Monthly State Let Construction Report For Atlanta District As Of Jun 15, 2016 Page 2 Of 2

Last Update: Wednesday, June 15, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRISON
Highway IH 20
From GREGG COUNTY LINE
To 0.5 MI. W. OF SH 43
CSJ 0495-08-096
Proj ID NH 2016(083)
Work Type INSTALL & UPGRADE ROADWAY LIGHTING
 
38.808 1038536.77 19606.34 499609.13 48.1
Work Order 10-21-15
Work Began 02-24-16
Work Completed  
Time Computed 02-19-16
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 14
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-096
FLEX SUPPLY, LLC (4.18%)
RANSOM DRILLING SERVICES, LLC(2.02%)
PATTERSON COMPLETE TREE SERV(OLD PRIME)(0.84%)
Contract # 09153216
Totals 1038536.77 19606.34 499609.13 48.1

CountyUPSHUR
Highway SH 155
From AT SABINE RIVER & SABINE RIVER RELI
To SOUTH OF BIG SANDY
CSJ 0520-02-037
Proj ID BR 2013(823)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.692 12644943.11 -194213.83 8429984.20 66.6
CountyUPSHUR
Highway SH 155
From AT UNION PACIFIC RAILROAD OVERPASS
To S. OF BIG SANDY
CSJ 0520-02-038
Proj ID BR 2013(823)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.117 2277242.66 444225.00 1615281.17 70.9
CountyUPSHUR
Highway SH 155
From SABINE RIVER RELIEF BRIDGE
To U.P.R.R. OVERPASS
CSJ 0520-02-039
Proj ID C 520-2-39
Work Type GR, STR, BASE, SURF
 
1.274 3947700.40 43743.50 2441489.99 61.8
Work Order 09-09-13
Work Began 09-30-13
Work Completed  
Time Computed 09-30-13
Contract Working Days 780
Addl Days Granted 0
Working Days Charged 440
Percent Time Used 56
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0520-02-037
MAC TRANSPORTATION, LTD, L.L.P.(6.50%)
STRIPING TECHNOLOGY, L.P.(1.11%)
AMERICAN REMEDIATION OPTIONS, INC. (0.56%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.31%)
ODUM SERVICES, L.P.(1.00%)
PANOLA SIGN & BARRICADE, INC.(0.16%)
HIGHWAY 19 CONSTRUCTION, LLC (0.62%)
ATS DRILLING, INC. (7.12%)
MCL CONTRACTING, LLC (0.20%)
TEX OP CONSTRUCTION, LP(0.02%)
Contract # 07133204
Totals 18869886.17 293754.67 12486755.36 66.1

CountyCASS
Highway FM 1399
From FM 250
To SH 8
CSJ 0546-08-011
Proj ID STP 2016(338)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
15.694 1162910.40 75731.79 477105.04 41.0
Work Order 12-21-15
Work Began 01-20-16
Work Completed  
Time Computed 01-20-16
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 36
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0546-08-011
N-LINE TRAFFIC MAINTENANCE, L.P. (1.16%)
SOUTHWEST ENVIRONMENT SERVICES LLC (4.54%)
DUSTIN ALLEN, INC. (4.76%)
Contract # 11153013
Totals 1162910.40 75731.79 477105.04 41.0

CountyCASS
Highway FM 1399
From FM 250
To SH 8
CSJ 0546-08-012
Proj ID STP 2016(138)HESG
Work Type FLASH CHEV, TEXT SHLDR & CL TEXTURE
 
24.202 896724.18 0.00 892454.13 99.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-24-15
Work Began 03-07-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 43
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0546-08-012
BRYDL CONTRACTING, INC.(0.78%)
Contract # 10153007
Totals 896724.18 0.00 892454.13 99.5

CountyCASS
Highway FM 125
From SH 43
To LOUISIANA STATE LINE
CSJ 0546-09-039
Proj ID STP 1502(226)HES
Work Type GR, STR, BS, SURF, HFST & PAV MRKS
 
37.671 3490097.96 394757.70 502237.70 14.3
Work Order 08-13-15
Work Began 05-25-16
Work Completed  
Time Computed 09-12-15
Contract Working Days 260
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 0
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0546-09-039
POLY-CARB, INC.(3.69%)
PANOLA SIGN & BARRICADE, INC.(0.89%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.98%)
STRIPE-A-ZONE, INC.( 13.72%)
TX TINMAN ENTERPRISES, LLC.(5.00%)
Contract # 06153214
Totals 3490097.96 394757.70 502237.70 14.3

