Monthly State Let Construction Report For Beaumont District As Of Jun 10, 2015 Page 2 Of 4

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyORANGE
Highway SH 62
From FM 1078
To 0.122 MILES SOUTH OF FM 1078
CSJ 0243-03-061
Proj ID CM 1402(095)
Work Type GR, BS, STR, PVMT
 
0.122 140492.90 0.00 133908.54 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-15-14
Work Began 09-08-14
Work Completed 12-04-14
Time Computed 08-31-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 86
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0243-03-061
AMERICAN REMEDIATION OPTIONS, INC. (3.90%)
CRABTREE BARRICADE SYSTEMS, INC. (9.30%)
Contract # 07143053
Totals 140492.90 0.00 133908.54 100.0

CountyJASPER
Highway SH 63
From ANGELINA COUNTY LINE
To 0.26 MILES WEST OF FM 2799
CSJ 0244-02-098
Proj ID STP 1502(350)
Work Type PLANE, ACP, STRIPE
 
14.382 6777550.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0244-02-098
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153021
Totals 6777550.00 0.00 0.00 0.0

CountyNEWTON
Highway SH 87
From FM 1004, SOUTH
To 7.5 MILES
CSJ 0305-03-041
Proj ID STP 1502(136)HES
Work Type CL TXT, TXT SHLDRS
 
7.500 74992.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-05-15
Work Began 00-00-00
Work Completed  
Time Computed 08-05-15
Contract Working Days 15
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CRABTREE BARRICADE SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0305-03-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153040
Totals 74992.50 0.00 0.00 0.0

CountyORANGE
Highway SH 73
From AT COW BAYOU
To .
CSJ 0306-01-059
Proj ID BR 2013(920)
Work Type REPAIR BRIDGE
 
0.616 9509229.88 215156.00 9394173.86 98.7
Work Order 10-30-13
Work Began 01-31-14
Work Completed  
Time Computed 11-15-13
Contract Working Days 476
Addl Days Granted 60
Working Days Charged 303
Percent Time Used 56
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0306-01-059
APAC-TEXAS, INC. (1.67%)
CRABTREE BARRICADE SYSTEMS, INC. (0.84%)
DUSTROL, INC.(0.20%)
INTECH CONTRACTING LLC ( 12.59%)
IOWA BRIDGE & CULVERT, LC( 16.80%)
LLOYD D. NABORS DEMOLITION LLC (1.17%)
RUSSELL MARINE, LLC( 11.46%)
UNDERWATER SERVICES, INC.(1.22%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.57%)
TX TINMAN ENTERPRISES, LLC.(8.01%)
L D CONSTRUCTION (2.39%)
MUSTANG COLT SERVICES, INC.(4.30%)
Contract # 08133252
Totals 9509229.88 215156.00 9394173.86 98.7

CountyJEFFERSON
Highway SH 87
From AT CRANE BAYOU
To (STR 030603027)
CSJ 0306-03-120
Proj ID BR 2013(856)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 2487698.29 16286.35 1829720.46 73.5
CountyJEFFERSON
Highway SH 73
From 25 ST @ CRANE BAYOU LATERAL
To (STR 050804166)
CSJ 0508-04-155
Proj ID BR 2013(856)
Work Type STR
 
0.100 308554.08 0.00 405352.73 99.9
Work Order 10-07-13
Work Began 12-03-13
Work Completed  
Time Computed 10-23-13
Contract Working Days 356
Addl Days Granted 48
Working Days Charged 286
Percent Time Used 70
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0306-03-120
CRABTREE BARRICADE SYSTEMS, INC. (2.13%)
AMERICAN REMEDIATION OPTIONS, INC. (2.32%)
NORMAN HIGHWAY CONSTRUCTORS, INC.( 35.12%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.04%)
PRIMATE CONSTRUCTION, INC. (0.22%)
CERTIFIED PLACERS LLC(0.24%)
CPAVE, INC.(0.09%)
Contract # 07133024
Totals 2796252.37 16286.35 2235073.19 79.9

CountyJEFFERSON
Highway SH 73
From AT RAINBOW BRIDGE
To (STR 030603015)
CSJ 0306-03-123
Proj ID NH 2014(978)
Work Type CLEAN AND REPAINT BRIDGE
 
1.460 26599824.20 2904440.00 10855048.48 40.8
Work Order 10-17-14
Work Began 01-05-15
Work Completed  
Time Computed 11-02-14
Contract Working Days 614
Addl Days Granted 0
Working Days Charged 124
Percent Time Used 20
Contractor(s)
SAFFO CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0306-03-123
CRABTREE BARRICADE SYSTEMS, INC. (0.09%)
JMD BUILDING PRODUCTS LLC(5.07%)
EMPIRE SCAFFOLD(6.33%)
CEKRA INC. (3.08%)
Contract # 07143202
Totals 26599824.20 2904440.00 10855048.48 40.8

