Monthly State Let Construction Report For Atlanta District As Of Apr 11, 2016 Page 1 Of 2

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTITUS
Highway US 67 ETC
From 0.1 MI W OF US 271
To 0.1 MI E OF FM 1734 W
CSJ 0010-06-040
Proj ID STP 2016(135)
Work Type SEAL COAT
 
160.145 6550235.52 0.00 472793.39 7.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-22-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-06-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153234
Totals 6550235.52 0.00 472793.39 7.2

CountyMORRIS
Highway US 67
From FM 161
To TITUS C/L
CSJ 0010-08-053
Proj ID STP 2016(073)HES
Work Type TEXTURIZE SHOULDERS & CL TEXTURING
 
22.528 664014.08 55215.60 55215.60 8.3
Work Order 10-22-15
Work Began 03-28-16
Work Completed  
Time Computed 12-21-15
Contract Working Days 115
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 34
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-08-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153224
Totals 664014.08 55215.60 55215.60 8.3

CountyBOWIE
Highway US 67
From FM 2149
To SH 8 (NORTH)
CSJ 0010-12-067
Proj ID STP 2016(076)HES
Work Type TEXTURIZE SHOULDERS & CL TEXTURING
 
34.615 1829345.43 83300.00 83300.00 4.5
Work Order 10-21-15
Work Began 03-07-16
Work Completed  
Time Computed 11-23-15
Contract Working Days 195
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 14
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0010-12-067
STRIPING SYSTEMS, INC. (0.00%)
BRYDL CONTRACTING, INC.(1.22%)
Contract # 09153009
Totals 1829345.43 83300.00 83300.00 4.5

CountyBOWIE
Highway US 82
From SH 98
To IH 30
CSJ 0046-04-060
Proj ID NH 1502(056)
Work Type GRADING, STRUCTURES, BASE & SURFACING
 
0.398 407780.13 60823.00 64823.00 15.8
Work Order 05-15-15
Work Began 03-28-16
Work Completed  
Time Computed 06-15-15
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 4
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0046-04-060
PANOLA SIGN & BARRICADE, INC.(1.14%)
RK HALL, LLC ( 32.44%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.60%)
STRIPING TECHNOLOGY, L.P.(6.19%)
Contract # 04153051
Totals 407780.13 60823.00 64823.00 15.8

CountyMARION
Highway US 59
From AT INTERSECTION OF FM 2208
To .
CSJ 0062-06-054
Proj ID NH 2015(995)
Work Type PLANING, ACP, CPCD & PAV MRKS
 
0.216 2267006.61 27807.61 1395080.37 61.5
Work Order 06-05-15
Work Began 07-07-15
Work Completed  
Time Computed 07-06-15
Contract Working Days 231
Addl Days Granted 1
Working Days Charged 181
Percent Time Used 78
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0062-06-054
STRIPING TECHNOLOGY, L.P.(8.15%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.30%)
AMERICAN REMEDIATION OPTIONS, INC. (1.39%)
PANOLA SIGN & BARRICADE, INC.(0.56%)
DIRECTIONAL DRILLING (0.04%)
TEXOP CONSTRUCTION (0.38%)
MAC TRANSPORTATION, LTD, L.L.P.(0.42%)
Contract # 04153028
Totals 2267006.61 27807.61 1395080.37 61.5

CountyHARRISON
Highway US 59 ETC
From MARION C/L
To US 80
CSJ 0062-07-084
Proj ID STP 2015(144)HESG
Work Type INSTALL SAFETY LIGHTING
 
117.385 670082.50 56489.09 598869.96 99.0
Work Order 11-24-14
Work Began 04-29-15
Work Completed  
Time Computed 03-24-15
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 246
Percent Time Used 175
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-084
PEAK COMMUNICATIONS LLC(1.50%)
DOUBLE S CONSTRUCTION(4.49%)
Contract # 09143206
Totals 670082.50 56489.09 598869.96 99.0

