Monthly State Let Construction Report For Beaumont District As Of Sep 15, 2016 Page 3 Of 3

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyJEFFERSON
Highway CS
From BLOCK STREET
To LLANO STREET, IN PORT NECHES
CSJ 0920-38-254
Proj ID STP 2014(096)TE
Work Type GR, BS, PVMT, LNDSCP
 
0.303 749492.52 0.00 691547.90 92.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-26-16
Work Began 04-25-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 25
Working Days Charged 62
Percent Time Used 66
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-38-254
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(8.61%)
CRABTREE BARRICADE SYSTEMS, INC. (2.83%)
JE CASEY, LLC(1.37%)
Contract # 08153266
Totals 749492.52 0.00 691547.90 92.2

CountyJEFFERSON
Highway PW
From AT JD MURPHREE WMA
To .
CSJ 0920-38-255
Proj ID C 920-38-255
Work Type OCST, ACP
 
0.193 55175.45 0.00 55719.60 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-07-15
Work Began 04-06-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 7
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 42
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-38-255
AMERICAN REMEDIATION OPTIONS, INC. (1.64%)
CRABTREE BARRICADE SYSTEMS, INC. (1.71%)
Contract # 12143231
Totals 55175.45 0.00 55719.60 99.9

CountyJEFFERSON
Highway FM 365
From AT GROUND GULLY
To .
CSJ 0932-02-053
Proj ID BR 1502(424)
Work Type REPLACE BRIDGE AND APPROACHES
 
1.036 1565852.57 0.00 169398.35 10.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0932-02-053
AMERICAN REMEDIATION OPTIONS, INC. (3.62%)
CRABTREE BARRICADE SYSTEMS, INC. (1.61%)
DUSTROL, INC.(0.91%)
HEMPHILL PILE DRIVING CO., A CORP. (5.03%)
CPAVE, INC.(0.17%)
HOUSTON SAWING & DRILLING(0.22%)
Contract # 08153263
Totals 1565852.57 0.00 169398.35 10.8

CountyJEFFERSON
Highway FM 365
From AT GREEN POND GULLY
To .
CSJ 0932-02-054
Proj ID BR 1502(425)
Work Type REPLACE BRIDGE AND APPROACHES
 
1.025 1196548.36 0.00 955463.11 79.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 01-04-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 21
Working Days Charged 89
Percent Time Used 100
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0932-02-054
AMERICAN REMEDIATION OPTIONS, INC. (4.53%)
CRABTREE BARRICADE SYSTEMS, INC. (2.06%)
DUSTROL, INC.(0.96%)
HEMPHILL PILE DRIVING CO., A CORP. (5.60%)
HOUSTON SAWING & DRILLING(0.23%)
CPAVE, INC.(0.22%)
Contract # 08153264
Totals 1196548.36 0.00 955463.11 79.8

CountyJEFFERSON
Highway FM 365
From 0.2 MILES EAST OF IH 10, EAST
To SH 124
CSJ 0932-02-055
Proj ID STP 2016(957)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
0.960 400896.15 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-13-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EXCAVATION & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0932-02-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163026
Totals 400896.15 0.00 0.00 0.0

CountyJASPER
Highway FM 1004
From US 96 AT CALL JUNCTION
To 2.5 MILES W OF US 96
CSJ 0947-03-029
Proj ID SSW 947-3-29
Work Type ADDITIONAL PAVED SURFACE WIDTH
 
2.500 1120934.72 0.00 936563.31 83.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-15
Work Began 02-24-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 3
Working Days Charged 56
Percent Time Used 71
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0947-03-029
AMERICAN REMEDIATION OPTIONS, INC. (1.85%)
CRABTREE BARRICADE SYSTEMS, INC. (2.29%)
Contract # 08153032
Totals 1120934.72 0.00 936563.31 83.5

CountyCHAMBERS
Highway FM 1405
From FM 565, SOUTH
To 1.28 MILES SOUTH OF SH 99
CSJ 1024-02-044
Proj ID STP 1502(426)
Work Type BS, PVMT, STRIPE
 
