Monthly Local Let Maintenance Report For Austin District As Of Aug 11, 2017 Page 2 Of 3

Last Update: Friday, August 11, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayRM1431
FromTRAVIS NORTH MAINTENANCE OFFICE
To.
CSJ6305-06-001
Proj IDSUP - 630506001
Work TypeJANITORIAL MAINTENANCE
 
0.00113601.287224.8053.1
Work Order00-00-00
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days731
Addl Days Granted0
Working Days Charged426
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161433
Totals13601.28478.067224.8053.1

CountyTRAVIS
HighwayFM0969
FromAT FM 969
ToOVER GILLELAND CREEK
CSJ6306-18-001
Proj IDBPM - 630618001
Work TypeRIPRAP REPAIR
 
0.100168715.0010500.006.2
Work Order00-00-00
Work Began07-19-17
Work Completed
Time Computed07-19-17
Contract Working Days24
Addl Days Granted0
Working Days Charged5
Percent Time Used20
Contractor(s)
FORSYTHE BROTHERS INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6306-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171401
Totals168715.0010500.0010500.006.2

CountyBURNET
HighwayUS0281
FromVARIOUS LOCATIONS IN BURNET, LLANO AND
ToWILLIAMSON COUNTIES
CSJ6307-21-001
Proj IDRMC - 630721001
Work TypeLITTER REMOVAL
 
0.001104505.1027627.6026.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-29-16
Work Completed
Time Computed03-27-17
Contract Working Days124
Addl Days Granted0
Working Days Charged32
Percent Time Used25
Contractor(s)
FLORES CONTRACTS
SUBCONTRACTOR(S) FOR CCSJ: 6307-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161401
Totals104505.100.0027627.6026.4

CountyTRAVIS
HighwayUS0290
FromTRAVIS SOUTH MAINTENANCE
To.
CSJ6307-32-001
Proj IDSUP - 630732001
Work TypeJANITORIAL MAINTENANCE
 
0.00111541.366251.5754.1
Work Order00-00-00
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged396
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161430
Totals11541.36480.896251.5754.1

CountyTRAVIS
HighwayIH0035
FromVARIOUS LOCATIONS DISTRICTWIDE
ToVARIOUS LOCATIONS DISTRICTWIDE
CSJ6307-55-001
Proj IDRMC - 630755001
Work TypeREPLACE SMALL SIGNS
 
0.001293800.0014550.004.9
Work Order00-00-00
Work Began06-10-17
Work Completed
Time Computed05-16-17
Contract Working Days730
Addl Days Granted0
Working Days Charged71
Percent Time Used9
Contractor(s)
L. UNITED BUILDING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6307-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171401
Totals293800.0014550.0014550.004.9

CountyTRAVIS
HighwayIH0035
FromAUSTIN DISTRICT HEADQUARTERS
To.
CSJ6308-02-001
Proj IDSUP - 630802001
Work TypeGROUNDS/LANDSCAPE MAINTENANCE
 
0.00131780.0056724.5099.9
Work Order00-00-00
Work Began08-03-16
Work Completed
Time Computed08-03-16
Contract Working Days365
Addl Days Granted61
Working Days Charged351
Percent Time Used82
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161430
Totals31780.004825.0056724.5099.9

CountyTRAVIS
HighwayIH0035
FromVARIOUS LOCATIONS ON IH35, US183
ToLP1, US290, ETC
CSJ6310-44-001
Proj IDSUP - 631044001
Work TypeLITTER PICK UP AND REMOVAL
 
0.001961240.40666957.6569.3
Work Order00-00-00
Work Began10-03-16
Work Completed
Time Computed10-03-16
Contract Working Days365
Addl Days Granted0
Working Days Charged185
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6310-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161430
Totals961240.4047597.75666957.6569.3

CountyGILLESPIE
HighwayUS0087
FromVARIOUS LOCATIONS IN GILLESPIE, BLANCO
ToAND LLANO COUNTIES
CSJ6310-66-001
Proj IDRMC - 631066001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001174624.80102870.8058.9
Work Order00-00-00
Work Began05-30-17
Work Completed
Time Computed05-30-17
Contract Working Days58
Addl Days Granted0
Working Days Charged13
Percent Time Used22
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6310-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171402
Totals174624.8059214.60102870.8058.9

CountyLLANO
HighwaySH0071
FromVARIOUS LOCATION IN LLANO, BURNET
ToAND BLANCO COUNTIES
CSJ6310-67-001
Proj IDRMC - 631067001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001218351.9254587.9825.0
Work Order00-00-00
Work Began06-20-17
Work Completed
Time Computed06-20-17
Contract Working Days76
Addl Days Granted0
Working Days Charged10
Percent Time Used13
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6310-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171401
Totals218351.9254587.9854587.9825.0

