Monthly Local Let Maintenance Report For Austin District As Of Apr 10, 2015 Page 4 Of 4

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway US0183
From VARIOUS LOCATIONS IN TRAVIS COUNTY
To .
CSJ 6276-37-001
Proj ID RMC - 627637001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 201097.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141408
Totals 201097.96 0.00 0.00 0.0

CountyGILLESPIE
Highway US0087
From VARIOUS LOCATIONS IN GILLESPIE, BLANCO
To AND LLANO COUNTIES
CSJ 6276-86-001
Proj ID RMC - 627686001
Work Type MOWING RIGHT OF WAY
 
0.001 181578.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6276-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141405
Totals 181578.40 0.00 0.00 0.0

CountyLLANO
Highway SH0071
From VARIOUS LOCATIONS IN LLANO, BURNET
To AND BLANCO COUNTIES
CSJ 6276-87-001
Proj ID RMC - 627687001
Work Type MOWING RIGHT OF WAY
 
0.001 258065.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6276-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141407
Totals 258065.20 0.00 0.00 0.0

CountyMASON
Highway US0087
From VARIOUS LOCATIONS IN MASON, LLANO
To AND GILLESPIE COUNTIES
CSJ 6276-88-001
Proj ID RMC - 627688001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 221836.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6276-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141406
Totals 221836.00 0.00 0.00 0.0

CountyTRAVIS
Highway IH0035
From AUSTIN DISTRICT
To VARIOUS LOCATIONS
CSJ 6279-85-001
Proj ID RMC - 627985001
Work Type TRAFFIC SIGNAL MAINTENANCE
 
0.001 223610.00 0.00 13650.00 6.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 02-18-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 349
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 9
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151402
Totals 223610.00 0.00 13650.00 6.1

CountyLEE
Highway US0290
From VARIOUS LOCATIONS IN
To LEE MAINTENANCE SECTION
CSJ 6280-14-001
Proj ID SUP - 628014001
Work Type LITTER REMOVAL
 
0.001 137724.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6280-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151430
Totals 137724.88 0.00 0.00 0.0

CountyTRAVIS
Highway IH0035
From SOUTH TRAVIS AREA OFFICE
To .
CSJ 6280-32-001
Proj ID SUP - 628032001
Work Type JANITORIAL MAINTENANCE
 
0.001 39408.00 1470.00 7350.00 18.6
Work Order 00-00-00
Work Began 11-01-14
Work Completed  
Time Computed 11-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 20
Contractor(s)
TIBH INDUSTRIES, INC.
VAUGHN HOUSE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141430
Totals 39408.00 1470.00 7350.00 18.6

CountyTRAVIS
Highway US0183
From VARIOUS LOCATIONS
To IN TRAVIS COUNTY
CSJ 6281-83-001
Proj ID RMC - 628183001
Work Type CRACK SEALING ASPHALTIC PAVEMENT
 
0.010 154596.00 0.00 26951.40 17.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 6
Working Days Charged 11
Percent Time Used 30
Contractor(s)
DE WALT CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6281-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12141403
Totals 154596.00 0.00 26951.40 17.4

CountyTRAVIS
Highway IH0035
From AUSTIN DISTRICT HEADQUARTERS
To .
CSJ 6281-88-001
Proj ID SUP - 628188001
Work Type JANITORIAL MAINTENANCE
 
0.001 173668.89 0.00 11742.42 6.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6281-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12141430
Totals 173668.89 0.00 11742.42 6.7

CountyWILLIAMSON
Highway US0079
From TAYLOR MAINTENANCE SECTION
To .
CSJ 6282-18-001
Proj ID SUP - 628218001
Work Type JANITORIAL MAINTENANCE
 
0.001 8752.32 364.68 1458.72 16.6
Work Order 00-00-00
Work Began 12-02-14
Work Completed  
Time Computed 12-07-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141430
Totals 8752.32 364.68 1458.72 16.6

CountyBASTROP
Highway FM1209
From SH 71
To 2.6 MI N OF SH 71
CSJ 6283-97-001
Proj ID RMC - 628397001
Work Type LEVEL UP & SEAL COAT
 
0.001 275221.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6283-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03151401
Totals 275221.80 0.00 0.00 0.0

CountyBASTROP
Highway FM3000
From ELGIN TO 3.7 MILES NE
To .
CSJ 6284-16-001
Proj ID SUP - 628416001
Work Type LITTER PICKUP AND REMOVAL
 
0.001 176356.04 0.00 26309.85 14.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 6
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6284-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151431
Totals 176356.04 0.00 26309.85 14.9