Monthly State Let Construction Report For Atlanta District As Of Jun 12, 2017 Page 2 Of 3

Last Update: Monday, June 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTITUS
HighwayUS 271
FromAT RIPLEY CREEK
To.
CSJ0221-05-064
Proj IDBR 1702(392)
Work TypeREPLACE BRIDGES AND APPROACHES
 
1.1178911050.610.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days325
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0221-05-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173205
Totals8911050.610.000.000.0

CountyPANOLA
HighwayBU 79-G
FromBU 59-D IN CARTHAGE
To0.3 MI E. OF US 79
CSJ0246-02-049
Proj IDSTP 2017(884)
Work TypePLANE ACP, ACP SURF, & PAV MARK
 
2.679876859.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-09-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days39
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0246-02-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173015
Totals876859.300.000.000.0

CountyTITUS
HighwaySH 49
FromAT ARIZONA STREET INTERSECTION
To.
CSJ0248-01-072
Proj IDSTP 1702(393)HES
Work TypeIMPROVE INTERSECTION SAFETY
 
0.009418186.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days161
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0248-01-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173031
Totals418186.600.000.000.0

CountyTITUS
HighwayUS 271
From0.7 MI. N. OF FM 3417
To0.3 MI. S. OF FM 3417
CSJ0248-01-077
Proj IDNH 1702(147)
Work TypeGR,STR,CONC PAVMT,& PAV MK
 
1.10512222495.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days208
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0248-01-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173039
Totals12222495.520.000.000.0

CountyCAMP
HighwayUS 271
FromAT SL 179
To.
CSJ0248-02-063
Proj IDSTP 2017(720)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.800599736.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days134
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0248-02-063
PANOLA SIGN & BARRICADE, INC. (1.46)
CARTHAGE DRILLING, INC. (1.90)
Contract #02173014
Totals599736.400.000.000.0

CountyUPSHUR
HighwayUS 271
FromAT SH 155 INTERSECTION
To.
CSJ0248-04-068
Proj IDSTP 1702(396)HES
Work TypeIMPROVE TRAFFIC SIGNAL, INSTALL ADV
 
0.006370150.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0248-04-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173033
Totals370150.000.000.000.0

CountyCASS
HighwaySH 77
From0.2 MILE WEST OF FM 251
To0.3 MILE EAST OF FM 1841
CSJ0278-01-044
Proj IDSTP 2015(702)
Work TypeGR, STR, BASE, C&G, ACP, ILL & PVT
 
1.0988162284.828629833.7599.9
Work Order05-21-15
Work Began10-05-15
Work Completed
Time Computed09-19-15
Contract Working Days370
Addl Days Granted0
Working Days Charged275
Percent Time Used74
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0278-01-044
BAHENA CONSTRUCTION CO.,INC. (9.92)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC. (0.79)
PANOLA SIGN & BARRICADE, INC. (0.26)
RK HALL, LLC (49.37)
SAMMY SMALLWOOD COMPANY (0.90)
STRIPING TECHNOLOGY, L.P. (0.85)
TEXAS ENVIRONMENTAL MANAGEMENT SA, INC. (3.78)
TEXAS TRAFFIC CONTROL SYSTEMS, INC. (4.45)
TEXOP CONSTRUCTION (0.62)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.97)
Contract #03153207
Totals8162284.82106970.278629833.7599.9

CountyUPSHUR ETC
HighwaySH 154 ETC
From0.1 MI E OF US 271
ToFM 726
CSJ0402-01-023
Proj IDSTP 2017(072)HESG
Work TypeTEXTURIZE SHOULDERS & CL TEXTURING
 
81.5341158627.94598493.6351.6
Work Order10-21-16
Work Began03-15-17
Work Completed
Time Computed11-21-16
Contract Working Days76
Addl Days Granted0
Working Days Charged49
Percent Time Used64
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0402-01-023
STRIPING SYSTEMS, INC. (0.38)
Contract #09163023
Totals1158627.9463512.58598493.6351.6

CountyHARRISON
HighwayIH 20
FromAT FM 450 UNDERPASS
To.
CSJ0495-08-086
Proj IDBR 2013(619)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.0104874784.264830741.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-30-15
Work Began09-01-15
Work Completed
Time Computed08-31-15
Contract Working Days225
Addl Days Granted0
Working Days Charged374
Percent Time Used166
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-086
PANOLA SIGN & BARRICADE, INC. (0.44)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.45)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.96)
STRIPING TECHNOLOGY, L.P. (3.24)
TEXOP CONSTRUCTION (1.50)
S & S BRIDGE PAINTING, INC. (0.06)
ODUM SERVICES, L.P. (3.08)
HOUSTON SAWING & DRILLING (0.10)
MCL CONTRACTING, LLC (0.17)
Contract #04153256
Totals4874784.260.004830741.0099.9

