Monthly State Let Construction Report For Atlanta District As Of Jul 14, 2017 Page 1 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTITUS ETC
HighwayUS 67 ETC
From0.1 MI W OF US 271
To0.1 MI E OF FM 1734 W
CSJ0010-06-040
Proj IDSTP 2016(135)
Work TypeSEAL COAT
 
160.1456550235.525741583.0787.7
Work Order01-22-16
Work Began05-22-16
Work Completed
Time Computed05-22-16
Contract Working Days50
Addl Days Granted0
Working Days Charged55
Percent Time Used110
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-06-040
STRIPE-A-ZONE, INC. (7.47)
BRYDL CONTRACTING, INC. (0.87)
Contract #09153234
Totals6550235.521679879.165741583.0787.7

CountyTITUS ETC
HighwayUS 67 ETC
FromUS 271
ToFRANKLIN C/L
CSJ0010-06-041
Proj IDSTP 2017(053)HESG
Work TypePROFILE EDGELINE MARKINGS
 
120.8311861333.541332422.6971.5
Work Order10-14-16
Work Began01-09-17
Work Completed
Time Computed04-10-17
Contract Working Days129
Addl Days Granted0
Working Days Charged105
Percent Time Used81
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-06-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163225
Totals1861333.5424678.861332422.6971.5

CountyTITUS ETC
HighwayUS 67 ETC
FromMORRIS C/L
To0.9 MI. E. OF FM 1402
CSJ0010-07-050
Proj IDSTP 2017(703)HESG
Work TypeTEXTURIZE SHOULDERS & CL TEXTURING
 
111.7101295587.0275923.115.8
Work Order03-22-17
Work Began06-26-17
Work Completed
Time Computed05-22-17
Contract Working Days125
Addl Days Granted0
Working Days Charged23
Percent Time Used18
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0010-07-050
BRYDL CONTRACTING, INC. (2.77)
STRIPING SYSTEMS, INC. (0.16)
Contract #02173228
Totals1295587.0275923.1175923.115.8

CountyBOWIE
HighwayUS 67
FromAT BASSETT'S CREEK
To.
CSJ0010-11-069
Proj IDBR 1702(389)
Work TypeCONCRETE STRUCTURE REPAIR
 
0.1291398421.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days192
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-11-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173021
Totals1398421.500.000.000.0

CountyBOWIE
HighwayUS 67
FromAT IH 369 INTERSECTION
To.
CSJ0010-13-087
Proj IDSTP 2017(333)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.009566437.35154501.9927.2
Work Order01-17-17
Work Began05-30-17
Work Completed
Time Computed05-17-17
Contract Working Days203
Addl Days Granted0
Working Days Charged25
Percent Time Used12
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-13-087
STRIPE-A-ZONE, INC. (4.40)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.85)
Contract #12163015
Totals566437.3531000.00154501.9927.2

CountyBOWIE ETC
HighwayFM 991 ETC
FromUS 67 W
ToUS 67 E
CSJ0010-19-011
Proj IDSTP 2017(175)
Work TypeSEAL COAT
 
104.0613968760.101185540.8729.8
Work Order01-17-17
Work Began00-00-00
Work Completed
Time Computed06-12-17
Contract Working Days60
Addl Days Granted0
Working Days Charged12
Percent Time Used20
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-19-011
STRIPING TECHNOLOGY, L.P. (8.20)
BRYDL CONTRACTING, INC. (0.97)
BARRICADES PLUS, LLC (1.36)
Contract #10163024
Totals3968760.100.001185540.8729.8

CountyBOWIE
HighwayUS 82
FromIH 369
ToUS 67
CSJ0046-06-079
Proj IDNH 1702(391)
Work TypePLANING, SURFACING & PAV MRKS
 
3.2101824808.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-12-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0046-06-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173208
Totals1824808.250.000.000.0

CountyHARRISON
HighwayUS 59
FromAT INTERSECTION OF SL 390
To.
CSJ0062-07-086
Proj IDNH 2013(617)
Work TypePLANING,ACP,CPCD & PAV MRKS
 
0.5315747430.106255941.9899.9
Work Order10-06-15
Work Began11-11-15
Work Completed
Time Computed11-05-15
Contract Working Days195
Addl Days Granted0
Working Days Charged258
Percent Time Used132
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-086
PANOLA SIGN & BARRICADE, INC. (1.10)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.89)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.42)
STRIPING TECHNOLOGY, L.P. (7.64)
ACU CONSTRUCTION LLC (0.57)
CARTHAGE DRILLING, INC. (0.21)
JEFF WILSON BORING (0.17)
TEX OP CONSTRUCTION, LP (0.10)
Contract #07153228
Totals5747430.1028707.006255941.9899.9

