Monthly State Let Construction Report For Beaumont District As Of Apr 10, 2017 Page 2 Of 3

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJEFFERSON
HighwaySH 73
FromAT RAINBOW BRIDGE
To(STR 030603015)
CSJ0306-03-123
Proj IDNH 2014(978)
Work TypeCLEAN AND REPAINT BRIDGE
 
1.46026599824.2028361316.1999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-17-14
Work Began01-05-15
Work Completed
Time Computed11-02-14
Contract Working Days614
Addl Days Granted0
Working Days Charged626
Percent Time Used101
Contractor(s)
SAFFO CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0306-03-123
CRABTREE BARRICADE SYSTEMS, INC. (0.09)
JMD BUILDING PRODUCTS LLC (5.07)
EMPIRE SCAFFOLD (6.33)
CEKRA INC. (3.08)
WIDGEON CONSTRUCTION, INC. (0.00)
Contract #07143202
Totals26599824.200.0028361316.1999.9

CountyJEFFERSON
HighwaySH 73
FromSH 87
To0.400 MILES EAST OF FM 366
CSJ0306-03-126
Proj IDNH 2017(301)
Work TypePVMT REPAIR, MILL, OCST, PFC
 
0.782649754.100.000.0
CountyJEFFERSON
HighwaySH 73
From0.300 MILES WEST OF SPUR 215, EAST
ToSH 87
CSJ0508-04-166
Proj IDNH 2017(301)
Work TypePVMT REPAIR, MILL, OCST, PFC
 
6.1157596920.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-27-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0306-03-126
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173021
Totals8246674.850.000.000.0

CountyCHAMBERS
HighwaySH 146
From@IH-10
To.
CSJ0389-02-051
Proj IDSTP 2017(491)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.200223068.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-13-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-02-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173237
Totals223068.550.000.000.0

CountyLIBERTY
HighwaySH 105
From0.647 MILES EAST OF SH 321
To1.251 MILES EAST OF SH 321
CSJ0593-01-117
Proj IDSTP 1602(153)HES
Work TypeGR, BASE, STRIPE, ACP
 
0.6041388679.601073855.9877.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-05-16
Work Began09-06-16
Work Completed
Time Computed00-00-00
Contract Working Days117
Addl Days Granted5
Working Days Charged97
Percent Time Used79
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0593-01-117
J & M CONTRACTING, COMPANY (14.84)
CEN TEX HYDROSEED, INC. (0.95)
WATERS CONSTRUCTION CO., INC. (2.17)
CRABTREE BARRICADE SYSTEMS, INC. (2.90)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.07)
COWBELL TRAFFIC SERVICES, INC. (0.43)
LONE STAR TRAFFIC SERVICE, INC. (0.33)
TEX OP CONSTRUCTION, LP (1.59)
JOHN REED AND COMPANY, LLC (19.47)
EROSION ABATEMENT, LLC (0.55)
CPAVE, INC. (1.34)
HOUSTON SAWING & DRILLING (0.17)
Contract #06163013
Totals1388679.600.001073855.9877.3

CountyTYLER
HighwayFM 92
FromFM 1013, NORTH
ToFM 1746
CSJ0703-01-059
Proj IDSTP 1602(061)HRR
Work TypeSFTY TRT FXD OBJ
 
6.988123460.25119243.1198.0
CountyHARDIN
HighwayFM 92
FromBEAN RD, SOUTH
ToFM 1122
CSJ0703-02-057
Proj IDSTP 1602(062)HRR
Work TypeSFTY TRT FXD OBJ
 
4.409339263.41404460.0299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-20-16
Work Began08-10-16
Work Completed
Time Computed00-00-00
Contract Working Days83
Addl Days Granted40
Working Days Charged126
Percent Time Used102
Contractor(s)
NORMAN HIGHWAY CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0703-01-059
AMERICAN REMEDIATION OPTIONS, INC. (4.74)
CRABTREE BARRICADE SYSTEMS, INC. (2.52)
Contract #05163226
Totals462723.660.00523703.1399.9

CountyJASPER
HighwayFM 105
FromUS 96
To2.0 MILES SOUTH OF US 96
CSJ0710-01-049
Proj IDSTP 2017(961)
Work TypeBASE REPAIR, 2" SMA
 
1.8721012112.490.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days32
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0710-01-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173017
Totals1012112.490.000.000.0

CountyCHAMBERS
HighwayIH 10
FromSH 73, EAST
ToJEFFERSON CO. LINE
CSJ0739-01-039
Proj IDNH 1602(470)
Work TypeRECONST GR, STRS BS & PAV
 
3.11324138551.423064611.1312.6
CountyJEFFERSON
HighwayIH 10
FromCHAMBERS CO/L, EAST
ToHAMSHIRE RD
CSJ0739-02-160
Proj IDNH 1602(470)
Work TypeGR, BS, STR, PVMT
 