CountyHARRISON
HighwayIH 20
FromGREGG C/L
To0.5 MI. W. OF SH 43, WB LANES ONLY
CSJ0495-08-100
Proj IDNH 2017(236)
Work TypePLANE,CONC PVMT REP,ACP SF,PAV MRK
 
24.48013599302.662374131.6017.4
Work Order01-17-17
Work Began02-21-17
Work Completed
Time Computed02-16-17
Contract Working Days250
Addl Days Granted0
Working Days Charged47
Percent Time Used18
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-100
PANOLA SIGN & BARRICADE, INC. (0.15)
O. TREVINO CONSTRUCTION, LLC (7.04)
B & E CONSTRUCTION INC. (6.03)
CHEROKEE SERVICES (0.86)
DUSTIN ALLEN, INC. (1.37)
SPARTAN CONSTRUCTION, INC. (9.43)
STRIPE-A-ZONE, INC. (0.35)
STRIPING TECHNOLOGY, L.P. (1.79)
W.O.E. CONSTRUCTION (0.30)
JOHNSON BROTHER"S TRUCKING (0.28)
Contract #11163211
Totals13599302.66960964.052374131.6017.4

CountyUPSHUR
HighwaySH 155
FromAT SABINE RIVER & SABINE RIVER RELI
ToSOUTH OF BIG SANDY
CSJ0520-02-037
Proj IDBR 2013(823)
Work TypeREPLACE BRIDGES AND APPROACHES
 
0.69212644943.1112033966.1695.1
CountyUPSHUR
HighwaySH 155
FromAT UNION PACIFIC RAILROAD OVERPASS
ToS. OF BIG SANDY
CSJ0520-02-038
Proj IDBR 2013(823)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1172277242.662241635.3698.4
CountyUPSHUR
HighwaySH 155
FromSABINE RIVER RELIEF BRIDGE
ToU.P.R.R. OVERPASS
CSJ0520-02-039
Proj IDC 520-2-39
Work TypeGR,STR,BASE,SURF
 
1.2743947700.405854429.4199.9
Work Order09-09-13
Work Began09-30-13
Work Completed
Time Computed09-30-13
Contract Working Days780
Addl Days Granted41
Working Days Charged655
Percent Time Used79
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0520-02-037
MAC TRANSPORTATION, LTD, L.L.P. (6.50)
STRIPING TECHNOLOGY, L.P. (1.11)
AMERICAN REMEDIATION OPTIONS, INC. (0.56)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.10)
ODUM SERVICES, L.P. (1.00)
PANOLA SIGN & BARRICADE, INC. (0.16)
HIGHWAY 19 CONSTRUCTION, LLC (0.62)
ATS DRILLING, INC. (7.12)
MCL CONTRACTING, LLC (0.20)
TEX OP CONSTRUCTION, LP (0.02)
ISAACS CONSTRUCTION SERVICES, LLC. (0.11)
ROYAL REBAR (0.06)
Contract #07133204
Totals18869886.17467521.0320130030.9399.9

CountyCASS
HighwayFM 125
FromSH 43
ToLOUISIANA STATE LINE
CSJ0546-09-039
Proj IDSTP 1502(226)HES
Work TypeGR,STR,BS,SURF,HFST & PAV MRKS
 
37.6713490097.962605569.5374.6
Work Order08-13-15
Work Began05-25-16
Work Completed
Time Computed09-12-15
Contract Working Days260
Addl Days Granted0
Working Days Charged83
Percent Time Used31
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0546-09-039
POLY-CARB, INC. (3.69)
PANOLA SIGN & BARRICADE, INC. (0.89)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.98)
STRIPE-A-ZONE, INC. (13.72)
TX TINMAN ENTERPRISES, LLC. (5.00)
Contract #06153214
Totals3490097.96124782.362605569.5374.6

CountyTITUS ETC
HighwayIH 30
FromFRANKLIN COUNTY LINE
ToMORRIS COUNTY LINE
CSJ0610-03-079
Proj IDNH 2015(407)
Work TypePAV REP, ACP SURFACING AND PAV MARK
 
97.96433725327.5429833551.7588.4
Work Order02-10-15
Work Began04-15-15
Work Completed
Time Computed04-11-15
Contract Working Days595
Addl Days Granted0
Working Days Charged458
Percent Time Used76
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-03-079
DUSTROL, INC. (3.91)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.33)
TOTAL HIGHWAY MAINTENANCE, LLC (0.32)
DUSTIN ALLEN, INC. (3.58)
STRIPE-A-ZONE, INC. (7.29)
JM YANEZ CONSTRUCTION (1.60)
SCR CONSTRUCTION CO., INC. (1.48)
EAST TEXAS BRIDGE, INC. (9.22)
STRAIGHT LINE SAWING & SEALING (0.36)
SAMMY GIST ENTERPRISES, INC. (0.20)
BRYDL CONTRACTING, INC. (0.03)
Contract #12143202
Totals33725327.54964895.0529833551.7588.4

