Monthly Local Let Maintenance Report For Austin District As Of Apr 11, 2014 Page 2 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLLANO
Highway SH0071
From VARIOUS LOCATIONS IN LLANO
To AND BURNET COUNTIES
CSJ 6247-44-001
Proj ID RMC - 624744001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 222332.80 0.00 111166.40 50.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-12-13
Work Began 06-14-13
Work Completed  
Time Computed 06-20-13
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 14
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6247-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131406
Totals 222332.80 0.00 111166.40 50.0

CountyTRAVIS
Highway US0183
From VARIOUS LOCATIONS IN TRAVIS
To AND WILLIAMSON COUNTIES
CSJ 6247-45-001
Proj ID SUP - 624745001
Work Type LITTER REMOVAL AND DISPOSAL
 
0.001 119009.24 4326.20 57341.52 48.1
Work Order 05-01-13
Work Began 05-13-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6247-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131430
Totals 119009.24 4326.20 57341.52 48.1

CountyTRAVIS
Highway FM0734
From TRAVIS CENTRAL/NORTH TRAVIS AO
To .
CSJ 6247-46-001
Proj ID SUP - 624746001
Work Type JANITORIAL MAINTENANCE
 
0.001 18641.28 776.72 8543.92 45.8
Work Order 05-17-13
Work Began 05-17-13
Work Completed  
Time Computed 05-24-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 312
Percent Time Used 42
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6247-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131430
Totals 18641.28 776.72 8543.92 45.8

CountyTRAVIS
Highway IH0035
From AUSTIN DISTRICT
To VARIOUS LOCATIONS
CSJ 6247-48-001
Proj ID RMC - 624748001
Work Type MAINTENANCE OF SIGNS
 
0.001 104500.00 0.00 61602.73 58.9
Work Order 12-13-12
Work Began 01-02-13
Work Completed  
Time Computed 01-02-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 454
Percent Time Used 62
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6247-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11121403
Totals 104500.00 0.00 61602.73 58.9

CountyTRAVIS
Highway IH0035
From SOUTH TRAVIS AREA OFFICE
To .
CSJ 6251-27-001
Proj ID SUP - 625127001
Work Type JANITORIAL MAINTENANCE
 
0.001 28656.00 1066.00 18655.00 65.0
Work Order 10-17-12
Work Began 10-17-12
Work Completed  
Time Computed 10-24-12
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 531
Percent Time Used 72
Contractor(s)
TIBH INDUSTRIES, INC.
VAUGHN HOUSE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10121430
Totals 28656.00 1066.00 18655.00 65.0

CountyWILLIAMSON
Highway US0079
From TAYLOR MAINTENANCE SECTION
To .
CSJ 6252-26-001
Proj ID SUP - 625226001
Work Type JANITORIAL MAINTENANCE
 
0.001 8752.32 364.68 6017.22 68.7
Work Order 11-13-12
Work Began 11-20-12
Work Completed  
Time Computed 11-20-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 497
Percent Time Used 68
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11121430
Totals 8752.32 364.68 6017.22 68.7

CountyTRAVIS
Highway IH0035
From AUSTIN DISTRICT HEADQUARTERS
To .
CSJ 6252-48-001
Proj ID SUP - 625248001
Work Type JANITORIAL MAINTENANCE
 
0.001 157238.22 7514.18 80669.81 51.3
Work Order 01-09-13
Work Began 01-15-13
Work Completed  
Time Computed 01-16-13
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 410
Percent Time Used 56
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6252-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01131430
Totals 157238.22 7514.18 80669.81 51.3

CountyTRAVIS
Highway IH0035
From VARIOUS LOCATIONS DISTRICT-WIDE
To VARIOUS LOCATIONS DISTRICT-WIDE
CSJ 6254-34-001
Proj ID RMC - 625434001
Work Type MAINTENANCE OF ILLUMINATION
 
0.001 246993.00 14865.00 86305.30 34.9
Work Order 05-27-13
Work Began 06-03-13
Work Completed  
Time Computed 06-03-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 302
Percent Time Used 41
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6254-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131402
Totals 246993.00 14865.00 86305.30 34.9

CountyBURNET
Highway US0281
From VARIOUS LOCATIONS
To IN THE AUSTIN DISTRICT
CSJ 6257-41-001
Proj ID RMC - 625741001
Work Type SURFACE ABRADING
 
0.001 192589.00 0.00 72719.17 37.7
Work Order 09-16-13
Work Began 09-16-13
Work Completed  
Time Computed 09-16-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 197
Percent Time Used 53
Contractor(s)
HUMBLE EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131401
Totals 192589.00 0.00 72719.17 37.7

