Monthly Local Let Maintenance Report For Austin District As Of Nov 9, 2016 Page 2 Of 4

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWILLIAMSON
Highway US0079
From TAYLOR MAINTENANCE SECTION
To .
CSJ 6282-18-001
Proj ID SUP - 628218001
Work Type JANITORIAL MAINTENANCE
 
0.001 8752.32 364.68 8387.64 95.8
Work Order 00-00-00
Work Began 12-02-14
Work Completed  
Time Computed 12-07-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 701
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141430
Totals 8752.32 364.68 8387.64 95.8

CountyBASTROP
Highway FM3000
From ELGIN TO 3.7 MILES NE
To .
CSJ 6284-16-001
Proj ID SUP - 628416001
Work Type LITTER PICKUP AND REMOVAL
 
0.001 176356.04 0.00 163129.32 92.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 02-24-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6284-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151431
Totals 176356.04 0.00 163129.32 92.4

CountyTRAVIS
Highway FM0734
From TRAVIS CENTRAL/NORTH TRAVIS AO
To .
CSJ 6287-65-001
Proj ID SUP - 628765001
Work Type JANITORIAL MAINTENANCE
 
0.001 19152.72 798.03 14364.54 75.0
Work Order 00-00-00
Work Began 05-01-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 544
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04151430
Totals 19152.72 798.03 14364.54 75.0

CountyTRAVIS
Highway IH0035
From VARIOUS LOCATIONS DISTRICT-WIDE
To VARIOUS LOCATIONS DISTRICT-WIDE
CSJ 6288-81-001
Proj ID RMC - 628881001
Work Type MAINTENANCE OF ILLUMINATION
 
0.001 251109.00 0.00 309025.76 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 300
Percent Time Used 41
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10151405
Totals 251109.00 0.00 309025.76 99.9

CountyTRAVIS
Highway IH0035
From VARIOUS LOCATIONS DISTRICT-WIDE
To VARIOUS LOCATIONS DISTRICT-WIDE
CSJ 6288-82-001
Proj ID RMC - 628882001
Work Type MAINTENANCE OF ILLUMINATION
 
0.001 347455.00 0.00 152162.50 43.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 239
Percent Time Used 32
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10151406
Totals 347455.00 0.00 152162.50 43.7

CountyTRAVIS
Highway FM0969
From TRAVIS EAST MAINTENANCE OFFICE
To .
CSJ 6289-18-001
Proj ID SUP - 628918001
Work Type JANITORIAL MAINTENANCE
 
0.001 8591.04 0.00 6085.32 70.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 519
Percent Time Used 71
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05151431
Totals 8591.04 0.00 6085.32 70.8

CountyBASTROP
Highway SH0021
From BASTROP MAINTENANCE OFFICE
To .
CSJ 6289-19-001
Proj ID SUP - 628919001
Work Type JANITORIAL MAINTENANCE
 
0.001 23191.68 0.00 16427.44 70.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 519
Percent Time Used 71
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05151432
Totals 23191.68 0.00 16427.44 70.8

CountyHAYS
Highway RM0012
From BLANCO RIVER
To BLANCO RIVER
CSJ 6289-77-001
Proj ID EMC - 628977001
Work Type BRIDGE RAIL REPAIR
 
0.100 724979.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6289-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06151430
Totals 724979.00 0.00 0.00 0.0

CountyWILLIAMSON
Highway IH0035
From GEORGETOWN AREA OFFICE
To .
CSJ 6291-27-001
Proj ID SUP - 629127001
Work Type JANITORIAL MAINTENANCE
 
0.001 14709.44 598.56 8978.40 61.0
Work Order 00-00-00
Work Began 08-01-15
Work Completed  
Time Computed 08-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 458
Percent Time Used 62
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07151433
Totals 14709.44 598.56 8978.40 61.0

CountyHAYS
Highway US0290
From VARIOUS LOCATIONS IN
To HAYS AND TRAVIS COUNTIES
CSJ 6291-56-001
Proj ID RMC - 629156001
Work Type TREE TRIMMING & BRUSH REMOVAL
 
