Monthly Local Let Maintenance Report For Austin District As Of Apr 11, 2014 Page 3 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway US0183
From VARIOUS LOCATIONS IN
To TRAVIS AND HAYS COUNTY
CSJ 6264-02-001
Proj ID RMC - 626402001
Work Type REMOVAL AND DISPOSAL OF TREES & BRUSH
 
0.010 184732.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FST CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6264-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131403
Totals 184732.00 0.00 0.00 0.0

CountyTRAVIS
Highway IH0035
From VARIOUS LOCATIONS IN TRAVIS
To AND WILLIAMSON COUNTIES
CSJ 6264-11-001
Proj ID RMC - 626411001
Work Type CRACK SEALING ASPHALT PAVEMENT ROADWAYS
 
0.001 168636.16 43505.55 98677.80 58.5
Work Order 00-00-00
Work Began 02-13-14
Work Completed  
Time Computed 02-13-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 40
Contractor(s)
RHB CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131406
Totals 168636.16 43505.55 98677.80 58.5

CountyTRAVIS
Highway US0183
From US 183
To LOOP 1 INTERCHANGE
CSJ 6264-12-001
Proj ID RMC - 626412001
Work Type DRAIN CLEANING AND REPAIR
 
1.000 162750.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-14
Work Began 00-00-00
Work Completed  
Time Computed 04-14-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPEDGE CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6264-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141401
Totals 162750.00 0.00 0.00 0.0

CountyBURNET
Highway US0183
From VARIOUS LOCATIONS IN BURNET,
To LLANO,BLANCO & HAYS COUNTIES
CSJ 6264-15-001
Proj ID RMC - 626415001
Work Type TREE AND BRUSH REMOVAL
 
0.001 180126.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6264-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131403
Totals 180126.12 0.00 0.00 0.0

CountyHAYS
Highway US0290
From VARIOUS ROADWAYS IN HAYS COUNTY
To TRAVIS COUNTY AND CALDWELL COUNTY
CSJ 6264-47-001
Proj ID RMC - 626447001
Work Type CLEANING AND SEALING JOINTS & CRACKS
 
193.630 145672.80 82373.55 108392.95 74.4
Work Order 01-14-14
Work Began 01-29-14
Work Completed  
Time Computed 01-21-14
Contract Working Days 22
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 86
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131402
Totals 145672.80 82373.55 108392.95 74.4

CountyCALDWELL
Highway US0183
From VARIOUS LOCATIONS IN CALDWELL
To BASTROP AND HAYS COUNTIES
CSJ 6264-79-001
Proj ID SUP - 626479001
Work Type LITTER REMOVAL AND DISPOSAL
 
0.001 98180.00 0.00 19380.00 19.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-18-13
Work Began 01-08-14
Work Completed  
Time Computed 10-01-13
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 14
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6264-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131430
Totals 98180.00 0.00 19380.00 19.7

CountyTRAVIS
Highway IH0035
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 6265-85-001
Proj ID RMC - 626585001
Work Type PAINT STRUCTURE NUMBERS DISTRICT WIDE
 
0.001 99950.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-26-14
Work Began 00-00-00
Work Completed  
Time Computed 04-01-14
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MPB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01141403
Totals 99950.00 0.00 0.00 0.0

CountyTRAVIS
Highway IH0035
From AUSTIN DISTRICT
To VARIOUS LOCATIONS
CSJ 6266-30-001
Proj ID RMC - 626630001
Work Type PREVENTATIVE MAINT OF TRAFFIC SIGNALS
 
0.002 199824.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04141401
Totals 199824.00 0.00 0.00 0.0

CountyLLANO
Highway SH0016
From VARIOUS LOCATIONS IN LLANO
To .
CSJ 6266-37-001
Proj ID SUP - 626637001
Work Type LITTER REMOVAL
 
0.001 83444.38 1535.95 16056.52 19.2
Work Order 00-00-00
Work Began 11-13-13
Work Completed  
Time Computed 04-24-14
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 9
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6266-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131430
Totals 83444.38 1535.95 16056.52 19.2

