Monthly Local Let Maintenance Report For Austin District As Of Jan 11, 2017 Page 2 Of 4

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayIH0035
FromVARIOUS LOCATIONS DISTRICT-WIDE
ToVARIOUS LOCATIONS DISTRICT-WIDE
CSJ6288-82-001
Proj IDRMC - 628882001
Work TypeMAINTENANCE OF ILLUMINATION
 
0.001347455.00168230.0048.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged300
Percent Time Used41
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10151406
Totals347455.000.00168230.0048.4

CountyTRAVIS
HighwayFM0969
FromTRAVIS EAST MAINTENANCE OFFICE
To.
CSJ6289-18-001
Proj IDSUP - 628918001
Work TypeJANITORIAL MAINTENANCE
 
0.0018591.046801.2479.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged580
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151431
Totals8591.040.006801.2479.1

CountyBASTROP
HighwaySH0021
FromBASTROP MAINTENANCE OFFICE
To.
CSJ6289-19-001
Proj IDSUP - 628919001
Work TypeJANITORIAL MAINTENANCE
 
0.00123191.6818360.0879.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged580
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151432
Totals23191.680.0018360.0879.1

CountyHAYS
HighwayRM0012
FromBLANCO RIVER
ToBLANCO RIVER
CSJ6289-77-001
Proj IDEMC - 628977001
Work TypeBRIDGE RAIL REPAIR
 
0.100724979.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6289-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151430
Totals724979.000.000.000.0

CountyWILLIAMSON
HighwayIH0035
FromGEORGETOWN AREA OFFICE
To.
CSJ6291-27-001
Proj IDSUP - 629127001
Work TypeJANITORIAL MAINTENANCE
 
0.00114709.4410175.5269.1
Work Order00-00-00
Work Began08-01-15
Work Completed
Time Computed08-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged519
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151433
Totals14709.44598.5610175.5269.1

CountyHAYS
HighwayUS0290
FromVARIOUS LOCATIONS IN
ToHAYS AND TRAVIS COUNTIES
CSJ6291-56-001
Proj IDRMC - 629156001
Work TypeTREE TRIMMING & BRUSH REMOVAL
 
0.00193807.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days17
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6291-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10151401
Totals93807.100.000.000.0

CountyMASON
HighwaySH0029
FromMASON COUNTY MAINTENANCE OFFICE
To.
CSJ6291-91-001
Proj IDSUP - 629191001
Work TypeJANITORIAL MAINTENANCE
 
0.00113622.528508.4262.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-15
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged519
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151435
Totals13622.520.008508.4262.4

CountyBLANCO
HighwayUS0281
FromVARIOUS LOCATIONS IN BLANCO, GILLESPIE
ToTO BURNET AND HAYS COUNTIES
CSJ6293-70-001
Proj IDSUP - 629370001
Work TypeLITTER REMOVAL
 
0.00198906.4049496.1550.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged29
Percent Time Used29
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6293-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151431
Totals98906.400.0049496.1550.0

CountyWILLIAMSON
HighwayIH0035
FromVARIOUS LOCATIONS IN WILLIAMSON ANDT
ToTRAVIS COUNTY
CSJ6294-34-001
Proj IDSUP - 629434001
Work TypeLITTER PICK UP AND REMOVAL
 
0.001100686.0873111.7472.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days170
Addl Days Granted0
Working Days Charged65
Percent Time Used38
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6294-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151432
Totals100686.080.0073111.7472.6

CountyTRAVIS
HighwayIH0035
FromVARIOUS LOCATIONS
ToIN THE AUSTIN DISTRICT
CSJ6295-27-001
Proj IDRMC - 629527001
Work TypeSURFACE ABRADING
 
0.100235000.00269630.8299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged10
Percent Time Used28
Contractor(s)
HUMBLE EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161401
Totals235000.000.00269630.8299.9

