Monthly Local Let Maintenance Report For Austin District As Of Jun 11, 2013 Page 2 Of 3

Last Update: Tuesday, June 11, 2013
FTP Icon Text Version
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWILLIAMSON
Highway US0079
From VARIOUS ROADWAYS IN WILLIAMSON
To TRAVIS AND BASTROP COUNTIES
CSJ 6242-22-001
Proj ID SUP - 624222001
Work Type LITTER REMOVAL
 
0.001 144852.44 12906.56 76871.54 53.0
Work Order 06-11-12
Work Began 06-11-12
Work Completed  
Time Computed 06-18-12
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 25
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6242-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03121430
Totals 144852.44 12906.56 76871.54 53.0

CountyMASON
Highway US0087
From VARIOUS LOCATIONS IN MASON COUNTY
To .
CSJ 6242-66-001
Proj ID RMC - 624266001
Work Type LITTER REMOVAL
 
0.001 69870.00 0.00 15521.00 22.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-12
Work Began 12-17-12
Work Completed  
Time Computed 12-17-12
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 18
Contractor(s)
H.T.S. CONSTRUCTION ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6242-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06121405
Totals 69870.00 0.00 15521.00 22.2

CountyWILLIAMSON
Highway FM0487
From VARIOUS LOCATIONS
To IN WILLIAMSON COUNTY
CSJ 6243-18-001
Proj ID SUP - 624318001
Work Type LITTER REMOVAL
 
0.001 123732.04 5036.26 60384.14 48.8
Work Order 05-07-12
Work Began 05-22-12
Work Completed  
Time Computed 05-21-12
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 376
Percent Time Used 51
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6243-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04121431
Totals 123732.04 5036.26 60384.14 48.8

CountyTRAVIS
Highway US0290
From VARIOUS LOCATIONS IN TRAVIS COUNTY
To .
CSJ 6243-24-001
Proj ID SUP - 624324001
Work Type LITTER REMOVAL
 
0.001 231277.92 16429.04 137492.79 59.4
Work Order 05-01-12
Work Began 05-01-12
Work Completed  
Time Computed 05-08-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 396
Percent Time Used 54
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6243-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04121430
Totals 231277.92 16429.04 137492.79 59.4

CountyGILLESPIE
Highway US0087
From FREDERICKSBURG MAINTENANCE OFFICE
To .
CSJ 6243-40-001
Proj ID SUP - 624340001
Work Type JANITORIAL MAINTENANCE
 
0.001 15163.56 538.41 7850.99 51.7
Work Order 05-14-12
Work Began 05-15-12
Work Completed  
Time Computed 05-21-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 382
Percent Time Used 52
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6243-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05121430
Totals 15163.56 538.41 7850.99 51.7

CountyTRAVIS
Highway RM1431
From TRAVIS NORTH MAINTENANCE OFFICE
To .
CSJ 6243-96-001
Proj ID SUP - 624396001
Work Type JANITORIAL MAINTENANCE
 
0.001 12843.12 535.13 6421.56 50.0
Work Order 05-29-12
Work Began 06-05-12
Work Completed  
Time Computed 06-01-12
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6243-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05121431
Totals 12843.12 535.13 6421.56 50.0

CountyTRAVIS
Highway LP0360
From LP360 SCENIC OVERLOOK
To .
CSJ 6244-79-001
Proj ID SUP - 624479001
Work Type PICNIC AREA MAINTENANCE AND MOWING
 
0.001 67220.00 2885.00 33060.00 49.1
Work Order 05-29-12
Work Began 06-01-12
Work Completed  
Time Computed 06-04-12
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6244-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05121432
Totals 67220.00 2885.00 33060.00 49.1

CountyMASON
Highway US0087
From AT LLANO RIVER
To .
CSJ 6244-90-001
Proj ID BPM - 624490001
Work Type BRIDGE REPAIRS
 
0.171 331426.33 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-16-13
Work Began 00-00-00
Work Completed  
Time Computed 05-16-13
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6244-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03131402
Totals 331426.33 0.00 0.00 0.0

CountyWILLIAMSON
Highway US0079
From RAILROAD OVERPASS AT US 79 IN TAYLOR,
To ETC.
CSJ 6245-38-001
Proj ID BPM - 624538001
Work Type BRIDGE PREVENTIVE MAINTENANCE
 
