Monthly State Let Construction Report For Beaumont District As Of Feb 10, 2017 Page 3 Of 3

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJEFFERSON
HighwayFM 365
FromAT GROUND GULLY
To.
CSJ0932-02-053
Proj IDBR 1502(424)
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.0361565852.57837448.7553.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-12-15
Work Began10-26-16
Work Completed
Time Computed00-00-00
Contract Working Days89
Addl Days Granted0
Working Days Charged50
Percent Time Used56
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0932-02-053
AMERICAN REMEDIATION OPTIONS, INC. (3.62)
CRABTREE BARRICADE SYSTEMS, INC. (1.61)
DUSTROL, INC. (0.91)
HEMPHILL PILE DRIVING CO., A CORP. (5.03)
CPAVE, INC. (0.17)
HOUSTON SAWING & DRILLING (0.22)
Contract #08153263
Totals1565852.570.00837448.7553.4

CountyJEFFERSON
HighwayFM 365
From0.2 MILES EAST OF IH 10, EAST
ToSH 124
CSJ0932-02-055
Proj IDSTP 2016(957)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
0.960400896.15305769.1279.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-13-16
Work Began10-06-16
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged65
Percent Time Used144
Contractor(s)
EXCAVATION & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0932-02-055
AMERICAN REMEDIATION OPTIONS, INC. (10.47)
CRABTREE BARRICADE SYSTEMS, INC. (1.25)
Contract #04163026
Totals400896.150.00305769.1279.2

CountyJASPER
HighwayFM 1004
FromUS 96 AT CALL JUNCTION
To2.5 MILES W OF US 96
CSJ0947-03-029
Proj IDSSW 947-3-29
Work TypeADDITIONAL PAVED SURFACE WIDTH
 
2.5001120934.721094675.5697.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-28-15
Work Began02-24-16
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted3
Working Days Charged74
Percent Time Used94
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0947-03-029
AMERICAN REMEDIATION OPTIONS, INC. (1.85)
CRABTREE BARRICADE SYSTEMS, INC. (2.29)
Contract #08153032
Totals1120934.720.001094675.5697.6

CountyCHAMBERS
HighwayFM 1405
FromFM 565, SOUTH
To1.28 MILES SOUTH OF SH 99
CSJ1024-02-044
Proj IDSTP 1502(426)
Work TypeBS, PVMT, STRIPE
 
5.11610486302.459838621.6893.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-16
Work Began03-14-16
Work Completed
Time Computed00-00-00
Contract Working Days143
Addl Days Granted0
Working Days Charged155
Percent Time Used108
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1024-02-044
CRABTREE BARRICADE SYSTEMS, INC. (1.93)
WILLOW CITY SIGN & RAIL, INC. (1.20)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.47)
CPAVE, INC. (2.34)
Contract #08153059
Totals10486302.450.009838621.6893.9

CountyLIBERTY
HighwayFM 686
FromCR 623
To0.083 MI W OF CR 621
CSJ1067-01-026
Proj IDSSW 1067-1-26
Work TypeGR,BASE, PAV, STRIPE
 
2.9501690130.301447444.8685.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-16
Work Began09-12-16
Work Completed
Time Computed00-00-00
Contract Working Days84
Addl Days Granted0
Working Days Charged74
Percent Time Used88
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1067-01-026
STRIPE LINES, INC. (1.61)
Contract #07163034
Totals1690130.300.001447444.8685.6

CountyJASPER
HighwayFM 777
FromUS 190 (WEST)
To5 MILES SOUTH OF US 190 (WEST)
CSJ1109-01-023
Proj IDSTP 2017(626)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
5.000368813.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORMAN HIGHWAY CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1109-01-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173207
Totals368813.000.000.000.0

CountyNEWTON
HighwayFM 1012
FromAT BIG COW CREEK
To(STR 127701004)
CSJ1277-01-015
Proj IDBR 2016(411)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1501777740.741443174.2083.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-03-16
Work Completed
Time Computed00-00-00
Contract Working Days101
Addl Days Granted16
Working Days Charged156
Percent Time Used133
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1277-01-015
AMERICAN REMEDIATION OPTIONS, INC. (3.73)
CRABTREE BARRICADE SYSTEMS, INC. (0.70)
PANOLA SIGN & BARRICADE, INC. (0.40)
TEXOP CONSTRUCTION (0.39)
MAC TRANSPORTATION, LTD, L.L.P. (0.80)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.13)
Contract #02163228
Totals1777740.740.001443174.2083.1

CountyORANGE
HighwayFM 1130
FromKCS RR, EAST
To1 MI N OF FM 3247
CSJ1284-01-070
Proj IDSTP 1502(182)
Work TypeREWORK BASE, FB, 2 CST
 