CountyJEFFERSON
Highway SH 87
From AT VETERANS MEMORIAL BRIDGE
To (STR 030603030)
CSJ 0306-03-124
Proj ID NH 2014(979)
Work Type STAY CABLE MAINTENANCE
 
1.787 2318400.00 40281.36 2466406.01 100.0
Work Order 09-22-14
Work Began 11-03-14
Work Completed 05-13-15
Time Computed 10-08-14
Contract Working Days 102
Addl Days Granted 5
Working Days Charged 90
Percent Time Used 84
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0306-03-124
CRABTREE BARRICADE SYSTEMS, INC. (0.16%)
INTECH CONTRACTING LLC ( 33.42%)
ALPIN TECHNIK UND INGENIEURSERVICE GMBH( 41.16%)
BRIDGES R US PAINTING CO., INC.( 12.93%)
Contract # 08143035
Totals 2318400.00 40281.36 2466406.01 100.0

CountyJEFFERSON
Highway SH 87
From AT INTRACOASTAL CANAL BRIDGE
To .
CSJ 0307-01-147
Proj ID BR 1502(005)
Work Type STR
 
0.941 3454612.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 179
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0307-01-147
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153053
Totals 3454612.26 0.00 0.00 0.0

CountyTYLER
Highway US 287
From AT RUSSELL CREEK
To (STR 202290034104027)
CSJ 0341-04-071
Proj ID BR 1502(044)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
0.040 269374.26 55470.00 55470.00 20.5
CountyJEFFERSON
Highway SH 347
From AT THE MAIN "A" CANAL
To (STR 201240066701005)
CSJ 0667-01-117
Proj ID BR 1502(009)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
0.015 97961.48 0.00 0.00 0.0
CountyJEFFERSON
Highway SH 347
From AT THE MAIN "B" CANAL
To (STR 201240066701009)
CSJ 0667-01-118
Proj ID BR 1502(009)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
0.003 52260.55 0.00 0.00 0.0
Work Order 05-08-15
Work Began 05-29-15
Work Completed  
Time Computed 07-08-15
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0341-04-071
AMERICAN REMEDIATION OPTIONS, INC. ( 18.47%)
CRABTREE BARRICADE SYSTEMS, INC. (3.97%)
Contract # 04153241
Totals 419596.29 55470.00 55470.00 13.2

CountyORANGE
Highway SH 12
From SH 62
To NEWTON CO/L
CSJ 0499-03-057
Proj ID STP 2014(803)
Work Type PLANE, SMA, STRIPE
 
3.859 2279714.00 0.00 2204541.48 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-07-14
Work Began 10-06-14
Work Completed 11-25-14
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 68
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0499-03-057
DUSTROL, INC.( 10.11%)
CRABTREE BARRICADE SYSTEMS, INC. (1.56%)
Contract # 04143232
Totals 2279714.00 0.00 2204541.48 100.0

CountyCHAMBERS
Highway IH 10
From 0.120 MILES EAST OF SH 99, EAST
To FM 565
CSJ 0508-02-113
Proj ID NH 2015(706)
Work Type GR, BS, OCST, STRIPE
 
3.645 1920391.04 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-24-15
Work Began 00-00-00
Work Completed  
Time Computed 05-25-15
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0508-02-113
A-1 EROSION CONTROL, LLC (0.39%)
STRIPE-A-LINE, INC.(3.17%)
Contract # 03153005
Totals 1920391.04 0.00 0.00 0.0

CountyCHAMBERS
Highway IH 10
From AT SH 99 & HACKBERRY GULLY
To (STR 200360050802349)
CSJ 0508-02-118
Proj ID BR 1502(011)
Work Type BRIDGE REPAIR
 
0.335 313764.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-14-15
Work Began 00-00-00
Work Completed  
Time Computed 06-14-15
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-02-118
LONE STAR TRAFFIC SERVICE, INC.(1.08%)
Contract # 04153209
Totals 313764.55 0.00 0.00 0.0

CountyJEFFERSON
Highway SP 215
From SH 73, EAST
To 0.794 MI W OF SH 87
CSJ 0508-06-020
Proj ID STP 2014(509)
Work Type FDR, BS, MILL, OVERLAY
 
1.371 1979708.80 63766.65 1806527.69 95.6
Work Order 04-02-14
Work Began 05-02-14
Work Completed  
Time Computed 04-18-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 186
Percent Time Used 248
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-06-020
AMERICAN REMEDIATION OPTIONS, INC. (6.15%)
CRABTREE BARRICADE SYSTEMS, INC. (1.57%)
CPAVE, INC.( 24.56%)
DUSTROL, INC.(4.06%)
PINNACLE GRINDING & GROOVING, LLC(4.03%)
Contract # 02143031
Totals 1979708.80 63766.65 1806527.69 95.6