CountyCALDWELL
HighwayUS0183
FromVARIOUS LOCATIONS IN CALDWELL
ToBASTROP AND HAYS COUNTIES
CSJ6296-10-001
Proj IDSUP - 629610001
Work TypeLITTER REMOVAL AND DISPOSAL
 
0.00195748.1259439.8562.0
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed02-01-16
Contract Working Days106
Addl Days Granted0
Working Days Charged19
Percent Time Used17
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6296-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151431
Totals95748.1220321.4559439.8562.0

CountyLLANO
HighwaySH0016
FromLLANO COUNTY MAINTENANCE OFFICE
To.
CSJ6298-61-001
Proj IDSUP - 629861001
Work TypeJANITORIAL MAINTENANCE
 
0.00114981.927295.8848.6
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed10-31-16
Contract Working Days730
Addl Days Granted0
Working Days Charged366
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151430
Totals14981.92507.207295.8848.6

CountyGILLESPIE
HighwayUS0290
FromVARIOUS LOCATIONS IN GILLESPIE
To.
CSJ6298-97-001
Proj IDSUP - 629897001
Work TypeLITTER PICKUP
 
0.00182670.6628097.1133.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged4
Percent Time Used6
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6298-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151431
Totals82670.660.0028097.1133.9

CountyHAYS
HighwaySH0021
From0.33 MILES WEST OF FM 2001 NORTH
To0.16 MILES WEST OF FM 2001 NORTH
CSJ6299-16-001
Proj IDEMC - 629916001
Work TypeCULVERT REPLACEMENT
 
0.172943304.001109872.8999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged27
Percent Time Used45
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6299-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02161401
Totals943304.000.001109872.8999.9

CountyTRAVIS
HighwayUS0290
FromVARIOUS LOCATIONS IN TRAVIS AND HAYS
To.
CSJ6300-45-001
Proj IDSUP - 630045001
Work TypeLITTER PICK UP AND REMOVAL
 
0.001168515.5052797.9931.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged244
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02161430
Totals168515.500.0052797.9931.3

CountyHAYS
HighwaySH0021
FromHAYS COUNTY MAINTENANCE OFFICE
To.
CSJ6301-10-001
Proj IDSUP - 630110001
Work TypeJANITORIAL MAINTENANCE
 
0.00116791.605462.1032.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged275
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161430
Totals16791.600.005462.1032.5

CountyHAYS
HighwayIH0035
FromVARIOUS LOCATIONS IN HAYS COUNTIES
To.
CSJ6302-72-001
Proj IDSUP - 630272001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.00126390.406597.6025.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-16
Work Completed
Time Computed00-00-00
Contract Working Days24
Addl Days Granted0
Working Days Charged3
Percent Time Used12
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAP ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6302-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161430
Totals26390.400.006597.6025.0

CountyBASTROP
HighwayFM0020
FromVARIOUS LOCATIONS IN BASTROP,
ToCALDWELL AND LEE COUNTIES
CSJ6302-99-001
Proj IDRMC - 630299001
Work TypeTREE TRIMMING/BRUSH REMOVAL
 
38.105293331.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161402
Totals293331.850.000.000.0

CountyWILLIAMSON
HighwayUS0079
FromVARIES
ToVARIES
CSJ6304-07-001
Proj IDRMC - 630407001
Work TypeCRACK SEALING
 
0.001214885.16140518.7665.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged12
Percent Time Used26
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6304-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161405
Totals214885.160.00140518.7665.3

CountyTRAVIS
HighwayUS0183
FromVARIOUS LOCATION IN WILLIAMSON
ToAND TRAVIS COUNTY
CSJ6304-08-001
Proj IDRMC - 630408001
Work TypeTREE TRIMMING & TREE/BRUSH REMOVAL
 
0.001213604.8154955.3325.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged25
Percent Time Used41
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161403
Totals213604.810.0054955.3325.7

page 1 | page 2 | page 3 | page 4