
0.001403580.50184401.9045.7
Work Order08-26-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged334
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162031
Totals403580.5017138.35184401.9045.7

CountyJEFFERSON
HighwaySH0347
FromSH 347
ToSH 347
CSJ6308-44-001
Proj IDSUP - 630844001
Work TypePORT ARTHUR GROUNDS
 
1.00024000.0015600.0065.0
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162009
Totals24000.002400.0015600.0065.0

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-29-001
Proj IDRMC - 631029001
Work TypeINSTALLATION OF DELINEATORS
 
0.001155900.00109892.8070.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-10-17
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged22
Percent Time Used14
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6310-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172001
Totals155900.00109892.80109892.8070.4

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-16-001
Proj IDSUP - 631116001
Work TypeDMV GROUNDS
 
1.0005217.002862.0054.8
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162002
Totals5217.00623.002862.0054.8

CountyORANGE
HighwaySH0062
FromSH 62
ToSH 62
CSJ6311-17-001
Proj IDSUP - 631117001
Work TypeORANGE GROUNDS MAINTENANCE
 
1.0008910.004455.0050.0
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162003
Totals8910.00990.004455.0050.0

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-18-001
Proj IDSUP - 631118001
Work TypeDISTRICT GROUNDS MAINTENANCE
 
1.00040571.0026546.0065.4
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162004
Totals40571.005724.0026546.0065.4

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-19-001
Proj IDSUP - 631119001
Work TypeWOODVILLE PICNIC MAINTENANCE
 
1.00038898.7025674.3066.0
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162005
Totals38898.703834.8025674.3066.0

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6311-20-001
Proj IDSUP - 631120001
Work TypeNEWTON PICNIC MAINTENANCE
 
1.00019211.9612270.9863.8
Work Order11-01-16
Work Began00-00-00
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162006
Totals19211.961910.2812270.9863.8

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6311-21-001
Proj IDSUP - 631121001
Work TypeJASPER PICNIC MAINTENANCE
 
1.00015654.609655.2061.6
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged301
Percent Time Used82
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162007
Totals15654.601544.809655.2061.6

CountyCHAMBERS
HighwaySH0073
FromVARIOUS LOCATIONS IN CHAMBERS
ToAND LIBERTY COUNTIES
CSJ6311-75-001
Proj IDBPM - 631175001
Work TypeJOINT/CONCRETE REP/CLEAN&SEAL/RAIL UPGRA
 
1.000262770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172004
Totals262770.000.000.000.0

CountyNEWTON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6312-26-001
Proj IDRMC - 631226001
Work TypeNEWTON ~ ROW MOWING
 
272.000295109.2070792.1023.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-28-17
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged11
Percent Time Used11
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172001
Totals295109.2070792.1070792.1023.9

CountyTYLER
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6312-30-001
Proj IDRMC - 631230001
Work TypeWOODVILLE ~ ROW MOWING
 
253.400317392.0073340.0023.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-19-17
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged8
Percent Time Used8
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172002
Totals317392.000.0073340.0023.1

CountyJEFFERSON
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6312-31-001
Proj IDRMC - 631231001
Work TypeBEAUMONT MAINTENANCE ROW MOWING
 
208.000338025.0060075.0017.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-30-17
Work Completed
Time Computed00-00-00
Contract Working Days154
Addl Days Granted0
Working Days Charged13
Percent Time Used8
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172003
Totals338025.000.0060075.0017.7

CountyHARDIN
HighwayUS0069
FromUS 69
ToUS 69
CSJ6313-29-001
Proj IDSUP - 631329001
Work TypeKOUNTZE BARRELS
 
1.00011310.004350.0038.4
Work Order01-01-17
Work Began01-01-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6313-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12162003
Totals11310.00696.004350.0038.4

CountyHARDIN
HighwayUS0069
FromUS 69
ToUS 69
CSJ6313-30-001
Proj IDSUP - 631330001
Work TypeKOUNTZE GROUNDS
 
1.0008229.003059.0037.1
Work Order01-01-17
Work Began01-01-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6313-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12162004
Totals8229.00874.003059.0037.1

CountyHARDIN
HighwayUS0069
FromUS 69
ToUS 69
CSJ6313-31-001
Proj IDSUP - 631331001
Work TypeKOUNTZE JANITORIAL
 
1.0005476.003466.0063.2
Work Order01-01-17
Work Began01-01-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6313-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12162002
Totals5476.00402.003466.0063.2

CountyLIBERTY
HighwaySH0105
FromVARIOUS ROADWAYS IN LIBERTY AND
ToCHAMBERS COUNTIES
CSJ6313-40-001
Proj IDRMC - 631340001
Work TypeSH 105 ETC., CRACK SEAL
 
25.68034854.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6313-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07172001
Totals34854.480.000.000.0

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6313-87-001
Proj IDSUP - 631387001
Work TypeBEAUMONT AO MO JANITORIAL
 
1.0008603.062845.1033.0
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged163
Percent Time Used44
Contractor(s)
TIBH INDUSTRIES, INC.
UNITED SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6313-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01172001
Totals8603.06569.022845.1033.0

CountyJEFFERSON
HighwayIH0010
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6314-11-001
Proj IDRMC - 631411001
Work TypeCABLE BARRIER REPAIR
 
0.001217150.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05172001
Totals217150.000.000.000.0

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6314-17-001
Proj IDSUP - 631417001
Work TypeWOODVILLE JANITORIAL
 
1.0004476.002238.0050.0
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged181
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6314-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01172002
Totals4476.00373.002238.0050.0

page 1 | page 2 | page 3 | page 4