5.116 10486302.45 0.00 8154771.48 77.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-16-16
Work Began 03-14-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 143
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 73
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1024-02-044
CRABTREE BARRICADE SYSTEMS, INC. (1.93%)
WILLOW CITY SIGN & RAIL, INC.(1.20%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.47%)
CPAVE, INC.(2.34%)
Contract # 08153059
Totals 10486302.45 0.00 8154771.48 77.7

CountyLIBERTY
Highway FM 686
From CR 623
To 0.083 MI W OF CR 621
CSJ 1067-01-026
Proj ID SSW 1067-1-26
Work Type GR, BASE, PAV, STRIPE
 
2.950 1690130.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-11-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1067-01-026
STRIPE LINES, INC. (1.61%)
Contract # 07163034
Totals 1690130.30 0.00 0.00 0.0

CountyLIBERTY
Highway FM 770
From HARDIN C/L
To 0.5 MI N OF FM 834
CSJ 1096-02-050
Proj ID STP 1502(230)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
2.111 1023264.24 0.00 997538.49 97.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-15
Work Began 10-14-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 81
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1096-02-050
J & M CONTRACTING, COMPANY ( 22.69%)
WATERS CONSTRUCTION CO., INC.(6.96%)
WILLOW CITY SIGN & RAIL, INC.(3.69%)
A1 EROSION CONTROL (0.55%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.80%)
COWBELL TRAFFIC SERVICES, INC. (0.63%)
Contract # 06153236
Totals 1023264.24 0.00 997538.49 97.4

CountyJASPER
Highway FM 1007
From US 96
To RE 255
CSJ 1276-01-020
Proj ID STP 1502(231)HES
Work Type PROVIDE ADDITIONAL WIDTH, TEXTURE
 
4.652 1655300.24 0.00 488440.10 29.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 03-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 47
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1276-01-020
AMERICAN REMEDIATION OPTIONS, INC. (6.28%)
CRABTREE BARRICADE SYSTEMS, INC. (3.04%)
NORMAN HIGHWAY CONSTRUCTORS, INC.(2.16%)
WEST TEXAS RUMBLE STRIP(0.36%)
Contract # 08153257
Totals 1655300.24 0.00 488440.10 29.5

CountyNEWTON
Highway FM 1012
From AT BIG COW CREEK
To (STR 127701004)
CSJ 1277-01-015
Proj ID BR 2016(411)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.150 1777740.74 0.00 559237.96 31.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 05-03-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 56
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1277-01-015
AMERICAN REMEDIATION OPTIONS, INC. (3.73%)
CRABTREE BARRICADE SYSTEMS, INC. (0.70%)
PANOLA SIGN & BARRICADE, INC.(0.40%)
TEXOP CONSTRUCTION (0.39%)
MAC TRANSPORTATION, LTD, L.L.P.(0.80%)
Contract # 02163228
Totals 1777740.74 0.00 559237.96 31.4

CountyORANGE
Highway FM 1130
From KCS RR, EAST
To 1 MI N OF FM 3247
CSJ 1284-01-070
Proj ID STP 1502(182)
Work Type REWORK BASE, FB, 2 CST
 
6.382 2917601.83 154213.74 2641294.48 91.0
Work Order 07-14-15
Work Began 11-10-15
Work Completed  
Time Computed 11-10-15
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 120
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1284-01-070
AMERICAN REMEDIATION OPTIONS, INC. (4.33%)
CRABTREE BARRICADE SYSTEMS, INC. (2.65%)
WEST TEXAS RUMBLE STRIP(0.35%)
J & M CONTRACTING, COMPANY ( 11.24%)
CPAVE, INC.(0.41%)
WEBBER BARRIER SERVICES, LLC.(0.66%)
Contract # 05153236
Totals 2917601.83 154213.74 2641294.48 91.0

CountyORANGE
Highway FM 1130
From FM 1136
To 10.7 MI SOUTHEAST
CSJ 1284-01-072
Proj ID STP 1602(067)HES
Work Type SFTY TRT FXD OBJ
 
