Monthly State Let Construction Report For Beaumont District As Of Sep 15, 2014 Page 2 Of 2

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyNEWTON
Highway SH 12
From NEWTON CO/L
To SH 87
CSJ 0499-02-029
Proj ID STP 2014(593)
Work Type PLANE, SMA, STRIPE
 
3.094 1990411.83 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-07-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 31
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0499-02-029
CPAVE, INC.(2.76%)
DUSTROL, INC.(9.83%)
CRABTREE BARRICADE SYSTEMS, INC. (1.56%)
Contract # 04143014
Totals 1990411.83 0.00 0.00 0.0

CountyORANGE
Highway SH 12
From SH 62
To NEWTON CO/L
CSJ 0499-03-057
Proj ID STP 2014(803)
Work Type PLANE, SMA, STRIPE
 
3.859 2279714.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-07-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0499-03-057
DUSTROL, INC.( 10.11%)
CRABTREE BARRICADE SYSTEMS, INC. (1.56%)
Contract # 04143232
Totals 2279714.00 0.00 0.00 0.0

CountyJEFFERSON
Highway SP 215
From SH 73, EAST
To 0.794 MI W OF SH 87
CSJ 0508-06-020
Proj ID STP 2014(509)
Work Type FDR, BS, MILL, OVERLAY
 
1.371 1979708.80 17525.00 413516.10 20.8
Work Order 04-02-14
Work Began 05-02-14
Work Completed  
Time Computed 04-18-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 90
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-06-020
AMERICAN REMEDIATION OPTIONS, INC. (6.15%)
CRABTREE BARRICADE SYSTEMS, INC. (1.57%)
CPAVE, INC.( 24.56%)
DUSTROL, INC.(4.06%)
PINNACLE GRINDING & GROOVING, LLC(4.03%)
Contract # 02143031
Totals 1979708.80 17525.00 413516.10 20.8

CountyJEFFERSON
Highway SP 136
From 0.65 MILES NORTH OF SH 347
To 0.61 MILES NORTH
CSJ 0653-01-013
Proj ID CM 2014(843)
Work Type GR, BS, STR, PVMT
 
0.610 569227.19 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-14
Work Began 00-00-00
Work Completed  
Time Computed 09-05-14
Contract Working Days 87
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0653-01-013
AMERICAN REMEDIATION OPTIONS, INC. (0.36%)
CRABTREE BARRICADE SYSTEMS, INC. (6.01%)
Contract # 06143045
Totals 569227.19 0.00 0.00 0.0

CountyCHAMBERS
Highway IH 10
From 0.210 MI WEST OF FM 1663, EAST
To JEFFERSON CO/L
CSJ 0739-01-045
Proj ID IM 0108(176)
Work Type PLANE, MBGF, PFC
 
2.528 1179835.95 0.00 1094396.91 96.6
CountyJEFFERSON
Highway IH 10
From CHAMBERS CO/L, EAST
To 0.65 MI E OF FM 365
CSJ 0739-02-147
Proj ID IM 0108(176)
Work Type PLANE, MBGF, PFC, UPGRADE BRIDGE RAIL
 
8.022 3506970.90 0.00 3630570.18 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-13
Work Began 08-04-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 218
Percent Time Used 127
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0739-01-045
WILLOW CITY SIGN & RAIL, INC.(4.20%)
CRABTREE BARRICADE SYSTEMS, INC. (2.62%)
SEMARCK LANDSCAPE SERVICES, INC. (0.09%)
CHEROKEE SERVICES(1.32%)
Contract # 02133208
Totals 4686806.85 0.00 4724967.09 99.9

CountyLIBERTY
Highway FM 787
From AT TARKINGTON BAYOU
To (STR 081301009)
CSJ 0813-01-096
Proj ID BR 2013(921)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 1341288.27 74628.06 845547.55 63.0
Work Order 01-06-14
Work Began 02-14-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 184
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 54
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0813-01-096
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 14.91%)
EROSION CONTROL, INC.(0.11%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.44%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.02%)
ROZCO CONTRACTING, INC.( 46.48%)
MESA ROD BUSTERS, INC. (0.30%)
JOHN REED AND COMPANY, LLC ( 40.30%)
Contract # 08133243
Totals 1341288.27 74628.06 845547.55 63.0

CountyJEFFERSON
Highway VA
From DISTRICTWIDE
To .
CSJ 0920-00-111
Proj ID STP 2013(710)
Work Type LANDSCAPE
 
1.000 432659.00 1000.00 377728.77 87.7
Work Order 08-08-13
Work Began 12-04-13
Work Completed  
Time Computed 11-04-13
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 105
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-111
CRABTREE BARRICADE SYSTEMS, INC. (2.09%)
Contract # 05133223
Totals 432659.00 1000.00 377728.77 87.7

CountyJEFFERSON
Highway VA
From DISTRICTWIDE
To .
CSJ 0920-00-116
Proj ID STP 2014(646)
Work Type LANDSCAPE
 
3.428 832522.01 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 219
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-116
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143219
Totals 832522.01 0.00 0.00 0.0

CountyLIBERTY
Highway CR
From CR 2331 AT LONG JOHN CREEK
To (STR AA2331001)
CSJ 0920-02-087
Proj ID BR 2014(255)
Work Type GR, BS, STR, PVMT
 
0.100 529670.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-14
Work Began 00-00-00
Work Completed  
Time Computed 09-05-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-02-087
STRIPES & STOPS COMPANY, INC.(1.13%)
FORDE CONSTRUCTION COMPANY, INC. (5.85%)
Contract # 07143229
Totals 529670.95 0.00 0.00 0.0