CountyHARRISON
HighwayUS 59
From3.3 MI. S. OF FM 1997
To0.1 MI. N. OF SH 43 (N)
CSJ0062-07-087
Proj IDNH 2016(967)
Work TypePLANING, ACP & PAV MARKINGS
 
4.2343413079.114260248.2099.9
Work Order05-16-16
Work Began07-24-16
Work Completed
Time Computed06-15-16
Contract Working Days55
Addl Days Granted13
Working Days Charged71
Percent Time Used104
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-087
PANOLA SIGN & BARRICADE, INC. (0.21)
STRIPE-A-ZONE, INC. (3.09)
DUSTIN ALLEN, INC. (1.13)
COWBELL TRAFFIC SERVICES, INC. (0.36)
B & E CONSTRUCTION INC. (0.96)
Contract #04163017
Totals3413079.11605517.414260248.2099.9

CountyHARRISON
HighwayUS 59
From0.2 MI. S. OF IH 20
ToFM 1186
CSJ0063-01-088
Proj IDNH 1702(151)
Work TypePLANE ACP, ACP SURF, & PAV MARK
 
14.4615342972.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-01-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173239
Totals5342972.800.000.000.0

CountyHARRISON
HighwayUS 59
FromAT JOHNSON ST INTERSECTION
To.
CSJ0063-01-091
Proj IDSTP 2017(235)HESG
Work TypeINSTALL TRAFFIC SIGNAL
 
0.406256403.00132334.7551.6
Work Order12-12-16
Work Began05-12-17
Work Completed
Time Computed04-11-17
Contract Working Days140
Addl Days Granted0
Working Days Charged36
Percent Time Used25
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-01-091
STRIPE-A-ZONE, INC. (3.89)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.24)
Contract #11163023
Totals256403.0058438.75132334.7551.6

CountyHARRISON ETC
HighwayFM 1186 ETC
FromUS 59
ToPANOLA C/L
CSJ0063-01-092
Proj IDSTP 2017(336)HESG
Work TypePROFILE EDGELINE MARKINGS
 
84.957814705.35219087.2026.8
Work Order03-02-17
Work Began05-16-17
Work Completed
Time Computed05-01-17
Contract Working Days90
Addl Days Granted0
Working Days Charged38
Percent Time Used42
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-01-092
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163008
Totals814705.3513587.39219087.2026.8

CountyPANOLA
HighwayUS 59
FromAT US 79 INTERSECTION
To.
CSJ0063-03-060
Proj IDSTP 2017(505)HES
Work TypeIMPROVE TRAFFIC SIGNAL & SAFE LIGHT
 
0.009524435.70317308.1060.5
Work Order02-13-17
Work Began05-08-17
Work Completed
Time Computed06-13-17
Contract Working Days190
Addl Days Granted0
Working Days Charged24
Percent Time Used12
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0063-03-060
PANOLA SIGN & BARRICADE, INC. (1.89)
COX CONTRACTORS, INC. (10.25)
Contract #01173245
Totals524435.70122130.90317308.1060.5

CountyPANOLA
HighwaySH 149
FromUS 79
To0.8 MI S. OF SH 315
CSJ0063-11-042
Proj IDSTP 2016(625)
Work TypeGR, STR, BS, SURF
 
1.98020892969.232098582.5110.0
Work Order08-05-16
Work Began09-08-16
Work Completed
Time Computed09-05-16
Contract Working Days540
Addl Days Granted0
Working Days Charged85
Percent Time Used15
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-11-042
PANOLA SIGN & BARRICADE, INC. (0.22)
WEST TEXAS RUMBLE STRIP (0.02)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC. (0.51)
SCOTT DERR PAINTING CO, LLC (0.00)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.43)
OSCAR ORDUNO, INC. (0.57)
STRIPING TECHNOLOGY, L.P. (3.67)
CARTHAGE DRILLING, INC. (0.05)
DIRECTIONAL DRILLING (0.03)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.74)
ISAACS CONSTRUCTION SERVICES, LLC. (0.22)
TJT CONSTRUCTION (0.52)
RAYFORD"S TRUCK & TRACTOR (0.28)
Contract #04163202
Totals20892969.23654568.122098582.5110.0