CountyHARRISON
Highway US 59
From AT INTERSECTION OF SL 390
To .
CSJ 0062-07-086
Proj ID NH 2013(617)
Work Type PLANING, ACP, CPCD & PAV MRKS
 
0.531 5747430.10 246855.18 1376970.66 23.9
Work Order 10-06-15
Work Began 11-11-15
Work Completed  
Time Computed 11-05-15
Contract Working Days 195
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 17
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-086
PANOLA SIGN & BARRICADE, INC.(1.10%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.89%)
MORRIS COUNTY CONTRACTORS, L.L.C.(2.42%)
STRIPING TECHNOLOGY, L.P.(7.64%)
ACU CONSTRUCTION LLC (0.57%)
Contract # 07153228
Totals 5747430.10 246855.18 1376970.66 23.9

CountyHARRISON
Highway US 59
From 3.3 MI. S. OF FM 1997
To 0.1 MI. N. OF SH 43 (N)
CSJ 0062-07-087
Proj ID NH 2016(967)
Work Type PLANING, ACP & PAV MARKINGS
 
4.234 3413079.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163017
Totals 3413079.11 0.00 0.00 0.0

CountyPANOLA
Highway SH 149
From US 79
To 0.8 MI S. OF SH 315
CSJ 0063-11-042
Proj ID STP 2016(625)
Work Type GR, STR, BS, SURF
 
1.980 20892969.23 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 540
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-11-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163202
Totals 20892969.23 0.00 0.00 0.0

CountyBOWIE
Highway US 259
From AT RED RIVER
To .
CSJ 0085-04-033
Proj ID BR 1402(085)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.416 7588340.84 287905.06 1721005.06 22.6
CountyBOWIE
Highway US 259
From ON TEXAS SIDE OF RED RIVER BRIDGE
To .
CSJ 0085-04-037
Proj ID BR 1402(202)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.398 2462742.58 362818.79 3070620.28 99.9
CountyBOWIE
Highway US 259
From ON OKLAHOMA SIDE OF RED RIVER BRIDG
To .
CSJ 0085-04-038
Proj ID CC 85-4-38
Work Type REPLACE BRIDGE AND APPROACHES
 
0.398 1789824.15 0.00 964062.12 53.8
Work Order 10-09-14
Work Began 12-08-14
Work Completed  
Time Computed 12-08-14
Contract Working Days 479
Addl Days Granted 0
Working Days Charged 135
Percent Time Used 28
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0085-04-033
TOTAL HIGHWAY MAINTENANCE, LLC (0.83%)
MOORE CONSTRUCTION, INC. (0.26%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (5.86%)
DUSTROL, INC.(1.40%)
WEST TEXAS RUMBLE STRIP(0.03%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.11%)
MCL CONTRACTING, LLC (2.94%)
PRIMATE CONSTRUCTION, INC. (0.12%)
FARR FOUNDATION, INC.(0.59%)
DUSTIN ALLEN, INC. (0.29%)
ATS DRILLING, INC. (9.03%)
Contract # 08143008
Totals 11840907.57 650723.85 5755687.46 48.6

CountyHARRISON
Highway US 80
From AT SL 390 INTERSECTION
To .
CSJ 0096-08-053
Proj ID STP 1602(079)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.006 396458.34 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-24-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ERNEST P. BREAUX ELECTRICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0096-08-053
ACACIA INDUSTRIES, LLC (3.78%)
DANRIK CONSTRUCTION, INC.(2.47%)
Contract # 09153018
Totals 396458.34 0.00 0.00 0.0

CountyHARRISON
Highway SH 43
From FM 2682
To MARSHALL LEIGH ROAD
CSJ 0208-02-038
Proj ID STP 2016(081)HES
Work Type FLASH CHEV, TEXT SHLDR & CL TEXTURE
 
22.453 1084210.98 686377.72 686377.72 63.3
Work Order 10-21-15
Work Began 02-29-16
Work Completed  
Time Computed 11-23-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 51
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0208-02-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153217
Totals 1084210.98 686377.72 686377.72 63.3