CountyTITUS
Highway IH 30
From FRANKLIN COUNTY LINE
To MORRIS COUNTY LINE
CSJ 0610-03-079
Proj ID NH 2015(407)
Work Type PAV REP, ACP SURFACING AND PAV MARK
 
97.964 33725327.54 112750.00 21208624.90 62.8
Work Order 02-10-15
Work Began 04-15-15
Work Completed  
Time Computed 04-11-15
Contract Working Days 595
Addl Days Granted 0
Working Days Charged 228
Percent Time Used 38
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-03-079
DUSTROL, INC.(3.91%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.33%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.32%)
DUSTIN ALLEN, INC. (3.58%)
STRIPE-A-ZONE, INC.(7.29%)
JM YANEZ CONSTRUCTION(1.60%)
SCR CONSTRUCTION CO., INC. (1.48%)
EAST TEXAS BRIDGE, INC.(9.22%)
STRAIGHT LINE SAWING & SEALING (0.36%)
SAMMY GIST ENTERPRISES, INC. (0.20%)
BRYDL CONTRACTING, INC.(0.03%)
Contract # 12143202
Totals 33725327.54 112750.00 21208624.90 62.8

CountyBOWIE
Highway IH 30
From SH 98
To SP 86
CSJ 0610-06-078
Proj ID IM 0303(126)
Work Type PAV REP, PLANING, ACP & PAV MRKS
 
17.707 8894155.74 0.00 8440701.24 95.3
Work Order 05-06-14
Work Began 07-08-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 113
Addl Days Granted 3
Working Days Charged 152
Percent Time Used 131
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-06-078
SOUTHWEST ENVIRONMENT SERVICES LLC (0.02%)
COWBELL TRAFFIC SERVICES, INC. (0.13%)
DUSTROL, INC.(8.10%)
SCR CONSTRUCTION CO., INC. (8.95%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23%)
DUSTIN ALLEN, INC. (2.50%)
STRIPING TECHNOLOGY, L.P.(1.27%)
Contract # 04143025
Totals 8894155.74 0.00 8440701.24 95.3

CountyBOWIE
Highway IH 30
From AT FM 2253 UNDERPASS
To .
CSJ 0610-07-098
Proj ID STP 2013(843)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.010 3821270.50 305022.09 2937005.77 76.8
Work Order 06-30-15
Work Began 08-18-15
Work Completed  
Time Computed 08-18-15
Contract Working Days 290
Addl Days Granted 0
Working Days Charged 154
Percent Time Used 53
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0610-07-098
MORRIS COUNTY CONTRACTORS, L.L.C.(5.81%)
TEXOP CONSTRUCTION (0.74%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.47%)
PENHALL COMPANY(0.19%)
RK HALL, LLC ( 14.06%)
PANOLA SIGN & BARRICADE, INC.(0.83%)
STRIPING TECHNOLOGY, L.P.(1.63%)
WRIGHT BROTHERS EXCAVATING CO. (1.28%)
CHEROKEE SERVICES(0.41%)
Contract # 05153012
Totals 3821270.50 305022.09 2937005.77 76.8

CountyCAMP
Highway FM 1519
From CR 3109
To FM 556
CSJ 0633-05-018
Proj ID STP 2016(286)HES
Work Type FLASH CHEV, TEXT SHLDR & CL TEXTURE
 
28.805 1439952.07 356163.71 1416759.52 98.3
Work Order 12-10-15
Work Began 04-01-16
Work Completed  
Time Computed 01-11-16
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 65
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0633-05-018
BRYDL CONTRACTING, INC.(0.69%)
Contract # 11153207
Totals 1439952.07 356163.71 1416759.52 98.3

CountyPANOLA
Highway FM 31
From US 79
To FM 123
CSJ 0640-02-029
Proj ID STP 2016(737)
Work Type CMT TRT EXIST MTL, OCST, ACP, & PM
 
4.848 3629436.31 0.00 737755.95 20.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-15-16
Work Began 05-03-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 11
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0640-02-029
PANOLA SIGN & BARRICADE, INC.(0.62%)
STRIPE-A-ZONE, INC.(3.30%)
DREWERY & WHEATON, LLC (1.92%)
TEXOP CONSTRUCTION (0.77%)
Contract # 02163028
Totals 3629436.31 0.00 737755.95 20.3

CountyPANOLA
Highway FM 123
From US 79
To FM 31
CSJ 0731-01-051
Proj ID STP 2016(738)
Work Type CMT TRT BASE, ACP & PVMT MARKINGS
 