CountyBOWIE
HighwayUS 259
FromAT RED RIVER
To.
CSJ0085-04-033
Proj IDBR 1402(085)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.4167588340.845595304.6673.7
CountyBOWIE
HighwayUS 259
FromON TEXAS SIDE OF RED RIVER BRIDGE
To.
CSJ0085-04-037
Proj IDBR 1402(202)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3982462742.583071607.2799.9
CountyBOWIE
HighwayUS 259
FromON OKLAHOMA SIDE OF RED RIVER BRIDG
To.
CSJ0085-04-038
Proj IDCC 85-4-38
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3981789824.15976082.1254.5
Work Order10-09-14
Work Began12-08-14
Work Completed
Time Computed12-08-14
Contract Working Days479
Addl Days Granted0
Working Days Charged168
Percent Time Used35
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0085-04-033
TOTAL HIGHWAY MAINTENANCE, LLC (0.83)
MOORE CONSTRUCTION, INC. (0.26)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (5.86)
DUSTROL, INC. (1.40)
WEST TEXAS RUMBLE STRIP (0.03)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.11)
MCL CONTRACTING, LLC (4.57)
PRIMATE CONSTRUCTION, INC. (0.12)
FARR FOUNDATION, INC. (0.59)
DUSTIN ALLEN, INC. (0.29)
ATS DRILLING, INC. (9.03)
H. V. CAVER, INC. (0.22)
Contract #08143008
Totals11840907.57694354.219642994.0581.4

CountyBOWIE
HighwayUS 259
From0.1 MI. S. OF US 82 IN DEKALB
To0.3 MI. S. OF FM 44(S)
CSJ0085-04-035
Proj IDSTP 2013(615)
Work TypeGR,STR,BS,SURF & PAV MRK
 
2.9135371369.95351018.956.5
Work Order05-16-17
Work Began00-00-00
Work Completed
Time Computed06-15-17
Contract Working Days317
Addl Days Granted0
Working Days Charged10
Percent Time Used3
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0085-04-035
HODGES AND SON CONSTRUCTION COMPANY, INC. (18.10)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.02)
MURRAY CONSTRUCTION (0.52)
PANOLA SIGN & BARRICADE, INC. (0.38)
ISAACS CONSTRUCTION SERVICES, LLC. (0.41)
RK HALL, LLC (26.74)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.77)
STRIPE-A-ZONE, INC. (0.23)
TEXOP CONSTRUCTION (1.50)
STRIPING TECHNOLOGY, L.P. (2.66)
Contract #04173040
Totals5371369.95351018.95351018.956.5

CountyHARRISON
HighwayUS 80
From0.1 MI. E. OF US 59
To0.2 MI. E. OF SL 390
CSJ0096-09-076
Proj IDSTP 2017(883)
Work TypePLANE ACP, ACP SURF, & PAV MARK
 
3.7501295848.080.000.0
Work Order04-24-17
Work Began07-11-17
Work Completed
Time Computed05-24-17
Contract Working Days48
Addl Days Granted0
Working Days Charged17
Percent Time Used35
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0096-09-076
PANOLA SIGN & BARRICADE, INC. (0.52)
STRIPE-A-ZONE, INC. (6.15)
Contract #03173206
Totals1295848.080.000.000.0

CountyBOWIE
HighwayUS 59
From1.6 MI. N. OF IH 30
To4.9 MI. N. OF IH 30
CSJ0217-01-034
Proj IDNH 1702(150)
Work TypePLANE ACP,ACP SURF, MBGF & PAV MARK
 
3.4671377443.860.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-08-17
Work Began00-00-00
Work Completed
Time Computed07-10-17
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0217-01-034
A.E. MOORE CONSTRUCTION, INC. DBA (0.85)
DIAMOND SURFACE, INC. (0.62)
DUSTIN ALLEN, INC. (6.68)
STRIPE-A-ZONE, INC. (5.60)
TEXOP CONSTRUCTION (1.24)
TOTAL HIGHWAY MAINTENANCE, LLC (0.82)
Contract #05173238
Totals1377443.860.000.000.0

CountyTITUS
HighwayUS 271
FromAT RIPLEY CREEK
To.
CSJ0221-05-064
Proj IDBR 1702(392)
Work TypeREPLACE BRIDGES AND APPROACHES
 
1.1178911050.610.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days325
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0221-05-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173205
Totals8911050.610.000.000.0

CountyPANOLA
HighwayBU 79-G
FromBU 59-D IN CARTHAGE
To0.3 MI E. OF US 79
CSJ0246-02-049
Proj IDSTP 2017(884)
Work TypePLANE ACP, ACP SURF, & PAV MARK
 
2.679876859.300.000.0
Work Order05-09-17
Work Began07-09-17
Work Completed
Time Computed06-08-17
Contract Working Days39
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0246-02-049
PANOLA SIGN & BARRICADE, INC. (0.67)
TEX OP CONSTRUCTION, LP (12.32)
STRIPE-A-ZONE, INC. (5.15)
FREDONIA CONSTRUCTION SERVICES (1.14)
Contract #03173015
Totals876859.300.000.000.0