CountyMASON
HighwayUS0087
FromVARIOUS LOCATIONS IN MASON, LLANO
ToAND GILLESPIE COUNITES
CSJ6310-68-001
Proj IDRMC - 631068001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001198114.4049527.6024.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-22-17
Work Completed
Time Computed05-22-17
Contract Working Days66
Addl Days Granted0
Working Days Charged8
Percent Time Used12
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6310-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171403
Totals198114.400.0049527.6024.9

CountyTRAVIS
HighwayUS0183
FromVARIOUS LOCATIONS
ToIN TRAVIS COUNTY
CSJ6310-96-001
Proj IDRMC - 631096001
Work TypeMOWING
 
0.001252179.0050235.8019.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days41
Addl Days Granted0
Working Days Charged9
Percent Time Used21
Contractor(s)
C & C MOWING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171404
Totals252179.000.0050235.8019.9

CountyWILLIAMSON
HighwayFM0487
FromVARIOUS LOCATIONS
ToIN WILLIAMSON COUNTY
CSJ6311-58-001
Proj IDSUP - 631158001
Work TypeLITTER REMOVAL
 
0.001107335.5071539.4466.6
Work Order00-00-00
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161433
Totals107335.504174.8971539.4466.6

CountyTRAVIS
HighwayIH0035
FromSOUTH AUSTIN
ToAREA OFFICE
CSJ6311-97-001
Proj IDSUP - 631197001
Work TypeJANITORIAL MAINTENANCE
 
0.00139408.0013230.0033.5
Work Order00-00-00
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged273
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161432
Totals39408.001470.0013230.0033.5

CountyWILLIAMSON
HighwayUS0079
FromVARIOUS ROADWAYS IN WILLIAMSON
ToTO TRAVIS AND BASTROP COUNTIES
CSJ6312-05-001
Proj IDSUP - 631205001
Work TypeLITTER PICK UP AND REMOVAL
 
0.00156868.0047652.0083.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-14-16
Work Completed
Time Computed12-14-16
Contract Working Days44
Addl Days Granted0
Working Days Charged8
Percent Time Used18
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161430
Totals56868.000.0047652.0083.7

CountyTRAVIS
HighwayUS0290
FromVARIOUS LOCATIONS IN TRAVIS COUNTY
To.
CSJ6312-68-001
Proj IDSUP - 631268001
Work TypeLITTER REMOVAL
 
0.00168631.7551382.7574.8
Work Order12-15-16
Work Began12-21-16
Work Completed
Time Computed12-21-16
Contract Working Days365
Addl Days Granted0
Working Days Charged227
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161430
Totals68631.754183.0051382.7574.8

CountyLLANO
HighwaySH0016
FromVARIOUS LOCATIONS
To.
CSJ6312-99-001
Proj IDSUP - 631299001
Work TypeLITTER PICK UP AND REMOVAL
 
0.00142039.8137796.7789.9
Work Order00-00-00
Work Began12-19-16
Work Completed
Time Computed12-19-16
Contract Working Days40
Addl Days Granted0
Working Days Charged11
Percent Time Used27
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161431
Totals42039.8116620.2937796.7789.9

CountyWILLIAMSON
HighwayUS0079
FromTAYLOR MAINTENANCE SECTION
To.
CSJ6313-06-001
Proj IDSUP - 631306001
Work TypeJANITORIAL MAINTENANCE
 
0.0014507.443004.9666.6
Work Order00-00-00
Work Began12-01-16
Work Completed
Time Computed12-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161432
Totals4507.44375.623004.9666.6

CountyTRAVIS
HighwayIH0035
FromAUSTIN DISTRICT HEADQUARTERS
To.
CSJ6313-64-001
Proj IDSUP - 631364001
Work TypeJANITORIAL MAINTENANCE
 
0.00191494.4254636.9659.7
Work Order00-00-00
Work Began01-01-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged211
Percent Time Used57
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6313-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161431
Totals91494.425871.2154636.9659.7

CountyTRAVIS
HighwayUS0290
FromVARIOUS PONDS
ToIN THE TRAVIS SOUTH MO AREA
CSJ6313-76-001
Proj IDSUP - 631376001
Work TypeDETENTION POND LITTER PICK UP REMOVAL
 
0.00126364.760.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161433
Totals26364.760.000.000.0

CountyHAYS
HighwayIH0035
FromVARIOUS LOCATIONS IN HAYS COUNTY
To.
CSJ6313-77-001
Proj IDSUP - 631377001
Work TypeLITTER PICKUP AND REMOVAL
 
0.00128977.9218024.5662.2
Work Order00-00-00
Work Began01-24-17
Work Completed
Time Computed01-24-17
Contract Working Days26
Addl Days Granted0
Working Days Charged14
Percent Time Used53
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6313-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161432
Totals28977.924431.5218024.5662.2