10.709 461438.96 0.00 2600.00 0.5
CountyORANGE
Highway FM 1136
From FM 1442
To IH 10
CSJ 1285-01-017
Proj ID STP 1602(066)HES
Work Type SFTY TRT FXD OBJ
 
4.658 374816.84 0.00 2600.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-22-16
Work Began 08-29-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORMAN HIGHWAY CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1284-01-072
AMERICAN REMEDIATION OPTIONS, INC. ( 12.03%)
CRABTREE BARRICADE SYSTEMS, INC. (2.12%)
Contract # 05163005
Totals 836255.80 0.00 5200.00 0.6

CountyJEFFERSON
Highway FM 1406
From AT VOGEL GULLY
To .
CSJ 1324-01-020
Proj ID BR 1502(427)
Work Type REPLACE BRIDGE AND APPROACHES
 
1.031 994488.34 0.00 646627.16 66.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-15
Work Began 01-04-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 136
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1324-01-020
AMERICAN REMEDIATION OPTIONS, INC. (6.82%)
CRABTREE BARRICADE SYSTEMS, INC. (2.65%)
DUSTROL, INC.(1.24%)
HEMPHILL PILE DRIVING CO., A CORP. (4.83%)
CPAVE, INC.(0.17%)
HOUSTON SAWING & DRILLING(0.25%)
Contract # 08153265
Totals 994488.34 0.00 646627.16 66.4

CountyLIBERTY
Highway FM 1413
From US 90
To UP RR
CSJ 1421-01-024
Proj ID STP 2013(923)
Work Type GR, BS, STR, PVT.
 
4.555 2173548.35 0.00 2368599.44 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-22-14
Work Began 05-06-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 120
Addl Days Granted 28
Working Days Charged 172
Percent Time Used 116
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1421-01-024
AMERICAN REMEDIATION OPTIONS, INC. (2.16%)
CRABTREE BARRICADE SYSTEMS, INC. (1.69%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.86%)
J & M CONTRACTING, COMPANY (0.71%)
Contract # 08133050
Totals 2173548.35 0.00 2368599.44 99.9

CountyNEWTON
Highway FM 2460
From SH 87
To FM 1416
CSJ 1949-01-016
Proj ID STP 1502(232)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
6.161 1301346.31 0.00 796342.51 61.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 01-06-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 159
Addl Days Granted 3
Working Days Charged 97
Percent Time Used 59
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1949-01-016
AMERICAN REMEDIATION OPTIONS, INC. (2.87%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.09%)
CRABTREE BARRICADE SYSTEMS, INC. (4.31%)
WEST TEXAS RUMBLE STRIP(0.34%)
WIDGEON CONSTRUCTION, INC. ( 30.09%)
Contract # 08153259
Totals 1301346.31 0.00 796342.51 61.1

CountyLIBERTY
Highway FM 2830
From 2.2 MILES NORTH OF FM 160
To FM 160
CSJ 2887-01-012
Proj ID STP 2016(958)HES
Work Type PROVIDE ADDITIONAL WIDTH, CL TXT
 
2.200 999523.59 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-03-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2887-01-012
WATERS CONSTRUCTION CO., INC.(6.29%)
WILLOW CITY SIGN & RAIL, INC.(1.46%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.91%)
A-1 EROSION CONTROL, LLC (0.54%)
Contract # 04163206
Totals 999523.59 0.00 0.00 0.0

CountyCHAMBERS
Highway FM 3180
From 0.52 MILES NORTH OF FM 565, SOUTH
To 0.60 MILES SOUTH OF FM 565
CSJ 3271-01-011
Proj ID STP 2016(959)
Work Type BS, GR, ACP, STR, STRIPE, SIGN
 
1.062 6439873.51 0.00 1044475.83 16.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-17-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 9
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 3271-01-011
THIRD COAST SERVICES LLC (4.36%)
STRIPE LINES, INC. (1.13%)
J&M CONTRACTING COMPANY( 13.99%)
WILLOW CITY SIGN & RAIL, INC.(0.52%)
J & M CONTRACTING, COMPANY ( 13.99%)
Contract # 04163009
Totals 6439873.51 0.00 1044475.83 16.2

page 1 | page 2 | page 3