2.10219031143.036201148.0032.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-13-16
Work Began10-27-16
Work Completed
Time Computed00-00-00
Contract Working Days696
Addl Days Granted0
Working Days Charged71
Percent Time Used10
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0739-01-039
INTERSTATE BARRICADES & MARKINGS, INC. (0.60)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.11)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
CPAVE, INC. (0.24)
SCOTT DERR PAINTING CO, LLC (0.05)
MESA ROD BUSTERS, INC. (5.50)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.69)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.92)
WEST TEXAS RUMBLE STRIP (0.11)
ANGEL BROTHERS ENTERPRISES, LTD. (1.65)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
Contract #09163201
Totals43169694.450.009265759.1321.4

CountyHARDIN
HighwayFM 418
FromFM 92, SOUTH
ToUS 96
CSJ0784-01-046
Proj IDSTP 1602(064)HES
Work TypeSFTY TRT FXD OBJ
 
1.6911031113.54725191.6770.3
CountyHARDIN
HighwayFM 1003
FromFM 1293
ToSOUTH, 2.5 MI
CSJ0811-02-028
Proj IDSTP 1602(065)HES
Work TypeSFTY TRT FXD OBJ
 
2.50046474.401860.004.0
CountyHARDIN
HighwayFM 787
FromFM 1293
ToSOUTH, 6.0 MI
CSJ0813-02-038
Proj IDSTP 1602(063)HES
Work TypeSFTY TRT FXD OBJ
 
6.000204002.85155545.5076.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-29-16
Work Began01-03-17
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted0
Working Days Charged51
Percent Time Used27
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0784-01-046
AMERICAN REMEDIATION OPTIONS, INC. (5.30)
CRABTREE BARRICADE SYSTEMS, INC. (2.13)
NORMAN HIGHWAY CONSTRUCTORS, INC. (23.51)
Contract #05163229
Totals1281590.790.00882597.1768.8

CountyORANGE
HighwayFM 2177
From0.7 MILES NORTH OF FM 1006
ToFM 1006
CSJ0882-01-013
Proj IDSTP 2017(962)HES
Work TypePROVIDE ADDITIONAL PAVED SURFACE
 
0.700328092.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0882-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173023
Totals328092.650.000.000.0

CountyORANGE
HighwayFM 105
FromUNION PACIFIC RR
To6.0 MI S OF IH 10
CSJ0883-02-068
Proj IDSTP 2016(410)
Work TypeGR, BS, STR. PVMT
 
3.9242668330.652313092.5786.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-28-16
Work Began04-18-16
Work Completed
Time Computed00-00-00
Contract Working Days69
Addl Days Granted55
Working Days Charged119
Percent Time Used95
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0883-02-068
CRABTREE BARRICADE SYSTEMS, INC. (1.87)
AMERICAN REMEDIATION OPTIONS, INC. (2.21)
NORMAN HIGHWAY CONSTRUCTORS, INC. (26.64)
WIDGEON CONSTRUCTION, INC. (1.76)
Contract #01163235
Totals2668330.650.002313092.5786.6

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-116
Proj IDSTP 2014(646)
Work TypeLANDSCAPE
 
3.428832522.01797876.2295.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-22-14
Work Began10-20-14
Work Completed
Time Computed00-00-00
Contract Working Days219
Addl Days Granted0
Working Days Charged198
Percent Time Used90
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-116
CLASSIC TEJAS CONSTRUCTION, INC. (3.46)
CRABTREE BARRICADE SYSTEMS, INC. (1.68)
Contract #05143219
Totals832522.010.00797876.2295.8

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-117
Proj IDSTP 1502(181)
Work TypeLANDSCAPE
 
1.000718877.79659979.0091.8
Work Order07-20-15
Work Began11-16-15
Work Completed
Time Computed08-20-15
Contract Working Days186
Addl Days Granted0
Working Days Charged100
Percent Time Used53
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-117
AMERICAN REMEDIATION OPTIONS, INC. (7.17)
CRABTREE BARRICADE SYSTEMS, INC. (1.28)
Contract #05153033
Totals718877.792500.00659979.0091.8

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-118
Proj IDSTP 1602(155)
Work TypeLANDSCAPE
 
1.567706493.95668087.0094.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-04-16
Work Began10-01-16
Work Completed
Time Computed00-00-00
Contract Working Days225
Addl Days Granted0
Working Days Charged28
Percent Time Used12
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-118
CRABTREE BARRICADE SYSTEMS, INC. (1.39)
HOLES INCORPORATED (0.00)
Contract #06163218
Totals706493.950.00668087.0094.5

CountyORANGE
HighwayCR
FromE ROUNDBUNCH RD AT COW BAYOU
To(STR AA2690006)
CSJ0920-30-077
Proj IDBR 2014(325)
Work TypeREHAB BRIDGE AND APPROACHES
 
0.26911399710.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-30-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-30-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173204
Totals11399710.800.000.000.0

CountyORANGE
HighwayCR
FromOLD HIGHWAY 90, S.OF I10 ACCESS RD.
ToEAST BANK OF NECHES RIVER
CSJ0920-30-081
Proj IDCM 2015(253)
Work TypeGR,BS,STR, PVMT,RR, SIGN
 