6.3822917601.833101913.1499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-14-15
Work Began11-10-15
Work Completed
Time Computed11-10-15
Contract Working Days90
Addl Days Granted0
Working Days Charged115
Percent Time Used127
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1284-01-070
AMERICAN REMEDIATION OPTIONS, INC. (4.33)
CRABTREE BARRICADE SYSTEMS, INC. (2.65)
WEST TEXAS RUMBLE STRIP (0.35)
J & M CONTRACTING, COMPANY (11.24)
CPAVE, INC. (0.41)
WEBBER BARRIER SERVICES, LLC. (0.66)
Contract #05153236
Totals2917601.830.003101913.1499.9

CountyORANGE
HighwayFM 1130
FromFM 1136
To10.7 MI SOUTHEAST
CSJ1284-01-072
Proj IDSTP 1602(067)HES
Work TypeSFTY TRT FXD OBJ
 
10.709461438.96340944.0073.8
CountyORANGE
HighwayFM 1136
FromFM 1442
ToIH 10
CSJ1285-01-017
Proj IDSTP 1602(066)HES
Work TypeSFTY TRT FXD OBJ
 
4.658374816.84278451.0074.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-22-16
Work Began08-29-16
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted3
Working Days Charged56
Percent Time Used60
Contractor(s)
NORMAN HIGHWAY CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1284-01-072
AMERICAN REMEDIATION OPTIONS, INC. (12.03)
CRABTREE BARRICADE SYSTEMS, INC. (2.12)
Contract #05163005
Totals836255.800.00619395.0074.0

CountyJEFFERSON
HighwayFM 1406
FromAT VOGEL GULLY
To.
CSJ1324-01-020
Proj IDBR 1502(427)
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.031994488.341132522.3199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-28-15
Work Began01-04-16
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted19
Working Days Charged159
Percent Time Used193
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1324-01-020
AMERICAN REMEDIATION OPTIONS, INC. (6.82)
CRABTREE BARRICADE SYSTEMS, INC. (2.65)
DUSTROL, INC. (1.24)
HEMPHILL PILE DRIVING CO., A CORP. (4.83)
CPAVE, INC. (0.17)
HOUSTON SAWING & DRILLING (0.25)
WIDGEON CONSTRUCTION, INC. (4.44)
Contract #08153265
Totals994488.340.001132522.3199.9

CountyLIBERTY
HighwayFM 1413
FromUS 90
ToUP RR
CSJ1421-01-024
Proj IDSTP 2013(923)
Work TypeGR, BS, STR, PVT.
 
4.5552173548.352368599.4499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-22-14
Work Began05-06-14
Work Completed
Time Computed03-01-14
Contract Working Days120
Addl Days Granted28
Working Days Charged172
Percent Time Used116
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1421-01-024
AMERICAN REMEDIATION OPTIONS, INC. (2.16)
CRABTREE BARRICADE SYSTEMS, INC. (1.69)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (0.86)
J & M CONTRACTING, COMPANY (0.71)
Contract #08133050
Totals2173548.350.002368599.4499.9

CountyNEWTON
HighwayFM 2460
FromSH 87
ToFM 1416
CSJ1949-01-016
Proj IDSTP 1502(232)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
6.1611301346.311248943.7595.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-12-15
Work Began01-06-16
Work Completed
Time Computed00-00-00
Contract Working Days159
Addl Days Granted4
Working Days Charged134
Percent Time Used82
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1949-01-016
AMERICAN REMEDIATION OPTIONS, INC. (2.87)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (0.09)
CRABTREE BARRICADE SYSTEMS, INC. (4.31)
WEST TEXAS RUMBLE STRIP (0.34)
WIDGEON CONSTRUCTION, INC. (30.09)
Contract #08153259
Totals1301346.310.001248943.7595.9

CountyCHAMBERS
HighwayFM 3180
From0.52 MILES NORTH OF FM 565, SOUTH
To0.60 MILES SOUTH OF FM 565
CSJ3271-01-011
Proj IDSTP 2016(959)
Work TypeBS, GR, ACP, STR, STRIPE, SIGN
 
1.0626439873.513160918.5549.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-16
Work Began07-18-16
Work Completed
Time Computed00-00-00
Contract Working Days212
Addl Days Granted4
Working Days Charged112
Percent Time Used51
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 3271-01-011
THIRD COAST SERVICES LLC (4.36)
STRIPE LINES, INC. (1.13)
J&M CONTRACTING COMPANY (13.99)
WILLOW CITY SIGN & RAIL, INC. (0.52)
J & M CONTRACTING, COMPANY (13.99)
SEMARCK LANDSCAPE SERVICES, INC. (0.50)
Contract #04163009
Totals6439873.510.003160918.5549.0

page 1 | page 2 | page 3