CountyTITUS
HighwayIH 30
FromSS 185
ToFM 1001
CSJ0610-03-090
Proj IDSTP 2017(239)HES
Work TypeSAFETY LIGHTING
 
28.8101841758.651157616.5962.8
Work Order12-12-16
Work Began03-06-17
Work Completed
Time Computed04-11-17
Contract Working Days236
Addl Days Granted0
Working Days Charged51
Percent Time Used21
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-03-090
FLEX SUPPLY, LLC (2.33)
RANSOM DRILLING SERVICES, LLC (2.28)
DEKALB TREE SPECIALIST (0.46)
Contract #11163212
Totals1841758.65249214.041157616.5962.8

CountyBOWIE
HighwayIH 30
From0.3 MI. W. OF US 82
To0.4 MI. E. OF SH 8
CSJ0610-06-080
Proj IDSTP 1702(398)HES
Work TypeINSTALL SAFETY LIGHTING
 
8.348640525.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-06-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173010
Totals640525.980.000.000.0

CountyPANOLA
HighwayFM 31
FromUS 79
ToFM 123
CSJ0640-02-029
Proj IDSTP 2016(737)
Work TypeCMT TRT EXIST MTL, OCST, ACP, & PM
 
4.8483629436.312837846.4778.1
Work Order03-15-16
Work Began05-03-16
Work Completed
Time Computed05-02-16
Contract Working Days176
Addl Days Granted0
Working Days Charged152
Percent Time Used86
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0640-02-029
PANOLA SIGN & BARRICADE, INC. (0.62)
STRIPE-A-ZONE, INC. (3.30)
DREWERY & WHEATON, LLC (1.92)
TEXOP CONSTRUCTION (0.77)
FREDONIA CONSTRUCTION SERVICES (0.27)
DREWERY BROS TREE SERVICE, INC. (2.16)
Contract #02163028
Totals3629436.3136096.822837846.4778.1

CountyPANOLA
HighwayFM 123
FromUS 79
ToFM 31
CSJ0731-01-051
Proj IDSTP 2016(738)
Work TypeCMT TRT BASE, ACP & PVMT MARKINGS
 
21.4223958704.282525549.9063.7
Work Order03-29-16
Work Began05-31-16
Work Completed
Time Computed04-28-16
Contract Working Days129
Addl Days Granted0
Working Days Charged126
Percent Time Used97
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0731-01-051
PANOLA SIGN & BARRICADE, INC. (0.47)
EAST TEXAS BRIDGE, INC. (10.92)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.15)
B & E CONSTRUCTION INC. (12.21)
DUSTIN ALLEN, INC. (4.78)
STRIPE-A-ZONE, INC. (9.16)
L. S. EQUIPMENT CO., INC. (0.64)
Contract #02163231
Totals3958704.28150660.402525549.9063.7

CountyHARRISON
HighwayFM 450
From0.2 MI. S. OF IH 20
ToFM 968
CSJ0843-06-019
Proj IDSTP 2017(508)HESG
Work TypeBASE, SURFACING & PAVEMENT MARKINGS
 
1.427474176.69344890.2272.7
Work Order03-01-17
Work Began04-06-17
Work Completed
Time Computed03-31-17
Contract Working Days68
Addl Days Granted0
Working Days Charged29
Percent Time Used42
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 0843-06-019
FLEX SUPPLY, LLC (1.39)
SOUTHWEST ENVIRONMENT SERVICES LLC (18.80)
JM YANEZ CONSTRUCTION (25.72)
ISAACS CONSTRUCTION SERVICES, LLC. (2.58)
STRIPING TECHNOLOGY, L.P. (1.56)
Contract #01173212
Totals474176.69148898.57344890.2272.7

CountyCASS
HighwayVA
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ0919-00-073
Proj IDSTP 1602(315)
Work TypePAVEMENT MARKINGS
 
95.991680959.20242719.3335.6
Work Order08-18-16
Work Began11-29-16
Work Completed
Time Computed10-24-16
Contract Working Days40
Addl Days Granted0
Working Days Charged28
Percent Time Used70
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0919-00-073
STRIPING SYSTEMS, INC. (0.70)
Contract #07163216
Totals680959.200.00242719.3335.6

CountyUPSHUR
HighwaySH 300
From3.0 MI N OF FM 726
ToFM 3358 (S)
CSJ1385-01-036
Proj IDNH 1702(149)
Work TypeACP LVL-UP&SURF,MBGF,BR RAIL,PV MKS
 
4.3282285447.840.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 1385-01-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173043
Totals2285447.840.000.000.0