0.4208977087.387362445.3382.0
Work Order06-01-15
Work Began01-07-16
Work Completed
Time Computed06-17-15
Contract Working Days157
Addl Days Granted137
Working Days Charged262
Percent Time Used89
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-30-081
A. H. BECK FOUNDATION CO., INC. (14.83)
INDUS CONSTRUCTION, L.P. (1.81)
J & M CONTRACTING, COMPANY (0.88)
RIVER CITY RAILROAD TROLLEY & TRANSIT CONSULTANTS (1.60)
CRABTREE BARRICADE SYSTEMS, INC. (0.44)
AMERICAN REMEDIATION OPTIONS, INC. (1.11)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.90)
JA BRUMLEY ENTERPRISES, INC. DBA RAM INDUSTRIAL CONSTRUCTION (1.31)
Contract #10143215
Totals8977087.38215939.677362445.3382.0

CountyJEFFERSON
HighwayCS
FromCONCORD RD FROM SH 105
ToLUCAS DR.
CSJ0920-38-153
Proj IDHP 450(1)
Work TypeGR, STR, BS, PVMT, STRIPE, SIGNAL
 
1.78011284746.7111062867.7098.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-12
Work Began04-23-13
Work Completed
Time Computed00-00-00
Contract Working Days364
Addl Days Granted103
Working Days Charged522
Percent Time Used111
Contractor(s)
AMERICAN HOME ASSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0920-38-153
CRABTREE BARRICADE SYSTEMS, INC. (0.39)
HEMPHILL PILE DRIVING CO., A CORP. (0.19)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (0.49)
AMERICAN REMEDIATION OPTIONS, INC. (0.88)
SOLIS TRUCKING (0.56)
GARY WHITMAN MATERIALS, INC. (0.16)
ACCESS DATA SUPPLY, INC. (6.52)
VIMAC-USA, INC. (5.87)
PREMIERE DESIGN SOLUTIONS, INC. (5.87)
APAC-TEXAS, INC. (0.56)
TEX OP CONSTRUCTION, LP (0.22)
TRAFFIC CONTROL PRODUCTS (HOUSTON) (0.50)
CJ EXPRESS (1.59)
TEXAS STERLING CONSTRUCTION CO. (75.51)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.02)
L D CONSTRUCTION (4.37)
AAA FLEXIBLE PIPE CLEANING COMPANY, INC. (0.22)
CPAV SPECIALTIES, LP (1.10)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.12)
MESA ROD BUSTERS, INC. (0.54)
R. ORTIZ TRUCKING (1.32)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (0.92)
CJ EXPRESS (5.52)
CURB PLANET INC. (0.11)
Contract #07123217
Totals11284746.710.0011062867.7098.6

CountyJEFFERSON
HighwayCS
FromBLOCK STREET
ToLLANO STREET, IN PORT NECHES
CSJ0920-38-254
Proj IDSTP 2014(096)TE
Work TypeGR, BS, PVMT, LNDSCP
 
0.303749492.52888613.3199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-26-16
Work Began04-25-16
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted25
Working Days Charged91
Percent Time Used97
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-38-254
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (8.61)
CRABTREE BARRICADE SYSTEMS, INC. (2.83)
JE CASEY, LLC (1.37)
Contract #08153266
Totals749492.520.00888613.3199.9

CountyCHAMBERS
HighwayVA
FromON FM 565 FROM FM 3360 TO FISHER RD
ToFM 3360 FROM CHERRY PT TO EAGLE PT
CSJ0920-39-023
Proj IDSTP 2017(422)TAPS
Work TypeGR, PVMT
 
1.733964954.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-31-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEZTEX INDUSTRIAL SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-39-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163037
Totals964954.450.000.000.0

CountyJEFFERSON
HighwayFM 365
FromAT GROUND GULLY
To.
CSJ0932-02-053
Proj IDBR 1502(424)
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.0361565852.571112633.2471.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-12-15
Work Began10-26-16
Work Completed
Time Computed00-00-00
Contract Working Days89
Addl Days Granted0
Working Days Charged85
Percent Time Used95
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0932-02-053
AMERICAN REMEDIATION OPTIONS, INC. (3.62)
CRABTREE BARRICADE SYSTEMS, INC. (1.61)
DUSTROL, INC. (0.91)
HEMPHILL PILE DRIVING CO., A CORP. (5.03)
CPAVE, INC. (0.17)
HOUSTON SAWING & DRILLING (0.22)
Contract #08153263
Totals1565852.570.001112633.2471.0

CountyJEFFERSON
HighwayFM 365
From0.2 MILES EAST OF IH 10, EAST
ToSH 124
CSJ0932-02-055
Proj IDSTP 2016(957)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
0.960400896.15367177.7495.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-13-16
Work Began10-06-16
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged74
Percent Time Used164
Contractor(s)
EXCAVATION & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0932-02-055
AMERICAN REMEDIATION OPTIONS, INC. (10.47)
CRABTREE BARRICADE SYSTEMS, INC. (1.25)
Contract #04163026
Totals400896.150.00367177.7495.8