0.001 93807.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6291-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10151401
Totals 93807.10 0.00 0.00 0.0

CountyMASON
Highway SH0029
From MASON COUNTY MAINTENANCE OFFICE
To .
CSJ 6291-91-001
Proj ID SUP - 629191001
Work Type JANITORIAL MAINTENANCE
 
0.001 13622.52 0.00 7580.64 55.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 458
Percent Time Used 62
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07151435
Totals 13622.52 0.00 7580.64 55.6

CountyBLANCO
Highway US0281
From VARIOUS LOCATIONS IN BLANCO, GILLESPIE
To TO BURNET AND HAYS COUNTIES
CSJ 6293-70-001
Proj ID SUP - 629370001
Work Type LITTER REMOVAL
 
0.001 98906.40 0.00 40873.43 41.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6293-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151431
Totals 98906.40 0.00 40873.43 41.3

CountyTRAVIS
Highway FM1100
From APPROX. 3 MILES WEST OF SH 95 TO 3.074
To MILES WEST OF SH 95
CSJ 6293-95-001
Proj ID RMC - 629395001
Work Type GRADING AND STRUCTURE REPAIR
 
0.001 136025.00 0.00 151676.94 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 22
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 100
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10151404
Totals 136025.00 0.00 151676.94 99.9

CountyWILLIAMSON
Highway IH0035
From VARIOUS LOCATIONS IN WILLIAMSON ANDT
To TRAVIS COUNTY
CSJ 6294-34-001
Proj ID SUP - 629434001
Work Type LITTER PICK UP AND REMOVAL
 
0.001 100686.08 0.00 62928.80 62.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6294-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151432
Totals 100686.08 0.00 62928.80 62.5

CountyTRAVIS
Highway IH0035
From VARIOUS LOCATIONS
To IN THE AUSTIN DISTRICT
CSJ 6295-27-001
Proj ID RMC - 629527001
Work Type SURFACE ABRADING
 
0.100 235000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUMBLE EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04161401
Totals 235000.00 0.00 0.00 0.0

CountyCALDWELL
Highway US0183
From VARIOUS LOCATIONS IN CALDWELL
To BASTROP AND HAYS COUNTIES
CSJ 6296-10-001
Proj ID SUP - 629610001
Work Type LITTER REMOVAL AND DISPOSAL
 
0.001 95748.12 0.00 39118.40 40.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 02-01-16
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 14
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6296-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09151431
Totals 95748.12 0.00 39118.40 40.8

CountyLLANO
Highway SH0016
From VARIOUS LOCATIONS IN LLANO
To .
CSJ 6297-32-001
Proj ID SUP - 629732001
Work Type LITTER REMOVAL
 
0.001 42518.79 0.00 37142.08 87.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 53
Contractor(s)
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10151430
Totals 42518.79 0.00 37142.08 87.3

CountyLLANO
Highway SH0016
From LLANO COUNTY MAINTENANCE OFFICE
To .
CSJ 6298-61-001
Proj ID SUP - 629861001
Work Type JANITORIAL MAINTENANCE
 
0.001 14981.92 507.20 6281.48 41.9
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 10-31-16
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 305
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12151430
Totals 14981.92 507.20 6281.48 41.9

CountyGILLESPIE
Highway US0290
From VARIOUS LOCATIONS IN GILLESPIE
To .
CSJ 6298-97-001
Proj ID SUP - 629897001
Work Type LITTER PICKUP
 
0.001 82670.66 0.00 14883.57 18.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 6
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6298-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12151431
Totals 82670.66 0.00 14883.57 18.0

CountyHAYS
Highway SH0021
From 0.33 MILES WEST OF FM 2001 NORTH
To 0.16 MILES WEST OF FM 2001 NORTH
CSJ 6299-16-001
Proj ID EMC - 629916001
Work Type CULVERT REPLACEMENT
 
0.172 943304.00 0.00 1109872.89 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 45
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6299-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02161401
Totals 943304.00 0.00 1109872.89 99.9