CountyJEFFERSON
Highway SP 136
From 0.65 MILES NORTH OF SH 347
To 0.61 MILES NORTH
CSJ 0653-01-013
Proj ID CM 2014(843)
Work Type GR, BS, STR, PVMT
 
0.610 569227.19 0.00 544325.26 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-14
Work Began 09-15-14
Work Completed 02-05-15
Time Computed 09-05-14
Contract Working Days 87
Addl Days Granted 8
Working Days Charged 51
Percent Time Used 64
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0653-01-013
AMERICAN REMEDIATION OPTIONS, INC. (0.36%)
CRABTREE BARRICADE SYSTEMS, INC. (6.01%)
Contract # 06143045
Totals 569227.19 0.00 544325.26 100.0

CountyCHAMBERS
Highway IH 10
From 0.210 MI WEST OF FM 1663, EAST
To JEFFERSON CO/L
CSJ 0739-01-045
Proj ID IM 0108(176)
Work Type PLANE, MBGF, PFC
 
2.528 1179835.95 0.00 1122606.21 100.0
CountyJEFFERSON
Highway IH 10
From CHAMBERS CO/L, EAST
To 0.65 MI E OF FM 365
CSJ 0739-02-147
Proj ID IM 0108(176)
Work Type PLANE, MBGF, PFC, UPGRADE BRIDGE RAIL
 
8.022 3506970.90 0.00 3631304.74 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-13
Work Began 08-04-13
Work Completed 02-27-15
Time Computed 00-00-00
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 218
Percent Time Used 127
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0739-01-045
WILLOW CITY SIGN & RAIL, INC.(4.20%)
CRABTREE BARRICADE SYSTEMS, INC. (2.62%)
SEMARCK LANDSCAPE SERVICES, INC. (0.09%)
CHEROKEE SERVICES(1.32%)
Contract # 02133208
Totals 4686806.85 0.00 4753910.95 100.0

CountyJEFFERSON
Highway FM 364
From DELAWARE STREET
To PHELAN BLVD.
CSJ 0786-01-080
Proj ID CM 2015(250)
Work Type CONCRETE PAVEMENT
 
1.309 647657.70 100166.21 545598.12 84.6
Work Order 11-17-14
Work Began 12-03-14
Work Completed  
Time Computed 12-03-14
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 109
Contractor(s)
WIDGEON CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0786-01-080
CRABTREE BARRICADE SYSTEMS, INC. (2.79%)
Contract # 10143212
Totals 647657.70 100166.21 545598.12 84.6

CountyLIBERTY
Highway FM 787
From AT TARKINGTON BAYOU
To (STR 081301009)
CSJ 0813-01-096
Proj ID BR 2013(921)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 1341288.27 7590.44 1390763.42 100.0
Work Order 01-06-14
Work Began 02-14-14
Work Completed 04-01-15
Time Computed 01-22-14
Contract Working Days 184
Addl Days Granted 0
Working Days Charged 172
Percent Time Used 93
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0813-01-096
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 14.91%)
EROSION CONTROL, INC.(0.11%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.44%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.02%)
ROZCO CONTRACTING, INC.( 46.48%)
MESA ROD BUSTERS, INC. (0.30%)
JOHN REED AND COMPANY, LLC ( 40.30%)
Contract # 08133243
Totals 1341288.27 7590.44 1390763.42 100.0

CountyTYLER
Highway FM 256
From US 190, NORTH
To 2.0 MI N OF US 190
CSJ 0877-04-025
Proj ID STP 1502(229)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
2.000 727007.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0877-04-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153238
Totals 727007.20 0.00 0.00 0.0

CountyORANGE
Highway FM 105
From OLD HWY 90, SOUTH
To UNION PACIFIC RR
CSJ 0883-02-079
Proj ID STP 2015(463)
Work Type MILL, ACP, GR, STRIPE
 
1.588 290384.74 0.00 276713.63 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-07-15
Work Began 04-28-15
Work Completed 06-01-15
Time Computed 00-00-00
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 70
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0883-02-079
CRABTREE BARRICADE SYSTEMS, INC. (6.54%)
DUSTROL, INC.(9.84%)
Contract # 12143020
Totals 290384.74 0.00 276713.63 100.0

CountyJEFFERSON
Highway VA
From DISTRICTWIDE
To .
CSJ 0920-00-111
Proj ID STP 2013(710)
Work Type LANDSCAPE
 
1.000 432659.00 1000.00 386728.77 89.7
Work Order 08-08-13
Work Began 12-04-13
Work Completed  
Time Computed 11-04-13
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 105
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-111
CRABTREE BARRICADE SYSTEMS, INC. (2.09%)
Contract # 05133223
Totals 432659.00 1000.00 386728.77 89.7