21.422 3958704.28 30165.61 30165.61 0.7
Work Order 03-29-16
Work Began 05-31-16
Work Completed  
Time Computed 04-28-16
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 2
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0731-01-051
PANOLA SIGN & BARRICADE, INC.(0.47%)
EAST TEXAS BRIDGE, INC.( 10.92%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.15%)
B & E CONSTRUCTION INC.( 12.21%)
DUSTIN ALLEN, INC. (4.78%)
STRIPE-A-ZONE, INC.(9.16%)
Contract # 02163231
Totals 3958704.28 30165.61 30165.61 0.7

CountyHARRISON
Highway FM 450
From AT LITTLE CYPRESS CREEK
To .
CSJ 0843-02-012
Proj ID BR 2013(659)
Work Type REPLACE BRIDGE & APPRS
 
2.006 7845576.22 71214.10 7636097.84 97.3
Work Order 08-08-13
Work Began 08-15-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 440
Addl Days Granted 0
Working Days Charged 353
Percent Time Used 80
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0843-02-012
PANOLA SIGN & BARRICADE, INC.(0.18%)
STRIPING TECHNOLOGY, L.P.(0.92%)
MAC TRANSPORTATION, LTD, L.L.P.(4.24%)
AMERICAN REMEDIATION OPTIONS, INC. (2.46%)
DENMAN DRILLING CO., INC.(0.33%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.25%)
Contract # 05133220
Totals 7845576.22 71214.10 7636097.84 97.3

CountyUPSHUR
Highway FM 555
From SH 155
To SH 154
CSJ 1018-02-017
Proj ID STP 1502(227)HES
Work Type GR, BS, SURF, HFST & PAV MRKS
 
10.673 1904823.20 399623.27 399623.27 20.9
Work Order 08-26-15
Work Began 05-09-16
Work Completed  
Time Computed 09-25-15
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 11
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1018-02-017
PANOLA SIGN & BARRICADE, INC.(0.76%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.55%)
TOTAL HIGHWAY MAINTENANCE, LLC ( 14.37%)
Contract # 06153224
Totals 1904823.20 399623.27 399623.27 20.9

CountyMARION
Highway FM 805
From CR 3410
To 1.3 MI. E. OF SH 43
CSJ 1101-01-013
Proj ID STP 1502(014)HES
Work Type SAFE TREAT FIXED OBJECTS & WIDEN LN
 
7.199 1172292.91 197169.26 923352.67 78.7
Work Order 06-01-15
Work Began 07-06-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 67
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1101-01-013
PANOLA SIGN & BARRICADE, INC.(0.76%)
SOUTHWEST ENVIRONMENT SERVICES LLC (4.55%)
JM YANEZ CONSTRUCTION(7.74%)
STRIPING TECHNOLOGY, L.P.(2.51%)
Contract # 04153228
Totals 1172292.91 197169.26 923352.67 78.7

CountyTITUS
Highway FM 1402
From 1.2 MI N OF IH 30
To 1.8 MI N OF IH 30
CSJ 1384-01-021
Proj ID C 1384-1-21
Work Type GR, BASE, SURF & PM
 
0.622 1351578.66 0.00 1404900.23 99.9
Work Order 01-17-14
Work Began 02-24-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 66
Contractor(s)
TEXANA LAND & ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1384-01-021
BAHENA CONSTRUCTION CO.,INC. (9.74%)
GIST ENTERPRISES, INC. (1.45%)
LYON BARRICADE AND CONSTRUCTION CO.(0.76%)
SAMMY G. SMALLWOOD (0.50%)
STRIPING TECHNOLOGY, L.P.(4.23%)
TURF WORKZ (2.28%)
MOORE CONSTRUCTION, INC. (3.27%)
Contract # 10133211
Totals 1351578.66 0.00 1404900.23 99.9

CountyHARRISON
Highway FM 2625
From FM 31
To FM 9
CSJ 3283-01-014
Proj ID STP 1502(055)
Work Type CEMENT TRT, FL BS, SURF & PAV MARKS
 
8.690 4532166.52 1200.00 1811089.76 39.9
Work Order 05-15-15
Work Began 06-15-15
Work Completed  
Time Computed 01-30-16
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 23
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3283-01-014
PANOLA SIGN & BARRICADE, INC.(0.45%)
STRIPING TECHNOLOGY, L.P.(2.27%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.14%)
JOHNSON CONSTRUCTION SERVICES, LLC.(0.45%)
Contract # 04153253
Totals 4532166.52 1200.00 1811089.76 39.9