CountyBOWIE
Highway IH 369
From 0.1 MI N OF US 82
To SH 93
CSJ 0218-02-039
Proj ID NH 1502(052)
Work Type PAV REP, PLANING, ACP & PAV MRKS
 
7.052 2836564.00 186712.30 2560641.11 91.3
Work Order 04-20-15
Work Began 07-30-15
Work Completed  
Time Computed 05-21-15
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 180
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0218-02-039
TOTAL HIGHWAY MAINTENANCE, LLC (0.39%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.37%)
DUSTROL, INC.(3.70%)
ODUM SERVICES, L.P.(5.70%)
STRIPING TECHNOLOGY, L.P.(7.41%)
Contract # 03153234
Totals 2836564.00 186712.30 2560641.11 91.3

CountyCASS
Highway US 59
From 0.1 MI N OF FM 3129
To BOWIE C/L (NORTHBOUND LANES ONLY)
CSJ 0218-03-083
Proj ID NH 1502(134)
Work Type PLANING, ACP, CPCD & PAV MARKINGS
 
2.225 5059588.95 6795.04 4989597.46 98.6
Work Order 06-15-15
Work Began 08-17-15
Work Completed  
Time Computed 08-17-15
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 92
Contractor(s)
INTERSTATE HIGHWAY CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0218-03-083
DUSTROL, INC.(0.18%)
ODUM SERVICES, L.P.(0.82%)
RK HALL, LLC ( 17.19%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.39%)
STRIPING TECHNOLOGY, L.P.(4.21%)
TEX OP CONSTRUCTION, LP(0.73%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.29%)
CLEVE BATTE CONSTRUCTION, INC. (0.41%)
OX & COMPANY CONSTRUCTION(0.41%)
HCB TRUCKING LLC (0.41%)
ROLL & ROCK(2.68%)
Contract # 05153211
Totals 5059588.95 6795.04 4989597.46 98.6

CountyCASS
Highway US 59
From AT BLACK BAYOU
To .
CSJ 0218-04-114
Proj ID BR 1502(419)
Work Type BRIDGE RAIL & MBGF
 
0.198 755932.75 106644.55 509088.95 69.4
Work Order 08-31-15
Work Began 11-03-15
Work Completed  
Time Computed 09-30-15
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 150
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0218-04-114
STRIPING TECHNOLOGY, L.P.(4.13%)
MORRIS COUNTY CONTRACTORS, L.L.C.(9.53%)
Contract # 07153214
Totals 755932.75 106644.55 509088.95 69.4

CountyCASS
Highway SH 77
From 0.2 MILE WEST OF FM 251
To 0.3 MILE EAST OF FM 1841
CSJ 0278-01-044
Proj ID STP 2015(702)
Work Type GR, STR, BASE, C & G, ACP, ILL & PVT
 
1.098 8162284.82 169522.24 2145757.91 26.2
Work Order 05-21-15
Work Began 10-05-15
Work Completed  
Time Computed 09-19-15
Contract Working Days 370
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 17
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0278-01-044
BAHENA CONSTRUCTION CO.,INC. (9.92%)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC. (0.79%)
PANOLA SIGN & BARRICADE, INC.(0.26%)
RK HALL, LLC ( 49.37%)
SAMMY SMALLWOOD COMPANY(0.90%)
STRIPING TECHNOLOGY, L.P.(0.85%)
TEXAS ENVIRONMENTAL MANAGEMENT SA, INC.(3.78%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(4.45%)
TEXOP CONSTRUCTION (0.62%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.97%)
Contract # 03153207
Totals 8162284.82 169522.24 2145757.91 26.2

CountyHARRISON
Highway IH 20
From AT FM 450 UNDERPASS
To .
CSJ 0495-08-086
Proj ID BR 2013(619)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.010 4874784.26 239826.85 2333169.22 47.8
Work Order 07-30-15
Work Began 09-01-15
Work Completed  
Time Computed 08-31-15
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 146
Percent Time Used 64
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-086
PANOLA SIGN & BARRICADE, INC.(0.44%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.45%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.96%)
STRIPING TECHNOLOGY, L.P.(3.24%)
TEXOP CONSTRUCTION (1.50%)
S & S BRIDGE PAINTING, INC.(0.06%)
ODUM SERVICES, L.P.(3.08%)
HOUSTON SAWING & DRILLING(0.10%)
MCL CONTRACTING, LLC (0.17%)
Contract # 04153256
Totals 4874784.26 239826.85 2333169.22 47.8