0.001 193743.00 0.00 142954.54 73.7
Work Order 12-05-12
Work Began 12-12-12
Work Completed  
Time Computed 12-12-12
Contract Working Days 40
Addl Days Granted 8
Working Days Charged 27
Percent Time Used 56
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11121404
Totals 193743.00 0.00 142954.54 73.7

CountyHAYS
Highway IH0035
From VARIOUS LOCATIONS IN HAYS COUNTY
To .
CSJ 6246-09-001
Proj ID SUP - 624609001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 115217.58 8375.08 57450.15 49.8
Work Order 07-01-12
Work Began 07-01-12
Work Completed  
Time Computed 07-02-12
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6246-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06121430
Totals 115217.58 8375.08 57450.15 49.8

CountyTRAVIS
Highway IH0035
From AUSTIN DISTRICT
To VARIOUS LOCATIONS
CSJ 6246-14-001
Proj ID RMC - 624614001
Work Type TRAFFIC SIGNAL MAINTENANCE
 
0.001 234685.00 2400.00 2400.00 1.0
Work Order 03-26-13
Work Began 04-03-13
Work Completed  
Time Computed 04-03-13
Contract Working Days 548
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 10
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6246-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01131401
Totals 234685.00 2400.00 2400.00 1.0

CountyBASTROP
Highway SH0071
From VARIOUS LOCATIONS IN
To BASTROP COUNTY
CSJ 6246-18-001
Proj ID RMC - 624618001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 205487.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WELLMANN ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6246-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131407
Totals 205487.00 0.00 0.00 0.0

CountyLEE
Highway US0290
From VARIOUS LOCATIONS IN
To LEE COUNTY
CSJ 6246-19-001
Proj ID RMC - 624619001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 211343.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-20-13
Work Began 00-00-00
Work Completed  
Time Computed 06-01-13
Contract Working Days 174
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6246-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131401
Totals 211343.68 0.00 0.00 0.0

CountyTRAVIS
Highway US0290
From TRAVIS SOUTH MAINTENANCE OFFICE
To .
CSJ 6246-40-001
Proj ID SUP - 624640001
Work Type JANITORIAL MAINTENANCE
 
0.001 11205.12 466.88 5018.96 44.7
Work Order 07-01-12
Work Began 07-01-12
Work Completed  
Time Computed 07-09-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6246-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07121430
Totals 11205.12 466.88 5018.96 44.7

CountyTRAVIS
Highway US0183
From VARIOUS LOCATIONS
To .
CSJ 6246-82-001
Proj ID BPM - 624682001
Work Type BRIDGE PREVENTIVE MAINTENANCE
 
0.001 61050.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 21
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPEDGE CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6246-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131401
Totals 61050.00 0.00 0.00 0.0

CountyTRAVIS
Highway US0183
From VARIOUS LOCATIONS IN TRAVIS COUNTY
To .
CSJ 6246-83-001
Proj ID RMC - 624683001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 213363.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-13
Work Began 00-00-00
Work Completed  
Time Computed 04-10-13
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SIGNATURE CONTRACTING SERVICES, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6246-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131403
Totals 213363.00 0.00 0.00 0.0

CountyGILLESPIE
Highway US0087
From VARIOUS LOCATIONS IN GILLESPIE, BLANCO,
To AND LLANO COUNTIES
CSJ 6247-42-001
Proj ID RMC - 624742001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 145510.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6247-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131402
Totals 145510.40 0.00 0.00 0.0

CountyMASON
Highway US0087
From VARIOUS LOCATIONS IN MASON, LLANO
To AND GILLESPIE_COUNTIES
CSJ 6247-43-001
Proj ID RMC - 624743001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 174866.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6247-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131404
Totals 174866.40 0.00 0.00 0.0

CountyLLANO
Highway SH0071
From VARIOUS LOCATIONS IN LLANO
To AND BURNET COUNTIES
CSJ 6247-44-001
Proj ID RMC - 624744001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 222332.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6247-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131406
Totals 222332.80 0.00 0.00 0.0

CountyTRAVIS
Highway US0183
From VARIOUS LOCATIONS IN TRAVIS
To AND WILLIAMSON COUNTIES
CSJ 6247-45-001
Proj ID SUP - 624745001
Work Type LITTER REMOVAL AND DISPOSAL
 
0.001 119009.24 0.00 0.00 8.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-01-13
Work Began 05-13-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6247-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131430
Totals 119009.24 0.00 0.00 8.4