AVERAGE LOW BID UNIT PRICE - MAINTENANCE - ATLANTA DISTRICT

Last Update: Friday, June 7, 2013
ITEMS 712 2002 TO 788 2001
Items Items Bid Code Range
0100 - 0168
0305 - 0340
0400 - 0496
0500 - 0544
0658 - 0672
0712 - 0788
3235 - 3235
7013 - 7224
8251 - 8909
712 2002 - 788 2001
Item No Description Units May 31, 2013 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
712 2002 JT / CRCK SEAL (POLY MOD ASPH EMULSION) LMI     25.200 615.00000 1
712 2005 JT / CRCK SEAL (RUBBER - ASPHALT) LMI     351.510 490.00000 1
730 2056 FULL - WIDTH MOWING - TRACT (1) AC     4,688.000 25.00000 1
730 2057 FULL - WIDTH MOWING - TRACT (2) AC     4,846.000 23.00000 1
730 2058 FULL - WIDTH MOWING - TRACT (3) AC     5,276.000 21.00000 1
730 2059 FULL - WIDTH MOWING - TRACT (4) AC     3,972.000 25.00000 1
730 2060 FULL - WIDTH MOWING - TRACT (5) AC     5,390.000 22.00000 1
730 2061 FULL - WIDTH MOWING - TRACT (6) AC     4,066.000 23.50000 1
730 2062 FULL - WIDTH MOWING - TRACT (7) AC     3,908.000 22.75000 1
730 2063 FULL - WIDTH MOWING - TRACT (8) AC     3,912.000 25.00000 1
730 2064 FULL - WIDTH MOWING - TRACT (9) AC     2,590.000 28.00000 1
730 2065 FULL - WIDTH MOWING - TRACT (10) AC     2,472.000 30.00000 1
730 2066 FULL - WIDTH MOWING - TRACT (11) AC     2,250.000 26.00000 1
730 2071 FULL - WIDTH MOWING - TRACT (16) AC     2,194.000 24.75000 1
730 2073 FULL - WIDTH MOWING - TRACT (18) AC     2,598.000 31.00000 1
734 2002 LITTER REMOVAL CYC     13.000 10,632.23077 13
734 2003 LITTER REMOVAL (SPOT) AC     1,050.000 14.71429 7
735 2001 DEBRIS REMOVAL (CNTR MEDIANS / MAINLANES CYC 52.000 800.00000 182.000 840.50857 4
752 2022 TREE REMOVAL (4" - 12" DIA) EA     1,950.000 49.74359 2
752 2023 TREE REMOVAL (12" - 18" DIA) EA     1,400.000 70.28571 2
752 2024 TREE REMOVAL (18" - 24" DIA) EA     865.000 117.63006 2
752 2025 TREE REMOVAL (24" - 30" DIA) EA     395.000 206.25316 2
752 2026 TREE REMOVAL (30" - 36" DIA) EA     270.000 293.70370 2
752 2027 TREE REMOVAL (36" - 42" DIA) EA     155.000 438.70968 2
752 2028 TREE REMOVAL (42" - 48" DIA) EA     99.000 609.40404 2
752 2029 TREE REMOVAL (48" - 60" DIA) EA     109.000 669.72477 2
752 2030 TREE REMOVAL (60" - 72" DIA) EA     49.000 755.10204 2
752 2045 STUMP REMOVAL EA     107.000 134.57944 2
752 2049 TREE TRIMMING (20' X 30') MI     59.160 1,900.00000 1
770 2001 REPAIR RAIL ELEMENT (W - BEAM) LF 7,500.000 8.50000 15,000.000 8.50000 2
770 2002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF 25.000 5.00000 50.000 5.00000 2
770 2003 REP RAIL ELMNT (THRIE - BM TRANS TO W - BM) LF 13.000 5.00000 26.000 5.00000 2
770 2004 REM / REPL TIMBER / STL POST W / O CONC FND EA 700.000 14.00000 1,400.000 14.00000 2
770 2005 REM / REPL TIMBER / STL POST W / CONC FND EA 63.000 20.00000 126.000 20.00000 2
770 2007 REPAIR OF TERMINAL ANCHORS POSTS EA 5.000 5.00000 10.000 5.00000 2
770 2008 REPLACE TERMINAL ANCHOR POSTS EA 8.000 5.00000 16.000 5.00000 2
770 2010 REPL SINGLE GDRAIL TERM IMPACT HEAD EA 90.000 160.00000 180.000 160.00000 2
770 2011 REPLACE SINGLE GDRAIL TERMINAL RAIL LF 3,000.000 18.00000 6,000.000 18.00000 2
770 2012 REPLACE SINGLE GDRAIL TERMINAL POST EA 300.000 45.00000 600.000 45.00000 2
770 2014 REPAIR STEEL POST WITH BASE PLATE EA 25.000 10.00000 50.000 10.00000 2
776 2004 REPAIR (STL POST W / DOUBLED W - BEAMS - T6) LF 150.000 4.00000 300.000 4.00000 2
776 2011 REP METAL POST W / BASE PLATE (T101 RAIL EA 25.000 10.00000 50.000 10.00000 2
776 2034 REPAIR (W - BEAM, TUBE & SPLICE - T101 RAIL) LF 300.000 8.00000 600.000 8.00000 2
776 2035 REPAIR (W - BEAM - T101 RAIL) LF 1,500.000 5.00000 3,000.000 5.00000 2
788 2001 CONCRETE BEAM REPAIR EA     8.000 2,100.00000 2