CountyHARRISON
Highway IH 20
From GREGG C/L
To 0.5 MI. W. OF SH 43, EB LANES ONLY
CSJ 0495-08-095
Proj ID NH 2016(371)
Work Type PLANE, CONC PVMT REP, ACP SF, PAV MRK
 
17.009 7872292.12 11000.00 11000.00 0.1
Work Order 02-17-16
Work Began 04-04-16
Work Completed  
Time Computed 03-18-16
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 4
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-095
PANOLA SIGN & BARRICADE, INC.(0.36%)
VANCE BROTHERS, INC. (3.85%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.33%)
STRIPING TECHNOLOGY, L.P.(1.66%)
B & E CONSTRUCTION INC.(6.23%)
COWBELL TRAFFIC SERVICES, INC. (0.34%)
DUSTIN ALLEN, INC. (2.47%)
O. TREVINO CONSTRUCTION, LLC (9.82%)
JOHNSON BROTHER"S TRUCKING (0.19%)
W.O.E. CONSTRUCTION(0.44%)
Contract # 12153217
Totals 7872292.12 11000.00 11000.00 0.1

CountyHARRISON
Highway IH 20
From GREGG COUNTY LINE
To 0.5 MI. W. OF SH 43
CSJ 0495-08-096
Proj ID NH 2016(083)
Work Type INSTALL & UPGRADE ROADWAY LIGHTING
 
38.808 1038536.77 390752.92 464769.38 44.7
Work Order 10-21-15
Work Began 02-24-16
Work Completed  
Time Computed 02-19-16
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 8
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-096
FLEX SUPPLY, LLC (4.18%)
RANSOM DRILLING SERVICES, LLC(2.02%)
PATTERSON COMPLETE TREE SERV(OLD PRIME)(0.84%)
Contract # 09153216
Totals 1038536.77 390752.92 464769.38 44.7

CountyUPSHUR
Highway SH 155
From AT SABINE RIVER & SABINE RIVER RELI
To SOUTH OF BIG SANDY
CSJ 0520-02-037
Proj ID BR 2013(823)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.692 12644943.11 61372.87 8637332.47 68.3
CountyUPSHUR
Highway SH 155
From AT UNION PACIFIC RAILROAD OVERPASS
To S. OF BIG SANDY
CSJ 0520-02-038
Proj ID BR 2013(823)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.117 2277242.66 178106.13 1019621.67 44.7
CountyUPSHUR
Highway SH 155
From SABINE RIVER RELIEF BRIDGE
To U.P.R.R. OVERPASS
CSJ 0520-02-039
Proj ID C 520-2-39
Work Type GR, STR, BASE, SURF
 
1.274 3947700.40 78269.94 2318039.99 58.7
Work Order 09-09-13
Work Began 09-30-13
Work Completed  
Time Computed 09-30-13
Contract Working Days 780
Addl Days Granted 0
Working Days Charged 440
Percent Time Used 56
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0520-02-037
MAC TRANSPORTATION, LTD, L.L.P.(6.50%)
STRIPING TECHNOLOGY, L.P.(1.11%)
AMERICAN REMEDIATION OPTIONS, INC. (0.56%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.31%)
ODUM SERVICES, L.P.(1.00%)
PANOLA SIGN & BARRICADE, INC.(0.16%)
HIGHWAY 19 CONSTRUCTION, LLC (0.62%)
ATS DRILLING, INC. (7.12%)
MCL CONTRACTING, LLC (0.20%)
TEX OP CONSTRUCTION, LP(0.02%)
Contract # 07133204
Totals 18869886.17 317748.94 11974994.13 63.4