Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPANOLA
Highway FM 1251
From 1.15 MI. E. OF FM 3231
To 1.893 MI. E. OF FM 3231
CSJ 1388-02-008
Proj ID CC 1388-2-8
Work Type GR, STR, BS, SURF, PAV MK
 
0.743 2821475.92 132737.49 2443998.03 90.5
Work Order 04-11-07
Work Began 04-30-07
Work Completed  
Time Computed 04-27-07
Contract Working Days 175
Addl Days Granted 1
Working Days Charged 187
Percent Time Used 106
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1388-02-008
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.85%)
PANOLA LIGHT & SIGN(0.27%)
STRIPING TECHNOLOGY, L.P.(0.69%)
D. B. INDUSTRIES, INC. (0.71%)
SOUTHWEST ENVIRONMENT SERVICES, INC. (0.66%)
ODUM SERVICES, L.P.(0.72%)
Contract # 03073008
Totals 2821475.92 132737.49 2443998.03 90.5

CountyUPSHUR
Highway FM 726
From AT WALNUT CREEK
To .
CSJ 1895-01-024
Proj ID BR 2008(566)
Work Type REHABILITATE BRIDGE AND APPROACHES
 
0.148 621123.42 59211.50 360590.46 58.0
Work Order 07-10-08
Work Began 07-30-08
Work Completed  
Time Computed 07-26-08
Contract Working Days 80
Addl Days Granted 3
Working Days Charged 49
Percent Time Used 59
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1895-01-024
JONA CONTRACTING, INC. (8.04%)
STRIPING TECHNOLOGY, L.P.(9.71%)
SOUTHWEST ENVIRONMENT SERVICES, INC. (0.51%)
D. B. INDUSTRIES, INC. (1.08%)
PANOLA SIGN & BARRICADE, INC.(1.05%)
Contract # 05083219
Totals 621123.42 59211.50 360590.46 58.0

CountyUPSHUR
Highway FM 2685
From AT GLADE CREEK
To .
CSJ 2157-01-016
Proj ID BR 2009(147)
Work Type REHABILITATE BRIDGE AND APPROACHES
 
0.142 637773.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2157-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12083014
Totals 637773.56 0.00 0.00 0.0

CountyPANOLA
Highway FM 2517
From AT SIX MILE CREEK, SIX MILE CREEK R
To SABINE RIVER & SABINE RIVER RELIEF
CSJ 2239-01-021
Proj ID BR 2008(808)
Work Type REPLACE / WIDEN BRIDGES & APPROACHES
 
2.261 5816981.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 385
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2239-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11083203
Totals 5816981.05 0.00 0.00 0.0