CountyHARDIN
Highway VA
From BIG THICKET VISITOR CENTER, SOUTH
To CITY OF KOUNTZE
CSJ 0920-03-073
Proj ID CM 2013(922)
Work Type GR, BS, PVMT, LNDSCP
 
6.862 2734519.40 0.00 2479136.31 90.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-25-13
Work Began 01-13-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 104
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-03-073
CRABTREE BARRICADE SYSTEMS, INC. (0.21%)
CLASSIC TEJAS CONSTRUCTION, INC. (5.58%)
Contract # 08133226
Totals 2734519.40 0.00 2479136.31 90.8

CountyNEWTON
Highway CR
From CR 2069 AT MCGRAW CREEK
To (STR AA0230001)
CSJ 0920-06-029
Proj ID BR 2014(257)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 354697.28 0.00 0.00 0.0
CountyNEWTON
Highway CR
From CR 2125 AT MCGRAW CRK
To (STR AA0153001)
CSJ 0920-06-030
Proj ID BR 2014(258)
Work Type GR, BS, STR, PVMT
 
0.100 306602.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-04-14
Work Began 00-00-00
Work Completed  
Time Computed 08-20-14
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0920-06-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143032
Totals 661300.20 0.00 0.00 0.0

CountyJEFFERSON
Highway CS
From CONCORD RD FROM SH 105
To LUCAS DR.
CSJ 0920-38-153
Proj ID HP 450(1)
Work Type GR, STR, BS, PVMT, STRIPE, SIGNAL
 
1.780 11284746.71 0.00 3762439.73 33.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-12
Work Began 04-23-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 364
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 3
Contractor(s)
TRADECO INFRAESTRUCTURA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-38-153
CRABTREE BARRICADE SYSTEMS, INC. (0.39%)
HEMPHILL PILE DRIVING CO., A CORP. (0.19%)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (0.49%)
AMERICAN REMEDIATION OPTIONS, INC. (0.88%)
SOLIS TRUCKING (0.56%)
GARY WHITMAN MATERIALS, INC. (0.16%)
ACCESS DATA SUPPLY, INC. (6.52%)
VIMAC-USA, INC.(5.87%)
PREMIERE DESIGN SOLUTIONS, INC.(5.87%)
Contract # 07123217
Totals 11284746.71 0.00 3762439.73 33.3

CountyJEFFERSON
Highway CS
From AT AMELIA ELEMENTARY SCHOOL
To .
CSJ 0920-38-218
Proj ID CM 2012(281)
Work Type GR, BS, STR, SIDEWALKS
 
0.100 113854.36 0.00 112296.53 98.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-12
Work Began 06-25-12
Work Completed  
Time Computed 06-04-12
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 94
Contractor(s)
PLACO, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0920-38-218
TRIANGLE CONCRETE SERVICES, INC. ( 62.12%)
Contract # 05123031
Totals 113854.36 0.00 112296.53 98.6

CountyLIBERTY
Highway FM 1008
From 5.0 MI S OF SH 321 (N), SOUTH
To 7.3 MI
CSJ 0952-01-051
Proj ID STP 2014(056)HES
Work Type GR, BS, STR, PVMT
 
7.296 3175645.38 114815.24 3173473.19 99.9
Work Order 01-17-14
Work Began 03-25-14
Work Completed  
Time Computed 03-19-14
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 102
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0952-01-051
WATERS CONSTRUCTION CO., INC.( 13.73%)
J & M CONTRACTING, COMPANY (1.81%)
BATTERSON,LLP(1.38%)
COWBELL TRAFFIC SERVICES, INC. (0.40%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.17%)
CEN TEX HYDROSEED, INC.(0.28%)
Contract # 10133016
Totals 3175645.38 114815.24 3173473.19 99.9

CountyNEWTON
Highway FM 1004
From SH 87, SOUTH
To JASPER CO/L
CSJ 1274-02-013
Proj ID STP 2014(481)
Work Type MILL, BASE, ACP, STR, STRIPE
 
4.142 1507560.61 192990.54 532790.90 35.3
Work Order 04-25-14
Work Began 00-00-00
Work Completed  
Time Computed 05-11-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 80
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1274-02-013
AMERICAN REMEDIATION OPTIONS, INC. (1.95%)
CRABTREE BARRICADE SYSTEMS, INC. (2.65%)
NORMAN HIGHWAY CONSTRUCTORS, INC.( 18.12%)
Contract # 03143220
Totals 1507560.61 192990.54 532790.90 35.3

CountyLIBERTY
Highway FM 1413
From US 90
To UP RR
CSJ 1421-01-024
Proj ID STP 2013(923)
Work Type GR, BS, STR, PVT.
 
4.555 2173548.35 393122.61 1106448.75 50.9
Work Order 04-22-14
Work Began 05-06-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 54
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1421-01-024
AMERICAN REMEDIATION OPTIONS, INC. (2.16%)
CRABTREE BARRICADE SYSTEMS, INC. (1.69%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.86%)
J & M CONTRACTING, COMPANY (0.71%)
Contract # 08133050
Totals 2173548.35 393122.61 1106448.75 50.9

CountyJEFFERSON
Highway SH 82
From AT MLK BRIDGE
To .
CSJ 2367-01-055
Proj ID BR 2012(754)
Work Type STR
 
0.120 4771980.50 54121.98 4860733.74 99.9
Work Order 09-24-12
Work Began 02-15-13
Work Completed  
Time Computed 10-10-12
Contract Working Days 356
Addl Days Granted 61
Working Days Charged 291
Percent Time Used 69
Contractor(s)
MIDWEST FOUNDATION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 2367-01-055
CRABTREE BARRICADE SYSTEMS, INC. (0.07%)
ALLSTATE SIGNAL & CONSTRUCTION, LLC(0.67%)
Contract # 08123020
Totals 4771980.50 54121.98 4860733.74 99.9