CountyBURNET
Highway RM1431
From AVENUE U
To AVENUE D
CSJ 6258-14-001
Proj ID RMC - 625814001
Work Type SPOT PAVEMENT REPAIR
 
1.322 79320.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6258-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131402
Totals 79320.00 0.00 0.00 0.0

CountyTRAVIS
Highway FM0969
From FM 969 AT GILLELAND CREEK BRIDGE
To .
CSJ 6259-99-001
Proj ID BPM - 625999001
Work Type BRIDGE PREVENTIVE MAINTENANCE
 
0.050 112950.00 26420.00 26420.00 23.3
Work Order 00-00-00
Work Began 03-14-14
Work Completed  
Time Computed 03-14-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 22
Contractor(s)
FORSYTHE BROTHERS INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6259-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01141402
Totals 112950.00 26420.00 26420.00 23.3

CountyTRAVIS
Highway IH0035
From VARIOUS LOCATIONS DISTRICT-WIDE
To VARIOUS LOCATIONS DISTRICT-WIDE
CSJ 6260-00-001
Proj ID RMC - 626000001
Work Type MAINTENANCE OF ILLUMINATION
 
0.001 235885.00 17267.50 63666.30 26.9
Work Order 08-23-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 29
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131401
Totals 235885.00 17267.50 63666.30 26.9

CountyTRAVIS
Highway FM0969
From TRAVIS EAST MAINTENANCE OFFICE
To .
CSJ 6260-08-001
Proj ID SUP - 626008001
Work Type JANITORIAL MAINTENANCE
 
0.001 8147.76 339.49 3394.90 41.6
Work Order 06-03-13
Work Began 06-03-13
Work Completed  
Time Computed 06-03-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 295
Percent Time Used 40
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131432
Totals 8147.76 339.49 3394.90 41.6

CountyBASTROP
Highway SH0021
From BASTROP MAINTENANCE OFFICE
To .
CSJ 6260-09-001
Proj ID SUP - 626009001
Work Type JANITORIAL MAINTENANCE
 
0.001 22362.48 931.77 9317.70 41.6
Work Order 06-01-13
Work Began 06-04-13
Work Completed  
Time Computed 06-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131433
Totals 22362.48 931.77 9317.70 41.6

CountyTRAVIS
Highway IH0035
From ONE SIDE
To THE OTHER
CSJ 6260-75-001
Proj ID RMC - 626075001
Work Type OVERLAY AND RESTRIPE
 
1.000 268000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 10
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6260-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141401
Totals 268000.00 0.00 0.00 0.0

CountyMASON
Highway SH0029
From MASON COUNTY MAINTENANCE OFFICE
To .
CSJ 6261-44-001
Proj ID SUP - 626144001
Work Type JANITORIAL MAINTENANCE
 
0.001 13355.32 454.79 3638.32 27.2
Work Order 07-24-13
Work Began 08-01-13
Work Completed  
Time Computed 08-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131430
Totals 13355.32 454.79 3638.32 27.2

CountyWILLIAMSON
Highway IH0035
From GEORGETOWN AREA OFFICE
To .
CSJ 6261-62-001
Proj ID SUP - 626162001
Work Type JANITORIAL MAINTENANCE
 
0.001 14239.28 578.97 4631.76 32.5
Work Order 07-31-13
Work Began 08-07-13
Work Completed  
Time Computed 08-06-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 238
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131431
Totals 14239.28 578.97 4631.76 32.5

CountyBLANCO
Highway US0281
From VARIOUS LOCATIONS IN BLANCO,GILLESPIE
To TO BURNET AND HAYS COUNTIES
CSJ 6263-84-001
Proj ID SUP - 626384001
Work Type LITTER REMOVAL
 
0.001 88978.50 0.00 12538.50 14.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-02-13
Work Began 12-09-13
Work Completed  
Time Computed 12-09-13
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 7
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6263-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131430
Totals 88978.50 0.00 12538.50 14.0

CountyTRAVIS
Highway US0183
From VARIOUS LOCATION
To IN TRAVIS COUNTY
CSJ 6263-99-001
Proj ID RMC - 626399001
Work Type CRACK SEALING ASPHALT PAVEMENT
 
0.010 208213.80 37374.02 203126.24 97.5
Work Order 02-03-14
Work Began 02-10-14
Work Completed  
Time Computed 02-10-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 37
Contractor(s)
FYL ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6263-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131401
Totals 208213.80 37374.02 203126.24 97.5

CountyTRAVIS
Highway US0183
From US 183 NB FRONTAGE FROM LP 360 TO
To DRIVEWAY
CSJ 6264-00-001
Proj ID RMC - 626400001
Work Type RIP - RAP
 
0.379 189635.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141403
Totals 189635.00 0.00 0.00 0.0

page 1 | page 2 | page 3