CountyBURNET
Highway US0281
From VARIOUS LOCATIONS IN BURNET COUNTY
To .
CSJ 6266-44-001
Proj ID SUP - 626644001
Work Type LITTER REMOVAL
 
0.001 141724.00 0.00 16877.31 11.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-06-14
Work Began 01-13-14
Work Completed  
Time Computed 01-13-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6266-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131431
Totals 141724.00 0.00 16877.31 11.9

CountyLEE
Highway US0290
From VARIOUS LOCATIONS
To IN LEE MAINTENANCE SECTION
CSJ 6266-91-001
Proj ID SUP - 626691001
Work Type LITTER REMOVAL
 
0.001 133594.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 00-00-00
Work Completed  
Time Computed 04-08-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
SUNDAGGER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131431
Totals 133594.64 0.00 0.00 0.0

CountyLLANO
Highway SH0016
From LLANO COUNTY MAINTENANCE OFFICE
To .
CSJ 6267-64-001
Proj ID SUP - 626764001
Work Type JANITORIAL MAINTENANCE
 
0.001 14688.00 841.50 2333.25 15.8
Work Order 11-26-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131430
Totals 14688.00 841.50 2333.25 15.8

CountyTRAVIS
Highway RM2322
From SH 71
To END STATE MAINTENANCE
CSJ 6268-21-001
Proj ID RMC - 626821001
Work Type TIER 1 SEAL
 
4.564 298395.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 18
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6268-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141402
Totals 298395.12 0.00 0.00 0.0

CountyTRAVIS
Highway SL0360
From 2.879 MILES SOUTH OF US 183
To 2.879 MILES SOUTH OF US 183
CSJ 6268-28-001
Proj ID EMC - 626828001
Work Type REPAIR CROSS CULVERT STRUCTURE
 
0.010 347996.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 21
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FORSYTHE BROTHERS INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6268-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141430
Totals 347996.00 0.00 0.00 0.0

CountyGILLESPIE
Highway US0290
From VARIOUS LOCATIONS IN GILLESPIE
To .
CSJ 6269-64-001
Proj ID SUP - 626964001
Work Type LITTER REMOVAL
 
0.001 84585.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6269-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141430
Totals 84585.82 0.00 0.00 0.0

CountyBASTROP
Highway FM3000
From ELGIN TO 3.7 MILES NE
To .
CSJ 6269-95-001
Proj ID SUP - 626995001
Work Type LITTER PICK UP AND REMOVAL
 
0.001 157531.74 25670.86 25670.86 16.2
Work Order 00-00-00
Work Began 03-03-14
Work Completed  
Time Computed 03-03-14
Contract Working Days 122
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 13
Contractor(s)
TIBH INDUSTRIES, INC.
SUNDAGGER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141431
Totals 157531.74 25670.86 25670.86 16.2

CountyTRAVIS
Highway US0290
From VARIOUS LOCATIONS IN TRAVIS AND HAYS
To .
CSJ 6271-27-001
Proj ID SUP - 627127001
Work Type LITTER PICK UP ANE REMOVAL
 
0.001 159306.58 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-09-14
Work Began 00-00-00
Work Completed  
Time Computed 04-09-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141431
Totals 159306.58 0.00 0.00 0.0

CountyWILLIAMSON
Highway US0079
From VARIOUS ROADWAYS IN WILLIAMSON
To TRAVIS AND BASTROP COUNTIES
CSJ 6271-31-001
Proj ID SUP - 627131001
Work Type LITTER REMOVAL
 
0.001 112098.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 118
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141432
Totals 112098.88 0.00 0.00 0.0

CountyHAYS
Highway IH0035
From VARIOUS LOCATIONS IN HAYS COUNTIES
To .
CSJ 6271-96-001
Proj ID SUP - 627196001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 15573.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6271-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04141430
Totals 15573.12 0.00 0.00 0.0

CountyHAYS
Highway SH0021
From HAYS COUNTY MAINTENANCE OFFICE
To .
CSJ 6272-31-001
Proj ID SUP - 627231001
Work Type JANITORIAL MAINTENANCE
 
0.001 16393.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 00-00-00
Work Completed  
Time Computed 04-08-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141433
Totals 16393.92 0.00 0.00 0.0